General_Conditions.pdf

PDF 269 KB Posted

Attached to
Wastewater Treatment Plant Phase 2 - Collection System Rehabilitation
Solicitation number
2027-06B
Issued by
Fort Bend County, Round Mountain Town, Texas

About this file

Summary

This document comprises the General and Special Conditions of Agreement for the Wastewater Treatment Plant No. 2 - Collection System Rehabilitation Project (Rosenberg Bid No. 2027-06B) for the City of Rosenberg, Texas, located in Fort Bend County. The project scope includes construction of approximately 4,365 linear feet of 8-inch HDPE sanitary sewer pipe by pipe bursting method, 1,623 linear feet of 8-inch HDPE pipe by static pipe bursting method, 210 linear feet of 8-inch HDPE sanitary sewer pipe by trenchless method, 345 linear feet of 12-inch PVC sanitary sewer pipe by open cut method, 355 linear feet of 8-inch PVC sanitary sewer pipe by open cut method, 60 linear feet of 8-inch PVC by trenchless method, six new standard-size sanitary sewer manholes, one new drop sanitary sewer manhole, and rehabilitation of existing brick and precast manholes with all appurtenances. The contract includes four alternate bid options covering additional footage in various pipe materials and methods. The work is divided into two primary areas within the City of Rosenberg's WWTP2 service area. The estimated project budget is $849,025 with an estimated completion period of 500 calendar days. The Engineer for the project is Kaluza, Inc., and the contract documents consist of 36 drawing sheets with detailed specifications, construction details, and traffic control plans.

Payment shall be made monthly based on the unit prices established in the Proposal with a five percent retainage until final completion and acceptance. The contractor must furnish separate performance and payment bonds, each in the amount of 100 percent of the total contract price, from surety companies acceptable to the Owner with ratings of at least "A" in the current Best Key Rating Guide for contracts exceeding $100,000. The contractor is responsible for all permits, fees, utility services, material testing, site maintenance, and restoration, including three months of ground surface maintenance following final acceptance. A one-year warranty from the date of final completion is required for all work and materials. The contractor may work Saturdays with 48 hours prior approval from the City at an hourly inspector rate of $150.00. Additional provisions require hydromulch for site restoration throughout the project limits with one row of full sodding 18 inches wide behind curbs or sidewalks, and specific material requirements for water service line connections including copper for the short side and EndoPure PE-4710 in sleeve or approved equal for the long side.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GC-1

GENERAL CONDITIONS OF THE AGREEMENT

TABLE OF CONTENTS

Page

1. Definition of Terms

1.01 Owner, Contractor and Engineer

1.02 Contract Documents

1.03 Subcontractor

1.04 Written Notice

1.05 Work

1.06 Extra Work

1.07 Working Day

1.08 Calendar Day

1.09 Substantially Completed

2. Responsibilities of the Engineer and the Contractor

2.01 Owner-Engineer Relationship

2.02 Professional Inspection by Engineer

2.03 Payments for Work

2.04 Initial Determinations

2.05 Objections

2.06 Lines and Grades

2.07 Contractor's Duty and Superintendence

2.08 Contractor's Understanding

2.09 Character of Workmen

2.10 Contractor's Buildings

2.11 Sanitation

2.12 Shop Drawings

2.13 Preliminary Approval

2.14 Defects and Their Remedies

2.15 Changes and Alterations

3. General Obligations and Responsibilities

3.01 Keeping of Plans and Specifications Accessible

3.02 Ownership of Drawings

3.03 Adequacy of Design

3.04 Right of Entry

3.05 Collateral Contracts

3.06 Discrepancies and Omissions

3.07 Equipment, Materials and Construction Plant

3.08 Damages

3.09 Protection Against Accident to Employees and the Public

3.10 Performance and Payment Bonds

3.11 Losses from Natural Causes

3.12 Protection of Adjoining Property

3.13 Protection Against Claims of Sub-Contractors, Etc

GC-2

3.14 Protection Against Royalties or Patented Invention

3.15 Laws and Ordinances

3.16 Assignment and Subletting

3.17 Indemnification

3.18 Contractor's Liability Insurance

3.18.1 Certificate of Insurance

4. Prosecution and Progress

4.01 Time and Order of Completion

4.02 Extension of Time

4.03 Hindrances and Delays

4.04 Guaranty/Maintenance Bond

5. Measurement and Payment

5.01 Quantities and Measurements

5.02 Estimated Quantities

5.03 Price of Work

5.04 Partial Payment

5.05 Use of Completed Portions

5.06 Final Completion and Acceptance

5.07 Final Payment

5.08 Payments Withheld

5.09 Remedies

5.10 Delayed Payments

6. Extra Work and Claims

6.01 Change Orders

6.02 Minor Changes

6.03 Extra Work

6.04 Time of Filing Claims

6.05 Mediation

7. Abandonment of Contract

7.01 Abandonment by Contractor

7.01.1 7.01.2

7.02 Abandonment by Owner

8. Miscellaneous Provisions

8.01 8.02 8.03

GC-3

GENERAL CONDITIONS OF THE AGREEMENT

1. DEFINITIONS OF TERMS

1.01 OWNER, CONTRACTOR AND ENGINEER. The OWNER, the CONTRACTOR and the ENGINEER are those persons or organizations identified as such in the Agreement and are referred to throughout the Contract Documents as if singular in number and masculine in gender. The term ENGINEER means the ENGINEER or his duly authorized representative.

The ENGINEER shall be understood to be the ENGINEER of the OWNER, and nothing contained in the Contract Documents shall create any contractual or agency relationship between the ENGINEER and the CONTRACTOR.

1.02 CONTRACT DOCUMENTS. The Contract Documents shall consist of the Notice to Bidders (Advertisement), Information and Instructions to Bidders (Instructions), Bid Proposal, signed Contract/Agreement (Contract), Performance and Payment Bonds (when required), Special Bonds (when required), General Conditions of the Agreement, Special Conditions of the Agreement (when required), Technical Specifications, Plans and all modifications thereof incorporated in any of the documents before the execution of the agreement.

The Contract Documents are complementary, and what is called for by anyone shall be as binding as if called for by all. In case of conflict between any of the Contract Documents, priority of interpretation shall be in the following order: Signed Contract (Contract), Performance and Payment Bonds, Special Bonds (if any), Bid Proposal, Special Conditions of the Agreement, Notice to Bidders, Technical Specifications, Plans and General Conditions of the Agreement. In case of claims of ambiguity, interpretation shall be by the Rosenberg City Council.

1.03 SUBCONTRACTOR. The term Subcontractor, as employed herein, includes only those having a direct contract with the CONTRACTOR and it includes one who furnishes material worked to a special design according to the plans or specifications of this work, but does not include one who merely furnishes material not so worked.

1.04 WRITTEN NOTICE. Written notice shall be deemed to have been duly served if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended or if delivered at or sent by registered mail to the last business address known to him who gives the notice.

1.05 WORK. The CONTRACTOR shall provide and pay for all materials, supplies, machinery, equipment, tools, superintendence, labor, services, insurance, and all water, light, power, fuel, transportation and other facilities necessary for the execution and completion of the work covered by the contract documents. Unless otherwise specified, all materials shall be new, and both workmanship and materials shall be of a good quality. The CONTRACTOR shall, if required, furnish satisfactory evidence as to the kind and quality of materials. Materials or work described in words which so applied have a well-known technical or trade meaning shall be held to refer to such recognized standards.

1.06 EXTRA WORK. The term "Extra Work" as used in this contract shall be understood to mean and include all work that may be required by the ENGINEER or OWNER to be done by the CONTRACTOR to accomplish any change, alteration or addition to the work shown upon

GC-4

the plans, or reasonably implied by the specifications, and not covered by the CONTRACTOR'S Bid Proposal, except as provided under "Changes and Alterations", herein.

1.07 WORKING DAY. A "Working Day" is defined as any day not including Saturdays, Sundays or any legal holidays, in which weather or other conditions, not under the control of the CONTRACTOR, will permit construction of the principal units of the work for a period of not less than seven (7) hours between 7:00 a.m. and 6:00 p.m.

1.08 CALENDAR DAY. "Calendar Day" is any day of the week or month, no days being excepted.

1.09 SUBSTANTIALLY COMPLETED. By the term "substantially completed" is meant that the structure has been made suitable for use of occupancy or the facility is in condition to serve its intended purpose but still may require minor miscellaneous work and adjustment.

2. RESPONSIBILITIES OF THE ENGINEER AND THE CONTRACTOR

2.01 OWNER-ENGINEER RELATIONSHIP. The ENGINEER will be the OWNER'S representative during construction. The duties, responsibilities and limitations of authority of the ENGINEER as the OWNER'S representative during construction are as set forth in the Contract Documents and shall not be extended or limited without written consent of the OWNER, and all of OWNER'S instructions to the CONTRACTOR shall be issued through the ENGINEER. The ENGINEER shall have authority to act on behalf of the OWNER only to the extent provided by this AGREEMENT.

2.02 PROFESSIONAL INSPECTION BY ENGINEER. The ENGINEER shall make periodic visits to the site to familiarize himself generally with the progress of the executed work and to determine if such work generally meets the essential performance and design features and the technical and functional engineering requirements of the Contract Documents; provided and except, however, that the ENGINEER shall not be responsible for making any detailed, exhaustive, comprehensive or continuous on-site inspection of the quality or quantity of the work or be in any way responsible, directly or indirectly, for the construction means, methods, techniques, sequences, quality, procedures, programs, safety precautions or lack of same incident thereto or in connection therewith. Notwithstanding any other provision of this agreement or any other Contract Document, the ENGINEER shall not be in any way responsible or liable for any acts, errors, omissions or negligence of the CONTRACTOR, any subcontractor or any of the CONTRACTOR'S or subcontractor's agents, servants or employees of any other person, firm or corporation performing or attempting to perform any of the work.

2.03 PAYMENTS FOR WORK. The ENGINEER shall review CONTRACTOR'S applications for payment and supporting data, determine the amount owed to the CONTRACTOR and approve, in writing, payment to CONTRACTOR in such amounts; such approval of payment to CONTRACTOR constitutes a representation to the OWNER of ENGINEER'S professional judgment that the work has progressed to the point indicated to the best of his knowledge, information and belief, but such approval of an application for payment to CONTRACTOR shall not be deemed as a representation by ENGINEER that ENGINEER has made any examination to determine how or for what purpose CONTRACTOR has used the moneys paid on account of the Contract price.

GC-5

2.04 INITIAL DETERMINATIONS. The ENGINEER initially shall determine all claims, disputes and other matters in question between the CONTRACTOR and the OWNER relating to the execution or progress of the work or the interpretation of the Contract Documents and the ENGINEER'S decision shall be rendered in writing within a reasonable time. Should the ENGINEER fail to make such decision within a reasonable time, resolution shall be as provided in paragraph 6.05.

2.05 OBJECTIONS. In the event the ENGINEER renders any decision which, in the opinion of either party hereto, is not in accordance with the meaning and intent of this contract, either party may file with the ENGINEER within thirty days his written objection to the decision, and by such action may reserve the right to submit the question so raised as provided in paragraph 6.05.

2.06 LINES AND GRADES. Unless otherwise specified, all lines and grades shall be furnished by the ENGINEER or his representative. Whenever necessary, construction work shall be suspended to permit performance of this work, but such suspension will be as brief as practicable and the CONTRACTOR shall be allowed no extra compensation therefore.

The CONTRACTOR shall give the ENGINEER ample notice of the time and place where lines and grades will be needed. All stakes, marks, etc., shall be carefully preserved by the CONTRACTOR, and in case of careless destruction or removal by him or his employees, such stakes, marks, etc., shall be replaced at the CONTRACTOR'S expense.

2.07 CONTRACTOR'S DUTY AND SUPERINTENDENCE. The CONTRACTOR shall give adequate attention to the faithful prosecution and completion of this contract and shall keep on the work, during its progress, a competent superintendent and any necessary assistants.

The superintendent shall represent the CONTRACTOR in his absence and all directions given to him shall be as binding as if given to the CONTRACTOR.

The CONTRACTOR is and at all times shall remain an independent contractor, solely responsible for the manner and method of completing his work under this contract, with full power and authority to select the means, method and manner of performing such work, so long as such methods do not adversely affect the completed improvements, the OWNER and ENGINEER being interested only in the result obtained and conformity of such completed improvements to the plans, specifications and contract.

Likewise, the CONTRACTOR shall be solely responsible for the safety of himself, his employees and other persons, as well as for the protection of the safety of the improvements being erected and the property of himself or any other person, as a result of his operations hereunder. Engineering construction drawings and specifications as well as any additional information concerning the work to be performed passing from or through the ENGINEER shall not be interpreted as requiring or allowing CONTRACTOR to deviate from the plans and specifications, the intent of such drawings, specifications and any other such instructions being to define with particularity the agreement of the parties as to the work the CONTRACTOR is to perform. CONTRACTOR shall be fully and completely liable, at his own expense, for design, construction, installation and use, or non-use, of all items and methods incident to performance of the contract, and for all loss, damage of injury incident thereto, either to person or property, including, without limitation, the adequacy of all temporary supports, shoring, bracing, scaffolding, machinery or equipment, safety precautions or

GC-6

devices, and similar items or devices used by him during construction.

Any review of work in process, or any visit or observation during construction, or any clarification of plans and specifications, by the ENGINEER, or any agent, employee, or representative of either of them, whether through personal observation on the project site or by means of approval of shop drawings for temporary construction or construction processes, or by other means or method, is agreed by the CONTRACTOR to be for the purpose of observing the extent and nature of work completed or being performed, as measured against the drawings and specifications constituting the contract, or for the purpose of enabling CONTRACTOR to more fully understand the plans and specifications so that the completed construction work will conform thereto, and shall in no way relieve the CONTRACTOR from full and complete responsibility for the proper performance of his work on the project, including but without limitation the propriety of means and methods of the CONTRACTOR in performing said contract, and the adequacy of any designs, plans or other facilities for accomplishing such performance. Deviation by the CONTRACTOR from plans and specifications that may have been in evidence during any such visitation or observation by the ENGINEER, or any of his representatives whether called to the CONTRACTOR'S attention or not, shall in no way relieve CONTRACTOR from his responsibility to complete all work in accordance with said plans and specifications.

2.08 CONTRACTOR'S UNDERSTANDING. It is understood and agreed that CONTRACTOR has, by careful examination, satisfied himself as to the nature and location of the work, the conformation of the ground, the character, quality and quantity of the materials to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the work, the general and local conditions, and all other matters which can in any way affect the work under this contract. No verbal agreement or conversation with any officer, agent or employee of the OWNER or ENGINEER either before or after the execution of this contract shall affect or modify any of the terms or obligations herein contained.

2.09 CHARACTER OF WORKMEN. The CONTRACTOR agrees to employ only orderly and competent men, skillful in the performance of the type of work required under this contract, to do the work; and agrees that whenever the ENGINEER shall inform him in writing that any man or men on the work are, in his opinion, incompetent, unfaithful or disorderly, such man or men shall be discharged from the work and shall not again be employed on the work without the ENGINEER'S written consent.

2.10 CONTRACTOR'S BUILDINGS. The building of structures for housing men or the erection of tents or other forms of protection, will be permitted only at such places as the ENGINEER shall direct, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a manner satisfactory to the ENGINEER.

2.11 SANITATION. Necessary sanitary conveniences for the use of laborers on the work, properly secluded from public observation, shall be constructed and maintained by the CONTRACTOR in such manner and at such points as shall be approved by the ENGINEER, and their use shall be strictly enforced.

2.12 SHOP DRAWINGS. The CONTRACTOR shall submit to the ENGINEER, with such promptness as to cause no delay in his own work or in that of any other Contractor, four (4) checked copies, unless otherwise specified, of all shop and/or setting drawings and

GC-7

schedules required for the work of the various trades, and the ENGINEER shall pass upon them with reasonable promptness, making desired corrections. The CONTRACTOR shall make any corrections required by the ENGINEER, file with him two (2) corrected copies and furnish such other copies as may be needed. The ENGINEER'S approval of such drawings or schedules shall not relieve the CONTRACTOR from responsibility for deviations from drawings or specifications, unless he has in writing called the ENGINEER'S attention to such deviations at the time of submission, nor shall it relieve him from responsibility for errors of any sort in shop drawings or schedules. It shall be the CONTRACTOR'S responsibility to fully and completely review all shop drawings to ascertain their effect on his ability to perform the required contract work in accordance with the plans and specifications and within the contract time.

Such review by the ENGINEER shall be for the sole purpose of determining the sufficiency of said drawings or schedules to result in finished improvements in conformity with the plans and specifications, and shall not relieve the CONTRACTOR of his duty as an independent contractor as previously set forth, it being expressly understood and agreed that the ENGINEER does not assume any duty to pass upon the propriety or adequacy of such drawings or schedules, or any means or methods reflected thereby, in relation to the safety of either person or property during CONTRACTOR'S performance hereunder.

2.13 PRELIMINARY APPROVAL. The ENGINEER shall not have the power to waive the obligations of this contract for the furnishing by the CONTRACTOR of good material, and of his performing good work as herein described, and in full accordance with the plans and specifications. No failure or omission of the ENGINEER to discover, object to or condemn any defective work or material shall release the CONTRACTOR from the obligations to fully and properly perform the contract, including without limitations, the obligation to at once tear out, remove and properly replace the same at any time prior to final acceptance upon the discovery of said defective work or material; provided, however, that ENGINEER shall, upon request of the CONTRACTOR, inspect and accept or reject any material furnished, and in event the material has been once accepted by the ENGINEER, such acceptance shall be binding on the OWNER, unless it can be clearly shown that such material furnished does not meet the specifications for this work.

Any questioned work may be ordered taken up or removed for re-examination, by the ENGINEER, prior to final acceptance, and if found not in accordance with the specifications for said work, all expense of removing, re-examination and replacement shall be borne by the CONTRACTOR, otherwise the expense thus incurred shall be allowed as EXTRA WORK, and shall be paid for by the OWNER; provided that, where inspection or approval is specifically required by the specifications prior to performance of certain work, should the CONTRACTOR proceed with such work without requesting prior inspection or approval he shall bear all expense of taking up, removing and replacing this work if so directed by the

ENGINEER.

2.14 DEFECTS AND THEIR REMEDIES. It is further agreed that if the work or any part thereof, or any material brought on the site of the work for use in the work or selected for the same, shall be deemed by the ENGINEER as unsuitable or not in conformity with the specifications, the CONTRACTOR shall, after receipt of written notice thereof from the ENGINEER, forthwith remove such material and rebuild or otherwise remedy such work so that it shall be in full accordance with this contract.

GC-8

2.15 CHANGES AND ALTERATIONS. The CONTRACTOR further agrees that the OWNER may make such changes and alterations as the OWNER may see fit, in the line, grade, form, dimensions, plans or materials for the work herein contemplated, or any part thereof, either before or after the beginning of the construction, without affecting the validity of this contract and the accompanying Performance and Payment Bonds.

If such changes or alterations diminish the quantity of work to be done, they shall not constitute the basis for a claim for damages, or anticipated profits on the work that may be dispensed with. If the amount of work is increased, and the work can fairly be classified under the specifications, such increase shall be paid for according to the quantity actually done and at the unit price, if any, established for such work under this contract, except as provided for unit price as provided under Extra Work. In case the OWNER shall make such changes or alterations as shall make useless any work already done or materials already furnished or used in said work, then the OWNER shall recompense the CONTRACTOR for any material or labor so used, and for any actual loss occasioned by such change, due to actual expenses incurred in preparation for the work as originally planned.

3. GENERAL OBLIGATIONS AND RESPONSIBILITIES

3.01 KEEPING OF PLANS AND SPECIFICATIONS ACCESSIBLE. The ENGINEER shall furnish the CONTRACTOR with an adequate and reasonable number of copies of all plans and specifications without expense to him, and the CONTRACTOR shall keep one copy of the same constantly accessible on the work, with the latest revisions noted thereon.

3.02 OWNERSHIP OF DRAWINGS. All drawings, specifications and copies thereof furnished by the ENGINEER shall not be reused on other work, and, with the exception of the signed contract sets, are to be returned to him on request, at the completion of the work. All models are the property of the OWNER.

3.03 ADEQUACY OF DESIGN. It is understood that the OWNER believes it has employed competent engineers and designers. It is, therefore, agreed that the OWNER shall be responsible for the adequacy of the design, sufficiency of the Contract Documents, the safety of the structure and the practicability of the operations of the completed project; provided the CONTRACTOR has complied with the requirements of the said Contract Documents, all approved modifications thereof, and additions and alterations thereto approved in writing by the OWNER. The burden of proof of such compliance shall be upon the CONTRACTOR to show that he has complied with the said requirements of the Contract Documents, approved modifications thereof and all approved additions and alterations thereto.

3.04 RIGHT OF ENTRY. The OWNER reserves the right to enter the property or location on which the works herein contracted for are to be constructed or installed, by such agent or agents as he may elect, for the purpose of inspecting the work, or for the purpose of constructing or installing such collateral work as said OWNER may desire.

3.05 COLLATERAL CONTRACTS. The OWNER agrees to provide, by separate contract or otherwise, all labor and material essential to the completion of the work specifically excluded from this contact, in such manner as not to delay the progress of the work, or damage said CONTRACTOR, except where such delays are specifically mentioned elsewhere in the

GC-9

Contract Documents.

3.06 DISCREPANCIES AND OMISSIONS. It is further agreed that it is the intent of this contract that all work must be done and all material must be furnished in accordance with the generally accepted practice, and in the event of any discrepancies between the separate contract documents, the priority of interpretation defined under paragraph 1.02, "Contract Documents" shall govern. In the event that there is still any doubt as to the meaning and intent of any portion of the contract, specifications or drawings, the ENGINEER shall define which is intended to apply to the work subject to the terms and conditions contained herein.

3.07 EQUIPMENT, MATERIALS AND CONSTRUCTION PLANT. The CONTRACTOR shall be responsible for the care, preservation, conservation, and protection of all materials, supplies, machinery, equipment, tools, apparatus, accessories, facilities, all means of construction, and any and all parts of the work, whether the CONTRACTOR has been paid, partially paid, or not paid for such work, until the entire work is completed and accepted.

3.08 DAMAGES. In the event the CONTRACTOR is damaged in the course of the completion of the work by the act, neglect, omission, mistake or default of the OWNER, or of the ENGINEER, or of any other CONTRACTOR employed by the OWNER upon the work, thereby causing loss to the CONTRACTOR, the OWNER agrees that he will reimburse the CONTRACTOR for such loss, as determined by OWNER. In the event the OWNER is damaged in the course of the work by the act, negligence, omission, mistake or default of the CONTRACTOR, or should the CONTRACTOR unreasonably delay the progress of the work being done by others on the job so as to cause loss for which the OWNER becomes liable, then the CONTRACTOR shall reimburse the OWNER for such loss.

3.09 PROTECTION AGAINST ACCIDENT TO EMPLOYEES AND THE PUBLIC. The CONTRACTOR shall at all times exercise reasonable precautions for the safety of employees and others on or near the work and shall comply with all applicable provisions of Federal, State, and Municipal safety laws and building and construction codes. All machinery and equipment and other physical hazards shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of the Associated General Contractors of America except where incompatible with guards, safe walkways, ladders, bridges, gangplanks and other safety devices. The safety precautions actually taken and their adequacy shall be the sole responsibility of the CONTRACTOR, acting at his discretion as an independent contractor.

3.10 PERFORMANCE AND PAYMENT BONDS. Unless otherwise specified, it is further agreed by the parties to this Contract that the CONTRACTOR will execute separate performance and payment bonds, each in the sum of one hundred percent (100%) of the total contract price, in standard forms for this purpose, guaranteeing faithful performance of the work and the fulfillment of any guarantees required, and further guaranteeing payment to all persons supplying labor and materials or furnishing him any equipment in the execution of the Contract. It is agreed that this Contract shall not be in effect until such performance and payment bonds are furnished and approved by the OWNER. Unless otherwise approved in writing by the OWNER, the surety company underwriting the bonds shall be acceptable according to the latest list of companies holding certificates of authority from the Secretary of the Treasury of the United States.

GC-10

Unless otherwise specified, the cost of the premium for the performance and payment bonds shall be included in the CONTRACTOR'S proposal.

Additional Language for Contracts over $100,000

Surety Companies executing bonds must have a rating of at least “A” in the current Best Key Rating Guide or appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the State of Texas. A bond that is made, given, tendered, or filed under Chapter 53, Property Code, or Chapter 2253, Government Code, may be executed only by a surety company that is authorized and admitted to write surety bonds in this state. If the amount of the bond exceeds $100,000, the surety must also:

(1) hold a certificate of authority from the United States secretary of the treasury to qualify as a surety on obligations permitted or required under federal law; and (2) have obtained reinsurance for any liability in excess of $100,000 from a reinsurer that is authorized and admitted as a reinsurer in this state and is the holder of a certificate of authority from the United States Secretary of the Treasury to qualify as a surety or reinsurer on obligations permitted or required under federal law. In determining whether the surety on the bond or the reinsurer holds a certificate of authority from the United States Secretary of the Treasury, a party may conclusively rely on the list of companies holding certificates of authority as acceptable sureties on federal bonds and as acceptable reinsuring companies published in the Federal Register by the United States Department of the Treasury covering the date on which the bond was executed. A purchaser, insurer of title, or lender acquiring or insuring an interest or title to real property may also conclusively rely on and is protected by a statement on a recorded bond or a sworn statement by the surety that is recorded and refers to the specific recorded bond and that states that, at the time the bond was executed, the surety:

(1) was holder of a certificate of authority from the United States Secretary of the Treasury to qualify as a surety on obligations permitted or required under federal law; and (2) had reinsured any liability in excess of $100,000 by a reinsurer holding a certificate of authority described previously in (1).

3.11 LOSSES FROM NATURAL CAUSES. Unless otherwise specified, all loss or damage to the CONTRACTOR arising out of the nature of the work to be done, or from the action of the elements, or from any unforeseen circumstance in the prosecution of the same, or from unusual obstructions or difficulties which may be encountered in the prosecution of the work, shall be sustained and borne by the CONTRACTOR at his own cost and expense.

3.12 PROTECTION OF ADJOINING PROPERTY. The said CONTRACTOR shall take proper means to protect the adjacent or adjoining property or properties in any way encountered, which might be injured or seriously affected by any process of construction to be undertaken under this Agreement, from any damage or injury by reason of said process of construction; and he shall be liable for any and all claims for such damage on account of his failure to fully protect all adjoining property. The CONTRACTOR agrees to indemnify, save and hold harmless the OWNER and ENGINEER as provided herein, against any claim or claims for damages due to any injury to any adjacent or adjoining property, arising or growing out of the performance of the Contract Documents.

3.13 PROTECTION AGAINST CLAIMS OF SUB-CONTRACTORS, LABORERS,

MATERIALMEN AND FURNISHERS OF MACHINERY, EQUIPMENT AND SUPPLIES.

The CONTRACTOR agrees that he will indemnify and save the OWNER and ENGINEER

GC-11

harmless from all claims growing out of the lawful demands of sub-contractors, laborers, workmen, mechanics, materialmen and furnishers of machinery and parts thereof, equipment, power tools and all supplies, including commissary, incurred in the furtherance of the performance of the work required by the Contract Documents as provided herein. When so desired by the OWNER, the CONTRACTOR shall furnish satisfactory evidence that all obligations of the nature herein above designated have been paid, discharged or waived. If the CONTRACTOR fails so to do, then the OWNER may, at the option of the OWNER, either pay directly any unpaid bills, of which the OWNER has written notice, or withhold from the CONTRACTOR'S unpaid compensation a sum of money deemed reasonably sufficient to liquidate any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully discharged, whereupon payments to the CONTRACTOR shall be resumed in full, in accordance with the terms of this contract, but in no event shall the provisions of this sentence be construed to impose any obligation upon the OWNER by either the CONTRACTOR or his Surety.

3.14 PROTECTION AGAINST ROYALTIES OR PATENTED INVENTION. The

CONTRACTOR shall pay all royalties and license fees, and shall provide for the use of any design, devise, material or process covered by letters patent or copyright by suitable legal agreement with the patentee or owner. The CONTRACTOR shall defend all suits or claims for infringement of any patent or copyright rights and shall indemnify and save the OWNER and ENGINEER harmless from any loss on account thereof, except that the OWNER shall defend all such suits and claims and shall be responsible for all such loss when a particular design, devise, material or process or the project of a particular manufacturer or manufacturers is specified or required by OWNER; provided, however, if choice of alternate design, devise, material or process is allowed to the CONTRACTOR, then CONTRACTOR shall indemnify and save OWNER harmless from any loss on account thereof.

Notwithstanding anything in this paragraph, to the contrary, if the material or process specified or required by the OWNER is an infringement, the CONTRACTOR shall be responsible for such loss unless he promptly gives such information to the OWNER.

3.15 LAWS AND ORDINANCES. The CONTRACTOR shall at all times observe and comply with all Federal, State and local laws, ordinances and regulations, which in any manner affect the contract or the work, and shall indemnify and save harmless the OWNER and ENGINEER against any claim arising from the violation of any such laws, ordinances, and regulations whether by the CONTRACTOR or his employees as provided for in the Contract. If the CONTRACTOR observes that the plans and specifications are at variance therewith, he shall promptly notify the ENGINEER in writing, and any necessary changes shall be adjusted as provided in the Contract for changes in the work. If the CONTRACTOR performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the ENGINEER, he shall bear all costs arising therefrom. In case the OWNER is a body politic and corporate, the law from which it derives its powers, insofar as the same regulates the objects for which, or the manner in which, or the conditions under which the OWNER may enter into contract, shall be controlling, and shall be considered as part of this contract, to the same effect as though embodied herein.

3.16 ASSIGNMENT AND SUBLETTING. The CONTRACTOR further agrees that he will retain personal control and will give his personal attention to the fulfillment of this contract and that he will not assign by Power of Attorney, or otherwise, or sublet said contract without the written consent of the OWNER and ENGINEER, and that no part or feature of the work

GC-12

will be sublet to anyone objectionable to the ENGINEER or the OWNER. The CONTRACTOR further agrees that the subletting of any portion or feature of the work, or materials required in the performance of this contract, shall not relieve the CONTRACTOR from his full obligations to the OWNER, as provided by this Agreement.

3.17 INDEMNIFICATION. The CONTRACTOR shall defend, indemnify and hold harmless the OWNER and the ENGINEER and their respective officers, agents and employees, from and against all damages, claims, losses, demands, suits, judgments and costs, including reasonable attorneys' fees and expenses, arising out of or resulting from the performance of the work provided in accordance with the Contract In addition, OWNER reserves the right to retain its own legal counsel and experts, at Contractor’s expense in the event of litigation.

3.18 INSURANCE. The CONTRACTOR at his own expense shall purchase, maintain and keep in force such insurance as will protect him from claims set forth below which may arise out of or result from the CONTRACTOR'S operations under the Contract, whether such operations be by himself or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable:

(1) Workmen's compensation claims, disability benefits and other similar employee benefit acts;

(2) Claims for damages because of bodily injury, occupational sickness or disease, or death of his employees, and claims insured by usual bodily injury liability coverages;

(3) Claims for damages because of bodily injury, sickness or disease, or death of any person other than his employees, and claims insured by usual bodily injury liability coverages;

(4) Claims for damages because of injury to or destruction of tangible property, including loss of use resulting therefrom; and

(5) Any and all other claims as provided in the Contract.

3.18.1 CERTIFICATE OF INSURANCE. Before commencing any of the work, CONTRACTOR shall file with the OWNER valid Certificates of Insurance acceptable to the OWNER and the ENGINEER. Such Certificates shall contain a provision that coverages afforded under the policies will not be canceled until at least thirty (30) days' prior written notice has been given to the OWNER.

The CONTRACTOR shall also file with the OWNER valid Certificates of Insurance covering all sub-contractors.

4. PROSECUTION AND PROGRESS

4.01 TIME AND ORDER OF COMPLETION. It is the meaning and intent of this contract, unless otherwise herein specifically provided, that the CONTRACTOR shall be allowed to prosecute his work at such times and seasons, in such order of precedence, and in such

GC-13

manner as shall be most conducive to economy of construction: provided, however, that the order and the time of prosecution shall be such that the work shall be substantially completed as a whole and in part, in accordance with the Contract Documents, specifically pursuant to the plans and specifications, and within the time of completion designated in the Proposal;

provided, also, that when the OWNER is having other work done, either by contract or by his own force, the ENGINEER may direct the time and manner of constructing the work done under this contract, so that conflict will be avoided and the construction of the various works being done for the OWNER shall be harmonized.

The CONTRACTOR shall submit, at such times as may reasonably be requested by the ENGINEER, schedules, which shall show the order in which the CONTRACTOR proposes to carry on the work, with dates at which the CONTRACTOR will start the several parts of the work, and estimated dates of completion of the several parts.

4.02 EXTENSION OF TIME. Should the CONTRACTOR be delayed in the completion of the work by any act or neglect of the OWNER or ENGINEER, or of any employee of either, or by other contractors employed by the OWNER or changes ordered in the work, or by strikes, lockouts, fires, and unusual delays by common carriers, or unavoidable cause or causes beyond the CONTRACTOR'S control, or by any cause which the OWNER shall decide justifies the delay, then an extension of time shall be allowed for completing the work, sufficient to compensate for the delay, the amount of the extension to be determined by the ENGINEER, provided, however, that the CONTRACTOR shall give the ENGINEER prompt notice in writing of the cause of such delay. No such extension of time shall release Contractor or surety on its performance bond from all CONTRACTOR’S obligations hereunder, which shall remain in full effect until discharge pursuant to the Contract Documents.

4.03 HINDRANCES AND DELAYS. No claims shall be made by the CONTRACTOR for damages resulting from hindrances or delays from any cause except when direct and unavoidable extra cost to CONTRACTOR is caused by failure of the OWNER to provide information or material, if any, which is to be furnished by OWNER or access to the work.

When such extra compensation is claimed, a written statement thereof shall be presented by CONTRACTOR to OWNER, and if by OWNER found correct shall be approved. If delay is caused by specific orders given by OWNER to stop work or by performance of extra work or by failure of OWNER to provide material or necessary instructions for carrying on the work, then such delay will entitle CONTRACTOR to an equivalent extension of time, CONTRACTOR’S application of which shall, however, be subject to approval by OWNER.

No such extension of time shall release CONTRACTOR or surety on its performance bond from all of CONTRACTOR’S obligations hereunder, which shall remain in full force until discharge pursuant to the Contract Documents.

4.04 GUARANTY/MAINTENANCE BOND. The CONTRACTOR shall furnish the OWNER with a written guaranty/maintenance bond on all workmanship and materials provided by CONTRACTOR on the work/project. The written guaranty shall be made to OWNER in a form satisfactory to OWNER’S legal counsel, guaranteeing all the work under the Contract Documents to be free from faulty material in every particular and free from improper workmanship; against unusual damage from proper and usual use; agreeing to replace or re-execute without cost to OWNER such work that may be found to be improper or imperfect, and to make good all damages caused to other work or material, due to such defective work or due to its required replacement or re-execution. This guaranty shall be made to cover a

GC-14

period of one-year from the date of acceptance of the work, as evidenced by OWNER’S Certificate of Acceptance, of the work. Neither the Certificate of Acceptance, final payment, nor any provision of the Contract Documents shall relieve CONTRACTOR of the responsibility for neglect or faulty material or workmanship during the period covered by this guaranty. The one-year period of any guaranty provisions will not limit the OWNERS other rights under common law or equity to have defects remedied when discovered after one-year.

5. MEASUREMENT AND PAYMENT

5.01 QUANTITIES AND MEASUREMENTS. No extra or customary measurements of any kind will be allowed, but the actual measured and/or computed length, area, solid contents, number and weight only shall be considered, unless otherwise specifically provided.

5.02 ESTIMATED QUANTITIES. This agreement, including the specifications, plans and estimate, is intended to show clearly all work to be done and material to be furnished hereunder. Where the estimated quantities are shown for the various classes of work to be done and material to be furnished under this contract, they are approximate and are to be used only as a basis for estimating the probable cost of the work and for comparing the proposals offered for the work. It is understood and agreed that the actual amount of work to be done and materials to be furnished under this contract may differ somewhat from these estimates, and that where the basis for payment under this contract is the unit price method, payment shall be for the actual amount of such work done and material furnished.

Where payment is based on the unit price method, the CONTRACTOR agrees that he will make no claim for damages, anticipated profits or otherwise on account of any differences which may be found between the quantities of work actually done, the material actually furnished under this contract and the estimated quantities contemplated and contained in the proposal. Neither party to this Agreement shall be entitled to a revised consideration upon any portion of the work due to an increase nor a decrease in the actual quantity of work done and/or material furnished.

5.03 PRICE OF WORK. In consideration of the furnishing of all the necessary labor, equipment and material, and the completion of all work by the CONTRACTOR, and on the completion of all work and of the delivery of all material embraced in this Contract in full conformity with the specifications and stipulations herein contained, the OWNER agrees to pay the CONTRACTOR the prices set forth in the Proposal hereto attached, which has been made a part of this Contract. The CONTRACTOR hereby agrees to receive such prices in full for furnishing all material and all labor required for the previously mentioned work, also for all expense incurred by him, and for well and truly performing the same and the whole thereof in the manner and according to the Agreement.

5.04 PARTIAL PAYMENTS. On or before the 10th day of each month, the CONTRACTOR shall prepare and submit to the ENGINEER for approval or modification a statement showing as completely as practicable the total value of the work done by the CONTRACTOR up to and including the last day of the preceding month; said statement shall also include the value of all sound materials delivered on the site of the work that are to be fabricated into the work.

The OWNER shall then pay the CONTRACTOR on or before the 15th day of the current month the total amount of the approved statement, less five percent (5%) of the amount

GC-15

thereof, which five percent (5%) shall be retained until final payment, and further less all previous payments and all further sums that may be retained by the OWNER under the terms of this Agreement. It is understood, however, that in case the whole work be near to completion and some unexpected and unusual delay occurs due to no fault or neglect on the part of the CONTRACTOR, the OWNER may, upon written recommendation of the ENGINEER, pay a reasonable and equitable portion of the retained percentage to the CONTRACTOR, or the CONTRACTOR at the OWNER'S option, may be relieved of the obligation to fully complete the work and, thereupon, the CONTRACTOR shall receive payment of the balance due him under the contract subject only to the conditions stated under "Final Payment."

5.05 USE OF COMPLETED PORTIONS. The OWNER shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions may not have expired but such taking possession and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost of or delays the work, the CONTRACTOR shall be entitled to such extra compensation, or extension of time, or both, as may be determined in accordance with the Contract Documents.

The CONTRACTOR shall notify the ENGINEER when, in the CONTRACTOR'S opinion, the contract is "substantially completed" and when so notifying the ENGINEER, the CONTRACTOR shall furnish to the ENGINEER in writing a detailed list of unfinished work.

The ENGINEER will review the CONTRACTOR'S list of unfinished work and will add thereto such items as the CONTRACTOR has failed to include. The "substantial completion" of the structure of facility shall not excuse the CONTRACTOR from performing all for the work undertaken, whether of a minor or major nature, and thereby completing the structure of facility in accordance with the Contract Documents.

5.06 FINAL COMPLETION AND ACCEPTANCE. Within ten (10) days after the CONTRACTOR has given the ENGINEER written notice that the work has been completed, the ENGINEER and the OWNER shall inspect the work and within said time, if the work be found to be completed in accordance with the Contract Documents, the ENGINEER shall issue to the OWNER and the CONTRACTOR his Certificate of Completion, and thereupon it shall be the duty of the OWNER within ten (10) days to issue a Certificate of Acceptance of the work to the CONTRACTOR, or to advise the CONTRACTOR in writing of the reason for non-acceptance.

5.07 FINAL PAYMENT. Upon the issuance of the Certificate of Final Completion, the ENGINEER shall proceed to make final measurements and prepare final statement of the value of all work performed and materials furnished under the terms of the Agreement and shall certify same to the OWNER, who shall pay to the CONTRACTOR on or after the 30th day, and before the 35th day, after the date of the Certificate of Completion, the balance due the CONTRACTOR under the terms of this Agreement, provided he has fully performed his contractual obligations under the terms of the Contract Documents; and said payment shall become due in any event upon said performance by the CONTRACTOR. Neither the Certificate of Acceptance nor the final payment, nor any provision in the Contract Documents, shall relieve the CONTRACTOR of the obligation for fulfillment of any warranty, which may be required.

GC-16

5.08 PAYMENTS WITHHELD. The OWNER may, on account of subsequently discovered evidence, withhold or nullify the whole or part of any certificate to such extent as may be necessary to protect itself from loss on account of:

(a) Defective work not remedied.

(b) Claims filed or reasonable evidence indicating probable filing of claims.

(c) Failure of the CONTRACTOR to make payments properly to subcontractors or for material or labor.

(d) Damage to another contractor.

(e) Reasonable doubt that the work can be completed for the unpaid balance of the contract amount.

(f) Reasonable indication that the work will not be completed within the contract time.

When the above grounds are removed, or the CONTRACTOR provides a Surety Bond satisfactory to the OWNER, which will protect the OWNER in the amount withheld, payment shall be made for amounts withheld because of them.

5.09 REMEDIES. It is expressly understood and agreed that the remedies of OWNER contained herein are cumulative and not exclusive, and OWNER shall have the right to withhold further payments, terminate the Contract, institute litigation for damages, (both actual and consequential) and pursue any other remedy available at law or in equity.

5.10 DELAYED PAYMENTS. Should the OWNER fail to make payment to the CONTRACTOR of the sum named in any partial or final statement, when payment is due, then the OWNER shall pay to the CONTRACTOR, in addition to the sum shown as due by such statement, interest thereon; at the rate of six percent (6%) annum, unless otherwise specified, from date due as provided under "Partial Payments" and "Final Payments," until fully paid, which shall fully liquidate any injury to the CONTRACTOR growing out of such delay in payment, but the right is expressly reserved to the CONTRACTOR in the event payments be not promptly made, as provided under "Partial Payments," to at any time thereafter treat the contract as abandoned by the OWNER and recover compensation, as provided under "Abandonment of Contract," unless such payments are withheld in accordance with the provisions of "Payments Withheld."

6. EXTRA WORK AND CLAIMS

6.01 CHANGE ORDERS. Without invalidating this Agreement, the OWNER may, at any time or from time to time, order additions, deletions or revisions to the work. Such changes will be authorized by written Change Order to be prepared by the ENGINEER for execution by the OWNER and the CONTRACTOR.