GEWA Water Operator SOW_Updated 62420.docx

DOCX document 365 KB Posted

Attached to
GEWA WATER PLANT OPERATOR Federal contract opportunity
Solicitation number
140P4220Q0053
Issued by
Department of the Interior National Park Service Northeast Region

View the file

Other files for this federal contract opportunity

Other files attached to GEWA WATER PLANT OPERATOR, newest first.
File Type Posted
Sol_140P4220Q0053.pdf PDF
WD 2015 4332 Rev.14.pdf PDF
Quote Worksheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Provide Waterworks and Wastewater Treatment Plant Operator to Monitor Water Systems for George Washington Birthplace National Monument

TABLE OF CONTENTS

GENERAL REQUIREMENTS

1. Summary of Work Contract Line

2. Items Meetings

3. Safety Requirements

APPENDIX

Appendix A:

1. National Park Service (NPS) Directors Order 83

2. Health.” NPS RM83A1 “Drinking Water”

Appendix B:

Waterworks and Wastewater Works Operators Regulations (18VAC160-30), Title 54.1, Chapter 23 (unofficial copy)

SUMMARY OF WORK

PART 1- GENERAL

1.1 SUMMARY:

1.2 George Washington Birthplace National Monument (GEWA), Washington’s Birthplace, VA 22443, operates one public water system.

The GEWA HQ Public Water System consists of one well, multiple pressure tanks, and a 55,000 gallon above ground storage tank, iron removal and chlorination equipment. The system serves the park administrative, housing and visitor center areas including the picnic grounds, maintenance and collection storage buildings. The work of this contract is to “Provide wastewater treatment operator services per the State of Virginia Required Testing of Water Systems”.

1. Provide Virginia State Licensed Operator for testing and submission of reports for the GEWA public water system. Contractor shall maintain a valid Waterworks Operator License during the entire contract period.

2. Provide wastewater sampling and reporting to include travel to sampling site, sampling wastewater, complete laboratory analysis, prepare and submit timely monthly regulatory reports per the state of Virginia and provide copies of said reports to Washington’s Birthplace National Monument for follow-up and filing.

3. Contractor responsibilities:

a. Advises and consults on the operation and maintenance of the water treatment plant.

b. Inspects the water treatment plant in accordance with permit requirements. Maintains current and up to date permits and licenses.

c. Reviews plant log records, gauges, meters, computer data tabulations, lab reports and

d. Other plants measuring and testing devices to verify that all equipment, including laboratory equipment, is functioning in accordance with the permit requirements.

e. Reviews, advises and consults on methods, and equipment used.

f. Assures that operations and procedures of the water and wastewater treatment systems comply with state and federal water quality regulations.

g. Provides review, completion, and signature for the monthly, quarterly, and annual State of Virginia water treatment plant submittals.

h. Contracted Licensed Operator Duties include:

The contracted licensed part time operator is on-site in accordance with permit requirements to provide administration, operational, and maintenance coverage of the Facility in order to assure continuous system operations. The operator oversees and/or performs sampling, monitoring and testing required to maintain compliance with Federal, State and Local regulations governing the water treatment process.

i. Water and Wastewater operator will be on site to ensure compliance with state and federal laws include waste water sampling and reporting to include travel to sampling site, providing all materials and equipment for sampling wastewater, transport samples to appropriate laboratory while ensuring integrity and chain of custody for the samples, complete laboratory analysis, prepare and submit monthly regulatory reports per the state of Virginia and provide copies of said reports to Washington’s Birthplace National Monument for follow-up and filing. Estimated number of hours per year is 180. Contractor shall bill on a monthly basis, in arrears, for actual hours worked.

1.3 DURATION OF THE CONTRACT/PERIOD OFPERFORMANCE

A. The estimated period of performance for this contract is:

1 July 2020-1 July 2021 with two (1) one-year option periods that may or may not be exercised at the discretion of the government.

1.4 LOCATION: The service location of the water system is on federal property (i.e. George Washington Birthplace National Monument), Washington’s Birthplace, Virginia 22443, Westmoreland County.

CONTRACTOR'S USE OF PREMISES:

A. Contractor services will be limited to the water plant and buildings that house the well pumps at well locations.

1. The Contractor’s service activities will not interfere with building access for National Park Service (NPS) operations outside the scope of services.

2. The NPS will not tolerate any deviation from the specifications noted in the safety plan for the operation of the water plant.

B. The Contractor will notify the park of their planned visits and work schedule. This procedure is necessary to prevent conflict with other Park operations.

C. The Contractor will at all times conduct their operations in a manner that is appropriate to the park setting and a professional workplace.

1. Use of AM/FM, satellite, or similar radios or other forms of entertainment systems is not permitted.

2. Loud noise will be kept to a minimum.

3. Conduct that is inappropriate to a professional workplace (e.g., crude language, yelling, fighting) is not permitted. The contractor must also abide by the requirements of Director’s Orders 16 E and F (Sexual Harassment and Harassment, respectively).

D. Nonsmoking Building: Smoking is not permitted in any building at any time. And must be done 25 feet from a door, window, or duct or vent.

1.5 WORK RESTRICTIONS

A. Vehicular Restrictions: Onsite parking for operations and testing will be at the water treatment plant.

1.6 SPECIAL REQUIREMENTS:

A. Regulatory Compliance:

1. Professional operations services for the potable water system must comply with all applicable federal, state, and local permits, regulations, and requirements, including the following (See Appendix A, B):

a. Code of Virginia Regulations: Title 54.1, Chapter 23, Waterworks and Wastewater Works Operators Licensing Regulations

b. National Park Service Directors Order 83, titled “Public Health.”, and NPS Reference Manuals 83A1 “Drinking Water”

B. Preservation of Natural and Cultural Features: All service operations will be confined to the public water system site.

C. Prior to start of work, the Contractor will examine work site/s with the Contracting Officer Representative (COR) to determine the conditions under which this work of the performed.

D. Temporary Controls:

1. Housekeeping:

a. The contractor is expected to keep project work site clean, orderly, and in a safe condition at all times.

b. The contractor is expected to collect any used materials, i.e.- containers, packaging, trash, etc., relevant to the work performed and remove from the site or deposited into the appropriate refuse or recycling containers provided by the park.

c. The contractor is expected to keep volatile wastes in accordance with Occupational Safety and Health Administration (OSHA) regulations.

2. Discarded and used equipment left on site becomes the property of the NPS for disposal in accordance with federal property policies.

1.7 Technical Qualifications:

E. Operator Services Qualifications: A firm that employs personnel, including supervisory personnel, in licensed operations indicated and required by Virginia Department of Environment regulations, specifically Code of Virginia Regulations : Code of Virginia Regulations: Title 54.1, Chapter 23, Waterworks and Wastewater Works Operators Licensing Regulations.

1. Virginia Licensed Water Operator, Level 3- Minimum F. The contractor will provide current copies of state licenses of the operators to the Contracting Officer for approval within three, (3), business days after date of award.

G. Copies of current Operator licenses will be posted at the GEWA water treatment plant.

H. All required licenses will be maintained and kept current for the duration of this contract.

DEFINITION OF CONTRACT, LINE ITEM

PART 1: GENERAL

1.1 SUMMARY

A. The intent of this section is to describe components of work by contract line item.

B. If no contract line item exists for a portion of the work, include the costs in a related item. PART 2: PRODUCTS N/A.

PART 3: EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 00010 –Licensed operations of one public water system as defined by Section 1.2 herein.

PART 4: MEASUREMENT AND PAYMENT

A. Invoices will be submitted monthly for the previous month’s work, in arrears, and by the unit prices identified in the schedule. Contractor will provide the COR a draft invoice prior to submitting in Invoicing Processing Platform (IPP). Once the COR reviews, signs, and approves the invoice. The contractor should submit it in IPP.

END OF SECTION

PROJECT MEETINGS AND COMMUNICATION

PART 1: GENERAL

1.1 SUMMARY

A. Contractor will attend and participate in monthly meetings as defined below in section 1.2.

B. Contractor will adhere to communication protocols as defined in section 1.3.

1.2 MEETINGS AND INSPECTIONS:

A. A start up meeting will be held prior to commencement of this contract. The meeting will include the contractor, COR, and Chief of Maintenance.

B. Monthly Meetings: The COR will schedule on-site meetings with the Contractor.

C. All operational inspections, monitoring, and sampling will be conducted in accordance Virginia specifications D. LOCATION: Meetings will be held at the GEWA Water Plant, unless otherwise determined by the COR.

1.3 PROJECT COMMUNICATION:

A. Required communication with local and state agencies will be in strict compliance with applicable permits and regulatory requirements identified above. The COR and CO will be copied on all communication with these entities and hard copies of these communications will be filed in the park water treatment plant office.

SAFETY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

B. The contractor will adhere to both federal and state safety and health requirements when working on site.

1.2 QUALITY CONTROL

A. In case of conflicts between federal and state safety and health requirements, the most stringent requirements will apply. Equipment or tools not meeting OSHA requirements are not allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

1.3 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. The COR is to be notified immediately in the event of any reportable accident. Within 7 days of a reportable accident, t h e contractor must fill out and forward to the COR an Accident/Property Damage Report (Form CM-22). Form may be obtained from the COR.

1.4 CONTRACT EMPLOYEE SITE SECURITY

A. The park will require that all contractor and subcontractor employees working on NPS property be properly identified with proper identification.

PART 2 – PRODUCTS

2.1 FIRST AID FACILITIES

A. The park will provide adequate facilities for the number of employees and the hazards associated with the types of ongoing operations at the site.

2.2 PERSONAL PROTECTIVE EQUIPMENT

A. The contractor will provide all contract personnel with appropriate personal protective equipment (PPE). All PPE will meet requirements of applicable ANSI standards.

PART 3 EXECUTION

3.1 EMERGENCY INSTRUCTIONS

A. The park has provided posted telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.2 FIRE AND LIFE SAFETY

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

B. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain readily available, on site, MSDS/SDS for each chemical.

1. Immediately report all spills of hazardous materials to the park.

2. The park will maintain a spill emergency response kit at the water treatment plant.

3.3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS

A. Review safety issues and concerns at the monthly meeting with follow-up as needed by the COR.

3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. A hard hat area will be designated by the park. The hard hat area will be posted by the park B. It is the contractor’s responsibility to require all contract employees working on or visiting the site to wear hard hats and other necessary personal protective equipment at all times.

APPENDICES

Appendix A:

· National Park Service (NPS) Directors Order 83, titled “Public Health.”

· NPS RM83A1 “Drinking Water”

Appendix B:

· Waterworks and Wastewater Works Operators Regulations (18VAC160-30), Title 54.1, Chapter 23 (unofficial copy), section 18VAC160-30-360 and 18VAC160-30- 370.

Appendix A

DIRECTOR'S ORDER #83: PUBLIC HEALTH

Approved: /s/ Donald W. Murphy (signed original on file) (for) Director

Effective Date: October 21, 2004

Sunset Date: October 21, 2010

This renewed edition of Director's Order #83 is essentially the same as the edition that was scheduled to sunset August 3, 2007. The only revision is in Section B.6, which now allows park unit managers to consider for front country use suitable alternate wastewater systems ( such as composting and evaporative toilets), in consultation with the assigned Regional Public Health Consultant or Park Environmental Health Officer/Sanitarian.

Index

I. Background and Purpose II. Authority III. General Policy IV. Operational Policies and Procedures A. Drinking Water B. Wastewater C. Food Safety and Sanitation D. Recreational Waters E. Illness Surveillance and Management F. Backcountry Operations G. Vectorborne and Zoonotic Diseases

I. Background and Purpose

The National Park Service hosts nearly 300 million visitors to the national parks each year. To provide for visitor enjoyment of the parks, the NPS operates (directly or indirectly) water supply systems, waste management systems, food service operations, bathing beaches, swimming pools and overnight accommodations. In most cases, there are Federal, State and/or local codes--designed to protect the public health--that govern the conditions under which these facilities and services are provided. To ensure these facilities and services are operated in a safe and healthful manner and according to existing public health laws and regulations, the NPS Public Health Program (PHP) conducts health risk and environmental compliance assessments. The PHP provides technical assistance to parks on request. PHP staff provides training to NPS personnel in the recognition and management of health risks, and provides health awareness information in the form of factsheets, messages in the Operational Notes section of the Ranger Morning Reports, and on its NPS internet website (http://www.nps.gov/public_health/) and the Inside Public Health intranet website (http://www.nps.gov/public_health/intra/).

The purpose of this Director's Order is to outline what the NPS will do to ensure compliance with prescribed public health policies, practices and procedures. This order establishes NPS policy with respect to all public health activities within areas of NPS jurisdiction, regardless of whether those activities are carried out by NPS or other Federal employees, or by other organizations, including the U.S. Public Health Service (PHS). The core PHP includes prevention, control and investigation of food-, water-, and vector-borne diseases in the national parks.

This Director's Order, and Reference Manual 83 (RM83), supersede and replace Director's Order-83 dated August1998 and any other previously issued policy or procedural statements that may be at variance with the policies and procedures stated herein. It applies to all facilities and services provided in the parks, whether by the NPS directly, or by concessioners, leaseholders, or permittees.

II. Authority

The authority to issue this Director's Order is contained in 16 U.S.C. 1 through 4 (the National Park Service Organic Act), and Part 245 of the Department of the Interior Manual.

III. General Policy

A. It is the policy of the NPS to protect the health and well-being of NPS employees and park visitors through the elimination or control of disease agents and the various modes of their transmission to man and to ensure compliance with applicable Federal, State and local public health laws, regulations and ordinances. Implementation of this policy will be tempered by the Organic Act's requirement that the NPS conserve the scenery and natural and historic objects and the wildlife therein in such manner and by such means as will leave them unimpaired for the enjoyment of future generations.

B. The Associate Director, Visitor and Resource Protection, will issue RM83 to provide more detailed information on the public health policies, practices, procedures and standards that park managers must adhere to in providing facilities and services to the public.

C. Based on the unique circumstances and conditions of National Park Service sites, the Public Health Consultant (PHC) has the discretion to recommend adaptations to these requirements considering specific site conditions and relevant authority under the law.

IV. Operational Policies and Procedures

A. Drinking Water

NPS unit managers will reduce the risk of waterborne diseases and provide safe drinking water to employees, the visiting public, and park partners by assuring that drinking water systems are properly operated, maintained, monitored, and deficiencies promptly corrected. Water systems will be regulated in accordance with 1) the Safe Drinking Water Act, as amended (42 U.S.C. 7401 et seq.), or

2) thePrimacy Agency (e.g. the agency designated by Federal law as having oversight responsibility). Additional guidance for non-public or other unregulated water systems is provided in RM83(A1).

A.1 All parks that operate public drinking water systems will have certified operators as required by the primacy agency. Parks that operate only non-public drinking water systems will have appropriately trained operators.

A.2 NPS unit managers will develop training plans and assure that operators receive any required and/or appropriate training.

A.3 NPS unit managers will assure that required records are maintained in permanent files for periodic review by the regional Public Health Consultant (PHC) or Primacy Agency representatives, and that reports are submitted on a timely basis as requested by the PHC and/or the Primacy Agency.

A.4 Bacteriological and chemical sampling will be performed in accordance with Federal, State and local laws/regulations. In the absence of Federal, State and local regulation, systems will comply with the requirements of RM83 (A1).

A.5 All water samples will be tested in laboratories certified by the Primacy Agency.

A.6 All surface water sources and any groundwater sources under the direct influence of (GWUDI) surface water, as determined by the Primacy Agency for public systems will be provided with approved filtration. Non-public surface water sources and groundwater sources under the direct influence of (GWUDI) surface water, as determined by the PHC, will be provided with approved filtration.

A.7 All public drinking water systems will be continuously disinfected. Acceptable disinfecting methods are those which provide a measurable disinfectant residual in the distribution system. The PHC may specifically exempt non-public systems after a complete sanitary survey of the system is made.

A.8 For park-operated, public drinking water systems utilizing a chemical disinfectant, one (1) disinfectant residual sample will be measured and recorded per day from representative points. Parks operating non-public drinking water systems or receiving water from municipalities should contact the PHC for residual monitoring guidance.

A.9 Sanitary surveys for State regulated, public drinking water systems will be conducted in accordance with Primacy Agency requirements. The PHC may conduct sanitary surveys of unregulated and/or non-public water systems.

A.10 All parks operating drinking water systems will have a documented cross connection control program on file for review by the Primacy Agency and/or the PHC (See RM83 (A2)).

A.11 Water for all NPS water hauling operations, whether conducted by the park or a private contractor, will be obtained from an approved water source that meets the requirements of the Safe Drinking Water Act.

A.12 All parks will comply with the public notification requirements of the Safe Drinking Water Act.

A.13 When drinking water system modifications or new construction is proposed, parks will contact the Primacy Agency to determine if plans and specifications should be submitted for approval. A copy of the plans and specifications will be provided to the PHC upon request.

A.14 Potable water for backcountry operations must be 1) obtained from an approved public system,

2) boiled, or 3) filtered and disinfected.

B. Wastewater

NPS unit managers will reduce the risk of waterborne diseases and provide safe wastewater disposal by ensuring wastewater systems are properly operated, maintained, monitored, and deficiencies promptly corrected. Wastewater systems will be in compliance with 1) the Clean Water Act, as amended (33 U.S.C. 1251 et seq or 2) the Primacy Agency (e.g. the agency designated by Federal law as having oversight responsibility). Additional guidance for non-public or other unregulated wastewater systems is provided in RM83 (B1).

B.1 NPS unit managers will ensure operators are adequately trained and certified in accordance with operator requirements of the Primacy Agency. Park managers will designate, in writing, primary operators, and backup operators who have adequate training and skills to operate the system(s). Parks that operate only individual, on-site wastewater systems will have appropriately trained operators.

B.2 NPS unit managers will develop training plans and assure that operators receive any required and/or appropriate training.

B.3 NPS unit managers will assure that required records are maintained in permanent files for periodic review by the PHC or Primacy Agency representatives and that reports are submitted on a timely basis as requested by the PHC and/or required by the Primacy Agency.

B.4 When wastewater system modifications or new construction are proposed, parks will submit plans and specifications to the Primacy Agency for approval. A copy of the plans and specifications will be provided to the PHC.

B.5 All wastewater facilities will be installed, operated and monitored in accordance with Primacy Agency requirements.

B.6 Typical front country wastewater systems include flush toilets, vault toilets, and chemical toilets (used only for temporary purposes). Where conditions are suitable, alternate wastewater systems, such as composting and evaporative toilets may be considered for front country use. Park unit managers must contact the assigned Regional Public Health Consultant or Park Environmental Health Officer / Sanitarian for guidance and advice when planning to install, upgrade, or make substantive changes to any wastewater system. All wastewater systems must be installed and operated according to the manufacturer's instructions and in compliance with Primacy Agency requirements.

B.7 Suitable backcountry waste systems include flush toilets; composting toilets; barrel toilets; evaporator toilets; incinerator toilets and pit privies. Pit privies should only be used as a last resort where other types of facilities are not possible. The Park Sanitarian or the PHC should conduct the siting of pit privies.

B.8 All new vault toilets will incorporate the U.S. Forest Service Sweet Smelling Toilet (SST) design features. Vault toilets will be pumped as necessary. The U.S. Forest Service In-Depth Design and Maintenance Manual for Vault Toilets is provided in RM83 (B2).

B.9 All toilet facilities will be cleaned and re-supplied as often as necessary to maintain a high degree of sanitation. The U.S. Forest Service guidance manual Cleaning Recreation Sites is provided in RM83 (B3).

B.10 Adequate sanitation facilities will be required for remote areas such as river rafting, horseback riding, back country biking, backpacking and similar activities in accordance with RM83 (F).

B.11 Septic tanks shall be inspected annually to determine the amount of accumulated scum and sludge. Records of septic tank measurements, inspections, and pumping will be available for review by the PHC. Septic tank risers will be provided for inspection holes to facilitate inspection and pumping. Septic tanks will be pumped when the scum and or sludge levels in the tank dictate (generally every 3- 5 years). The bottom of the scum should never be closer than 3 inches to the bottom of the outlet device, and the top to the sludge layer should never be less than 8 inches from the bottom of the outlet device.

B.12 Septic tank drain fields shall be surveyed annually during a high use period to identify system failures such as odors and surfacing wastewater. The drain field should be kept clear of trees and bushes, which may send roots into the drain field piping system resulting in clogging and causing premature failure.

B.13 Personnel who routinely come into contact with sewage, work in, or inspect wastewater treatment facilities, lagoons, etc. will have a current immunization for tetanus.

B.14 Wastewater treatment plant personnel will not eat, drink or smoke when performing maintenance or inspecting equipment, which may be contaminated with human sewage.

B.15 In the event of a major wastewater leak or spill, the PHC will be notified within one business day. Facilities and equipment contaminated with sewage as a result of leaks, spills, and sewage system backflow will be thoroughly washed down with water and detergent. Further guidance is provided in RM83 (B4) - Raw Sewage Spill Notification and Cleanup

C. Food Safety and Sanitation

NPS unit managers will reduce the risk of foodborne illness to employees, the visiting public, and park partners by ensuring that all food service facilities are operated in accordance with the most recent edition of the FDA Food Code, unless specifically exempted by PHC, and DO48. Food operations include but are not limited to NPS operations, concessioner operations, special events, incidental business permit operations and emergency incidents. The FDA Food Code is provided in RM83 (C1).

C.1 All permanent food service facilities will be inspected according to schedules established by the PHC and concession program manager.

C.2 Temporary food service operations (stationary and non-stationary facilities) will meet the same general requirements as permanent facilities by complying with the FDA Food Code and consultin with the regional PHC to determine additional recommendations and alternative compliance options to the Food Code. See RM83 (C2) for additional guidance on temporary food service operations and RM83 (F) for backcountry operations.

D. Recreational Waters

NPS unit managers will reduce the risk of waterborne diseases by ensuring that recreational water sites are properly operated, maintained and monitored in accordance with state or local regulations.

Deficiencies will be promptly corrected with applicable state/local regulations. In the absence of applicable state or local regulations, the following NPS policies will apply.

D.1 Bathing Beaches. NPS unit managers will reduce the risk of waterborne diseases by ensuring designated bathing beaches are properly operated, maintained and monitored. Deficiencies will be promptly corrected, in compliance with the Beaches Environmental Assessment and Coastal Health Act of 2000 and applicable state/local regulations. In the absence of applicable state or local regulations, the following NPS policies will apply. Bathing beaches can be located at lakes, rivers, oceans, hot springs, and other bodies of water. Additional guidance is provided in RM83 (D1). The complete Beaches Environmental Assessment and Coastal Health Act of 2000 can be accessed at: http://www.epa.gov/ost/beaches/beachbill.pdf.

a. Bathing beach monitoring is required for each designated beach. Designated beaches are those that the Park has identified (using signs, brochures etc.) as available to the public for contact recreational water activities. Monitoring is recommended for other areas that are heavily used (40 or more people per 100 linear feet of shoreline). Specific requirements of the monitoring program include:

(1) Conducting a sanitary survey;

(2) Preparing a bathing beach monitoring protocol. This protocol includes the names of areas to be sampled; sampling station locations; a map or sketch of each area showing the location of each sampling station; bacterial standard used; and the name of the laboratory doing the bacterial analyses;

(3) Sampling for enterococcus or Escherichia coli bacteria levels; and

(4) Issuing swimming advisories when bathing beach waters exceed the bacterial standards.

b. A copy of the bathing beach monitoring plan and current bathing beach sanitary survey report will be sent to the PHC for review and concurrence approximately 1 month before the beginning of the recreational season.

c. Samples will be collected in conformance with the most recent edition of Standard Methods for the Examination of Water and Wastewater.

d. Analyses will be done in conformance with the most recent edition of Standard Methods for the Examination of Water and Wastewater. Parks that have their own laboratory should meet state certification requirements. Parks that do not do their own sample analyses will use a certified microbiological laboratory.

e. Parks will submit bacteriological sampling results to the PHC.

f. When the applicable bacterial density standard is exceeded, Park managers will report the bacterial density results to the PHC and the applicable state agency. Advise the PHC, applicable state agency and the local news media that a health advisory regarding the affected area will be posted. The advisory will notify the public of the potential health risks from swimming at the designated beach. The affected beach will be re-sampled immediately by taking two samples each day at each sampling location where the bacterial standard was exceeded. Re-sampling will be continued until the bacterial standard is not exceeded for two consecutive days. The PHC can waive this re-sampling requirement. Resume routine monitoring and notify the PHC, the local public health agency and the news media of the decision to reopen the beach. All signs should be removed.

D.2 Swimming Pools. NPS unit managers will reduce the risk of waterborne illness by ensuring that NPS and concessioner swimming pools are properly constructed, operated, maintained, monitored, and deficiencies promptly corrected in accordance with applicable state or local regulations. In the absence of applicable state/local regulations, the NPS has adopted "The National Pool and Spa Institute's ANSI Standard for Public Swimming Pools" as policy. A copy of this standard is provided in RM83 (D2).

D3. Spa and Hot Tubs. NPS unit managers will reduce the risk of waterborne diseases by ensuring that NPS and concessioner run spas and hot tubs are properly constructed, operated, maintained, monitored, and deficiencies promptly corrected in accordance with applicable state or local regulations. In the absence of applicable state/local regulations, the NPS has adopted "The National Pool and Spa Institute's ANSI Standard for Public Spas" as policy. A copy of this standard is provided in RM83 (D3).

E. Illness Surveillance and Initial Response

NPS unit managers will reduce the risk of waterborne, foodborne and vectorborne diseases by designating, in writing, a person responsible for implementing and coordinating the Illness Surveillance and Initial Response Program. Responsibilities include maintaining reporting logs, notifying PHC's or WASO Public Health when a suspected outbreak is occurring, and coordinating, at the park level, the appropriate response. When a Sanitarian or Environmental Health Specialist is located in the park, that person should be designated as the Illness Reporting Program Coordinator. A copy of the written designation will be provided to the PHC. Additional guidance is provided in RM83 (E).

E.1 When a foodborne, waterborne, vectorborne or occupational illness is suspected, the Illness Surveillance and Initial Response Coordinator will contact the PHC for advice and support. At the direction of the PHC, request assistance from applicable local, state, or Federal public health agencies that are staffed with trained public health professionals. Depending upon park jurisdiction, federal agencies will respond only at the request of local health departments.

E.2 NPS unit managers will take any appropriate steps to restrict or close, in whole or in part, any establishment, facility, or operation when evidence suggests an outbreak of disease may be occurring, or recurring. These steps may include the closure of the entire park or portion thereof where conditions warrant. This authority may be found in 36 CFR 1.5. Such a decision should be made after careful consideration of all facts, and in consultation with the PHC, the Illness reporting Coordinator, and involved local/state/federal health officials.

E.3 NPS unit managers and/or the Public Affairs Officer will decide when or if a news media release is appropriate.

E.4 The Illness Surveillance and Initial Response Coordinator, and where appropriate, dispatch centers, district rangers, and NPS unit managers will maintain a list of applicable telephone numbers for PHC's and applicable local and state health agencies.

E.5 The park concession office will be notified when an illness investigation is conducted in a concessioner's facility.

E.6 Persons who complain of illness while in a park will be referred to a health care provider for evaluation, and possible laboratory confirmation.

E.7 For guidance on collecting, storing, shipping and analysis of samples, the Illness Reporting Coordinator will consult with the PHC or local/state/federal consultants contacted for support.

E.8 The Illness Surveillance and Initial Response Coordinator will keep the NPS unit manager informed of the status of the investigation. A written summary of the investigation should be submitted to the NPS unit manager, with a copy to the PHC within 30 days. The report should include pertinent information such as the number of ill persons, symptoms, diagnosis (confirmed or suspect), duration of outbreak, action taken, conclusions, and recommendations to prevent similar outbreaks from occurring.

F. Backcountry Operations

NPS unit managers will reduce the risk of waterborne, foodborne and vectorborne diseases by ensuring that all backcountry water, wastewater and food operations (NPS, concessioner, special events, incidental business permits and emergency incidents) are operated in accordance with current Public Health regulations and policies. Additional guidance is provided in RM83 (F).

F.1 Potable water for backcountry operations must be 1) hauled from an approved public system, or

2) boiled, or 3) filtered and disinfected.

F.2 Adequate sanitation facilities are required for remote activities such as trail maintenance, firefighting, ranger stations, river rafting, and horseback riding, backcountry biking, backpacking, and similar activities.

F.3 NPS Park Managers will ensure that all backcountry food service operations (stationary and non- stationary facilities) meet the same general requirements as permanent facilities by complying with the FDA Food Code and consulting with the PHC to determine additional recommendations and alternative compliance options to the FDA Food Code.

G. Vectorborne and Zoonotic Disease

G.1 NPS unit managers will reduce the risk of transmission of vector-borne and zoonotic diseases to park visitors and employees through education, surveillance, and control efforts when necessary. Control procedures will reduce risk while minimizing adverse impact on natural and cultural resources. The NPS will follow an integrated pest management approach in addressing vector-borne disease issues as outlined in Director's Order 77-7.

G.2 At minimum, parks shall establish a point of contact at the local public health and/or vector-borne disease control agency in order to keep up to date on potential and current trends in vector-borne disease prevalence in and around the park. Some parks may need to assign an individual to coordinate vector-borne disease issues based on an elevated risk and the recommendation of the PHC.

G.3 The designated park staff member responsible for addressing vector-borne and zoonotic disease issues will have the responsibility to implement the recommendations of the PHC. Whenever possible, this individual should be the park Integrated Pest Management (IPM) coordinator or the park sanitarian. The duties and responsibilities may include:

· Coordinate with local and state departments of health, PHC, and IPM program coordinator.

· Ensure educational materials are available for park staff and visitors and conduct or coordinate preventive education and training sessions.

· Establish and maintain a passive surveillance program within the park.

· Coordinate active surveillance activities within the park.

G.4 Guidance and information will be provided on specific diseases by the Zoonotic, Vector-borne and Environmentally Transmitted Disease (ZED) Steering Committee, a collaborative effort of the Biological Resource Management Division, Public Health and Risk Management Programs. Further information on ZED can be found at http://www.nps.gov/public_health/zed/zed.htm.

----------End of Director's Order----------

Appendix A

REFERENCE MANUAL 83A1 DRINKING WATER

Contents

A.
Drinking Water Policy
2
B.
Water System Definitions
3
C.
Bacteriological Monitoring
4
D.
Chemical Monitoring
6
E.
Lead and Copper
9
F.
Radionuclides
10
G.
Water Treatment
10
H.
Operator Requirements
16
I.
Sanitary Surveys
16
J.
Cross Connection Control
17
K.
Potable Water Hauling
17
L.
Reports and Records Retention
17
M.
Water Conservation
18
N.
Payment of Fees for Service
18
O.
Public Notification
18
P.
Plan Review and Approval
19
Q.
Potable Water for Backcountry Operations
19
R.
Consumer Confidence Reports
20
S.
Drinking Water Security and Emergency Preparedness
20
T.
General Definitions
21

Table 1

Total Coliform Sample Requirements for Public Systems

Table 2
National Primary Drinking Water Standards
24
Table 3
National Secondary Drinking Water Standards
39
Table 4
General Minerals
40
Table 5
Summary of Monitoring Requirements
41

A. DRINKING WATER POLICY

NPS Unit Managers will reduce the risk of waterborne diseases and provide safe drinking water to employees, the visiting public, and park partners by assuring that drinking water systems are properly operated, maintained, monitored, and deficiencies promptly corrected. Drinking water systems will be regulated in accordance with 1) the Safe Drinking Water Act, as amended (42 U.S.C. 7401 et seq.), or 2) the Primacy Agency (e.g. the agency designated by Federal law as having oversight responsibility). Additional guidance for non-public or other unregulated drinking water systems is provided in RM83 (A1).

A.1 All parks that operate public drinking water systems will have certified operators as required by the primacy agency. Parks that operate only non-public drinking water systems will have appropriately trained operators.

A.2 NPS Unit Managers will develop training plans and assure that operators receive any required and/or appropriate training. NPS Unit Managers will assure that required records are maintained in permanent files for periodic review by the regional Public Health Consultant (PHC) or Primacy Agency representatives, and that reports are submitted on a timely basis as requested by the PHC and/or the Primacy Agency.

A.3 Bacteriological and chemical sampling will be performed in accordance with Federal, State and local laws/regulations and will comply with the requirements of RM83(A1).

A.4 All water samples will be tested in laboratories certified by the Primacy Agency.

A.5 All surface water sources and any groundwater sources under the direct influence of (GWUDI) surface water, as determined by the Primacy Agency for public systems will be provided with approved filtration. Non-public surface water sources and groundwater sources under the direct influence of (GWUDI) surface water, as determined by the PHC, will be provided with approved filtration.

A.6 All public drinking water systems will be continuously disinfected. Acceptable disinfecting methods are those which provide a measurable disinfectant residual (minimum .2 mg/l free chlorine, optimum range is .5 to 1.0 mg/l free chlorine) in the distribution system. The PHC may specifically exempt non-public systems after a complete sanitary survey of the system is made.

A.7 For those park operated, public drinking water systems utilizing a chemical disinfectant, one (1) disinfectant residual sample will be measured and recorded per day from representative points. Parks operating non-public drinking water systems or receiving water from municipalities should contact the PHC for residual monitoring guidance.

A.8 Sanitary surveys for State regulated, public drinking water systems will be conducted in accordance with Primacy Agency requirements. The PHC may conduct sanitary surveys of unregulated and/or non-public water systems.

A.9 All parks operating drinking water systems will have a documented cross connection control program on file for review by the Primacy Agency and/or the PHC(See

RM83 (A2)).

A.10 Water for all NPS water hauling operations, whether conducted by the park or a private contractor, will be obtained from an approved water source that meets the requirements of the Safe Drinking Water Act.

A.11 All parks will comply with the public notification requirements of the Safe Drinking Water Act.

A.12 When drinking water system modifications or new construction are proposed, parks will contact the Primacy Agency to determine if plans and specifications should be submitted for approval. A copy of the plans and specifications will be provided to the PHC upon request.

A.13 Potable water for backcountry operations must be 1) obtained from an approved public system, 2) boiled, or 3) filtered and disinfected.

A.14 Appropriate training requirements for non-certified operators will be described in park policy that is reviewed and approved by the Regional Public Health Consultant.

A.15 All parks operating drinking water systems will have an Operations and Maintenance Plan and an Emergency Management Plan.

B. WATER SYSTEM DEFINITIONS

B.1
Public Water System (PWS):
A system which provides water to the public for human consumption through pipes or “other constructed conveyances, if such system has at least 15 service connections or regularly serves an average of at least 25 individuals daily at least 60 days per year”.
B.2
Community Water System (CWS):
A public water system that serves at least 15 service connections used by year-round residents or regularly serves at least 25 year-round residents.
B.3
Non-Transient Non-Community Water System (NTNC):
A public water system that is not a [CWS] and that regularly serves at least 25 of the same persons over 6 months per year. Examples: Systems

serving facilities such as schools or non-residential work sites where the same people use the water on a regular basis.

B.4
Transient Non-Community Water System (TNC):
Any public water system not described in 1 or 2 above that serves more than 25 persons per day at least sixty days out of the year. Examples: systems serving campgrounds or other non-residential areas not used by at least 25 of the same persons over 6 months a year.
B.5
Non-Public Water Systems (NP):
A water system that serves less than 15 service connections, or an average of less than 25 of the same persons per day. Examples could include

systems serving ranger stations, individual residences and small campgrounds.

C. BACTERIOLOGICAL MONITORING

Definitions of the systems described below, as well as definitions of other terms used in this guideline are listed above and on pages 21-22.

C.1 Number and Frequency of Samples:

a. Community Water Systems [CWS]: Two samples per month, minimum, or as per Table 1 (Page 23). Samples must be taken at equally spaced intervals two times per month.

b. Non-Community Water Systems [NTNC & TNC]: Two samples per month, minimum, or as per Table 1 (Page 23). Samples must be taken at equally spaced intervals two times per month.

c. Non-Public Water Systems [NP]: One sample per month. The sampling frequency may be changed if authorized in writing by the PHC. This authorization will only be given after a complete sanitary survey and review of the operational records indicates a reduced sampling frequency would not increase risk to end-users.

C.2 Special Sampling Requirements:

a. Seasonal systems: Seasonal systems must obtain two consecutive, negative samples prior to utilization of the system. Samples may be collected on the same day, but not at the same time and must be collected at different sampling sites according to the site- sampling plan, if applicable.

b. Source water monitoring: Some Primacy Agencies require periodic source (raw) water monitoring. Sampling of source water must be in accordance with the Primacy Agency requirements.

c. Municipal supplies: National Park Service operated distribution systems serviced by municipal systems should be included in the municipality’s bacteriological sampling programs whenever feasible. When the municipality does not monitor a distribution system, the PHC should be contacted to determine if and when the system requires sampling.

C.3 Site-sampling plan: Each system must have a written site-sampling plan available for review by the Primacy Agency, and/or the PHC. All bacteriological samples must be collected from identified sampling sites.

C.4 Positive samples: All positive total coliform samples require that the system operator obtain repeat samples in accordance with the Primacy Agency or at a minimum the following:

a. Public systems: Three repeat samples must be collected within 24 hours of laboratory notification of the positive result. One sample must be collected at the site of the positive sample, and one sample collected upstream and one downstream of the positive sample site, each within 5 service connections of positive sample site. In addition, a minimum of five samples must be collected the following month. NOTE: This includes public non-community systems.

b. . Non-public systems: Two repeat samples must be collected and analyzed. One sample must be collected at the site of the positive sample.

C.5 Non-compliance - Public Systems: If any repeat samples are positive, the park must notify the Primacy Agency and the PHC by close of business of the day following receipt of notification of sample results. If the repeat test results indicate a fecal coliform or an E.coli contamination, public notification and corrective action must be taken immediately. The Park must contact the Primacy Agency for their concurrence on the content and method to be used in notifying the public. The Primacy Agency and the PHC must be contacted for assistance in determining the source of the contamination and in implementing corrective action.

Public notification is required if the requisite number of samples is not collected, or if more than one routine sample per month is positive for total coliform. Coordination with the Primacy Agency and/or the PHC is required.

C.6 Non-compliance - Non-Public Systems: The procedure described for public systems must be followed except that notification and involvement of the Primacy Agency is not required.

D. CHEMICAL MONITORING

The monitoring requirements in this section may be waived for non-public and/or unregulated systems if authorized, in writing, by the PHC. This authorization will only be given after a complete sanitary survey of the system and review of the operational records indicates a reduced sampling frequency or waiver would not increase risk to end-users.

Systems connected to municipal supplies are not required to perform chemical monitoring if current analyses are available from the municipality. If current analyses are not available, the Park may be requested by the PHC to perform the analyses.

Monitoring requirements are as shown in Table 5: National Park Service Water Systems Routine Monitoring Requirements.

For a complete overview of the EPA National Primary Drinking Water Standards go to: http://www.epa.gov/safewater/standards.html

D.1 Primary, secondary, and general mineral: Primary inorganic, secondary inorganic and general mineral analyses must be conducted to meet regulatory requirements and/Orto determine the most feasible treatment methodologies to provide water of satisfactory quality. Samples shall be collected from the source before treatment. NOTE –Nitrates are required annually for all sources.

For more information on inorganic chemicals, specific rule information, compliance dates, and regulatory updates, go to: http://www.epa.gov/safewater/mcl.html#inorganic

D.2 Organics:

a. Pesticides, Herbicides & PCB's: All public community and public non-transient non-community systems must be sampled annually unless a State or Primacy Agency waiver has been issued. All public non-community (transient users only) and non-public systems must be sampled one time. Additional sampling requirements are dependent upon the initial sampling results and source vulnerability. Samples should be collected after treatment and prior to entry to the distribution system.

b. Volatile Organic Chemicals (VOC): There are fifty-five VOC's that have MCL's (regulated or unregulated) that must be analyzed.