GCI Expansion - Addendum No. 03 - 10.07.2026.pdf
PDF 5 MB Posted
- Attached to
- GCI Expansion Project
- Solicitation number
- RFP GIS 260000002727 4
- Issued by
- Genesee County, Michigan
About this file
This is Addendum No. 3 to the contract documents for the GCI Expansion Project at Genesee Career Institute, a facility addition project located in Michigan and administered by the Genesee Intermediate School District. The addendum, issued on October 7, 2026, modifies the original bidding and contract requirements for Bid Release #1 with a bid proposal due date of October 15, 2026, at 1:50 P.M. Key modifications include reissued specifications for Division 27 (Communication Systems) and Division 28 (Electronic Safety and Security Systems), updated drawing sheets (T1.1, T2.1, T2.2, and T2.3), clarifications to concrete lintels responsibility under Bid Category 03A, revisions to gas piping and excavation responsibilities under Bid Category 23B, addition of Mandatory Alternate #3 to Bid Categories 26A and 31A, and inclusion of the A232-2019 General Conditions. The addendum incorporates 15 pre-bid RFI responses addressing generator panel location, communication and security devices, existing structures, metal panel details, casework specifications, hydronics, door locations, masonry specifications, sitework scope, utility requirements, fiber optic work, and temporary fencing. A pre-bid conference was held on October 5, 2026, with an attendee sign-in sheet included.
The contract structure utilizes a Stipulated Sum pricing model with the contract sum, alternates, and allowances to be detailed in the Contractor's Pricing Form based on the Project Schedule contained in the Project Manual. Retainage is set at ten percent (10%) of each progress payment until substantial completion, with final payment due within sixty days of project completion and all closeout documentation approval. Mandatory Alternate #3 requires bidders to provide costs for demolition of the electrical feed and conduit to the existing chicken coop (26A) and demolition of the existing chicken coop structure and fencing (31A). An allowance of $100,000 is included for undercutting subbase material under Bid Category 31A. The project requires compliance with Michigan's Prevailing Wage Act (Public Act 10 of 2023), and all contractors must maintain insurance with the Owner and Construction Manager named as additional insured parties and provide performance and payment bonds. Clark Construction Company serves as the Construction Manager, and Kingscott Associates, Inc. serves as the Architect, with the Owner's representative identified as Jeff Jansen, Director of Operations for the Genesee Intermediate School District.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 3
10/7/2026
ADDENDUM NO. 3
PROJECT: Genesee ISD GCI Addition
DESCRIPTION: GCI Addition
BID PACKAGE RELEASE NUMBER: Bid Release #1
CLARK PROJECT NO: #26-3013
BID PROPOSAL DUE DATE/TIME: 1:50 P.M., Thursday, October 15, 2026
The following clarifications and/or Changes made to the Contract Documents are hereby made part of the Contract Documents.
The general character of the Work clarified or revised by this Addendum shall be the same as required by the complete set of Contract Documents. All incidentals required in connection with the Work of this Addendum shall be included in the Scope of Work even though not specifically specified.
All bidders shall be held responsible to review the Addendum and to include in its Bid Proposal all Work reasonably inferred to be included in its Scope of Work.
Acknowledge receipt of this Addendum in the space provided on the Bid Proposal Form.
1) Division 00 – Bidding and Contract Requirement Modifications
a) SECTION 000110 – K-12 Table of Contents
i) Reissued to include Division 27 & 28 Specifications as listed in A/E Addendum No.
03 Write-Up
b) SECTION 000115 – List of Drawing Sheets
i) Reissued for updated drawings T1.1, T2.1, T2.2 and T2.3
c) SECTION 002416 – Bid Cat. 03A Concrete & Foundations
i) Reissued to clarify the responsibility of concrete lintels
d) SECTION 002416 – Bid Cat. 23B HVAC & Plumbing
i) Reissued to clarify responsibility of gas piping and excavation, backfill and restoration associated with the work of this bid category.
e) SECTION 002416 – Bid Cat. 26A Electrical
i) Reissued to add new Division 27 & 28 specifications and added Mandatory Alternate
#3
f) SECTION 002416 – Bid Cat. 31A Earthwork & Utilties
i) Reissued to removed gas piping from scope, clarify requirements for construction gravel material thickness, construction fence posts, snow removal, and added
Mandatory Alternate #3
Addendum No. 3
g) SECTION 005216 – K-12 Agreement Form
i) Reissued to include A232-2019 General Conditions
2) DIVISION 01 – GENERAL REQUIREMENTS
a) SECTION 012300 – Alternates
i) Reissued to add Alternate #3.
3) A/E (Kingscott) Documentation
a) Addendum No. 3 Write-Up
b) Specifications:
i) 271116 Communications Cabinets, Racks, Frames and Enclosures (Initial issuance – Addendum 03)
ii) 271323 – Communications Optical Fiber Backbone Cabling (Initial issuance – Addendum 03)
iii) 271513 – Communications Copper Horizontal Cabling (Initial issuance – Addendum
03)
iv) 274116 – Integrated Audio Video Systems (Initial issuance – Addendum 03)
v) 275116 – Public Address & Clock Systems (Initial issuance – Addendum 03)
vi) 280000 – Security Systems (Initial issuance – Addendum 03)
c) Drawings:
i) T1.1 – Technology Legend and Details (reissued)
ii) T2.1 – First Floor Structured Cabling Plan (reissued)
iii) T2.2 – First Floor Security Plan (reissued)
iv) T2.3 – First Floor PA and Clock Plan (reissued)
4) Pre-Bid RFI Responses
a) RFI 0001 – GCI – Generator Panel Location for Sanitary Pump Station
b) RFI 0003 – GCI – Communication and Security Devices
c) RFI 0012 – GCI – Existing Greenhouse and Chicken Coop
d) RFI 0015 – GCI – 07B Scope Clarification and Metal Panel Details
e) RFI 0016 – GCI – Casework Specification 12 30 00
f) RFI 0021 – GCI – Hydronics and Balancing
g) RFI 0024 – GCI – Door 601 Locations
h) RFI 0025 – GCI – Specified Masonry Compressive Strength
i) RFI 0027 – GCI – Schedule Clarifications for Masonry Scope
j) RFI 0028 – GCI – 31A Sitework Scope Questions
k) RFI 0029 – GCI – Project Requirements for Textura or Autodesk
l) RFI 0030 – GCI – Portal Frame Concrete Lintel
m) RFI 0031 – GCI – Below Grade Waterproofing Responsibility
n) RFI 0032 – GCI – Existing Fiber Relocation
o) RFI 0033 – GCI – Sawcutting & Restoration for Utilties
p) RFI 0034 – GCI – Fiber Termination Location & Equipment Rack Specification
q) RFI 0037 – GCI – Decorative CMU Clarification
r) RFI 0038 – GCI – Fire Protection Pipe Thickness
s) RFI 0041 – GCI – Temporary Fencing
5) Pre-Bid Conference Sign-In Sheet
a) Sign-in sheet from meeting held on 10.05.26 attached
000110-1
Section 000110-Table of Contents JANUARY 2024
SECTION 000110
PROJECT MANUAL
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
INTRODUCTORY INFORMATION
000101 PROJECT MANUAL COVER
000110 TABLE OF CONTENTS
000115 LIST OF DRAWING SHEETS
BIDDING REQUIREMENTS
001100 ADVERTISEMENT/INVITATION FOR BIDS
002113 INSTRUCTIONS TO BIDDERS
002413 SCOPE OF WORK - GENERAL NOTES
002416 SCOPE OF WORK - BID CATEGORY SPECIFIC NOTES
003113 PROJECT MILESTONE SCHEDULE
004126 BID PROPOSAL FORM
004126.1 FAMILIAL DISCLOSURE FORM
004126.2 IRAN SANCTION FORM
004126.3 CRIMMINAL AFFIDAVIT FORM
CONTRACTING REQUIREMENTS
005216 AGREEMENT FORM
006113 PERFORMANCE AND PAYMENT BOND
006200 CERTIFICATES AND OTHER FORMS
007216 GENERAL CONDITIONS
DIVISION 01 – GENERAL REQUIREMENTS
011000 SUMMARY
012100 ALLOWANCES
012300 ALTERNATES
012500 SUBSTITUTION PROCEDURES
012600 CONTRACT MODIFICATION PROCEDURES
012900 PAYMENT PROCEDURES
012973 SCHEDULE OF VALUES
013000 ADMINISTRATIVE REQUIREMENTS
013119 PROJECT MEETINGS
013300 SUBMITTAL PROCEDURES
013316 DESIGN DATA (BIM COORDINATION)
013323 SHOP DRAWINGS, PROJECT DATA AND SAMPLES
013529 HEALTH, SAFETY AND EMERGENCY RESPONSE PROCEDURES
000110-2
013543 ENVIRONMENTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014100 AIR BARRIER SYSTEM REQUIREMENTS
014126 PERMIT REQUIREMENTS
014216 DEFINITIONS
014339 MOCKUPS
014516 FIELD QUALITY CONTROL PROCEDURES
014516.01 CONCRETE TESTING
014516.02 DENSITY AND AGGREGATE TESTING
014533 CODE-REQUIRED SPECIAL INSPECTIONS
014517 NON-CONFORMANCE PROCEDURE
015000 TEMPORARY FACILITIES AND CONTROLS
015726 DUST CONTROL
016000 PRODUCT REQUIREMENTS
016116 VOLITILE ORGANIC COMPOUND (VOC) CONTENT
RESTRICTIONS
017000 EXECUTION AND CLOSEOUT REQUIREMENTS
017123 FIELD ENGINEERING
017123.16 CONSTRUCTION STAKING BY CONTRACTOR
DIVISION 01 – GENERAL REQUIREMENTS (CONTINUED)
017329 CUTTING AND PATCHING
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017610 TEMPORARY PROTECTIVE COVERINGS
017700 CLOSEOUT PROCEDURES
017800 CLOSEOUT SUBMITTALS
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
018113 SUSTAINABLE DESIGN (LEED) REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
023200 GEOTECHNICAL INVESTIGATIONS
024113.13 PAVEMENT REMOVAL
024119 SELECTIVE DEMOLITION
DIVISION 03 – CONCRETE
033000 – CAST-IN-PLACE CONCRETE
000110-3
TABLE OF CONTENTS
ADDENDUM NO. 3
DIVISION 04 – MASONRY
042000 UNIT MASONRY
044316 STONE FABRICATIONS
DIVISION 05 – METALS
051200 STRUCTURAL STEEL FRAMING
052100 STEEL JOIST FRAMING
053100 STEEL DECKING
054000 COLD-FORM METAL FRAMING
055133 METAL LADDERS
DIVISION 06 – WOOD, PLASTICS AND COMPOSITIES
061053 MISCELLANEOUS ROUGH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
071300 SHEET WATERPROOFING
072100 THERMAL INSULATION
072119 FOAMED-IN-PLACE INSULATION
072500 WEATHER BARRIERS
074213 METAL WALL PANELS
075323 ETHYLENE-PROYLENE-DIENE-MONOMER ROOFING (EPDM) –
ELEVATE
075419 POLYVINYL-CHLORIDE ROOFING – DURO-LAST (ALTERNATE
#1)
076200 SHEET METAL FLASHING AND TRIM
076500 FLEXIBLE FLASHING
077100 ROOF SPECIALTIES
077200 ROOF ACCESSORIES
078400 FIRESTOPPING
079200 JOINT SEALANTS
079513 EXPANSION JOINT COVER ASSEMBLIES
DIVISION 08 – OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES
081742 HYBRID FRP DOORS
083100 ACCESS DOORS AND PANELS
084313 ALUMINUM-FRAMED STOREFRONTS
087100 DOOR HARDWARE
000110-4
TABLE OF CONTENTS
ADDENDUM NO. 3
088000 GLAZING
088853 SECURITY GLAZING – IMPACT SECURITY
DIVISION 09 – FINISHES
092116 GYPSUM BOARD ASSEMBLIES
092216 NON-STRUCTURAL METAL FRAMING
093000 TILING
095100 ACOUSTICAL CEILINGS
096500 RESILIENT FLOORING
096723 RESINOUS FLOORING
096816 SHEET CARPETING
097200 WALL COVERINGS
098430 SOUND-ABSORBING WALL AND CEILING UNITS
099123 INTERIOR PAINTING
099600 HIGH-PERFORMANCE COATINGS
DIVISION 10 – SPECIALTIES
101100 VISUAL DISPLAY UNITS
101419 DIMENSIONAL LETTER SIGNAGE
102113.17 PHENOLIC TOILET COMPARTMENTS
102123 CUBICLE CURTAINS AND TRACK
102800 TOILET, BATH, AND LAUNDRY ACCESSORIES
104400 FIRE PROTECTION SPECIALTIES
DIVISION 12 – FURNISHINGS
122400 WINDOW SHADES
123000 MANUFACTURERED PLASTIC LAMINATE CLAD CASEWORK
123661.16 SOLID SURFACE COUNTERTOPS
DIVISION 21 – FIRE SUPPRESSION
210500 COMMON WORK RESULTS FOR FIRE SUPPRESSION
210523 GENERAL DUTY VALVES FOR WATER BASED FIRE
SUPPRESSION PIPING
210553 IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND
EQUIPMENT
211300 FIRE-SUPPRESSION SPRINKLER SYSTEMS
DIVISION 22 – PLUMBING
000110-5
220005 BASIC PLUMBING REQUIREMENTS
220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
220519 METERS AND GAUGES FOR PLUMBING PIPING
220523 GENERAL DUTY VALVES FOR PLUMBING PIPING
220553 INDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
220593 TESTING, ADJUSTING, AND BALANCING FOR PLUMBING
220719 PLUMBING PIPING INSULATION
220800 PLUMBING COMMISSIONING REQUIREMENTS
221005 PLUMBING PIPING
221006 PLUMBING PIPING SPECIALTIES
221123 DOMESTIC WATER PUMPS
222300 PLUMBING EQUIPMENT
224000 PLUMBING FIXTURES
DIVISION 23 – HEATING, VENTILATING & AIR-CONDITIONING (HVAC)
230005 BASIC HVAC REQUIREMENTS
230130.51 HVAC AIR-DISTRIBUTION SYSTEM CLEANING
230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
230519 METERS AND GAUGES FOR HVAC PIPING
230523 GENERAL DUTY VALVES FOR HVAC PIPING
230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING AND BALANCING FOR HVAC
230713 DUCT INSULATION
230714 DUCT ACOUSTICAL LINER AND LAGGING
230716 HVAC EQUIPMENT INSULATION
230719 HVAC PIPING INSULATION
230800 HVAC COMMISSIONING REQUIREMENTS
230913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
230923 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC
230934 VARIABLE-FREQUENCY MOTOR CONTROLLERS FOR HVAC
230945 GAS DETECTION AND ALARM
231123 NATURAL GAS PIPING, VALVES AND ACCESSORIES
232113 HVAC PIPING
232114 HYDRONIC SPECIALTIES
232123 HVAC PUMPS
232500 HVAC WATER TREATMENT
233100 HVAC DUCTS AND CASINGS
233300 AIR DUCT ACCESSORIES
233319 DUCT SILENCERS
233423 HVAC POWER VENTILATORS
000110-6
233600 AIR TERMINAL UNITS
233700 AIR OUTLETS AND INLETS
235100 BREECHINGS, CHIMNEYS, AND STACKS
235216 CONDENSING BOILERS
237223 PACKAGED AIR-TO-AIR ENERGY RECOVERY UNITS
238126.13 SMALL-CAPACITY SPLIT-SYSTEM AIR CONDITIONERS
238200 CONVECTION HEATING AND COOLING UNITS
DIVISION 26 – ELECTRICAL
260005 SES BASIC ELECTRICAL REQUIREMENTS
260505 SELECTIVE DEMOLITION FOR ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533.13 CONDUIT FOR ELECTRICAL SYSTEMS
260533.16 BOXES FOR ELECTRICAL SYSTEMS
260533.23 SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS
260536 CABLE TRAYS FOR ELECTRICAL SYSTEMS
260553 INDENTIFICATION FOR ELECTRICAL SYSTEMS
260573 POWER SYSTEM STUDIES
260923 LIGHTING CONTROL DEVICES
262200 LOW-VOLTAGE TRANSFORMERS
262416 PANELBOARDS
262726 WIRING DEVICES
262813 FUSES
262816.16 ENCLOSED SWITCHES
264300 SURGE PROTECTIVE DEVICES
265100 INTERIOR LIGHTING
265600 EXTERIOR LIGHTING
DIVISION 27 – COMMUNICATION SYSTEMS
271116 COMMUNICATIONS CABINETS, RACKS, AND FRAMES
271323 COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING
271513 COMMUNICATIONS COPPER HORIZONTAL CABLING
274116 INTEGRATED AUDIO VIDEO SYSTEMS
275116 PUBLIC ADDRESS & CLOCK SYSTEMS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
280000 SECURITY SYSTEMS
000110-7
TABLE OF CONTENTS
ADDENDUM NO. 3
284600 FIRE DETECTION AND ALARM
DIVISION 31 – EARTHWORK
311001 CLEARING AND REMOVAL OF MISCELLANEOUS STRUCTURES
312301 EXCAVATING, FILLING AND GRADING
312302 EXCAVATING AND BACKFILLING FOR UTILITY
CONSTRUCTION
312500 SOIL EROSION AND SEDIMENTATION CONTROL
313219 GEOTETILE FABRIC
313700 RIPRAP
DIVISION 32 – EXTERIOR IMPROVEMENTS
321116 GRANULAR SUBBASE
321123 AGGREGATE BASE COURSES
321216 HMA PAVING
321300 CONCRETE CURB AND GUTTER, SIDEWALK AND
MISCELLANEOUS PAVEMENT
321500 AGGREGATE SURFACING
321723 PAVEMENT MARKINGS
328423 UNDERGROUND SPRINKLERS
329119 TOPSOIL FOR LANDSCAPING AND SODDING
329200 NATURAL TURF AND SODDING
329200 TURF ESTABLISHMENT
329300 PLANTS
329400 LANDSCAPE MAINTENANCE AND WARRANTY STANDARDS
DIVISION 33 – UTILITIES
330500 ADJUSTING STRUCTURES
331100 WATERMAIN (GENESSEE COUNTY)
333100 SANITARY SEWER (GENESSEE COUNTY)
334400 STORM SEWERS
END OF SECTION
000115-1
Section 000115-List of Drawing Sheets, JANUARY 2024
SECTION 000115
LIST OF DRAWING SHEETS
1. LIST OF DRAWINGS PREPARED BY KINGSCOTT
SHEET NO. TITLE DATE
G0.1 TITLE SHEET 08-24-2026
G0.2 DATA SHEET 08-24-2026
C0.0 COVER SHEET 08-24-2026
C0.1 GENERAL NOTES AND PROJECT
CONTROL SHEET
08-24-2026
C0.2 GCDC NOTES SHEET 08-24-2026
C0.3 LEGEND SHEET 08-24-2026
C1.0 EXISTING CONDITIONS AND REMOVAL
PLAN
08-24-2026
C1.1 SITE PLAN 08-24-2026
C1.2 PROPOSED GRADING AND STORM
SEWER PLAN
08-24-2026
C1.3 PROPOSED STORMWATER PLAN 08-24-2026
C1.4 SESC PLAN 08-24-2026
C1.5 WATER AND SANITARY PLAN 08-24-2026
C1.6 WATER AND SANITARY PLAN 08-24-2026
C1.7 SANITARY PROFILES 08-24-2026
C1.8 WATERMAIN PROFILES 08-24-2026
C5.1 SITE DETAILS 08-24-2026
C5.2 GCDC WATER DETAILS 08-24-2026
C5.3 GCDC WATER DETAILS 08-24-2026
C5.4 GCDC PUMP STATION DETAILS 08-24-2026
C5.5 SESC KEY 08-24-2026
L1.1 SITE LAYOUT 08-24-2026
L1.2 SITE DETAILS 08-24-2026
L2.1 PLANTING PLAN 08-24-2026
L2.2 PLANTING DETAILS 08-24-2026
L2.3 PLANTING DETAILS 08-24-2026
L3.1 IRRIGATION PLAN 08-24-2026
L3.2 IRRIGATION NOTES 08-24-2026
S0.1 STRUCTURAL NOTES 08-24-2026
S0.2 SPECIAL INSPECTIONS & DESIGN
LOADS
08-24-2026
S0.3 TYPICAL DETAILS 08-24-2026
S1.0 FOUNDATION PLAN 08-24-2026
S1.1 ROOF FRAMING PLAN 08-24-2026
S2.1 ELEVATIONS 08-24-2026
S3.1 SECTIONS 08-24-2026
000115-2
ADDENDUM NO. 3
A0.1 FIRST FLOOR COMPOSITE PLAN 08-24-2026
A0.2 FIRST FLOOR CODE COMPOSITE PLAN
& INFO
08-24-2026
A0.3 CODE PLAN UNIT 800 & ENLARGED
EGRESS
08-24-2026
A0.4 ROOF COMPOSITE PLAN 08-24-2026
D1.6 FIRST FLOOR DEMOLITION PLAN- UNIT
08-24-2026
A1.8 FIRST FLOOR PLAN – UNIT 800
ADDITION
08-24-2026
A1.18 FIRST FLOOR PLAN – UNIT 800
ADDITION DIMENSIONS
08-24-2026
A1.28 FIRST FLOOR EQUIPMENT PLAN – UNIT
800 ADDITION
08-24-2026
A1.29 FIRST FLOOR EQUIPMENT SCHEDULES
& SIGNAGE
08-24-2026
A1.41 ENLARGED PLANS 08-24-2026
A2.8 FIRST FLOOR REFLECTED CEILING
PLAN – UNIT 800 ADDITION
08-24-2026
A2.30 INTERIOR PARTITION TYPES 08-24-2026
A3.1 EXTERIOR ELEVATIONS 08-24-2026
A3.2 BUILDING SECTIONS 08-24-2026
A4.1 WALL SECTIONS 08-24-2026
A4.2 WALL SECTIONS 08-24-2026
A5.1 BUILDING DETAILS 08-24-2026
A5.2 BUILDING DETAILS 08-24-2026
A6.1 DOOR SCHEDULE & OPENING
ELEVATIONS
08-24-2026
A6.2 DOOR & WINDOW DETAILS 08-24-2026
A6.3 DOOR & WINDOW DETAILS 08-24-2026
A8.8 FIRST FLOOR COLOR LAYOUT PLAN -
UNIT 800
08-24-2026
A9.1 INTERIOR ELEVATIONS 08-24-2026
A9.2 INTERIOR ELEVATIONS 08-24-2026
A9.3 INTERIOR ELEVATIONS 08-24-2026
A9.4 INTERIOR FINISH DETAILS 08-24-2026
A9.5 INTERIOR RENDERINGS 08-24-2026
FP0.0 FIRE PROTECTION DATA SHEET 08-24-2026
FP1.8 FIRST FLOOR FIRE PROTECTION PLAN –
UNIT 800 ADDITION
08-24-2026
P0.0 PLUMBING DATA SHEET 08-24-2026
P0.8 UNDERGROUND PLUMBING PLAN –
UNIT 800 ADDITION
08-24-2026
P1.8 FIRST FLOOR PLUMBING PLAN – UNIT 08-24-2026
000115-3
ADDENDUM NO. 3
800 ADDITION
P3.8 PLUMBING ROOF PLAN – UNIT 800
ADDITION
08-24-2026
P4.1 PLUMBING ENLARGED PLANS 08-24-2026
P5.1 PLUMBING DETAILS 08-24-2026
P6.1 PLUMBING SCHEDULES 08-24-2026
M0.0 MECHANICAL DATA SHEET 08-24-2026
MH1.8 FIRST FLOOR MECHANICAL HVAC
PLAN – UNIT 800 ADDITION
08-24-2026
MP1.4 FIRST FLOOR MECHANICAL PIPING
PLAN – UNIT 400
08-24-2026
MP1.8 FIRST FLOOR MECHANICAL PIPING
PLAN – UNIT 800 ADDITION
08-24-2026
M3.8 MECHANICAL ROOF PLAN – UNIT 800
ADDITION
08-24-2026
M4.1 MECHANICAL ROOM ENLARGED PLANS
& SECTIONS
08-24-2026
M4.2 MECHANICAL SECTIONS 08-24-2026
M5.1 MECHANICAL PIPING DIAGRAMS 08-24-2026
M5.2 MECHANICAL DETAILS 08-24-2026
M5.3 MECHANICAL DETAILS 08-24-2026
M5.4 MECHANICAL DETAILS 08-24-2026
M6.1 MECHANICAL SCHEDULES 08-24-2026
M6.2 MECHANICAL SCHEDULES 08-24-2026
M6.3 MECHANICAL SCHEDULES 08-24-2026
M8.0 CONTROLS DATA SHEET 08-24-2026
M8.1 MECHANICAL CONTROLS 08-24-2026
M8.2 MECHANICAL CONTROLS 08-24-2026
M8.3 MECHANICAL CONTROLS 08-24-2026
M8.4 MECHANICAL CONTROLS 08-24-2026
ED1.2 FIRST FLOOR ELECTRICAL
DEMOLITION PLAN – UNIT 600
08-24-2026
ES1.0 ELECTRICAL SITE PLAN 08-24-2026
EP1.8 FIRST FLOOR POWER PLAN – UNIT 800
ADDITION
08-24-2026
EL1.8 FIRST FLOOR LIGHTING
PLAN -UNIT 800 ADDITION
08-24-2026
E4.0 ENLARGED ELECTRICAL
PLANS
08-24-2026
E6.0 PANEL SCHEDULES 08-24-2026
T1.1 TECHNOLOGY LEGEND AND DETAILS 10-06-2026
T2.1 FIRST FLOOR STRUCTURED CABLING
PLAN – UNIT 800 ADDITION
10-06-2026
T2.2 FIRST FLOOR SECURITY PLAN – UNIT 10-06-2026
000115-4
ADDENDUM NO. 3
800 ADDITION
T2.3 FIRST FLOOR PA AND CLOCK PLAN –
UNIT 800 ADDITION
10-06-2026
002416-1 Section 002416-Scope of Work-Bid Category Specific Notes, Bid Category 3X-Building Foundations JUNE 2026
SECTION 002416
SCOPE OF WORK
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
BID CATEGORY 03A - Concrete & Building Foundations
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible for performing all work reasonably interpreted to be included in its scope of work in accordance with the drawings and specifications in addition to these Bid
Category notes of clarification.
BASE SPECIFICATION(S) – (Include all Work specified or reasonably inferred.)
002413 – SCOPE OF WORK GENERAL NOTES
Divisions 00 & 01
014516.01 – CONCRETE TESTING
033000 – CAST-IN-PLACE CONCRETE
321300 – CONCRETE CURB AND GUTTER, SIDEWALK, AND MISC PAVEMENT
071300 – SHEET WATERPROOFING
REFERENCE SPECIFICATION(S) – (Include portions of the Work specified as noted below)
015000 – TEMPORARY FACILITIES AND CONTROLS
014000 – AIR BARRIER SYSTEM REQUIREMENTS
014516.02 – DENSITY AND AGGREGATE TESTING
014533 – CODE-REQUIRED SPECIAL INSTRUCTIONS
017123.16 – CONSTRUCTION STAKING BY CONTRACTOR
051200 – STRUCTURAL STEEL FRAMING
072100 – THERMAL INSULATION
072500 – WEATHER BARRIERS
076500 – FLEXIBLE FLASHING
079200 – JOINT SEALANTS
321116 – GRANULAR SUBBASE
321123 – AGGREGATE BASE COURSES
312301 – EXCAVATING, FILLING, AND GRADING
Include (Furnish and Install unless.noted.otherwise (u.n.o.)
1. All work under this contract shall be done in a safe manner and comply with the
O.S.H.A and M.I.O.S.H.A requirements as well as Clark Construction Company’s safety program.
2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark
Construction Superintendents
002416-2
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.
4. Pumping of water to accomplish the Work of this bid category.
5. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.
6. Determine location of existing underground utilities prior to any excavation work.
Contact MISS DIG a minimum of 3 days in advance of any excavation work, more than 3 days if required to allow adequate time for MISS DIG to mark underground utilities as required to meet excavation work schedules. Submit verification of MISS DIG work order to Clark Construction Company. Hand dig as necessary to avoid contact with underground utilities.
7. Determine location of existing underground utilities prior to any excavation work outside of the responsibility of MISS DIG for marking including fiber optic lines and other non-public utilities.
8. Contract GPRS services or hand dig to locate and expose privately owned utilities shown on the drawings.
9. Verify and accept building pad elevation and subbase elevations prior to performing the Work. Report discrepancies to Clark Construction Company in writing.
10. Verify existing grade prior to performing the Work. Report discrepancies to Clark
Construction Company in writing.
11. Receive, unload, store, layout and install miscellaneous steel fabrications furnished by others (e.g. imbed angles, anchor bolts, bearing and leveling plates, wall plates, etc.). Include grouting as required.
12. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.
13. Coordinate and cooperate with the project Independent Testing and Inspection
Company for inspection and/or testing of the Work.
14. Pumping water required to accomplish the Work of this bid category.
15. Contractor is responsible for all control points to perform the work of this bid category. Benchmarks are located on the drawings.
16. Contractor is responsible for all excavations and backfill for footings and foundations.
17. Contractor to leave top of foundations clean for next trade contractor to begin work.
18. Restore grade to conditions that existed prior to performing the Work.
19. Reinforcing steel associated with the Work of this bid category includes reinforcing dowels as required for masonry.
20. Coordinate dowel location requirements with other Trades.
21. Concrete forms and accessories as required to complete the work of this bid category.
002416-3
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
22. Finished concrete flatwork shall have positive drainage over the entire surface as required.
23. Clean reinforcing of loose or flaking rust, dried concrete, oil, and other foreign material that may reduce the bond between the reinforcing and the concrete.
24. Openings, pockets, box outs, etc. Coordinate required location and dimensions with other Trades.
25. Install sleeves furnished by others. Coordinate required location with other
Trades.
26. Cooperate in verification of correct anchor bolt and other embed placement with other Trades. Make corrections as needed in a timely manner to meet the project schedule.
27. Protect anchor bolt threads with grease or other approved means.
28. Install and grout (at required elevations) structural steel leveling plates furnished by others.
29. All cast-in-place concrete and concrete paving shown in the bid documents including but not limited to flatwork, foundations, stoops, bollards, concrete curbs and curb edging, etc.
30. Complete bollard assembly including excavation and proper removal of spoils, steel pipe and bollard covers.
31. Locate on site where and remove from site all concrete wash out as directed by
Clark Construction Company.
32. Protection of adjacent materials and surrounding surfaces. Clean and restore material affected by concrete splatter.
33. Provide certification to Clark Construction Company that structural concrete to receive structural steel has achieved 75% of design strength at each location prior to erection of structural steel at that location.
34. Vapor barrier below slab on grade is the responsibility of this bid category.
35. Rigid insulation below slab on grade and at perimeter of foundation.
36. Waterproofing applied to below-grade concrete.
37. Floor expansion joints.
38. All joint sealants associated with the work of this bid category.
39. Install appropriate backer rod in joints as needed.
40. All concrete work shall meet American Concrete Institute (ACI) standards. Prior to performing concrete flatwork, submit for acceptance by the Architect/Engineer, a concrete joint layout plan of all isolation, construction and contraction joints.
The joint layout plan shall at a minimum meet ACI standards. Review and approval will be required prior to performing work.
41. Coordinate adjustment of all storm catch basins, manhole covers, and valve boxes, etc. with other Trades prior to performing the Work of this bid category.
42. Finished concrete flatwork shall have positive drainage over the entire surface as required.
43. All equipment and housekeeping pads are the responsibility of this contractor.
Coordinate exact size and location with other trades.
002416-4
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
44. Weather protection as required to meet the project schedule.
45. Fine grading of aggregate/granular base material is the responsibility of this bid category.
46. Verify existing grade prior to performing the Work. Report discrepancies to
Clark Construction Company in writing.
47. Warranty and guarantee start date shall be the project Substantial Completion date.
48. This bid category shall establish and maintain, local control points for building layout for footing and foundation work.
49. Furnish and install exterior steel bollards including vinyl covers as indicated in the documents.
50. Provide and install concrete lintels as indicated in the Documents. Include skim coating as required to create smooth exposed surface.
Exclude:
1. Sealing of Concrete Floors
Bid Category 07X-Metal Wall Panels and Siding JUNE 2026
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
BID CATEGORY 07B-Metal Wall Panels and Siding
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings and specifications in addition to these Bid
BASE SPECIFICATION(S) – (Include all Work specified or reasonably inferred)
072500 – WEATHER BARRIERS
074213 – METAL WALL PANELS
REFERENCE SPECIFICATION(S) – (Include portions of the Work specified as noted
014100 – AIR BARRIER SYSTEM REQUIREMENTS
014533 – CODE-REQUIRED SPECIAL INSPECTIONS
076200 – SHEET METAL FLASHING AND TRIM
079200 – JOINT SEALANTS
Include (Furnish and Install u.n.o):
safety program.
2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark
Construction Superintendents
3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.
4. Girts, furring and other supports systems as required to accomplish the Work of this bid category whether or not indicated in the documents.
5. Verify quality of substrate installed by other Trades to result in quality results of this bid category. Report discrepancies to Clark Construction Company in writing.
6. Field measure to assure proper fit as necessary to meet the project schedule.
7. Coordinate location and dimensions of penetrations through the system as required by other Trades. Provide weather tight seal and/or accessories as required.
Bid Category 07X-Metal Wall Panels and Siding JUNE 2026
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
8. Joint sealants associated with the work of this bid category.
9. Miscellaneous closures, soffits and other metal fabrications as required for a complete system as indicated in the Documents.
10. Flashings and counter flashings as required for a complete system.
11. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.
12. Warranty and guarantee start date shall be the project Substantial Completion date.
13. Reinstallation of existing building metal wall panel system at building tie-in.
material to be salvaged by selective demolition bid category.
14. Provide and install weather barriers behind metal panels
Bid Category 23X-HVAC JUNE 2026
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
BID CATEGORY 23A - HVAC, Plumbing, & Mechanical
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of
BASE SPECIFICATION(S) - (Include all Work specified or reasonably inferred)
22 00 05 – BASIC PLUMBING REQUIREMENTS
22 05 17 – SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
22 05 19 – METERS AND GAUGES FOR PLUMBING PIPING
22 05 23 – GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 05 53 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 05 93 – TESTING, ADJUSTING AND BALANCING FOR PLUMBING
22 07 19 – PLUMBING PIPING INSULATION
22 08 00 – PLUMBING COMMISSIONING REQUIREMENTS
22 10 05 – PLUMBING PIPING
22 10 06 – PLUMBING PIPING SPECIALTIES
22 11 23 – DOMESTIC WATER PUMPS
22 30 00 – PLUMBING EQUIPMENT
22 40 00 – PLUMBING FIXTURES
23 00 05 – BASIC HVAC REQUIREMENTS
23 01 30.51 – HVAC AIR-DISTRIBUTION SYSTEMS CLEANING
23 05 17 – SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
23 05 19 – METERS AND GAUGES FOR HVAC PIPING
23 05 23 – GENERAL-DUTY VALVES FOR HVAC PIPING
23 05 48 – VIBRATION AND SEISMIC CONTROLS FOR HVAC
23 05 53 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 – TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 – DUCT INSULALTION
23 07 14 – DUCT ACOUSTICAL LINER AND LAGGING
23 07 16 – HVAC EQUIPMENT INSULATION
23 07 19 – HVAC PIPING INSULAITON
23 08 00 – HVAC COMMISSIONING REQUIREMENTS
23 09 13 – INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23 – DIRECT-DIGITAL CONTROL SYSTEMS FOR HVAC
23 09 34 – VARIABLE-FREQUENCY MOTOR CONTROLLERS FOR HVAC
23 09 45 – GAS DETECTION AND ALARM
23 11 23 – NATURAL GAS PIPING, VALVES AND ACCESSORIES
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
23 21 13 – HVAC PIPING
23 21 14 – HYDRONIC SPECIALTIES
23 21 23 – HVAC PUMPS
23 25 00 – HVAC WATER TREATMENT
23 31 00 – HVAC DUCTS AND CASINGS
23 33 00 – AIR DUCT ACCESSORIES
23 33 19 – DUCT SILENCERS
23 34 23 – HVAC POWER VENTILATORS
23 36 00 – AIR TERMINAL UNITS
23 37 00 – AIR OUTLETS AND INLETS
23 51 00 – BREECHINGS, CHIMNEYS, AND STACKS
23 52 16 – CONDENSING BOILERS
23 72 23 – PACKAGED AIR-TO-AIR ENERGY RECOVERY UNITS
23 81 26.13 – SMALL-CAPACITY SPLIT-SYSTEM AIR CONDITIONERS
23 82 00 – CONVECTION HEATING AND COOLING UNITS
REFERENCE SPECIFICATION(S) - (Include portions of the Work specified as noted
015000 – TEMPORARY FACILITIES & CONTROLS
014533 – CODE-REQUIRED SPECIAL INSPECTIONS
033000 – CAST-IN-PLACE CONCRETE
078400 – FIRESTOPPING
079200 – JOINT SEALANTS
083100 – ACCESS DOORS & PANELS
312301 – EXCAVATION, FILLING, AND GRADING
312302 – EXCAVATING AND BACKFILLING FOR UTILITY CONSTRUCTION
safety program.
2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark
Construction Superintendents
3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.
4. Obtain permits required to complete the Work of this bid category.
5. MEP Contractors are required to submit MEP Cost Breakdown as a start-up submittal for approval.
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
6. Coordinate design of system material and equipment routing with other Trade
Contractors as required to avoid conflicts.
a. This Trade Contractor shall develop shop drawings equal to scale as that to be used by other Trade Contractors in which conflicts have potential to occur. Drawing scale shall be coordinated prior to start of shop drawings.
b. Shop drawings shall be extensively and thoroughly coordinated with each Trade Contractor with which conflicts have potential to occur to the extent required to eliminate conflicts prior to fabrication and installation.
c. Conflicts encountered during fabrication and installation which could have been foreseen through a more extensive coordination effort shall be corrected by this bid category.
d. All costs for modifications which are a result of conflicts with items noted in the Contract Documents shall be born by this bid category.
e. In the event of conflict with items indicated in shop drawings of other
Trade Contractors and not in the Contract Documents, the cost shall be shared equally by the Trade Contractors involved.
7. Material bends and offsets in addition to those indicated in the documents associated with the Work of this bid category and required to avoid installation conflicts. Contract Documents shall not be interpreted to include all bends and offsets required to avoid conflicts.
8. Hangers, supports, unistrut or miscellaneous steel required for a complete installation.
9. Coordinate openings required to accommodate installation of equipment prior to enclosure of spaces by other Trades.
10. Coordinate roof and other opening dimensions and locations required with
Structural and other Contractors.
11. Remove temporary covers over mechanical openings installed by others prior to performing the Work (including cutting metal deck or burning of welds).
Maintain openings in safe manner.
12. Furnish sleeves as needed and not indicated in the Documents for installation by others. Provide layout and assistance with placement.
13. Furnish, for installation by others, access panels as required for this Work but not indicated in the documents. Confirm type of panel required with Clark
Construction Company prior to ordering.
14. Access panels as required in duct to access in-duct coils or other equipment.
15. HVAC Work as described in specification section “Temporary Facilities and
Controls”.
16. Gas piping connection for temporary heat.
17. Mechanical and plumbing insulation.
18. Roof curbs associated with the Work of this bid category.
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
19. Provide and install roof drains as indicated in the documents. Coordinate with with other Trades.
20. All plumbing and gas piping within building to +/- 5’-0 outside of building including connection point. Include tie-ins to existing buildings.
21. Concrete housekeeping pads for mechanical equipment required and not indicated in the documents.
22. Support steel required for mechanical equipment and not indicated in the documents.
23. Pumps and associated variable frequency drives.
24. Disconnects and motor starters for mechanical equipment as indicated in the documents.
25. Electrical Work from electrical disconnects to equipment is the responsibility of this bid category.
26. Control and/or low voltage wiring of equipment. Electrical Contractor shall have a single point connection only.
27. Coring as required to perform the Work of this bid category.
28. Fire stopping of penetrations associated with the Work of this bid category.
29. Seal all penetrations through roof, walls & floors.
30. Temperature controls including raceways, wiring, complete commissioning and user training.
31. Aluminum pipe enclosures and supports.
32. Coordinate floor drain elevations with Clark Construction Company and other
Trades.
33. Protect floor drain elevations and locations during concrete pours. Protect floor drains from debris during the construction process.
34. Commissioning of mechanical and plumbing systems as indicated in the
Documents. Coordinate with Owner’s Commissioning Agent as required.
35. Testing and balancing of system. Submit final test and balance reports in a timely manner as not to delay other project requirements.
36. Complete check, test and start up of mechanical systems. Provide written plan and documentation to Clark Construction Company of check, test and start of each component of the system.
37. Identification, labeling and tagging system equipment, piping, duct, etc.
38. Framed identification charts in mechanical rooms providing valve and major equipment information.
39. Perform complete flushing, disinfecting, cleaning, and testing of mechanical and plumbing systems and equipment.
40. Participate in fire alarm testing process as it relates to the Work of this bid category.
41. Train Owner’s representative(s) on proper start-up, operation and maintenance of all mechanical systems. Provide video recording of training for Owner.
42. Paint touch-up of factory finished equipment.
43. Complete chemical treatment of system.
002416-5
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
44. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.
45. Warranty and guarantee start date shall be the project Substantial Completion date.
46. All utility shut downs and tie ins must be completed on 2nd shift/weekend work with approval from Clark Construction Company and Owner in advance.
47. This trade shall include mechanical and plumbing work for the construction phase egress plan shown on drawing A0.3 and MP1.8.
48. Furnish, install, and remove at a later date, temporary water meter with backflow preventor at mechanical room riser to be used during construction.
49. Control wiring, connections, and programing of Duct Detectors for code required operations of equipment.
50. This contractor is responsible for all gas piping as indicated in the documents, including outside of +/- 5’ of the building.
51. Excavation, backfill and compaction associated with the Work of this bid category.
52. Restore grade to condition that existed prior to start of the Work.
Bid Category 26A-Electrical JUNE 2026
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
BID CATEGORY 26A - Electrical
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of
BASE SPECIFICATION(S) - (Include all Work specified or reasonably inferred)
26 00 05 – SES BASIC ELECTRICAL REQUIREMENTS
26 05 26 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 – HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33.13 – CONDUIT FOR ELECTRICAL SYSTEMS
26 05 33.16 – BOXES FOR ELECTRICAL SYSTEMS
26 05 33.23 – SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS
26 05 36 – CABLE TRAYS FOR ELECTRICAL SYSTEMS
26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 73 – POWER SYSTEMS STUDIES
26 09 23 – LIGHTING CONTROL DEVICES
26 22 00 – LOW-VOLTAGE TRANSFORMERS
26 24 16 – PANELBOARDS
26 27 26 – WIRING DEVICES
26 28 13 – FUSES
26 28 16.16 – ENCLOSED SWITCHES
26 43 00 – SURGE PROTECTIVE DEVICES
26 51 00 – INTERIOR LIGHTING
26 56 00 – EXTERIOR LIGHTING
27 11 16 – COMMUNICATIONS CABINETS, RACKS, AND FRAMES
27 13 23 – COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING
27 15 16 – COMMUNICATIONS COPPER HORIZONTAL CABLING
27 41 16 – INTEGRATED AUDIO VIDEO SYSTEMS
27 51 16 – PUBLIC ADDRESS & CLOCK SYSTEMS
28 00 00 – SECURITY SYSTEMS
28 46 00 – FIRE DETECTION AND ALARM
REFERENCE SPECIFICATION(S) - (Include portions of the Work specified as noted
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
014533 – CODE-REQUIRED SPECIAL INSPECTIONS
26 05 05 – SELECTIVE DEMOLITION FOR ELECTRICAL
033000 – CAST-IN-PLACE CONCRETE
078400 – FIRESTOPPING
079200 – JOINT SEALANTS
083100 – ACCESS DOORS AND PANELS
087100 – DOOR HARDWARE
312301 – EXCAVATION, FILLING, AND GRADING
312302 – EXCAVATION AND BACKFILLING FOR UTILITY CONSTRUCTION
313219 – GEOTEXTILE FABRIC
321116 – GRANULAR SUBBASE
321123 – AGGREGATE BASE COURSES
321500 – AGGREGATE SURFACING
safety program.
2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark
Construction Superintendents
3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.
4. Obtain permits required to complete the Work of this bid category.
5. MEP Contractors are required to submit MEP Cost Breakdown as a start-up submittal for approval.
6. Coordinate design of system material and equipment routing with other Trade
Contractors as required to avoid conflicts.
a. This Trade Contractor shall develop shop drawings equal to scale as that to be used by other Trade Contractors in which conflicts have potential to occur. Drawing scale shall be coordinated prior to start of shop drawings.
b. Shop drawings shall be extensively and thoroughly coordinated with each Trade Contractor with which conflicts have potential to occur to the extent required to eliminate conflicts prior to fabrication and installation.
c. Conflicts encountered during fabrication and installation which could have been foreseen through a more extensive coordination effort shall be corrected by this bid category.
d. All costs for modifications which are a result of conflicts with items noted in the Contract Documents shall be born by this bid category.
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
e. In the event of conflict with items indicated in shop drawings of other
Trade Contractors and not in the Contract Documents, the cost shall be shared equally by the Trade Contractors involved.
7. Coordinate openings required to accommodate installation of equipment prior to enclosure of spaces by other Trades.
8. Hangers, supports, unistrut or misc. steel required for a complete installation.
9. Equipment support structures as required.
10. Furnish only, for installation by others, access panels as required for this Work but not indicated in the documents. Confirm type of panel required with Clark
Construction Company prior to ordering.
11. Concrete housekeeping pads for electrical equipment required and not indicated in the documents.
12. Fire stopping of penetrations associated with the Work of this bid category.
13. Excavation, backfill and compaction associated with the Work of this bid category.
14. Warning tape in trenches above conduit and wire.
15. Restore grade to condition that existed prior to start of the Work.
16. Furnish sleeves as needed and not indicated in the Documents for installation by others. Provide layout and assistance with placement.
17. Cut/Cap/Make safe for electrical demo as required.
18. Coring as required to perform the Work of this bid category.
19. Firestopping of penetrations associated with the Work of this bid category.
20. Seal all penetrations through roof, walls & floors.
21. Provide and install door position switches as required for doors.
22. Complete wiring for door hardware provided by others.
23. Perform final hook up of equipment furnished by Owner and others. Coordinate rough in location with equipment supplier and Clark Construction Company.
24. Electrical Work associated with fire protection system equipment (e.g. tamper and flow switches, etc.) installed by Fire Protection Contractor.
25. Electrical identification and labeling.
26. Obtain permits required to complete the work of this bid category.
27. Electrical work as described in specification section 015000 “Temporary
Facilities and controls”
28. Electrical connections for temporary heat
29. Site electrical work is the responsibility of this contractor.
30. Site lighting including light pole bases.
31. Include directional drilling under service road behind the Davis Building for power feeds to the sanitary force main pump station.
32. Backfill material for underground utilities under concrete and asphalt shall match road sections in the civil documents.
33. Fire Alarm system. Coordinate tie in requirements with other trades.
34. Provide and install duct detectors as required.
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
35. Remove spoils from the site and backfill in accordance with the plans and specifications requirements.
36. Furnish and install starters and disconnects for equipment by others as indicated in the documents.
37. Install variable speed drives furnished by others including conduit and wiring.
38. Install TVs and brackets provided by Owner. Coordinate required in-wall backing with other trades.
39. Train Owner’s representative(s) on proper start-up, operation and maintenance of all mechanical systems. Provide video recording of training for Owner.
40. Include any patching needed.
41. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.
42. Warranty and guarantee start date shall be the project Substantial Completion date.
43. This trade shall include work for the construction phase egress plan shown on drawing A0.3 Include revised lighting layout with battery back up emergency lights, exit signs and additional horn strobe fire alarm devices for code compliance. This trade shall include rework of the egress corridor to return to previous condition at the end of the project.
44. All utility shut downs and tie ins must be completed on 2nd shift/weekend work with approval from Clark Construction Company and Owner in advance.
Mandatory Bid Alternates:
1. Costs for the following alternative scope items must be provided with your bid.
2. Refer to Section 012300 ALTERNATES for more information.
3. Any applicable mark-up, OH&P, management costs, and/or general conditions costs must be accounted for in the alternate cost
a. Alternate #3: Demolition of electrical feed and conduit to existing chicken coop as shown on C1.0.
Bid Category 31-Mass Grading JUNE 2026
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
BID CATEGORY 31A - Sitework, Utilities, Landscaping & Asphalt Paving
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of
BASE SPECIFICATION - (Include all Work specified or reasonably inferred)
00 24 13 – SCOPE OF WORK GENERAL NOTES
014126 – PERMIT REQUIREMENTS
014516.02 – DENSITY AND AGGREGATE TESTING
015726 – DUST CONTROL
0017123.16 – CONSTRTUCTION STAKING BY CONTRACTOR
024113.13 – PAVEMENT REMOVAL
311001 – CLEARING AND REMOVAL OF MISCELLANEOUS STRUCTURES
312301 – EXCAVATING, FILLING, AND GRADING
312302 – EXCAVATING AND BACKFILLING FOR UTILITY CONSTRUCTION
312500 – SOIL EROSION AND SEDIMENTATION CONTROL
312319 – GEOTEXTILE FABRIC
313700 – RIPRAP
321116 – GRANULAR SUBBASE
321123 – AGGREGATE BASE COURSES
321216 – HMA PAVING
321500 – AGGREGATE SURFACING
321723 – PAVEMENT MARKINGS
328423 – UNDERGROUND SPRINKLERS
329119 – TOPSOIL FOR LANDSCAPING & CONSTRUCTION
329200 – NATURAL TURF & SODDING
329200 – TURF ESTABLISHMENT
329300 – PLANTS
329400 – LANDSCAPE MAINTENANCE & WARRANTY STANDARDS
330500 – ADJUSTING STRUCTURES
331100 – WATER MAIN (Genesee County)
333100 – SANITARY SEWER (Genesee County)
334400 – STORM SEWERS
REFERENCE SPECIFICATION - (Include portions of the Work specified as noted
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
012100 – ALLOWANCES
014533 – CODE-REQUIRED SPECIAL INSPECTIONS
017123.16 – CONSTRUCTION STAKING BY CONTRACTOR
024119 – SELECTIVE DEMOLITION
033000 – CAST-IN-PLACE CONCRETE
042000 – UNIT MASONRY
231123 – NATURAL GAS PIPING, VALVES AND ACCESSORIES
321300 – CONCRETE CURB AND GUTTER, SIDEWALK, AND MISC. PAVMT.
safety program.
2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark
Construction Superintendents
3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.
4. Obtain permits required to complete the Work of this bid category.
5. Verify on-site and surrounding grades are in accordance with the Documents prior to start of the work. Report discrepancies to Clark Construction Company in writing.
6. Verify location of existing utilities prior to performing the work. Hand dig as required to avoid contact with underground utilities.
7. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.
8. Remove debris and/or spoils from the site in a timely manner.
9. Import and export of soil material, cut and fill, grading, and compaction to achieve grades required by the documents.
10. Site grading to plus or minus 1/10 of a foot of design to balance.
11. All subbase is the responsibility of this bid category.
12. Pumping water to perform the work of this bid category.
13. Provide, maintain, and coordination location of dumpsters for demolition.
14. Legal disposal of materials off site.
15. Provide erosion control for entire project, including soil permit, installation, maintenance, storm water operator and removal at completion of project.
16. Topsoil raking and removal of rocks, stones and debris.
17. Clean-up on a daily basis.
18. Broom cleaning of hard surfaces.
19. Initial staking/support of plantings.
20. Final connection of irrigation system to water supply.
21. Weed control and fertilizer per specifications.
22. Temporary watering as required until irrigation system is fully functioning.
BID CATEGORY SPECIFIC NOTES
ADDENDUM NO. 03
23. Tree removal, clearing and grubbing.
24. Protect existing structures and/or trees and landscaping to remain.
25. Construct building pad including import material, placement, grading, and compaction.
26. Strip, stockpile and re-spread topsoil at a later date as directed by Clark
Construction Company. Include remobilization.
27. Grade, seed and mulch areas disturbed outside of construction limits as a result of the work of this bid category.
28. Proof rolling of sub-grade as required prior to placement of stone base, asphalt, concrete or other materials.
29. Perform water, sanitary and storm tie-in to public utility system in accordance with requirements of authorities having jurisdiction.
30. Extend utility piping to connect to building systems to 5’-0” from the building line. Coordinate with building Trade Contractors and other design documents the exact location and elevation of connection prior to performing the Work. Report discrepancies to Clark Construction Company in writing.
31. Install drainage structures such that Subgrade will drain completely by gravity.
Final adjustments of the drainage structures shall be performed by this bid category at a later date just prior to placement of finished surfaces and as directed by Clark Construction Company. Final adjustments shall include required excavation, backfill and compaction.
32. Coordinate and perform final adjustments of valve boxes and other utilities prior to placement of finished surfaces by others.
33. Dust control for the duration of the Work of this bid category.
34. Restore disturbed grade to condition that existed prior to performing the Work.
35. Underdrain system as indicated in documents.
36. Grade, seed and mulch areas disturbed outside of the building area as a result of the Work of this bid category.
37. Clean dirt and debris out of storm water system upon completion of the project when directed by Clark Construction Company.
38. All site demolition including asphalt and concrete indicated in the drawings.
39. Verify telephone riser is abandoned prior to demolition. If riser is determined to be active, notify Clark Construction Company for final direction from Owner.
40. Temporary fencing, gates, laydown areas, and site development as indicated on the site logistics plan. Include restoration of site area upon project completion.
Topsoil to be stripped and stockpiled on site for laydown area development per logistics plan
a. Gravel…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .