MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY

WATER RESOURCES DIVISION

PERMIT

Issued To:

USDA Forest Service Attn: Rebecca Cain 400 E Munising Ave Munising, MI 49862

Permit No: WRP011716 Submission No.: HND-N0YQ-C1MFE Site Name: 02-Powell Point - Williams Landing - Grand Island Twp Issued: May 29, 2018 Expires: May 29, 2023

This permit is being issued by the Michigan Department of Environmental Quality (MDEQ), Water Resources Division, under the provisions of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (NREPA); specifically:

Part 301, Inland Lakes and Streams Part 323, Shorelands Protection and Management Part 303, Wetlands Protection Part 325, Great Lakes Submerged Lands Part 315, Dam Safety Part 353, Sand Dunes Protection and Management Part 31, Water Resources Protection (Floodplain Regulatory Authority)

Permission is hereby granted, based on permittee assurance of adherence to State of Michigan requirements and permit conditions, to:

Authorized Activity:

Dredge 100 cubic yards of material annually from the Powell Point Landing area and dredge 100 cubic yards of material annually from the William’s Landing area by mechanical means. All dredge material shall be disposed of in uplands. All work shall be completed in accordance with the approved plans and specifications of this permit.

Authority granted by this permit does not waive any jurisdiction of the United States Army Corps of Engineers or the need for a federal permit, if required.

Waterbody Affected: Lake Superior Property Location: Alger County, Grand Island Township, Town/Range/Section 47N19W22

Authority granted by this permit is subject to the following limitations:

A. Initiation of any work on the permitted project confirms the permittee's acceptance and agreement to comply with all terms and conditions of this permit.

B. The permittee, in exercising the authority granted by this permit, shall not cause unlawful pollution as defined by Part 31 of the NREPA.

C. This permit shall be kept at the site of the work and available for inspection at all times during the duration of the project or until its date of expiration.

D. All work shall be completed in accordance with the approved plans and specifications submitted with the application and/or plans and specifications attached to this permit.

E. No attempt shall be made by the permittee to forbid the full and free use by the public of public waters at or adjacent to the structure or work approved. DEQ-WRD WRP011716 v1.0

Approved Issued On:05/29/2018

Expires On:05/29/2023

USDA Forest Service WRP11716

F. It is made a requirement of this permit that the permittee give notice to public utilities in accordance with 2013 PA 174 (Act 174) and comply with each of the requirements of Act 174.

G. This permit does not convey property rights in either real estate or material, nor does it authorize any injury to private property or invasion of public or private rights, nor does it waive the necessity of seeking federal assent, all local permits, or complying with other state statutes.

H. This permit does not prejudice or limit the right of a riparian owner or other person to institute proceedings in any circuit court of this state when necessary to protect his rights.

I. Permittee shall notify the MDEQ within one week after the completion of the activity authorized by this permit by completing and forwarding the attached preaddressed postcard to the office addressed thereon.

J. This permit shall not be assigned or transferred without the written approval of the MDEQ.

K. Failure to comply with conditions of this permit may subject the permittee to revocation of permit and criminal and/or civil action as cited by the specific state act, federal act, and/or rule under which this permit is granted.

L. All dredged or excavated materials shall be disposed of in an upland site (outside of floodplains, unless exempt under Part 31 of the NREPA, and wetlands).

M. In issuing this permit, the MDEQ has relied on the information and data that the permittee has provided in connection with the submitted application for permit. If, subsequent to the issuance of a permit, such information and data prove to be false, incomplete, or inaccurate, the MDEQ may modify, revoke, or suspend the permit, in whole or in part, in accordance with the new information.

N. The permittee shall indemnify and hold harmless the State of Michigan and its departments, agencies, officials, employees, agents, and representatives for any and all claims or causes of action arising from acts or omissions of the permittee, or employees, agents, or representative of the permittee, undertaken in connection with this permit. The permittee’s obligation to indemnify the State of Michigan applies only if the state: (1) provides the permittee or its designated representative written notice of the claim or cause of action within 30 days after it is received by the state, and (2) consents to the permittee’s participation in the proceeding on the claim or cause of action. It does not apply to contested case proceedings under the Administrative Procedures Act, 1969 PA 306, as amended, challenging the permit. This permit shall not be construed as an indemnity by the State of Michigan for the benefit of the permittee or any other person.

O. Noncompliance with these terms and conditions and/or the initiation of other regulated activities not specifically authorized shall be cause for the modification, suspension, or revocation of this permit, in whole or in part. Further, the MDEQ may initiate criminal and/or civil proceedings as may be deemed necessary to correct project deficiencies, protect natural resource values, and secure compliance with statutes.

P. If any change or deviation from the permitted activity becomes necessary, the permittee shall request, in writing, a revision of the permitted activity from the MDEQ. Such revision request shall include complete documentation supporting the modification and revised plans detailing the proposed modification.

Proposed modifications must be approved, in writing, by the MDEQ prior to being implemented.

Q. This permit may be transferred to another person upon written approval of the MDEQ. The permittee must submit a written request to the MDEQ to transfer the permit to the new owner. The new owner must also submit a written request to the MDEQ to accept transfer. The new owner must agree, in writing, to accept all conditions of the permit. A single letter signed by both parties that includes all of the above information may be provided to the MDEQ. The MDEQ will review the request and, if approved, will provide written notification to the new owner.

R. Prior to initiating permitted construction, the permittee is required to provide a copy of the permit to the contractor(s) for review. The property owner, contractor(s), and any agent involved in exercising the permit are held responsible to ensure that the project is constructed in accordance with all drawings and specifications. The contractor is required to provide a copy of the permit to all subcontractors doing work authorized by the permit.

S. Construction must be undertaken and completed during the dry period of the wetland. If the area does not dry out, construction shall be done on equipment mats to prevent compaction of the soil.

T. Authority granted by this permit does not waive permit requirements under Part 91, Soil Erosion and Sedimentation Control, of the NREPA, or the need to acquire applicable permits from the County Enforcing Agent (CEA).

DEQ-WRD

WRP011716 v1.0

Approved

U. Authority granted by this permit does not waive permit requirements under the authority of Part 305, Natural Rivers, of the NREPA. A Natural Rivers Zoning Permit may be required for construction, land alteration, streambank stabilization, or vegetation removal along or near a natural river.

V. The permittee is cautioned that grade changes resulting in increased runoff onto adjacent property is subject to civil damage litigation.

W. Unless specifically stated in this permit, construction pads, haul roads, temporary structures, or other structural appurtenances to be placed in a wetland or on bottomland of the water body are not authorized and shall not be constructed unless authorized by a separate permit or permit revision granted in accordance with the applicable law.

X. For projects with potential impacts to fish spawning or migration, no work shall occur within fish spawning or migration timelines (i.e., windows) unless otherwise approved in writing by the Michigan Department of Natural Resources, Fisheries Division.

Y. Work to be done under authority of this permit is further subject to the following special instructions and specifications:

1. Authority granted by this permit does not waive permit or program requirements under Part 91 of the

NREPA or the need to acquire applicable permits from the CEA. To locate the Soil Erosion Program Administrator for your county, visit www.mi.gov/deqstormwater and select "Soil Erosion and Sedimentation Control Program" under “Related Links.”

2. The authority to conduct the activity as authorized by this permit is granted solely under the provisions of the governing act as identified above. This permit does not convey, provide, or otherwise imply approval of any other governing act, ordinance, or regulation, nor does it waive the permittee's obligation to acquire any local, county, state, or federal approval or authorization necessary to conduct the activity.

3. No fill, excess soil, or other material shall be placed in any wetland, floodplain, or surface water area not specifically authorized by this permit, its plans, and specifications.

4. This permit does not authorize or sanction work that has been completed in violation of applicable federal, state, or local statutes.

5. The permit placard shall be kept posted at the work site, in a prominent location at all times for the duration of the project, or until permit expiration.

6. This permit is being issued for the maximum time allowed and no extensions of this permit will be granted. Initiation of the construction work authorized by this permit indicates the permittee’s acceptance of this condition. The permit, when signed by the MDEQ, will be for a five-year period beginning on the date of issuance. If the project is not completed by the expiration date, a new permit must be sought.

7. Prior to commencement of any dredging authorized by this permit, the entire dredged area shall be enclosed with a turbidity curtain to prevent off-site siltation. The turbidity curtain shall be installed to extend from the bed of the waterbody to a point above the existing water's surface. The turbidity curtain shall be maintained for the duration of the project and shall be left in place after completion of dredging until all disturbed sediments have settled.

8. No work or dredging within the water authorized by this permit is allowed from April 1 to June 14 or from November 1 to December 14 due to critical spawning, migration, and/or recreational use periods.

9. The permittee is cautioned that excessive dredging resulting in the impairment of the structural integrity of seawalls on neighboring riparian properties is subject to civil damage litigation.

10. All slurry resulting from any dewatering operation shall be discharged through a filter bag or pumped to a sump located away from wetlands and surface waters and allowed to filter through natural upland vegetation, gravel filters, or other engineered devices for a sufficient distance and/or period of time necessary to remove sediment or suspended particles. The discharge of slurry water resulting from the hydrodemolition of concrete is not allowed to enter a lake, stream, or wetland.

11. Placement of dredge/excavated material into open water, onto ice, or onto exposed bottomland is not authorized by this permit.

12. The permittee acknowledges that the dredged material has not been classified as to contaminant status. Disposal of the dredged sediments is to uplands. If the dredged sediments are determined to be contaminated at a future date, permittee and dredge sediments disposal location landowner are considered potentially responsible parties and remain liable for any and all necessary site restoration DEQ-WRD

WRP011716 v1.0 Approved

Issued On:05/29/2018 http://www.mi.gov/deqstormwater and clean up under Part 115, Solid Waste Management, and Part 201, Environmental Remediation, of the NREPA. If the permittee is not the dredge sediments disposal location landowner, permittee is responsible for notifying landowner of this condition.

Issued By:

Helana Nelson Upper Peninsula District Office Water Resources Division 906-202-1507 cc: Grand Island Township Clerk Alger County CEA USACE, Marquette

DEQ-WRD

WRP011716 v1.0

Approved