Q&As_GSA Enhanced Check Out_GECO_2_Store Portal_SP__Jun 17_2019
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment: 0001
Title: Questions & Answers (Q&As) - RFQ No. GQIQSC190005:
GSA Enhanced Check Out (GECO) 2/Store Portal (SP)
Server Upgrades.
Questions Due: June 14, 2019
Q&As Issued: June 17, 2019
1. Question 1: There are inconsistencies in the length of executing the upgrade schedule. Can you confirm which is correct?
a. Section 6 – DELIVERABLES SCHEDULE AND MILESTONE DATES – The
Execute Schedule deliverable is defined as 60 days.
GSA Answer 1a: "Section 6 should read the same as Section 14.2 - PERIOD OF
PERFORMANCE date is: Three (3) months/90 days from Date of Award
(DOA)."
b. Section 7 - QUALITY ASSURANCE - The Execute Upgrade Schedule Acceptable
Quality Level (AQL) is defined as 60 working days.
GSA Answer 1b: Section 7 should read the same as "Section 14.2 - PERIOD OF
PERFORMANCE date is: Three (3) months/90 days from Date of Award
(DOA)."
2. Question 2: Under Section 17, FACTOR 2 – Can we use two projects performed for GSA on
GECO2? Or, should we look for examples outside of the GECO2 project?
GSA Answer 2: Yes, you may use GECO2-related projects from in or outside of GSA.
3. Question 3: Our team is concerned with the short timelines because SQL Server goes out of support on July 9, 2019.
GSA Answer 3: The due date for quotes has been changed (move up the date) from: June
20, 2019 to: Tuesday, Jun 18, 2019, not later than 3pm Eastern Time due to the urgency of the project milestone dates.