This document is an overview for an Industry Day hosted by NOAA's Office of Geostationary Earth Orbit Observations (GEO) on November 7, 2024 at the NASA Goddard Visitor Center. The purpose is to provide an overview of the GEO Program, the current GEO Ground System operations, and NOAA's plans to evolve the Ground System to support additional NOAA-NASA satellite missions like the Geostationary Extended Observations (GeoXO) program. The event will include a program overview, discussion of the current GEO Ground System architecture and operations, and the future evolutionary plans to reduce sustainment costs and align with the NESDIS enterprise. Interested vendors will have the opportunity for private one-on-one sessions with the Government in the afternoon to discuss their capabilities. A preliminary Request for Information (RFI) is provided for informational purposes only, and NOAA will publish a final RFI in the weeks following this Industry Day event. The event is open to a limited number of attendees who must register by November 1, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GEO Ground Project Industry Day: GEO Ground System Sustainment & Evolution
NASA Goddard Visitor Center | November 7, 2024 9432 Greenbelt Road, Greenbelt, MD 20771 sam.gov/opp/e84751d134b34aa5afdcb2d1f42f1959/view
Welcome!
2GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Introduction/Administrative Remarks
Jerry Robertson, NOAA Contracting Officer
10 Minutes
GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Administrative Information
Welcome to the NASA Goddard Visitor Center!
Restrooms are located behind you, just off the exhibit hallway
Mobile Phones should be set to silent (ringer off), please
Refreshments, including coffee and water, are available. Please make sure to dispose of all trash in the marked receptacles
There are two exits for this room behind you
Questions for the GEO Ground Project
5GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
BEFORE DURING AFTER
Questions collected from the Industry Day RSVP Google Form
Use the index cards provided to write down your question (one question per card)
After this event has concluded, questions may be submitted to gerald.robertson@noaa.gov and tamalia.adams@noaa.gov by COB 14 November 2024
All questions and answers will be aggregated into a single document. NOAA AGO will post the final NOAA GEO Ground Q&A document on SAM.gov in mid November.
Schedule/Agenda
Morning Schedule
Afternoon Schedule
From 1:00p to 4:00p the GEO Ground Project Team will meet with industry vendors
- There will be six 25-minute in-person one-on-one (1:1) sessions this afternoon
▪ Vendor representatives should report to the Visitor Center front desk/lobby 10 minutes prior to their scheduled appointment time
- The remaining 1:1 sessions will be virtual and have been scheduled by NOAA AGO (Jerry & Tamalia)
Overview of Industry Day and Ground Rules (Robertson) 09:00 – 09:10
GEO Program Overview by Leadership (Valenti) 09:10 – 09:40
GEO Ground Project Overview (Grippando) 09:40 – 10:10
BREAK 10:10 – 10:25
GEO Ground System Current & Evolutionary Path (McMahon) 10:25 – 11:35
Contract & Closing Remarks (Conclusion of Morning Session) (Robertson) 11:35 – 11:45
Industry Day Objectives
Industry Day = collaboration and networking between the agency and industry partners in which Industry gains understanding of Agency requirements and the Government gains understanding of industry capabilities.
• Opportunity for the agency to provide an overview of anticipated requirements and for the industry to ask questions and start thinking about how best to meet the agencies anticipated requirements.
• When a Request For Information (RFI) is published to sam.gov in the coming weeks, Industry will be better prepared and more excited to respond.
GEO Program Overview
Jim Valenti, GEO Assistant Director
30 Minutes
NOAA’s Geostationary Satellite System
• Our “eyes in the sky,” providing the only persistent coverage of the Western Hemisphere
– Enable weather forecasters to issue emergency warnings to protect life and property
• Protects the one billion people who live and work in the Americas
– 100,000+ premature U.S. deaths per year from extreme weather and poor air quality
• Provides essential information for disaster preparation and prevention, transportation, energy management, agriculture, recreation, tourism, and more.
Aftermath of Galveston 1900 Hurricane
Constant, real time observation of the Western Hemisphere
“ The greatest single advancement in observing tools for tropical meteorology was unquestionably the advent of the geosynchronous meteorological satellite.”
- Former National Hurricane Center Director Bob Sheets
9GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
NOAA-NASA Partnership
NOAA oversees the program through an integrated NOAA-NASA office, managing the ground system, operating the satellites, and distributing their data to users worldwide.
NASA provides systems engineering, mission assurance and flight elements (spacecraft, instruments, launch vehicle).
Mission is supported by industry partners
10GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Office of Geostationary Earth Orbit Observations
11GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
History of GEO Weather Satellites
12GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Current Generation: The GOES-R Series
The GOES-R Series the Western Hemisphere’s most advanced weather-observing and environmental monitoring system. GOES-R observations contribute to public safety, protection of property, and our nation’s economic health and prosperity.
✓ Hurricane track and intensity forecasts
✓ Early warning of severe storms
✓ Fire detection, monitoring, and intensity estimation
✓ Data for air quality warnings and alerts
✓ Detection of low clouds and fog
✓ Data for aviation route planning and reducing weather-related flight delays
✓ Detection of volcanic eruptions and monitoring of ash and sulfur dioxide
✓ First-ever operational lightning mapper from geostationary orbit
✓ Data for long-term climate variability studies
✓ Warning of space weather hazards responsible for communications and navigation disruptions and power blackouts
✓ Monitoring of energetic particles responsible for radiation hazards
ABI GLM MAG and SEISS EXIS, SUVI, CCOR*
*GOES-U only 13GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Hurricane Tracking and Intensity Estimation
14GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Lightning Detection and Severe Weather
Fire Detection and Monitoring
16GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GeoXO Constellation
Future: GeoXO (Geostationary Extended Observations)
BAE Systems
L3Harris
BAE Systems
Lockheed Martin
18GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GeoXO Constellation
19GEO Ground System Sustainment & Evolution Industry Day
GeoXO Data Delivery
20GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GeoXO Spacecraft Implementation contracts:
MS0 MS1
KDP
AMCR
Form.
Auth.
NOAA
Endorses
Observation Set
SRR
KDP
dA
MS2/3
(DOC Baseline)
User Reqts Working Group
Convened
MDR
KDP
B
FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
PDR
KDP
C CDR SIR
KDP
D ORR
KDP
E
Congressional Baseline
(Tentative)
GeoXO-I1 LaunchWe are here
✔Ocean Color: BAE Systems ✔Spacecraft: Lockheed Martin ✔Lightning Mapper: Lockheed Martin
✔Imager: L3Harris ✔Sounder: BAE Systems ✔Atmo. Comp.: BAE Systems
GeoXO Timeline
21GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GeoXO Flight Implementation Contracts:
• NOAA’s GOES satellites provide the only constant, real-time view of weather and environmental conditions across the U.S. and Western Hemisphere.
– Essential forecast information to protect life and property and support the Nation's economy
• The GOES-R Series will provide critical data into the early 2030s.
• The next generation GeoXO satellites will provide continuity and extend observations to include monitoring of atmosphere, oceans, and climate to meet growing environmental and health challenges facing our nation and planet.
– Maintain and advance NOAA’s observational capabilities through the 2050s
22GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Conclusion
GEO Ground Project Overview
Steve Grippando, GEO Ground Project Manager
23November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
30 Minutes
Why are we here?
• We have a mature ground system that successfully supports the GOES-R constellation, and is ready to support SWFO-L1 launch next year
– Following the successful GOES-19 launch this past spring, we are simplifying the ground system and migrating Data Operations to the cloud
• We are 18 months into the 5-year Geostationary Ground Sustainment Services (GGSS) contract
– Prepping for the follow-on effort called GEO Ground Multi-Mission
Sustainment and Evolution (GMSE)
– We look forward to hearing your input as we shape the next sustainment & evolution requirements and get ready for an RFI in the future
24November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
GEO Ground History
• GOES has evolved over the past 50 years
– The satellite bus and satellite instrumentation has radically transformed over this time to provide high-resolution environmental data for weather forecasting
– Ground System operations has also transformed over this time to handle the increased data flow and meet stringent latency requirements
• GEO Ground development and sustainment contracts have helped the GEO Ground Project create one of the most advanced ground systems in the world
25November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
GOES Data Collection & Distribution c.1974
Background
• Our responsibility to the GEO Program Office is to provide ground system services for Geostationary weather satellite constellation and SWFO-L1 lifecycles:
– GOES-R constellation has an expected operational life through the mid 2030s
– SWFO-L1 has an expected operational life through the mid 2030s
– GeoXO through 2055 with launches planned to begin in 2032
• Our evolutionary goals:
– Improve Operability
– Simplify the System
– Adopt Cloud
– Manage IT Security
– Manage lifecycle costs
26November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
CUI//SP-PROCURE
National Critical Sectors, Functions, and GEO
55 total defined National Critical Functions
GEO Ground directly supports 2 with critical weather and climate information:
• Prepare for and manage emergencies
• Provide Public Safety
GEO Ground indirectly supports multiple national critical functions by providing critical data:
• Transport Cargo and Passengers by Air – NOAA Weather Forecasts are critical to the FAA
• Provide Material and Operational Support to Defense – The DoD utilizes NOAA weather data for regions without sufficient DoD assets
• Distribute Electricity – NOAA space weather data is one piece in ensuring stability of the national electrical grid
GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
National Critical Functions: The functions of government and the private sector so vital to the United States that their disruption, corruption, or dysfunction would have a debilitating effect on security, national economic security, national public health or safety, or any combination thereof.
GEO Ground Project Organization
28GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Introductions
Steve Grippando GEO Ground Project Manager
Lili Alvarado-Ortiz GEO Ground Assistant Project Manager
Patrick Serengulian GEO Ground System Evolution Lead
Kevin McMahon GEO Ground Chief Engineer
Michael Burnett GEO Ground Chief Architect
Deputy Project Managers Elizabeth Corderman (NASA) Candace Masters (NASA) Margaret Pavlik (NASA)
GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Jerry Robertson Contracting Officer, NOAA AGO SIAD
GEO Lifecycle Definitions
30GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024 evelop :
Conceiving, specifying, designing, programming, documenting, testing, and transitioning to operations to create information systems and applications perate :
Ensure the efficient and effective command and control of satellites and selected reference climate networks, data acquisition from a spectrum of observing and computational systems, product generation, archive, & product distribution aintain :
Ensure the continued operation of the system meets scientific, technical, functional, and performance requirements in addition to availability and reliability requirements. Maintains IT security posture ustain :
Develop, modernize, enhance or improve ground system components addressing obsolescence, reliability and lifecycle efficiencies
D
S
M
O
GEO Ground Project Responsibilities
RF Comm MM
Data Operations Compute Storage
Network Security
Level 1b PG Level 2 PG Data/Product Distribution
N/A N/A (L0 data to SWPC)
N/A (L0/L1b data to NCCF)
GeoXO
GOES-R
SWFO-L1
36GEO Ground System Sustainment & Evolution Industry Day
Development
D S
Sustainment Maintenance
November 7, 2024
D S
S S
D S
D S
(Critical data to NWS/AWIPS; All data to
NESDIS Enterprise)
O&M is the responsibility of another NESDIS organization D
S M
O Operations
D S
D S
S
D S
D S
D S D S
D S
S
GEO Ground Elements
• GEO Ground Project is responsible for development & sustainment of the GEO Ground System
• GEO Ground System is a multi-mission NESDIS ground system currently supporting GOES-R and SWFO missions and planning GeoXO in the future
Key elements:
32November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Enterprise Management/Infrastructure (EM/IS) : Functions to manage the compute, storage, networking, & security infrastructure
Data Operations (DO) : Product Generation (PG) creates L1b products from L0 data provided by MM and L2 products from L1b data. Product Distribution (PD) distributes products to end-users
Mission Management (MM) : Functions to command and control the spacecraft and instruments to maintain health and safety
RF Communications : Antenna network communicates with the satellites in orbit
09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
GEO Ground Contract Background
GOES-R Core & Antenna (Dev, Maint, Sust)
GGSS (Sust)
SWFO-L1 (Dev)
GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GEO Ground Project is in the market research phase of the acquisition lifecycle to develop the requirements for the follow-on to GGSS.
GMSE (Dev, Sust, Evol)
GEO Ground Project Conclusion
• The GEO Ground System has been tremendously successful
– Supports the GOES-R satellite constellation with 4 satellites in orbit
– Integrated all capabilities to support the SWFO-L1 launch in 2025
– Meets all performance and quality measures
• Aligning with the NESDIS enterprise vision
• Executing an evolutionary plan through 2028
– Migrating capabilities to the cloud
– Simplifying what remains on-premise
• Defining the plan beyond 2028
– Looking for industry feedback on evolutionary approaches for the GMSE effort:
• Resize
• Expand
• Innovate
• Combination
• Follow-on GMSE effort focuses on sustaining the system for the current missions and evolving for GeoXO 34November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Break
15 Minutes
Remember, if you've got a question written down on the index card, please hand it in to a Government representative
GEO Ground System Current & Evolutionary Path
Kevin McMahon, GEO Ground Project Chief Engineer
70 Minutes
GEO Ground System Overview Agenda
• Key Ground System responsibilities and existing solution
• Goals that drive evolution
• Current evolution activities
• Anticipated GGSS end state
• Key GeoXO mission deltas
• Evolution approaches
• Conclusion
37GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
GEO Ground System Overview (2024)
November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day 38
Refer to the Backup Content Section for a table of acronyms and definitions
GEO Ground "By the Numbers"
39November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
IT Security
~ 330 NIST 800-53 security controls
~ 4,000 firewall rules
- Compliance with DOC and NOAA requirements
~ 15 Primary external interfaces
~23 Distinct site/zone/environments
Hardware
~ 450 workstations deployed (Dell)
~ 550 servers deployed (95% Dell)
~ 260 racks of equipment (Dell, Cisco, F5, IBM, Juniper etc.)
~ 90 miles of rack cabling
~ 215 TFLOPS product processing capability
- 6 tri-band 16.4m antennas (S/L/X)
~ 500 Unique hardware components
Software
~ 3M SLOC of developed software
~ 440 operational OTS software packages (RHEL7, OpenAudIT, Oracle RDBMS and Coherence, ClearCase/ClearQuest, IBM Tivoli Suite, AD, etc.)
~ 5M SLOC of test code
~100 tools managed outside of the sustainment vendor
L3Harris Factory, Melbourne, FL NCWCP, College Park, MD
3 Operational Sites:
- NSOF
- WCDAS
- CBU
Maintained Artifacts
~ 20 Document Categories and 94 Unique Document IDs
~ 850 Unique Word, Powerpoint, Excel, PDF Files
- More than 50K pages/slides
~ 2,400 Drawings
2 Operational Support Locations
Functional View of the Architecture
• 3 primary sites
- Operators located at NSOF
- Antennas at WCDAS/CBU
- CBU fully redundant for WCDAS
• Cloud services deployed in AWS
• Key external interfaces
- Data users
▪ National Weather Service (NWS) Advanced Weather Interactive Processing System
(AWIPS)
▪ GOES-R Rebroadcast receivers
- Further data generation and distribution
▪ Product Distribution and Access (PDA)
▪ National Centers for Environmental
Information (NCEI)
▪ Space Weather Prediction Center (SWPC)
- Radio Frequency (RF) links to GOES-R satellites
November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day 40
GeoCloud Services SEIT-019A-MSCDR2-R20.vsdx
14 October 2024
WCDASNSOFCBU
GRB
TLM
CMD
AWIPS
Sectorized CMI Gridded GLM
L0, L1b, L2+, GRB Sectorized CMI, Gridded GLM
Product Users
L0 Pkt, GRB
Enterprise Management
- Monitor
- Supervise
L1b, L2+
Raw Data, GRB, TLM
Sectorized CMI Gridded GLM
Enterprise Management
- Monitor
- Superv ise
Product Distribution
- Format
- Secto rize
- Distribute
A n c ill a ry
D a ta
GRB,
CMD
GRB
CMD
TLM
CLASS
L0, L1b, L2+, GRB Sectorized CMI, Gridded GLM
HRIT/EMWIN
GL0ASc
GRB
L1b,L2+
GOES East
GOES West
Mission Management
- TT&C
Product Generation
- L0
- L1b
- L2+ GLM
- L2+ CMI
- GRB
Product Distribution
- Format
- Secto rize
- Distribute
Product Distribution
- Forma t
- Distribute
L0 Pkt, GRB
GRB
Raw Data, GRB, TLM
GRB,
CMD
Enterprise Management
- Monitor
- Supervise
Product Distribution & Access (PDA)
GOES-R Antenna
HRIT/EMWIN
GOES-R Antenna
Mission Management
- TT&C
Product Generation
- L0
- L1b
- L2+ GLM
- L2+ CMI
- GLM
L2+
L0 (CCOR-1)L0 (CCOR-1)
NCEI-NC
SWPC/SWPC APS
Mission Management
- TT&C
Product Generation
- Recover L1b
- L2+
L0, L1b, L2+
SCMI, GGLM
GPAS USER
2eGRES 2eGRES 2eGRES
2 eGRESc eGRESc USER
L0, L2+CMI,
L2+GLM
L0, L2+CMI,
L2+GLM
eGRES
GeoStream GeoStream USER
L0, L1b, L2+
SWFO L0
SCMI, GGLM
GRB
L0
L0
GPAS
DCS
Effectivity E01: SWFO
SWFO L0
Packet Data
S W
FO
L
D a ta
S tr e a m
SWFO L0
Packet Data
GEO Ground System Current State
• With SWFO C2 added
SWFO Antenna Network
SWFO C2
SWFO Antenna Network
SWFO C2
TLM,
Ranging
CMD,
Ranging
TLM,
Ranging
CMD,
Ranging
Primary Processing
Backup Processing
Backup Ground Processing
External Systems
Primary Ground Processing
NOAA5050
LEGEND
Administrative
SWFO-L1
Mission
Goals That Drive Evolution
41November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Total Lifecycle Cost (Reducing labor and material)
- Development
- Operations (ease of operations/operability)
- Maintenance
- Sustainment (obsolescence)
IT Security/Risk Management
- Vulnerability management
- Reduced surface threat area
- Proactive security posture
- Align with Commerce, NOAA IT Security
NESDIS Enterprise Citizenship
- Unified tooling (common services)
- Integrating with NESDIS Enterprise Services
Mission Responsibility
- Meet multiple mission needs based on functional and performance requirements, including all NFRs
- Rate of Change
Goal: Lifecycle Cost Management
Total Lifecycle Cost = what is the total cost to architect, develop, sustain, and overall maintain the system?
42November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
C o st
Time (Years)
Approach C
Approach B
Approach A
When selecting an evolution approach we know there will be upfront costs. The question becomes, based on the evolution approach selected, what will the TLC be (sum of labor and resources) over a specified time period?
Goal: NESDIS Enterprise Citizenship
43November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
• NESDIS (OCS & OSPO) are providing enterprise-scale common services based on cloud technologies via the NESDIS Common Cloud Framework (NCCF)
• GEO Ground interfaces with the NCCF and will adjust as it evolves
Current NCCF Diagram
Evolution Activities Through 2028
44November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Successful launch of final GOES-R series satellite & handover of Ops to the Office of Satellite and Product Operations (OSPO) has evolved the Operations Concept
Exploring capabilities that can be retired or slimmed down Case example: operationalization of all instruments and algorithms eliminates the need for dedicated workstations at the National Centers for Weather and Climate Prediction (NCWCP)
Retirement
Cloud Migration
On-Premise Footprint Reduction
Migration of existing on-premises Data Operations capability into cloud technologies
Three step process
1. Proof of Concept
2. Prototype
3. Operationalize
Approaches:
• Refactoring capabilities into cloud-native solutions
• Adopting SAFe® Agile processes
Decommission of on-premise HW and reorganization of environments post cloud migration
Expected results:
• Minimize physical infrastructure while retaining IT Sec
• Recover hardware components to increase spare stocks
• Reduce active hardware/software licenses
• Significant increase in cloud presence
– Data Operations (L1b and L2+) in Cloud
• Reduced on-premise footprint and environments
• Adopt contemporary agile process (IaC, CI/CD, etc.)
Anticipated GGSS End State GEO Ground System
Projected state late CY2027
• L2+,L1b & MLS Operational in the Cloud
• Final PDA in the Cloud
GCCS
L2+ Product Generation & Distribution
GRB
GRB
L1b Product Generation & Distribution
WCDASNSOFCBU
TLM
CMD
Enterprise Management
- Monitor
- Supervise
Raw Data, GRB, TLM
Enterprise Management
- Monitor
- Supervise
CMD
CMD
TLM
GOES East
GOES West
Mission Management
- TT&C
Raw Data, GRB, TLM
CMD
Enterprise Management
- Monitor
- Supervise
GOES-R Antenna GOES-R Antenna
Mission Management
- TT&C
Mission Management
- TT&C
2eGRES 2eGRES 2eGRESS W
FO
L
P a c ke t
D a ta
S W
FO
L
D a ta
S tr e a m
S W
FO
L
P a c ke t D a ta
L0 Pkt, GRB
HRIT/EMWIN
GRB
HRIT/EMWIN
DCS
L0 Pkt, GRB
S W
FO
L
D a ta S tr e a m
NCCF
GeoCloud Services
L0, L1b, GRB
SCMI, GGLM
GL0ASc NCEI-NC
SWPC/SWPC APS
L0, L1b, L2+
SCMI, GGLM
GPAS USER
2 eGRESc eGRESc USEReGRES
L0
L0
GPAS
Ancillary Data
GRB
L2+
Sectorized CMI Gridded GLM
L2+
SWFO L0
Product Dissemination
Service
AWIPS
L1 b
, L
L0, L1b, SCMI, GGLM
GeoStream GeoStream USER
L0 (CCOR-1)
GRB
Product Users
CLASS
SWFO Antenna Network
SWFO C2
SWFO Antenna Network
SWFO C2
TLM,
RangingCMD, Ranging
TLM,
Ranging
CMD,
Ranging
L1 b
, S C
M I, G
G L
M
SEIT-019A-MSCDR2-R20.vsdx 14 October 2024
Effectivity E04: NCCF Product Dissemination Service
Operational
Backup Ground Processing
External Systems
Primary Ground Processing
SWFO-L1
Mission
LEGEND
Primary Processing Backup Processing
Administrative
NOAA5065-2
NOAA5065
FISMA
NOAA5050
Key GeoXO Mission Deltas
46November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Topic GOES-R Constellation GeoXO Constellation
Number of Satellites 4 Satellites
2 Operational (East, West) 2 In-Orbit spares
6 Satellites 3 Operational (East, West, Central)
▪ Additional antenna capacity ~ FY2036
3 In-Orbit spares
Satellite Configurations Single satellite configuration:
Imager (ABI), Lightning (GLM), and SWx Instruments
Two satellite configurations:
Imager (GXI), Lightning (LMX), & Ocean Color (OCX) Instruments
Sounder (GXS), Atmospheric Composition (ACX) Instruments
▪ First GeoXO Sounder satellite launching in FY2036
Product Responsibility Responsible for L1b, L2 PG; all Product Distribution, including KPPs; and GRB distribution
Allocation of some functions to the NCCF (OCS/OSPO), such as L2 PG; all Product Distribution, including HAPs;
and GRB equivalent stream generation
Optimal Path to the Future GEO Ground System
GEO Ground System (2024)
GEO Ground System (2028)
Cloud
On-Prem
What should we Resize by adding capacity?
GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Cloud
On-Prem
Future GEO Ground System (2030s, 2040s, 2050s)What should we Expand by adding new elements or environments?
Where should we Innovate by creating something new?
What is the best Combination of approaches to efficiently meet our goals?
Is there Something Else we haven't considered?
Conclusion
• GEO Ground System:
– Successfully executing the current mission and meeting all performance requirements
– Must evolve to incorporate GeoXO requirements
– Must remain operational through 2036 for GOES-R, 2035 for SWFO-L1, and 2055 for GeoXO
• GEO Ground Project:
– Defined goals and objectives
– An overall evolution concept
• Near-Term: High-level approach through 2028
• Long-Term: Currently establishing the plan for 2028 and beyond
• Seeking industry input to help refine and inform long-term evolution plan
– Technologies and strategies
– Impacts to LCC, IT Security and Operations
• Input from your RFI responses may inform our evolutionary path for 2028 and beyond
48GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Contract & Closing Remarks
Jerry Robertson, NOAA Contracting Officer
10 Minutes
Government/Vendor 1:1 Session Ground Rules
• The Government/Vendor one-on-one (1:1) sessions will start at 1:00p ET here at the Visitor Center
– There are six sessions scheduled for this afternoon
– The remaining sessions will be conducted virtually on November 8 and November 12
• Each vendor that requested a 1:1 session will have 25 minutes with the Government audience
• The Government/Vendor 1:1 sessions are an opportunity for the vendor to discuss and demonstrate their capabilities
• The Government is in receive mode during these sessions (we want to hear from you!)
– These sessions are not private Q&A sessions between the two parties. Any question asked that the Government chooses to answer will be added to the post event SAM.gov posting
• Conversations between the Government and Vendor are for Government use only and will not be disseminated
• Just as any of today's discussions, topics discussed during these sessions should not be construed as any form of commitment by the Government
50GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Closing Remarks
Thank you for attending the GEO Ground Project Industry Day Event!
Next Steps for GEO Ground Project:
1. Complete the one-on-one sessions
2. Collate and digitize all questions and answers into a single document.
3. Update the SAM.gov notice with a copy of this presentation, attendee list, and the Q&A document.
4. Publish the final RFI and supporting documents on SAM.gov.
Next Step for Industry Watch SAM.Gov for the RFI and any future postings. Make sure to follow directions in the posting and provide great submissions
If you're scheduled to meet with the Government this afternoon, then we'll see you at your appointed time. For everyone else, thank you for coming out to Greenbelt this morning!
Thank you www.facebook.com/GOESRsatellite www.youtube.com/user/NOAASatellites twitter.com/NOAASatellites www.flickr.com/photos/noaasatellites
For more information visit:
www.goes-r.gov www.nesdis.noaa.gov/geoxo
52GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Lunch Break (12:00 – 1:00)
1 Hour
There are nearby shopping centers with different lunch options (Five Guys, BK, Wendys, Subway, etc.)
Backup Content
54GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
Acronym Definition Acronym Definition
AWIPS The NWS Advanced Weather Interactive Processing System LEO The Office of Low Earth Orbit Observations
AWS Amazon Web Services MM Mission Management
C2 Command & Control NCEI NOAA’s National Centers for Environmental Information
CBU Consolidated Backup Facility NESDIS National Environmental Satellite, Data, and Information Service
CMD Command NSOF NOAA Satellite Operations Facility
CMI Cloud and Moisture Imagery OCS The NESDIS Office of Common Services
DO Data Operations OSPO The NESDIS Office of Satellite & Product Operations
GEO The Office of Geostationary Earth Orbit Observations PD Product Distribution
GGSS Geostationary Ground Sustainment IDIQ Contract PDA Product Distribution & Access
GLM Geostationary Lightning Mapper PG Product Generation
GMSE GEO Ground Multi-Mission Sustainment and Evolution SAM.gov System for Award Management Government Website
GRB GOES ReBroadcast SAN SWFO Antenna Network
HAP High Availability Product SWFO Space Weather Follow-On Program
IaC Infrastructure as Code SWFO-L1 Space Weather Follow-On Lagrange Point 1
KPP Key Performance Parameter SWO The Office of Space Weather Observations
L0 Level Zero (Level 0) Product SWPC The NWS Space Weather Prediction Center
L1b Level One “B” (Level 1b) Product TGRB Terrestrial GRB
L2+ Level Two (Level 2) and Above Products TLM Telemetry
LCC Life Cycle Cost WCDAS Wallops Command & Data Acquisition
Acronyms & Definitions
55November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
GEO Data Processing Levels
56November 7, 2024 GEO Ground System Sustainment & Evolution Industry Day
Level 0 (L0):
• L0 products are observation data received directly from the satellite instruments. The data is not meaningful to most users prior to processing by the ground system.
Level 1b (L1b):
• L1b products are calibrated and, where applicable, geographically corrected, L0 data. This means that the data has been processed so that its values are in standard units of physical quantities.
• For ABI, the L1b product is Radiances. This is useful for users who require radiance units, instead of reflectance/brightness (Kelvin) units.
• All of the instruments have L1b products available except GLM, which is only distributed as an L2+ product.
• For technical information, see the Product User Guide (PUG) Volume 3: L1b Products, Revision 2.3.
Level 2+ Products:
• L2+ products contain environmental physical qualities, such as cloud top height or land surface temperature. Aside from the GLM Lightning Detection Product, the data source for these products is the ABI L1b data.
• The mission-critical ABI product is Cloud and Moisture Imagery (CMI), which utilizes all 16 ABI spectral bands, and is used to generate an array of products aiding forecasters in monitoring and predicting weather hazards.
• For technical information, see the GOES-R Series Product Definition & Users’ Guide (PUG) Volume 5: L2+ Products, Revision 2.4.
SOURCE: Beginner’s Guide to GOES-R Series Data https://www.ospo.noaa.gov/resources/documents/PUG/GS%20Series%20416-R-PUG-L2%20Plus-0349%20Vol%205%20v2.4.pdf https://www.goes-r.gov/downloads/resources/documents/Beginners_Guide_to_GOES-R_Series_Data.pdf
57GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
58GEO Ground System Sustainment & Evolution Industry DayNovember 7, 2024
File details come from the government source that posted it. Updated .