Georges Creek WWRF EQ - Technical Specification Division I - IFB 9-25-26.pdf
PDF 8 MB Posted
- Attached to
- Georges Creek WRRF EQ Upgrades Division I RFB
- Solicitation number
- 146891
- Issued by
- Greenville County, South Carolina
About this file
This is a technical specification document for Division I general requirements of the Georges Creek Wastewater Reclamation Facility (WRRF) Equalization (EQ) Basin Upgrades project, prepared for Renewable Water Resources in Greenville, South Carolina, with HUD Community Project Funding (B-23-CP-SC-1362). The project encompasses electrical and instrumentation modifications, mechanical and structural improvements to the EQ basin including eight 15 HP floating mixers, an 18-inch diversion force main installation, concrete lining of the existing effluent basin, site grading, erosion control, and associated appurtenances. Work must be performed with minimal inconvenience to the existing water reclamation facility, requiring coordination with the Owner's operations and compliance with all applicable federal, state, county, and municipal codes. The specifications establish requirements for construction staking, measurement and payment on a lump sum basis for general construction, yard piping, basin upgrades (concrete liner, floating mixers, electrical, and gravel access drive), and an instrumentation and controls integration allowance. A pre-construction conference must be held before work commences, and the Contractor must submit a preliminary construction schedule within ten days of Notice to Proceed, with monthly updates throughout the project duration.
Payment will be made by extending unit prices multiplied by quantities or through established lump sum amounts as indicated in the Bid Form, with all costs for mobilization, demobilization, bonds, insurance, temporary facilities, erosion and sediment control, site cleanup, and incidental work included in the bid prices. The Contractor bears responsibility for obtaining all necessary permits, developing a comprehensive site-specific Health and Safety Plan, and providing continuous treatment to prevent wastewater bypass during construction. Federal requirements apply due to HUD funding, including procedures to ensure consideration of small businesses, minority businesses, women's business enterprises, veteran-owned businesses, and labor surplus area firms in accordance with 20 CFR 200.321. The project does not have Davis-Bacon or Build America Buy America requirements. Testing services required by the specifications will be paid by the Owner, while retesting of failed items will be the Contractor's expense. Shop drawings must be submitted electronically in PDF format or as hard copies with minimum 30-day review periods by the Engineer prior to installation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
GEORGES CREEK WWRF
EQ UPGRADES
DIVISION I
HUD FUNDING # B-23-CP-SC-1362
September 2026
Prepared for:
Renewable Water Resources (ReWa)
Greenville, South Carolina
KCI Project No:
00013511_005
ISSUED FOR BIDS
THIS PAGE INTENTIONALLY LEFT BLANK
GEORGES CREEK WWRF
EQ UPGRADES DIVISION I
HUD FUNDING # B-23-CP-SC-1362
Prepared for Renewable Water Resources
Greenville, South Carolina
KCI Project No. 00013511_005
September 2026
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
TOC- 1 Renewable Water Resources
TABLE OF CONTENTS
DIVISION 1 – GENERAL REQUIREMENTS
SECTION TITLE
01010 Summary of Work
01016 Occupancy
01025 Measurement and Payment
01055 Construction Staking
01060 Regulatory Requirements
01091 Codes & Standards
01140 Maintenance of Plant Operations
01200 Project Meetings
01297 Schedule of Values
01320 Construction Project Schedule
01340 Shop Drawings, Product Data & Samples
01350 Safety Requirements
01410 Testing Laboratory Services
01500 Temporary Facilities
01540 Job Site Security
01562 Dust Control
01610 Transportation & Handling
01611 Storage and Protection
01640 Product Handling
01650 General Equipment Requirements
01660 Technical Services
01700 Contract Closeout
01710 Cleaning
01720 Project Record Documents
01740 Warranties and Bonds
DIVISION 2 – SITE CONSTRUCTION
02010 Subsurface Investigation
02060 Demolition
02110 Clearing and Grubbing
02220 Excavating/Backfilling for Structures
02221 Trenching & Backfilling for Utilities
02240 Dewatering
02260 Erosion and Sediment Control
02310 Site Grading
02444 Chain Link Fence
TOC- 2 Renewable Water Resources
DIVISION 2 – SITE CONSTRUCTION (continued)
SECTION TITLE
02511 Crushed Stone Paving
02513 Asphaltic Concrete Paving
02930 Grassing
DIVISION 3 – CONCRETE
03300 Cast-In-Place Concrete
03600 Non-Shrink Grout
DIVISION 5 – METALS
05500 Miscellaneous Metal
DIVISION 9 – FINISHES
09900 Painting
DIVISION 11 – EQUIPMENT
11379 Floating Mixers
DIVISION 15 – MECHANICAL
15200 Plant Piping, Valves and Appurtenances
DIVISION 16 – ELECTRICAL
16400 Electrical
APPENDICES
A CITI Controls Integration Scope of Supply
B Geotechnical Report
DIVISION 1
GENERAL REQUIREMENTS
Section 01010
SUMMARY OF WORK
01010-1 Renewable Water Resources
PART 1 - GENERAL
1.1 LOCATION OF WORK
All of the work of this Contract shall be installed at locations shown on the drawings.
1.2 SCOPE OF WORK
A. The Contractor shall furnish all labor, materials, equipment, tools, services and incidentals to complete all work required by these specifications and as shown on the drawings.
B. The Contractor shall perform the work complete, in place, and ready for continuous service, and shall include repairs, testing, permits, clean-up, replacements and restoration required as a result of damages caused during this construction.
C. All materials, equipment, skills, tools and labor which are reasonable and properly inferable and necessary for the proper completion of the work in a substantial manner and in compliance with the requirements stated or implied by these specifications or drawing shall be furnished and installed by the Contractor without additional compensation, whether specifically indicated in the contract documents or not.
D. The Contractor shall comply with all municipal, county, state, federal, and other codes which are applicable to the proposed construction work.
1.3 GENERAL DESCRIPTION OF WORK TO BE PERFORMED
A. Furnish all labor, materials, equipment, and incidentals required and construct the Georges
Creek WRRF EQ Upgrades, as shown on the drawings and specified herein.
B. The work includes, but is not necessarily limited to, the following:
1. Electrical, instrumentation, and controls modifications
2. Mechanical and structural improvements to the EQ basin including mixers and associated basin appurtenances
3. Site grading and erosion control
4. 18-inch diversion force main installation
5. Concrete lining of the existing effluent basin for conversion to the EQ basin
6. All other work as noted on the plans.
1.4 WORK SEQUENCE
A. All work to be done under this contract shall be done with minimum inconvenience to the existing water reclamation facility.
01010-2 Renewable Water Resources
B. Coordinate the construction schedule and operations with the Owner’s representative.
1.5 CONSTRUCTION AREAS
A. Contractor shall limit his use of the construction areas for work and for storage, to allow for:
1. Owner use.
B. Coordinate use of work site.
C. Assume full responsibility for the protection and safekeeping of products under this contract, stored on the site.
D. Move and store products, under Contractor’s control which interfere with operations of the
Owner or separate Contractor.
E. Obtain and pay for the use of additional storage or work areas needed for operations.
1.6 PLANS AND SPECIFICATIONS
A. The technical specifications consist of three parts: General, Products, and Execution. The
General Section contains General Requirements which govern the work. Products and
Execution modify and supplement the General Requirements. The Products and Execution parts shall always govern whenever there appears to be a conflict.
B. Intent
All work called for in the specifications applicable to this contract, but not shown on the plans in their present form, or vice versa, shall be of like effect as if shown or mentioned in both. Work not specified in either the plans or in the specifications but involved in carrying out their intent or in the complete and proper execution of the work, is required and shall be performed by the Contractor as though were specifically delineated or described.
The apparent silence of the specifications as to any detail, or the apparent omission from them of a detailed description concerning any work to be done and materials to be furnished, shall be regarded as meaning that only the best general practice is to prevail and that only material and workmanship of the best quality is to be used, and interpretation of these specifications shall be made upon that basis. The inclusion of the General Requirements (or work specified elsewhere) in the general part of the specifications is only for the convenience of the Contractor and shall not be interpreted as a complete list of related specification sections.
1.8 OWNER OCCUPANCY
Owner will have full access to and use of all existing wastewater conveyance facilities. Cooperate with Owner’s representative in all construction operations to minimize conflict and to facilitate
Owner usage.
01010-3 Renewable Water Resources
1.9 PARTIAL OWNER OCCUPANCY
The Contractor shall schedule his operations for completion of portions of the work, as designated, for the Owner’s occupancy prior to substantial completion of the entire work.
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
END OF SECTION
01010-4 Renewable Water Resources
Section 01016
OCCUPANCY
01016-1 Renewable Water Resources
1.1 PARTIAL OCCUPANCY BY OWNER
Whenever, in the opinion of the Engineer, any section or portion of the work or any structure is in suitable condition, it may be put into use upon the written order of the Engineer and such usage will not be held in any way as an acceptance of said Work or structure, or any part thereof, or as a waiver of any of the provisions of the specifications and the contract. Pending final completion and acceptance of the Work, all necessary repairs and replacement, due to defective materials or workmanship or operations of the Contractor, for any section of the work so put into use shall be performed by the Contractor at Contractor’s own expense.
Section 01016
OCCUPANCY
01016-2 Renewable Water Resources
01025-1 Renewable Water Resources
Section 01025
Measurement & Payment
A. SCOPE
A. The bid form lists each item of the project for which payment will be made. No payment will be made for any items other than those listed in the bid form.
B. Required items of work and incidentals necessary for the satisfactory completion of the
Work which are not specifically listed in the bid, and which are not specified in this section to be measured or to be included in one of the items listed in the bid, shall be considered as incidental to the work. All costs thereof, including Contractor’s overhead costs and profit, shall be considered as included in the lump sum or unit prices bid for the various bid items. The Contractor shall prepare the bid accordingly.
C. Work includes furnishing all labor, equipment, tools and materials, which are not furnished by the Owner and performing all operations required to complete the work satisfactorily, in place, as specified and as indicated on the drawings.
B. DESCRIPTIONS
A. Measurement of an item of work will be by the unit indicated in the bid.
B. Payment will include all necessary and incidental related work not specified to be included in any other item or work listed in the bid.
C. Payment will be made by extending unit prices multiplied by quantities provided and then summing the extended prices to reflect actual work. Such price and payment shall consti-tute full compensation to the Contractor for furnishing all permits, labor, equipment, tools and materials not furnished by the Owner and for performing all operations required to provide to the owner the entire project, complete in place, as specified and as indicated on the drawings.
D. No separate payment will be made for any item of work, materials, parts, equipment, sup-plies or related items required to perform and complete the work. The costs for all such items required shall be included in the price bid for item of which it is a part. The Bid
Form is provided for the Contractor’s convenience and to assign values to the work to be performed. No separate payment shall be made for incidental work required in the contract documents. The total bid amount shall be all inclusive of the work to be performed, in place, complete, and accepted. No separate payment shall be made for any work not spe-cifically listed on the Bid Form, but required to perform the work in the bid documents.
This work will be considered incidental to the performance of the contract.
E. “Products” shall mean materials or equipment permanently incorporated into the work.
01025-2 Renewable Water Resources
PART 2 – BID ITEMS
A. GENERAL CONSTRUCTION
1. General Construction shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, materials, and incidentals necessary for the general requirements of the Work. Payment shall include mobilization and demobilization, pay-ment and performance bonds, insurance, Contractor’s temporary facilities, erosion and sed-iment control installation, maintenance and removal, site cleanup, and all other general construction items required for completion of the Project that are not specifically included under another bid item.
B. YARD PIPING
1. Yard Piping shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, and materials necessary to furnish and install the yard piping improvements as shown on the plans and as specified herein. Payment shall include the 18 inch EQ Force Main, 4 inch utility water line, tapping sleeves and valves, yard hydrants, fittings, restrained joints, bends, tees, valve boxes, excavation, trenching, sheeting and shoring as required, dewatering, bedding, thrust restraint, backfill, compaction, testing, pavement removal and patching, restoration of access drives, grassing and other disturbed areas, cleanup, and all other items required for complete and operational yard piping in-stallations.
C. BASIN UPGRADES
1. Concrete Liner shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, and materials necessary to remove the existing synthetic liner and furnish and install a new cast in place reinforced concrete liner within the EQ
Basin as shown on the structural drawings and as specified herein. Payment shall include draining and cleaning of the basin as required, removal and proper disposal of the existing synthetic liner and appurtenances, excavation, grading, and subgrade preparation to estab-lish required slopes and elevations, furnishing and installing reinforcing steel, dowels, an-chors, waterstops, expansion joints, formwork, placement and finishing of concrete, curing, concrete sumps, basin piping under the liner, joint sealants, coordination with embedded items and penetrations, restoration of disturbed areas, cleanup, and all other items required for a complete and functional concrete liner installation.
2. Floating Mixers shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, and materials necessary to furnish and install Eight (8)
-15 HP Model SS Endura Series AquaDDM mixers complete with stainless steel floats, propellers, motor assemblies, restrained mooring frames, mooring post stop frame assem-blies, stainless steel mooring posts, adhesive anchor systems, power supply cables, cable protection, strain relief fittings, vinyl cable floats, pressure transducer assembly, and motor starter panels as specified herein. Payment shall include delivery, unloading, assembly, installation, anchoring, coordination with basin liner and concrete pad installation as re-quired, startup assistance, testing, cleanup, and all other items required for a complete and operational mixer installation. Electrical wiring and final power connections to the starter panels shall be paid for under Bid Item 3 – Electrical.
01025-3 Renewable Water Resources
3. Electrical shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, and materials necessary to complete the EQ Basin electrical demolition and installation as shown on the plans and as specified herein. Payment shall include demolition of existing conduit, wiring, devices, and equipment indicated for re-moval; furnishing and installing conduit, conductors, duct banks, pull boxes, junction boxes, wiring and terminations for eight EQ mixers and associated starters; installation, mounting, conduit, wiring, and terminations for PLC panels and level; connections to pan-els, instrumentation, equipment rack and canopy; testing, labeling, startup assistance, res-toration of disturbed areas, cleanup, and all other items required for a complete and opera-tional electrical system serving the EQ Basin. The Integrator shall furnish the PLC and level instrumentation and perform programming and system integration.
4. Gravel Access Drive shall be paid at the Lump Sum amount established in the Bid Form and shall include all equipment, labor, and materials necessary to regrade and resurface the existing gravel access drive serving the EQ Basin as shown on the plans and as specified herein. Payment shall include, shaping and grading of the existing drive, furnishing and placing new aggregate, compaction, tie ins to existing grades, erosion control as required, cleanup, and all other items necessary to provide a stable and properly graded gravel access drive.
D. ALLOWANCES
1. INSTRUMENTATION AND CONTROLS INTEGRATION Shall paid at the Lump
Sum allowance amount established in the Bid Form and shall be used to compensate the
Owner’s system integrator, CITI, for instrumentation and control system integration ser-vices associated with the entire project. This allowance shall include furnishing all instru-mentation and the new PLC as well as all integration of new and modified flow meters, level sensors, pressure transducers, motor controls, valves, mixers, pumps, and associated instrumentation into the existing SCADA system; programming, configuration, graphics development, database updates, communications setup, loop checks, testing, and startup support. The pre-negotiated Instrumentation and Controls Integration proposal submitted by CITI is included in Appendix B. The Contractor shall be responsible for all work and associated cost not included in the proposal. The Contractor’s portion of the work shall be included under the corresponding items in Bid Item A through E.
E. CONTINGENCY
1. Owner Directed Contingency Will be added to the Total Bid Price for the Project. This allowance is intended to cover costs associated with unforeseen conditions encountered during the execution of the Work. Use of this allowance shall be authorized only through a written Work Change Directive issued by the Engineer. Any portion of the allowance not expended by the completion of the Contract shall be credited back to the Owner. The
Owner reserves the right to remove the allowance from the Contract prior to award without affecting the validity of the Bid.
END OF SECTION 01025
Section 01055
CONSTRUCTION STAKING
01055-1 Renewable Water Resources
1.1 SCOPE
A. Construction staking shall include all of the surveying work required to layout the work and control the location of the finished project. The Contractor shall have the full responsibility for constructing the project to the correct horizontal and vertical alignment, as shown on the drawings, as specified, or as ordered by the Engineer. The Contractor shall assume all costs associated with rectifying work constructed in the wrong location.
B. From the information shown on the drawings and the information to be provided as indicated under project conditions below, the Contractor shall:
1. Be responsible for setting reference points and/or offsets, establishment of baselines and all other layout, staking, and all other surveying required for the construction of the project.
2. Safeguard all reference points, stakes, grade marks, horizontal and vertical control points, and shall bear the cost of re-establishing same if disturbed.
3. Stake out the limits of construction to ensure that the work is not deviating from the indicated limits.
4. Be responsible for all damage done to reference points, baselines, center lines and temporary benchmarks, and shall be responsible for the cost of re-establishment of reference points, baselines, center lines and temporary benchmarks as a result of the operations.
C. Baselines shall be defined as the line to which the location of the work is referenced; i.e., edge of pavement, road centerline, property line, right-of-way or survey line.
D. Record drawing surveys shall be performed in accordance with Section 01720 of these specifications.
1.2 PROJECT CONDITIONS
A. The drawings provide the location and/or coordinates of principal components of the project. The alignment of some components of the project may be indicated in the specifications. The Engineer may order changes to the location of some of the components of the project or provide clarification to questions regarding the correct alignment.
B. The Contractor’s Surveyor will provide the following:
1. Vertical control points, with elevation, as shown on the plans.
2. Horizontal control points, with coordinates, as shown on the plans.
Section 01055
CONSTRUCTION STAKING
01055-2 Renewable Water Resources
1.3 QUALITY ASSURANCE
A. The level of detail of survey required shall be that from which the correct location of the pipeline or appurtenances can be established for the construction and verified by the
Engineer.
B. Any deviations from the drawings shall be confirmed by the Engineer prior to construction of that portion of the project.
The contractor shall provide all equipment and field supplies, including but not limited to, stakes, hubs, PK nails, flagging, paint, etc. necessary to perform construction staking.
3.1 STAKING PRECISION
The precision of construction staking required shall be that from which the correct location and elevation of all proposed piping, structures, and appurtenances can be established for construction and verified by the Engineer. Where the location of any components shown on the drawings, including structures, fittings, or utility crossings, are not dimensioned, the establishment of these locations shall be based on scaling from the drawings in relation to survey reference points.
3.2 REFERENCE POINTS
A. Reference points shall be placed, at or no more than three feet from the outside of the construction easement or right-of-way. The location of the reference points shall be recorded in a log with a copy provided to the Engineer for use, prior to verifying reference point locations. Distances shall be accurately measured to 0.01 foot.
B. The Contractor shall give the Engineer reasonable notice that reference points are set.
The reference point locations must be verified by the Engineer prior to commencing clearing and grubbing operations.
Section 01060
REGULATORY REQUIREMENTS
01060-1 Renewable Water Resources
A. Permits and Responsibilities
The Contractor shall, at no additional cost to the Owner, be responsible for obtaining all necessary licenses and permits, including building permits, and for complying with any applicable federal, state, county and municipal laws, ordinances, codes and regulations, in connection with the performance of the work. Copies of permits already obtained by the
Owner will be provided no later than the pre-construction conference.
B. The Contractor shall take proper safety and health precautions to protect the work, the workers, the public and the property of others.
C. Prior to commencing any work, the Contractor shall submit a job-specific Health and
Safety Plan to the Owner for their records.
D. Contractor shall provide inspection of sediment and erosion control measures required by the NPDES General Permit for Stormwater Discharges, SCR10000, and as described in the Stormwater Pollution Prevention Plan for the project. The Contractor shall be listed as a co-permittee in the Notice of Intent for coverage under the permit and shall sign the required certification for co-permittees.
E. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
F. The Contractor shall post a copy of the construction permit in a conspicuous location on site.
Section 01060
REGULATORY REQUIREMENTS
01060-2 Renewable Water Resources
Section 01091
CODES & STANDARDS
01091-1 Renewable Water Resources
1.1 DESCRIPTION
A. Whenever reference is made to conforming to the standards of any technical society, organization, body, code or standard, it shall be construed to mean the latest standard, code, or specification adopted and published at the time of advertisement for bids. This shall include the furnishing of materials, testing of materials, fabrication and installation practices. In those cases where the Contractor’s quality standards establish more stringent quality requirements, the more stringent requirement shall prevail. Such standards are made a part hereof to the extent which is indicated or intended.
B. The inclusion of an organization under one category does not preclude that organization’s standards from applying to another category.
C. In addition, all work shall comply with the applicable requirements of local codes, utilities and other authorities having jurisdiction.
D. All material and equipment for which a UL Standard, an AGA or NSF approval, or an
ASME requirement is established, shall be so approved and labeled or stamped. The label or stamp shall be conspicuous and not covered, painted, or otherwise obscured from visual inspection.
E. The standards which apply to this project are not necessarily restricted to those organizations which are listed in Article 1.2.
1.2 STANDARD ORGANIZATIONS
A. Piping and Valves
ACPA American Concrete Pipe Association
ANSI American National Standards Institute
API American Petroleum Institute
ASME American Society of Mechanical Engineers
AWWA American Water Works Association
CISPI Cast Iron Soil Pipe Institute
DIPRA Ductile Iron Pipe Research Association
FCI Fluid Controls Institute
MSS Manufacturers Standardization Society
NCPI National Clay Pipe Institute
NSF National Sanitation Foundation
PPI Plastic Pipe Institute
PVCPA Uni-Bell PVC Pipe Association
B. Materials
AASHTO American Association of State Highway and Transportation Officials
ANSI American National Standards Institute
ASTM American Society for Testing and Materials
01091-2 Renewable Water Resources
C. Painting and Surface Preparation
NACE National Association of Corrosion Engineers
SSPC Steel Structures Painting Council
D. Aluminum
AA Aluminum Association
AAMA American Architectural Manufacturers Association
E. Steel and Concrete
ACI American Concrete Institute
AISC American Institute of Steel Construction, Inc.
AISI American Iron and Steel Institute
CRSI Concrete Reinforcing Steel Institute
NRMA National Ready-Mix Association
PCA Portland Cement Association
PCI Prestressed Concrete Institute
F. Welding
ASME American Society of Mechanical Engineers
AWS American Welding Society
G. Government and Technical Organizations
AIA American Institute of Architecture
APHA American Public Health Association
APWA American Public Works Association
ASA American Standards Association
ASAE American Society of Agricultural Engineers
ASCE American Society of Civil Engineers
ASQC American Society of Quality Control
ASSE American Society of Sanitary Engineers
CFR Code of Federal Regulations
CSI Construction Specifications Institute
EDA Economic Development Administration
EPA Environmental Protection Agency
FCC Federal Communications Commission
FmHA Farmers Home Administration
FS Federal Specifications
IAI International Association of Identification
ISEA Industrial Safety Equipment Association
ISO International Organization for Standardization
ITE Institute of Traffic Engineers
NBFU National Board of Fire Underwriters
(NFPA) National Fluid Power Association
NBS National Bureau of Standards
NISO National Information Standards Organization
OSHA Occupational Safety and Health Administration
01091-3 Renewable Water Resources
SI Salt Institute
SPI The Society of the Plastics Industry, Inc.
USDC United States Department of Commerce
WEF Water Environment Federation
H. Roadways
AREA American Railway Engineering Association
DOT Department of Transportation
SSRBC Standard Specifications for Construction of Transportation Systems
SCDOT South Carolina Department of Transportation
I. Plumbing
AGA American Gas Association
NSF National Sanitation Foundation
PDI Plumbing Drainage Institute
SPC SBCC Standard Plumbing Code
1.3 SYMBOLS
Symbols and material legends shall be as scheduled on the drawings.
01091-4 Renewable Water Resources
Section 01410
MAINTENANCE OF PLANT OPERATIONS
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
01010-1 Renewable Water Resources
1.1 SUMMARY
A. Section includes:
1. General, administrative, and submittal requirements for coordinating with Owner’s operations during performance of the Work.
2. General information concerning site conditions.
3. Suggested sequence of Work.
4. Requirements for tie-ins and shutdowns necessary to complete the Work without impact on Owner’s operations except as allowed in this Section.
5. Requirements for coordinating with Owner’s Operations during testing, startup, and commissioning of new facilities.
1.2 GENERAL REQUIREMENTS
A. The Contractor shall furnish all labor, materials, equipment, tools, services and incidentals to complete all work required by these specifications and as shown on the drawings to:
1. Coordinate with Owner’s operations during the Work.
2. Test, startup, and commission all new facilities.
B. Except for shutdowns specified in this Section, perform the Work such that Owner’s facility remains in continuous satisfactory operation during the Project. Schedule and conduct the Work such that the Work does not: impede Owner’s production or processes, create potential hazards to operating equipment and personnel, reduce the quality of the facility’s products or effluent, or cause odors or other nuisances.
C. Work not specifically covered in this Section or in referenced Sections may, in general, be completed at any time during regular working hours in accordance with the General
Conditions and Supplementary Conditions, subject to the requirements in this Section.
D. Contractor has the option of providing additional temporary facilities that can eliminate or mitigate a constraint without additional cost to Owner, provided such additional temporary facilities: do not present hazards to the public, personnel, structures, and equipment; that such additional temporary facilities do not adversely affect Owner’s ability to comply with Laws and Regulations, permits, and operating requirements; that such temporary facilities do not generate or foster the generation of odors and other nuisances; and that requirements of the Contract Documents are fulfilled.
E. The Contractor shall comply with all municipal, county, state, federal, and other codes which are applicable to the proposed construction work.
F. Coordinate shutdowns with Owner and Engineer. When possible, combine multiple tie-ins
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
01010-2 Renewable Water Resources into a single shutdown to minimize impacts on Owner’s operations and processes.
G. Do not shut off or disconnect existing operating systems, unless accepted by Engineer in writing. Operation of existing equipment shall be by Owner unless otherwise specified or indicated.
H. The Owner makes no guarantee that existing valves or gates are free of leaks. Therefore, Contractor shall seal or bulkhead Owner-operated gates and valves to prevent leakage that may affect the Work, Owner’s operations, or both. Provide temporary watertight plugs, bulkheads, and line stops as required. After completing the Work, remove seals, plugs, bulkhead, and line stops to satisfaction of Engineer.
I. Continuous Treatment Provision:
1. Federal regulations prohibit bypassing of untreated or partially treated wastewater or sewage during construction Work.
2. Contractor shall provide labor, equipment, materials, and incidentals to provide continuous treatment to the level prior to construction Work.
3. Contractor shall be responsible for providing temporary pumping facilities, systems, piping, valve, appurtenances, equipment, materials, and temporary utilities necessary to complete the Work without treatment bypassing.
1.3 GENERAL DESCRIPTION OF WORK TO BE PERFORMED
A. Furnish all labor, materials, equipment, and incidentals required and construct the Georges
Creek WRRF EQ Upgrades Division I, as shown on the drawings and specified herein.
B. The work includes, but is not necessarily limited to, the following:
1. Electrical, instrumentation, and controls
2. Mechanical and structural improvements to the EQ basin including mixers and associated basin appurtenances
3. Site grading and erosion control
4. 18-inch fill/drain installation
5. Concrete lining of the existing effluent basin for conversion to the EQ basin
6. All other work as noted on the plans.
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination:
1. Review installation procedures under other Specification sections and coordinate
Work that must be performed with or before the Work specified in this Section.
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
01010-3 Renewable Water Resources
2. Notify other contractors in advance of Work requiring coordination with Owner’s operations, to provide other contractors sufficient time for work included in their contracts that must be installed with or before Work specified in this Section.
3. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on Owner’s operations and processes.
B. Pre-Shutdown Meetings: Contractor shall schedule and conduct meeting with Owner and
Engineer prior to scheduling shutdown. The Pre-Shutdown Meeting shall occur at least 72 hours prior to scheduled shutdown.
C. Proposed Sequence:
1. Perform the Work in the specified sequence. Certain phases or stages of the Work may require working 24-hour days or work during hours outside of regular working hours. Work may be accelerated from a later stage to an earlier stage if Owner’s operations are not adversely affected by proposed sequence change, with Engineer’s acceptance. Stages specified in this Section are sequential in performance of the
Work.
D. Scheduling:
1. Work that may interrupt normal operations shall be accomplished at times convenient to the Owner.
1.5 CONSTRUCTION AREAS
A. Contractor shall limit his use of the construction areas for work and for storage to areas of work shown on the drawings.
B. Coordinate use of work site with Owner to maintain WRRF normal operations.
C. Contractor shall assume full responsibility for the protection and safekeeping of products under this contract, stored on the site.
D. Move and store products under Contractor’s control which interfere with operations of the
Owner or separate Contractor.
E. Obtain and pay for the use of additional storage or work areas needed for operations.
1.6 CONSTRUCTION SEQUENCING
A. Construct EQ Basin
1. Work shall include but is not limited to:
a. Drain basin and remove all debris
b. Owner to assist with draining the basin using existing valves and piping;
Contractor responsible for draining the remainder of the basin (+/-2 feet)
c. Demolish and dispose of existing synthetic liner
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
01010-4 Renewable Water Resources
i. Contractor shall dispose of solid material / debris off-site
d. Demolish existing inlet structure and cap piping as shown on Contract Drawings
e. Install drainage sumps and EQ drain piping
f. Partially demolish and modify existing outlet structure and cap piping as shown on Contract Drawings
g. Install concrete liner and access ramp
h. Install mixers
i. Install new electrical and instrumentation
j. Finish associated sitework and permanent grassing
k. Install perimeter fencing
1.7 OWNER OCCUPANCY
A. Owner will have full access to and use of all existing wastewater conveyance facilities.
Cooperate with Owner’s representative in all construction operations to minimize conflict and to facilitate Owner usage.
1.8 PARTIAL OWNER OCCUPANCY
A. The Contractor shall schedule his operations for completion of portions of the work, as designated, for the Owner’s occupancy prior to substantial completion of the entire work.
3.1 WATER FOR TESING, STARTUP, AND COMMISSONING OF NEW FACILITIES
A. Water Supply
1. Water used to fill structures for water tightness testing, equipment testing, pipe testing, and facility startup / commissioning shall be supplied from the Owner’s existing utility water system located on the site. The Contractor shall coordinate with the Owner and Engineer to schedule use of utility water. At no time shall Contactor’s use of utility water interfere with Owner’s use of the water to operate any other
Owner facility whether on this site or at another location.
2. The Contractor shall be responsible for all labor, equipment, and materials including but not limited to temporary piping, valving, and pumping systems necessary to convey reclaimed water to all structures, facilities, piping, etc. to be tested or started up.
3. Testing and startup of structures, equipment, and piping shall be performed per individual specification sections.
KCI Project No. 00013511_005 Georges Creek WWRF EQ Upgrades Division I
01010-5 Renewable Water Resources
4. Potable water shall not be used for any testing.
B. Disposal of Water
1. Disposal of concrete washout water shall be in strict accordance with requirements contained within the Contract Drawings.
2. Coordinate draining of test water from structures, pipe and equipment with the
Engineer and Owner.
01010-6 Renewable Water Resources
Section 01200
PROJECT MEETINGS
01200-1 Renewable Water Resources
A. Work under this section includes all scheduling and administration of pre-construction and progress meetings as herein specified and necessary for the proper and complete performance of this work.
B. Scheduling and Administration by Engineer/Owner:
1. Prepare agenda.
2. Make physical arrangements for the meetings.
3. Preside at meetings.
4. Record minutes and include significant proceedings and decisions.
5. Distribute copies of the minutes to participants.
1.2 PRE-CONSTRUCTION CONFERENCE
A. The Engineer shall schedule the pre-construction conference prior to the issuance of the
Notice to Proceed.
B. Representatives of the following parties are to be in attendance at the meeting:
1. Owner
2. Engineer
3. Contractor and superintendent
4. Major subcontractors
5. Representatives of governmental or regulatory agencies when appropriate
C. The agenda for the pre-construction conference shall consist of the following as a minimum:
1. Distribute and discuss a list of major subcontractors and a tentative construction schedule.
2. Critical work sequencing.
3. Designation of responsible personnel and emergency telephone numbers.
4. Processing of field decisions and change orders.
5. Adequacy of distribution of contract documents.
01200-2 Renewable Water Resources
6. Schedule and submittal of shop drawings, product data and samples.
7. Pay request format, submittal cutoff date, pay date and retainage.
8. Procedures for maintaining record documents.
9. Use of premises, including office and storage areas and owner’s requirements.
10. Major equipment deliveries and priorities.
11. Safety and first aid procedures.
12. Security procedures.
13. Housekeeping procedures.
14. Work hours.
1.3 PROJECT COORDINATION MEETINGS
A. Schedule regular monthly meetings as directed by the Engineer.
B. Hold called meetings as the progress of the work dictates.
C. The meetings shall be held at the location indicated by the Engineer.
D. Representatives of the following parties are to be in attendance at the meetings:
1. Engineer
2. Contractor and superintendent
3. Major subcontractors as pertinent to the agenda
4. Owner’s representative as appropriate
5. Representatives of governmental or other regulatory agencies as appropriate
E. The minimum agenda for progress meetings shall consist of the following.
1. Review and approve minutes of previous meetings.
2. Review work progress since last meeting.
3. Note field observations, problems and decisions.
4. Identify problems which impede planned progress.
5. Review off-site fabrication problems.
01200-3 Renewable Water Resources
6. Review Contractor’s corrective measures and procedures to regain planned schedule.
7. Review Contractor’s revision to the construction schedule.
8. Review submittal schedule; expedite as required to maintain schedule.
9. Maintenance of quality and work standards.
10. Review changes proposed by Owner for their effect on the construction schedule and completion date.
11. Complete other current business.
01200-4 Renewable Water Resources
Section 01350
SAFETY REQUIREMENTS
01350-1 Renewable Water Resources
A. Section includes:
1. General requirements for preliminary and final Schedule of Values.
2. Schedule of Values and the Progress Schedule updates specified in Section 01 32 00
Construction Progress Schedule, shall be basis for preparing each Application for Pay-ment. Schedule of Values may be used as a basis for negotiating price of changes, if any, in the Work.
1.2 ADMINISTRATION REQUIREMENTS
A. The following abbreviations are used in this Specification section:
1. Contractor’s comprehensive site and project specific safety program or site-specific health and safety plan (HASP) applicable to the construction work of this Project.
1.3 REGULATORY REQUIREMENTS
A. General Requirements:
1. Schedule of Values shall include breakdown of costs for materials and equipment, in-stallation, and other costs used in preparing the Bid by Contractor and each Subcontrac-tor. List purchase and delivery costs for materials and equipment for which Contractor may apply for payment as stored materials.
2. Include separate amounts for each Specification Section in the Contract
Documents by structure, building, and work area.
3. Identify each line item with number corresponding to the associated Specification Sec-tion number. List sub-items of major products or systems, as appropriate or when re-quested by Engineer.
4. Include in Schedule of Values unit price payment items with their associated quantity.
Provide in the Schedule of Values detailed breakdown of unit prices when required by
Engineer.
5. Include in Schedule of Values itemized list of Work for each major part of the Contract, for each payment item specified in Section 01 20 00 – Measurement and Payment.
6. Sum of individual values shown on the Schedule of Values shall equal the total of asso-ciated payment item. Sum of payment item totals in the Schedule of Values shall equal
01350-2 Renewable Water Resources the Contract Price.
B. Specific Requirements:
1. Include in each line item a directly proportional amount of Contractor’s overhead and profit. Do not include overhead and profit as separate item(s).
2. Include separate line item for each allowance, and for each unit price item.
3. Include line item for bonds and insurance in amount not exceeding two percent of the
Contract Price. This may be applied for in the first Application for Payment.
4. Include items for the General Conditions, permits (when applicable), construction Pro-gress Schedule, and other items required by Engineer. Include such items in Applica-tions for Payment on schedule accepted by Engineer.
5. Line items for Site maintenance such as dust control, snow removal, compliance with storm water pollution prevention plans and permits, spill prevention control and coun-termeasures plans, and for construction photographic documentation; temporary utili-ties and temporary facilities, field offices, temporary controls, field engineering, and similar Work shall be included in the Schedule of Values and proportioned in Appli-cations for Payment throughout duration of the Work.
6. Include separate line items under each appropriate payment item for mobilization and demobilization. Document for Engineer the activities included in mobilization and demobilization line items.
a. Mobilization will be limited to two percent of the Contract Price, and will be paid in two payments, each of 50 percent of total amount for mobilization.
b. Demobilization shall be one percent of the Contract Price and shall be included with the Application for Payment following Substantial Completion, or other schedule accepted by Engineer.
7. Costs for submittals, operations and maintenance manuals, field testing, and train-ing of operations and maintenance personnel shall be as follows, unless otherwise accepted by Engineer:
a. Up to three percent of total cost of each item (including overhead and profit), in-cluding materials and equipment, and installation, may be apportioned to testing and included in the Application for Payment following Engineer’s acceptance of the associated written Site testing report(s).
C. Preliminary Schedule of Values: Submit preliminary Schedule of Values to Engineer for ini-tial review. Contractor shall incorporate Engineer’s comments into the Schedule of Values and resubmit to Engineer. Engineer may require corrections and re-submittals until Schedule of Values is acceptable.
01350-3 Renewable Water Resources
D. Time Frame for Submittals:
1. Submit preliminary Schedule of Values within ten days of date that the Contract
Times commence running in accordance with the Notice to Proceed.
2. Submittal of the Schedule of Values shall be in accordance with the General Con-ditions. Engineer will not accept Applications for Payment without an acceptable
Schedule of Values.
3. When required by Engineer, promptly submit updated Schedule of Values to in-clude cost breakdowns for changes in the Contract Price.
1.4 SUBMITTALS
A. Submit the following:
1. Electronic copy of preliminary Schedule of Values.
2. Electronic copy of Schedule of Values.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used
01350-4 Renewable Water Resources
Section 01320
CONSTRUCTION PROGRESS SCHEDULE
A. Section includes: Detailed requirements and/or procedures for, including but not limited to, the Preliminary Project Schedule, Project Schedule Updates, Project Schedule development, Time Impact Analysis, and Recovery Schedules
B. The Contractor shall develop, revise, and provide all information and input required for the
Project Schedule for the performance of the Work in accordance with the requirements of the
Contract Documents in general and, in particular, this section. The Progress Schedule shall in-corporate the requirements of General Conditions, Supplementary Conditions, and all items specified in this section.
C. Except as otherwise provided herein or elsewhere in the Contract Documents, the planning, scheduling, coordination, and execution of the Work is the sole responsibility of the Con-tractor.
1.2 REFERENCES
A. Definitions:
1. Activity: An element of the construction work that has the following specific character-istics: consumes time, consumes resources, has a definable start and finish, is assignable, and is measurable.
2. Constraint: An imposed date on the Progress Schedule or an imposed tie between Ac-tivities. The Contract Times are Constraints.
3. CPM Progress Schedule: Computerized Progress Schedule in Critical Path Method
(CPM) format which accounts for the entire Work, defines the interrelationships be-tween elements of the Work, reflects the uncompleted Work, and indicates the sequence with which the Work has been completed, indicates the sequence in which uncompleted
Work will be completed, and indicates the duration of each Activity.
4. Critical Path: The continuous chain of Activities with the longest duration for completion within the Contract Times.
5. Early Start: The earliest possible date an Activity can start according to the assigned relationships among Activities.
6. Early Finish: The earliest possible date an Activity can finish according to the as-signed relationships among the Activities.
7. Late Finish: The latest possible date an Activity can finish without extending the Contract Times.
8. Late Start: The latest possible date an Activity can start without extending the Contract
Times.
9. Total Float: The total number of days that an Activity (or chain of Activities) can be de-layed without affecting the Contract Times. Total float for each Activity shall be calcu-lated as the difference between Early Finish and Late Finish.
10. Network Diagram: A time-scaled logic diagram depicting the durations and relation-ships of the Activities.
11. Work Areas, Area, or System: A logical breakdown of the Project elements or a group of Activities which, when collectively assembled, are readily identifiable on the Project
(for example, yard piping, a structure or building, a treatment process, or other logical grouping).
1.3 ADMINISTRATIVE REQUIREMENTS
A. Initial Progress Schedule
1. Type and organization of progress schedule:
a. Prepare one Progress Schedule covering the entire Project using Primavera
Planner (P6 or newer), or Microsoft Project scheduling software.
b. Schedule submittals shall include the electronic native file format (i.e., scheduling software file), and a PDF file of the schedule’s logic diagram.
c. Time Scale: Indicate first date of each work week.
d. Activity Designations: Indicate title concise description of the Work repre-sented by the activity and related Specification Section number. The Work related to each activity shall be limited to one work trade and one construc-tion area.
e. Regulations: Comply with applicable federal, State of South Carolina and lo-cal health and safety regulations, laws, rules, codes, ordinances, and require-ments, including but not necessarily limited to the following:
2. Submitted PDF files shall be in a Gantt Chart Format and shall show the fol-lowing:
a. Activity identification number.
b. Activity description.
c. Activity duration (in workdays).
d. Activity percent complete
e. Start, Early Start, Late Start, Finish, Early Finish, and Late Finish Dates
01350-3 Renewable Water Resources
f. Total Float for each Activity.
g. Critical Path denoted.
3. Organization:
a. Group shop drawings, samples and other submittals into a separate sub-schedule that is part of the Progress Schedule.
b. Group deliveries of materials and equipment into a separate sub-schedule that is part of the Progress Schedule.
c. Group construction into Work Area sub-schedules (that are part of the Pro-gress Schedule) by Activity.
d. Clearly indicate the Critical Path on the Progress Schedule.
e. Organize each Work Area sub-schedule by Specification Section number.
4. Preliminary Progress Schedule:
a. Contractor shall submit to Engineer the Preliminary Progress Schedule with-in ten (10) days after the Contract Times commence running.
5. Preliminary Progress Schedule:
a. At least 10 days before submission of the first Application for Payment, Con-tractor shall schedule a conference at the Site for review of the Preliminary
Progress Schedule.
1. Attendees shall include Contractor, Engineer, Owner, and others as required.
2. Contractor shall have an additional 10 days to make corrections and adjustments and to complete and resubmit the Progress
Schedule.
3. Owner reserves the right to not make progress payment to Con-tractor until acceptable Progress Schedule, and other reports and schedule-related documents required are submitted to En-gineer.
b. least Initially-accepted Progress Schedule shall be identified as the Baseline
Progress Schedule. The Baseline Progress Schedule shall not be revised without Owner and Engineer approval.
B. Project Schedule Updates:
1. Project Schedule Updates shall be prepared on a monthly basis throughout the entire
Contract Time and until Project Final Completion. The Engineer will not recommend progress payments by the Owner until a complete Project Schedule Update (including
Schedule Narrative Report) is received, reviewed, and accepted by the Engineer.
01350-4 Renewable Water Resources
2. The update to the Progress Schedule shall be based on retained logic. Progress override logic is not allowed.
3. Required scheduling software, and schedule organization, format, and content for updated Progress Schedules are identical to that required in this Section for initial Progress Schedules.
4. For all Project Schedule Updates, the percent complete reported for individual Ac-tivities shall be based on Work accepted and paid for the by Owner in monthly pay applications. Failure to comply with this requirement shall be result in rejection of the submitted update.