GCI Expansion - Addendum No. 03 - 10.07.2026.pdf

PDF 5 MB Posted

Attached to
GCI Expansion Project
Solicitation number
RFP GIS 260000002727 4
Issued by
Genesee County, Michigan

About this file

This is Addendum No. 3 to the contract documents for the GCI Expansion Project at Genesee Career Institute, a facility addition project located in Michigan and administered by the Genesee Intermediate School District. The addendum, issued on October 7, 2026, modifies the original bidding and contract requirements for Bid Release #1 with a bid proposal due date of October 15, 2026, at 1:50 P.M. Key modifications include reissued specifications for Division 27 (Communication Systems) and Division 28 (Electronic Safety and Security Systems), updated drawing sheets (T1.1, T2.1, T2.2, and T2.3), clarifications to concrete lintels responsibility under Bid Category 03A, revisions to gas piping and excavation responsibilities under Bid Category 23B, addition of Mandatory Alternate #3 to Bid Categories 26A and 31A, and inclusion of the A232-2019 General Conditions. The addendum incorporates 15 pre-bid RFI responses addressing generator panel location, communication and security devices, existing structures, metal panel details, casework specifications, hydronics, door locations, masonry specifications, sitework scope, utility requirements, fiber optic work, and temporary fencing. A pre-bid conference was held on October 5, 2026, with an attendee sign-in sheet included.

The contract structure utilizes a Stipulated Sum pricing model with the contract sum, alternates, and allowances to be detailed in the Contractor's Pricing Form based on the Project Schedule contained in the Project Manual. Retainage is set at ten percent (10%) of each progress payment until substantial completion, with final payment due within sixty days of project completion and all closeout documentation approval. Mandatory Alternate #3 requires bidders to provide costs for demolition of the electrical feed and conduit to the existing chicken coop (26A) and demolition of the existing chicken coop structure and fencing (31A). An allowance of $100,000 is included for undercutting subbase material under Bid Category 31A. The project requires compliance with Michigan's Prevailing Wage Act (Public Act 10 of 2023), and all contractors must maintain insurance with the Owner and Construction Manager named as additional insured parties and provide performance and payment bonds. Clark Construction Company serves as the Construction Manager, and Kingscott Associates, Inc. serves as the Architect, with the Owner's representative identified as Jeff Jansen, Director of Operations for the Genesee Intermediate School District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 3

10/7/2026

ADDENDUM NO. 3

PROJECT: Genesee ISD GCI Addition

DESCRIPTION: GCI Addition

BID PACKAGE RELEASE NUMBER: Bid Release #1

CLARK PROJECT NO: #26-3013

BID PROPOSAL DUE DATE/TIME: 1:50 P.M., Thursday, October 15, 2026

The following clarifications and/or Changes made to the Contract Documents are hereby made part of the Contract Documents.

The general character of the Work clarified or revised by this Addendum shall be the same as required by the complete set of Contract Documents. All incidentals required in connection with the Work of this Addendum shall be included in the Scope of Work even though not specifically specified.

All bidders shall be held responsible to review the Addendum and to include in its Bid Proposal all Work reasonably inferred to be included in its Scope of Work.

Acknowledge receipt of this Addendum in the space provided on the Bid Proposal Form.

1) Division 00 – Bidding and Contract Requirement Modifications

a) SECTION 000110 – K-12 Table of Contents

i) Reissued to include Division 27 & 28 Specifications as listed in A/E Addendum No.

03 Write-Up

b) SECTION 000115 – List of Drawing Sheets

i) Reissued for updated drawings T1.1, T2.1, T2.2 and T2.3

c) SECTION 002416 – Bid Cat. 03A Concrete & Foundations

i) Reissued to clarify the responsibility of concrete lintels

d) SECTION 002416 – Bid Cat. 23B HVAC & Plumbing

i) Reissued to clarify responsibility of gas piping and excavation, backfill and restoration associated with the work of this bid category.

e) SECTION 002416 – Bid Cat. 26A Electrical

i) Reissued to add new Division 27 & 28 specifications and added Mandatory Alternate

#3

f) SECTION 002416 – Bid Cat. 31A Earthwork & Utilties

i) Reissued to removed gas piping from scope, clarify requirements for construction gravel material thickness, construction fence posts, snow removal, and added

Mandatory Alternate #3

Addendum No. 3

g) SECTION 005216 – K-12 Agreement Form

i) Reissued to include A232-2019 General Conditions

2) DIVISION 01 – GENERAL REQUIREMENTS

a) SECTION 012300 – Alternates

i) Reissued to add Alternate #3.

3) A/E (Kingscott) Documentation

a) Addendum No. 3 Write-Up

b) Specifications:

i) 271116 Communications Cabinets, Racks, Frames and Enclosures (Initial issuance – Addendum 03)

ii) 271323 – Communications Optical Fiber Backbone Cabling (Initial issuance – Addendum 03)

iii) 271513 – Communications Copper Horizontal Cabling (Initial issuance – Addendum

03)

iv) 274116 – Integrated Audio Video Systems (Initial issuance – Addendum 03)

v) 275116 – Public Address & Clock Systems (Initial issuance – Addendum 03)

vi) 280000 – Security Systems (Initial issuance – Addendum 03)

c) Drawings:

i) T1.1 – Technology Legend and Details (reissued)

ii) T2.1 – First Floor Structured Cabling Plan (reissued)

iii) T2.2 – First Floor Security Plan (reissued)

iv) T2.3 – First Floor PA and Clock Plan (reissued)

4) Pre-Bid RFI Responses

a) RFI 0001 – GCI – Generator Panel Location for Sanitary Pump Station

b) RFI 0003 – GCI – Communication and Security Devices

c) RFI 0012 – GCI – Existing Greenhouse and Chicken Coop

d) RFI 0015 – GCI – 07B Scope Clarification and Metal Panel Details

e) RFI 0016 – GCI – Casework Specification 12 30 00

f) RFI 0021 – GCI – Hydronics and Balancing

g) RFI 0024 – GCI – Door 601 Locations

h) RFI 0025 – GCI – Specified Masonry Compressive Strength

i) RFI 0027 – GCI – Schedule Clarifications for Masonry Scope

j) RFI 0028 – GCI – 31A Sitework Scope Questions

k) RFI 0029 – GCI – Project Requirements for Textura or Autodesk

l) RFI 0030 – GCI – Portal Frame Concrete Lintel

m) RFI 0031 – GCI – Below Grade Waterproofing Responsibility

n) RFI 0032 – GCI – Existing Fiber Relocation

o) RFI 0033 – GCI – Sawcutting & Restoration for Utilties

p) RFI 0034 – GCI – Fiber Termination Location & Equipment Rack Specification

q) RFI 0037 – GCI – Decorative CMU Clarification

r) RFI 0038 – GCI – Fire Protection Pipe Thickness

s) RFI 0041 – GCI – Temporary Fencing

5) Pre-Bid Conference Sign-In Sheet

a) Sign-in sheet from meeting held on 10.05.26 attached

000110-1

Section 000110-Table of Contents JANUARY 2024

SECTION 000110

PROJECT MANUAL

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

000101 PROJECT MANUAL COVER

000110 TABLE OF CONTENTS

000115 LIST OF DRAWING SHEETS

BIDDING REQUIREMENTS

001100 ADVERTISEMENT/INVITATION FOR BIDS

002113 INSTRUCTIONS TO BIDDERS

002413 SCOPE OF WORK - GENERAL NOTES

002416 SCOPE OF WORK - BID CATEGORY SPECIFIC NOTES

003113 PROJECT MILESTONE SCHEDULE

004126 BID PROPOSAL FORM

004126.1 FAMILIAL DISCLOSURE FORM

004126.2 IRAN SANCTION FORM

004126.3 CRIMMINAL AFFIDAVIT FORM

CONTRACTING REQUIREMENTS

005216 AGREEMENT FORM

006113 PERFORMANCE AND PAYMENT BOND

006200 CERTIFICATES AND OTHER FORMS

007216 GENERAL CONDITIONS

DIVISION 01 – GENERAL REQUIREMENTS

011000 SUMMARY

012100 ALLOWANCES

012300 ALTERNATES

012500 SUBSTITUTION PROCEDURES

012600 CONTRACT MODIFICATION PROCEDURES

012900 PAYMENT PROCEDURES

012973 SCHEDULE OF VALUES

013000 ADMINISTRATIVE REQUIREMENTS

013119 PROJECT MEETINGS

013300 SUBMITTAL PROCEDURES

013316 DESIGN DATA (BIM COORDINATION)

013323 SHOP DRAWINGS, PROJECT DATA AND SAMPLES

013529 HEALTH, SAFETY AND EMERGENCY RESPONSE PROCEDURES

000110-2

013543 ENVIRONMENTAL PROCEDURES

014000 QUALITY REQUIREMENTS

014100 AIR BARRIER SYSTEM REQUIREMENTS

014126 PERMIT REQUIREMENTS

014216 DEFINITIONS

014339 MOCKUPS

014516 FIELD QUALITY CONTROL PROCEDURES

014516.01 CONCRETE TESTING

014516.02 DENSITY AND AGGREGATE TESTING

014533 CODE-REQUIRED SPECIAL INSPECTIONS

014517 NON-CONFORMANCE PROCEDURE

015000 TEMPORARY FACILITIES AND CONTROLS

015726 DUST CONTROL

016000 PRODUCT REQUIREMENTS

016116 VOLITILE ORGANIC COMPOUND (VOC) CONTENT

RESTRICTIONS

017000 EXECUTION AND CLOSEOUT REQUIREMENTS

017123 FIELD ENGINEERING

017123.16 CONSTRUCTION STAKING BY CONTRACTOR

DIVISION 01 – GENERAL REQUIREMENTS (CONTINUED)

017329 CUTTING AND PATCHING

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017610 TEMPORARY PROTECTIVE COVERINGS

017700 CLOSEOUT PROCEDURES

017800 CLOSEOUT SUBMITTALS

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

018113 SUSTAINABLE DESIGN (LEED) REQUIREMENTS

DIVISION 02 – EXISTING CONDITIONS

023200 GEOTECHNICAL INVESTIGATIONS

024113.13 PAVEMENT REMOVAL

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

033000 – CAST-IN-PLACE CONCRETE

000110-3

TABLE OF CONTENTS

ADDENDUM NO. 3

DIVISION 04 – MASONRY

042000 UNIT MASONRY

044316 STONE FABRICATIONS

DIVISION 05 – METALS

051200 STRUCTURAL STEEL FRAMING

052100 STEEL JOIST FRAMING

053100 STEEL DECKING

054000 COLD-FORM METAL FRAMING

055133 METAL LADDERS

DIVISION 06 – WOOD, PLASTICS AND COMPOSITIES

061053 MISCELLANEOUS ROUGH CARPENTRY

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

071300 SHEET WATERPROOFING

072100 THERMAL INSULATION

072119 FOAMED-IN-PLACE INSULATION

072500 WEATHER BARRIERS

074213 METAL WALL PANELS

075323 ETHYLENE-PROYLENE-DIENE-MONOMER ROOFING (EPDM) –

ELEVATE

075419 POLYVINYL-CHLORIDE ROOFING – DURO-LAST (ALTERNATE

#1)

076200 SHEET METAL FLASHING AND TRIM

076500 FLEXIBLE FLASHING

077100 ROOF SPECIALTIES

077200 ROOF ACCESSORIES

078400 FIRESTOPPING

079200 JOINT SEALANTS

079513 EXPANSION JOINT COVER ASSEMBLIES

DIVISION 08 – OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

081742 HYBRID FRP DOORS

083100 ACCESS DOORS AND PANELS

084313 ALUMINUM-FRAMED STOREFRONTS

087100 DOOR HARDWARE

000110-4

TABLE OF CONTENTS

ADDENDUM NO. 3

088000 GLAZING

088853 SECURITY GLAZING – IMPACT SECURITY

DIVISION 09 – FINISHES

092116 GYPSUM BOARD ASSEMBLIES

092216 NON-STRUCTURAL METAL FRAMING

093000 TILING

095100 ACOUSTICAL CEILINGS

096500 RESILIENT FLOORING

096723 RESINOUS FLOORING

096816 SHEET CARPETING

097200 WALL COVERINGS

098430 SOUND-ABSORBING WALL AND CEILING UNITS

099123 INTERIOR PAINTING

099600 HIGH-PERFORMANCE COATINGS

DIVISION 10 – SPECIALTIES

101100 VISUAL DISPLAY UNITS

101419 DIMENSIONAL LETTER SIGNAGE

102113.17 PHENOLIC TOILET COMPARTMENTS

102123 CUBICLE CURTAINS AND TRACK

102800 TOILET, BATH, AND LAUNDRY ACCESSORIES

104400 FIRE PROTECTION SPECIALTIES

DIVISION 12 – FURNISHINGS

122400 WINDOW SHADES

123000 MANUFACTURERED PLASTIC LAMINATE CLAD CASEWORK

123661.16 SOLID SURFACE COUNTERTOPS

DIVISION 21 – FIRE SUPPRESSION

210500 COMMON WORK RESULTS FOR FIRE SUPPRESSION

210523 GENERAL DUTY VALVES FOR WATER BASED FIRE

SUPPRESSION PIPING

210553 IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND

EQUIPMENT

211300 FIRE-SUPPRESSION SPRINKLER SYSTEMS

DIVISION 22 – PLUMBING

000110-5

220005 BASIC PLUMBING REQUIREMENTS

220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

220519 METERS AND GAUGES FOR PLUMBING PIPING

220523 GENERAL DUTY VALVES FOR PLUMBING PIPING

220553 INDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220593 TESTING, ADJUSTING, AND BALANCING FOR PLUMBING

220719 PLUMBING PIPING INSULATION

220800 PLUMBING COMMISSIONING REQUIREMENTS

221005 PLUMBING PIPING

221006 PLUMBING PIPING SPECIALTIES

221123 DOMESTIC WATER PUMPS

222300 PLUMBING EQUIPMENT

224000 PLUMBING FIXTURES

DIVISION 23 – HEATING, VENTILATING & AIR-CONDITIONING (HVAC)

230005 BASIC HVAC REQUIREMENTS

230130.51 HVAC AIR-DISTRIBUTION SYSTEM CLEANING

230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

230519 METERS AND GAUGES FOR HVAC PIPING

230523 GENERAL DUTY VALVES FOR HVAC PIPING

230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593 TESTING, ADJUSTING AND BALANCING FOR HVAC

230713 DUCT INSULATION

230714 DUCT ACOUSTICAL LINER AND LAGGING

230716 HVAC EQUIPMENT INSULATION

230719 HVAC PIPING INSULATION

230800 HVAC COMMISSIONING REQUIREMENTS

230913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

230923 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC

230934 VARIABLE-FREQUENCY MOTOR CONTROLLERS FOR HVAC

230945 GAS DETECTION AND ALARM

231123 NATURAL GAS PIPING, VALVES AND ACCESSORIES

232113 HVAC PIPING

232114 HYDRONIC SPECIALTIES

232123 HVAC PUMPS

232500 HVAC WATER TREATMENT

233100 HVAC DUCTS AND CASINGS

233300 AIR DUCT ACCESSORIES

233319 DUCT SILENCERS

233423 HVAC POWER VENTILATORS

000110-6

233600 AIR TERMINAL UNITS

233700 AIR OUTLETS AND INLETS

235100 BREECHINGS, CHIMNEYS, AND STACKS

235216 CONDENSING BOILERS

237223 PACKAGED AIR-TO-AIR ENERGY RECOVERY UNITS

238126.13 SMALL-CAPACITY SPLIT-SYSTEM AIR CONDITIONERS

238200 CONVECTION HEATING AND COOLING UNITS

DIVISION 26 – ELECTRICAL

260005 SES BASIC ELECTRICAL REQUIREMENTS

260505 SELECTIVE DEMOLITION FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND

CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533.13 CONDUIT FOR ELECTRICAL SYSTEMS

260533.16 BOXES FOR ELECTRICAL SYSTEMS

260533.23 SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS

260536 CABLE TRAYS FOR ELECTRICAL SYSTEMS

260553 INDENTIFICATION FOR ELECTRICAL SYSTEMS

260573 POWER SYSTEM STUDIES

260923 LIGHTING CONTROL DEVICES

262200 LOW-VOLTAGE TRANSFORMERS

262416 PANELBOARDS

262726 WIRING DEVICES

262813 FUSES

262816.16 ENCLOSED SWITCHES

264300 SURGE PROTECTIVE DEVICES

265100 INTERIOR LIGHTING

265600 EXTERIOR LIGHTING

DIVISION 27 – COMMUNICATION SYSTEMS

271116 COMMUNICATIONS CABINETS, RACKS, AND FRAMES

271323 COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING

271513 COMMUNICATIONS COPPER HORIZONTAL CABLING

274116 INTEGRATED AUDIO VIDEO SYSTEMS

275116 PUBLIC ADDRESS & CLOCK SYSTEMS

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

280000 SECURITY SYSTEMS

000110-7

TABLE OF CONTENTS

ADDENDUM NO. 3

284600 FIRE DETECTION AND ALARM

DIVISION 31 – EARTHWORK

311001 CLEARING AND REMOVAL OF MISCELLANEOUS STRUCTURES

312301 EXCAVATING, FILLING AND GRADING

312302 EXCAVATING AND BACKFILLING FOR UTILITY

CONSTRUCTION

312500 SOIL EROSION AND SEDIMENTATION CONTROL

313219 GEOTETILE FABRIC

313700 RIPRAP

DIVISION 32 – EXTERIOR IMPROVEMENTS

321116 GRANULAR SUBBASE

321123 AGGREGATE BASE COURSES

321216 HMA PAVING

321300 CONCRETE CURB AND GUTTER, SIDEWALK AND

MISCELLANEOUS PAVEMENT

321500 AGGREGATE SURFACING

321723 PAVEMENT MARKINGS

328423 UNDERGROUND SPRINKLERS

329119 TOPSOIL FOR LANDSCAPING AND SODDING

329200 NATURAL TURF AND SODDING

329200 TURF ESTABLISHMENT

329300 PLANTS

329400 LANDSCAPE MAINTENANCE AND WARRANTY STANDARDS

DIVISION 33 – UTILITIES

330500 ADJUSTING STRUCTURES

331100 WATERMAIN (GENESSEE COUNTY)

333100 SANITARY SEWER (GENESSEE COUNTY)

334400 STORM SEWERS

END OF SECTION

000115-1

Section 000115-List of Drawing Sheets, JANUARY 2024

SECTION 000115

LIST OF DRAWING SHEETS

1. LIST OF DRAWINGS PREPARED BY KINGSCOTT

SHEET NO. TITLE DATE

G0.1 TITLE SHEET 08-24-2026

G0.2 DATA SHEET 08-24-2026

C0.0 COVER SHEET 08-24-2026

C0.1 GENERAL NOTES AND PROJECT

CONTROL SHEET

08-24-2026

C0.2 GCDC NOTES SHEET 08-24-2026

C0.3 LEGEND SHEET 08-24-2026

C1.0 EXISTING CONDITIONS AND REMOVAL

PLAN

08-24-2026

C1.1 SITE PLAN 08-24-2026

C1.2 PROPOSED GRADING AND STORM

SEWER PLAN

08-24-2026

C1.3 PROPOSED STORMWATER PLAN 08-24-2026

C1.4 SESC PLAN 08-24-2026

C1.5 WATER AND SANITARY PLAN 08-24-2026

C1.6 WATER AND SANITARY PLAN 08-24-2026

C1.7 SANITARY PROFILES 08-24-2026

C1.8 WATERMAIN PROFILES 08-24-2026

C5.1 SITE DETAILS 08-24-2026

C5.2 GCDC WATER DETAILS 08-24-2026

C5.3 GCDC WATER DETAILS 08-24-2026

C5.4 GCDC PUMP STATION DETAILS 08-24-2026

C5.5 SESC KEY 08-24-2026

L1.1 SITE LAYOUT 08-24-2026

L1.2 SITE DETAILS 08-24-2026

L2.1 PLANTING PLAN 08-24-2026

L2.2 PLANTING DETAILS 08-24-2026

L2.3 PLANTING DETAILS 08-24-2026

L3.1 IRRIGATION PLAN 08-24-2026

L3.2 IRRIGATION NOTES 08-24-2026

S0.1 STRUCTURAL NOTES 08-24-2026

S0.2 SPECIAL INSPECTIONS & DESIGN

LOADS

08-24-2026

S0.3 TYPICAL DETAILS 08-24-2026

S1.0 FOUNDATION PLAN 08-24-2026

S1.1 ROOF FRAMING PLAN 08-24-2026

S2.1 ELEVATIONS 08-24-2026

S3.1 SECTIONS 08-24-2026

000115-2

ADDENDUM NO. 3

A0.1 FIRST FLOOR COMPOSITE PLAN 08-24-2026

A0.2 FIRST FLOOR CODE COMPOSITE PLAN

& INFO

08-24-2026

A0.3 CODE PLAN UNIT 800 & ENLARGED

EGRESS

08-24-2026

A0.4 ROOF COMPOSITE PLAN 08-24-2026

D1.6 FIRST FLOOR DEMOLITION PLAN- UNIT

08-24-2026

A1.8 FIRST FLOOR PLAN – UNIT 800

ADDITION

08-24-2026

A1.18 FIRST FLOOR PLAN – UNIT 800

ADDITION DIMENSIONS

08-24-2026

A1.28 FIRST FLOOR EQUIPMENT PLAN – UNIT

800 ADDITION

08-24-2026

A1.29 FIRST FLOOR EQUIPMENT SCHEDULES

& SIGNAGE

08-24-2026

A1.41 ENLARGED PLANS 08-24-2026

A2.8 FIRST FLOOR REFLECTED CEILING

PLAN – UNIT 800 ADDITION

08-24-2026

A2.30 INTERIOR PARTITION TYPES 08-24-2026

A3.1 EXTERIOR ELEVATIONS 08-24-2026

A3.2 BUILDING SECTIONS 08-24-2026

A4.1 WALL SECTIONS 08-24-2026

A4.2 WALL SECTIONS 08-24-2026

A5.1 BUILDING DETAILS 08-24-2026

A5.2 BUILDING DETAILS 08-24-2026

A6.1 DOOR SCHEDULE & OPENING

ELEVATIONS

08-24-2026

A6.2 DOOR & WINDOW DETAILS 08-24-2026

A6.3 DOOR & WINDOW DETAILS 08-24-2026

A8.8 FIRST FLOOR COLOR LAYOUT PLAN -

UNIT 800

08-24-2026

A9.1 INTERIOR ELEVATIONS 08-24-2026

A9.2 INTERIOR ELEVATIONS 08-24-2026

A9.3 INTERIOR ELEVATIONS 08-24-2026

A9.4 INTERIOR FINISH DETAILS 08-24-2026

A9.5 INTERIOR RENDERINGS 08-24-2026

FP0.0 FIRE PROTECTION DATA SHEET 08-24-2026

FP1.8 FIRST FLOOR FIRE PROTECTION PLAN –

UNIT 800 ADDITION

08-24-2026

P0.0 PLUMBING DATA SHEET 08-24-2026

P0.8 UNDERGROUND PLUMBING PLAN –

UNIT 800 ADDITION

08-24-2026

P1.8 FIRST FLOOR PLUMBING PLAN – UNIT 08-24-2026

000115-3

ADDENDUM NO. 3

800 ADDITION

P3.8 PLUMBING ROOF PLAN – UNIT 800

ADDITION

08-24-2026

P4.1 PLUMBING ENLARGED PLANS 08-24-2026

P5.1 PLUMBING DETAILS 08-24-2026

P6.1 PLUMBING SCHEDULES 08-24-2026

M0.0 MECHANICAL DATA SHEET 08-24-2026

MH1.8 FIRST FLOOR MECHANICAL HVAC

PLAN – UNIT 800 ADDITION

08-24-2026

MP1.4 FIRST FLOOR MECHANICAL PIPING

PLAN – UNIT 400

08-24-2026

MP1.8 FIRST FLOOR MECHANICAL PIPING

PLAN – UNIT 800 ADDITION

08-24-2026

M3.8 MECHANICAL ROOF PLAN – UNIT 800

ADDITION

08-24-2026

M4.1 MECHANICAL ROOM ENLARGED PLANS

& SECTIONS

08-24-2026

M4.2 MECHANICAL SECTIONS 08-24-2026

M5.1 MECHANICAL PIPING DIAGRAMS 08-24-2026

M5.2 MECHANICAL DETAILS 08-24-2026

M5.3 MECHANICAL DETAILS 08-24-2026

M5.4 MECHANICAL DETAILS 08-24-2026

M6.1 MECHANICAL SCHEDULES 08-24-2026

M6.2 MECHANICAL SCHEDULES 08-24-2026

M6.3 MECHANICAL SCHEDULES 08-24-2026

M8.0 CONTROLS DATA SHEET 08-24-2026

M8.1 MECHANICAL CONTROLS 08-24-2026

M8.2 MECHANICAL CONTROLS 08-24-2026

M8.3 MECHANICAL CONTROLS 08-24-2026

M8.4 MECHANICAL CONTROLS 08-24-2026

ED1.2 FIRST FLOOR ELECTRICAL

DEMOLITION PLAN – UNIT 600

08-24-2026

ES1.0 ELECTRICAL SITE PLAN 08-24-2026

EP1.8 FIRST FLOOR POWER PLAN – UNIT 800

ADDITION

08-24-2026

EL1.8 FIRST FLOOR LIGHTING

PLAN -UNIT 800 ADDITION

08-24-2026

E4.0 ENLARGED ELECTRICAL

PLANS

08-24-2026

E6.0 PANEL SCHEDULES 08-24-2026

T1.1 TECHNOLOGY LEGEND AND DETAILS 10-06-2026

T2.1 FIRST FLOOR STRUCTURED CABLING

PLAN – UNIT 800 ADDITION

10-06-2026

T2.2 FIRST FLOOR SECURITY PLAN – UNIT 10-06-2026

000115-4

ADDENDUM NO. 3

800 ADDITION

T2.3 FIRST FLOOR PA AND CLOCK PLAN –

UNIT 800 ADDITION

10-06-2026

002416-1 Section 002416-Scope of Work-Bid Category Specific Notes, Bid Category 3X-Building Foundations JUNE 2026

SECTION 002416

SCOPE OF WORK

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

BID CATEGORY 03A - Concrete & Building Foundations

GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible for performing all work reasonably interpreted to be included in its scope of work in accordance with the drawings and specifications in addition to these Bid

Category notes of clarification.

BASE SPECIFICATION(S) – (Include all Work specified or reasonably inferred.)

002413 – SCOPE OF WORK GENERAL NOTES

Divisions 00 & 01

014516.01 – CONCRETE TESTING

033000 – CAST-IN-PLACE CONCRETE

321300 – CONCRETE CURB AND GUTTER, SIDEWALK, AND MISC PAVEMENT

071300 – SHEET WATERPROOFING

REFERENCE SPECIFICATION(S) – (Include portions of the Work specified as noted below)

015000 – TEMPORARY FACILITIES AND CONTROLS

014000 – AIR BARRIER SYSTEM REQUIREMENTS

014516.02 – DENSITY AND AGGREGATE TESTING

014533 – CODE-REQUIRED SPECIAL INSTRUCTIONS

017123.16 – CONSTRUCTION STAKING BY CONTRACTOR

051200 – STRUCTURAL STEEL FRAMING

072100 – THERMAL INSULATION

072500 – WEATHER BARRIERS

076500 – FLEXIBLE FLASHING

079200 – JOINT SEALANTS

321116 – GRANULAR SUBBASE

321123 – AGGREGATE BASE COURSES

312301 – EXCAVATING, FILLING, AND GRADING

Include (Furnish and Install unless.noted.otherwise (u.n.o.)

1. All work under this contract shall be done in a safe manner and comply with the

O.S.H.A and M.I.O.S.H.A requirements as well as Clark Construction Company’s safety program.

2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark

Construction Superintendents

002416-2

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.

4. Pumping of water to accomplish the Work of this bid category.

5. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.

6. Determine location of existing underground utilities prior to any excavation work.

Contact MISS DIG a minimum of 3 days in advance of any excavation work, more than 3 days if required to allow adequate time for MISS DIG to mark underground utilities as required to meet excavation work schedules. Submit verification of MISS DIG work order to Clark Construction Company. Hand dig as necessary to avoid contact with underground utilities.

7. Determine location of existing underground utilities prior to any excavation work outside of the responsibility of MISS DIG for marking including fiber optic lines and other non-public utilities.

8. Contract GPRS services or hand dig to locate and expose privately owned utilities shown on the drawings.

9. Verify and accept building pad elevation and subbase elevations prior to performing the Work. Report discrepancies to Clark Construction Company in writing.

10. Verify existing grade prior to performing the Work. Report discrepancies to Clark

Construction Company in writing.

11. Receive, unload, store, layout and install miscellaneous steel fabrications furnished by others (e.g. imbed angles, anchor bolts, bearing and leveling plates, wall plates, etc.). Include grouting as required.

12. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.

13. Coordinate and cooperate with the project Independent Testing and Inspection

Company for inspection and/or testing of the Work.

14. Pumping water required to accomplish the Work of this bid category.

15. Contractor is responsible for all control points to perform the work of this bid category. Benchmarks are located on the drawings.

16. Contractor is responsible for all excavations and backfill for footings and foundations.

17. Contractor to leave top of foundations clean for next trade contractor to begin work.

18. Restore grade to conditions that existed prior to performing the Work.

19. Reinforcing steel associated with the Work of this bid category includes reinforcing dowels as required for masonry.

20. Coordinate dowel location requirements with other Trades.

21. Concrete forms and accessories as required to complete the work of this bid category.

002416-3

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

22. Finished concrete flatwork shall have positive drainage over the entire surface as required.

23. Clean reinforcing of loose or flaking rust, dried concrete, oil, and other foreign material that may reduce the bond between the reinforcing and the concrete.

24. Openings, pockets, box outs, etc. Coordinate required location and dimensions with other Trades.

25. Install sleeves furnished by others. Coordinate required location with other

Trades.

26. Cooperate in verification of correct anchor bolt and other embed placement with other Trades. Make corrections as needed in a timely manner to meet the project schedule.

27. Protect anchor bolt threads with grease or other approved means.

28. Install and grout (at required elevations) structural steel leveling plates furnished by others.

29. All cast-in-place concrete and concrete paving shown in the bid documents including but not limited to flatwork, foundations, stoops, bollards, concrete curbs and curb edging, etc.

30. Complete bollard assembly including excavation and proper removal of spoils, steel pipe and bollard covers.

31. Locate on site where and remove from site all concrete wash out as directed by

Clark Construction Company.

32. Protection of adjacent materials and surrounding surfaces. Clean and restore material affected by concrete splatter.

33. Provide certification to Clark Construction Company that structural concrete to receive structural steel has achieved 75% of design strength at each location prior to erection of structural steel at that location.

34. Vapor barrier below slab on grade is the responsibility of this bid category.

35. Rigid insulation below slab on grade and at perimeter of foundation.

36. Waterproofing applied to below-grade concrete.

37. Floor expansion joints.

38. All joint sealants associated with the work of this bid category.

39. Install appropriate backer rod in joints as needed.

40. All concrete work shall meet American Concrete Institute (ACI) standards. Prior to performing concrete flatwork, submit for acceptance by the Architect/Engineer, a concrete joint layout plan of all isolation, construction and contraction joints.

The joint layout plan shall at a minimum meet ACI standards. Review and approval will be required prior to performing work.

41. Coordinate adjustment of all storm catch basins, manhole covers, and valve boxes, etc. with other Trades prior to performing the Work of this bid category.

42. Finished concrete flatwork shall have positive drainage over the entire surface as required.

43. All equipment and housekeeping pads are the responsibility of this contractor.

Coordinate exact size and location with other trades.

002416-4

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

44. Weather protection as required to meet the project schedule.

45. Fine grading of aggregate/granular base material is the responsibility of this bid category.

46. Verify existing grade prior to performing the Work. Report discrepancies to

Clark Construction Company in writing.

47. Warranty and guarantee start date shall be the project Substantial Completion date.

48. This bid category shall establish and maintain, local control points for building layout for footing and foundation work.

49. Furnish and install exterior steel bollards including vinyl covers as indicated in the documents.

50. Provide and install concrete lintels as indicated in the Documents. Include skim coating as required to create smooth exposed surface.

Exclude:

1. Sealing of Concrete Floors

Bid Category 07X-Metal Wall Panels and Siding JUNE 2026

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

BID CATEGORY 07B-Metal Wall Panels and Siding

GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings and specifications in addition to these Bid

BASE SPECIFICATION(S) – (Include all Work specified or reasonably inferred)

072500 – WEATHER BARRIERS

074213 – METAL WALL PANELS

REFERENCE SPECIFICATION(S) – (Include portions of the Work specified as noted

014100 – AIR BARRIER SYSTEM REQUIREMENTS

014533 – CODE-REQUIRED SPECIAL INSPECTIONS

076200 – SHEET METAL FLASHING AND TRIM

079200 – JOINT SEALANTS

Include (Furnish and Install u.n.o):

safety program.

2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark

Construction Superintendents

3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.

4. Girts, furring and other supports systems as required to accomplish the Work of this bid category whether or not indicated in the documents.

5. Verify quality of substrate installed by other Trades to result in quality results of this bid category. Report discrepancies to Clark Construction Company in writing.

6. Field measure to assure proper fit as necessary to meet the project schedule.

7. Coordinate location and dimensions of penetrations through the system as required by other Trades. Provide weather tight seal and/or accessories as required.

Bid Category 07X-Metal Wall Panels and Siding JUNE 2026

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

8. Joint sealants associated with the work of this bid category.

9. Miscellaneous closures, soffits and other metal fabrications as required for a complete system as indicated in the Documents.

10. Flashings and counter flashings as required for a complete system.

11. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.

12. Warranty and guarantee start date shall be the project Substantial Completion date.

13. Reinstallation of existing building metal wall panel system at building tie-in.

material to be salvaged by selective demolition bid category.

14. Provide and install weather barriers behind metal panels

Bid Category 23X-HVAC JUNE 2026

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

BID CATEGORY 23A - HVAC, Plumbing, & Mechanical

GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of

BASE SPECIFICATION(S) - (Include all Work specified or reasonably inferred)

22 00 05 – BASIC PLUMBING REQUIREMENTS

22 05 17 – SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

22 05 19 – METERS AND GAUGES FOR PLUMBING PIPING

22 05 23 – GENERAL-DUTY VALVES FOR PLUMBING PIPING

22 05 53 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22 05 93 – TESTING, ADJUSTING AND BALANCING FOR PLUMBING

22 07 19 – PLUMBING PIPING INSULATION

22 08 00 – PLUMBING COMMISSIONING REQUIREMENTS

22 10 05 – PLUMBING PIPING

22 10 06 – PLUMBING PIPING SPECIALTIES

22 11 23 – DOMESTIC WATER PUMPS

22 30 00 – PLUMBING EQUIPMENT

22 40 00 – PLUMBING FIXTURES

23 00 05 – BASIC HVAC REQUIREMENTS

23 01 30.51 – HVAC AIR-DISTRIBUTION SYSTEMS CLEANING

23 05 17 – SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

23 05 19 – METERS AND GAUGES FOR HVAC PIPING

23 05 23 – GENERAL-DUTY VALVES FOR HVAC PIPING

23 05 48 – VIBRATION AND SEISMIC CONTROLS FOR HVAC

23 05 53 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 05 93 – TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 13 – DUCT INSULALTION

23 07 14 – DUCT ACOUSTICAL LINER AND LAGGING

23 07 16 – HVAC EQUIPMENT INSULATION

23 07 19 – HVAC PIPING INSULAITON

23 08 00 – HVAC COMMISSIONING REQUIREMENTS

23 09 13 – INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23 – DIRECT-DIGITAL CONTROL SYSTEMS FOR HVAC

23 09 34 – VARIABLE-FREQUENCY MOTOR CONTROLLERS FOR HVAC

23 09 45 – GAS DETECTION AND ALARM

23 11 23 – NATURAL GAS PIPING, VALVES AND ACCESSORIES

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

23 21 13 – HVAC PIPING

23 21 14 – HYDRONIC SPECIALTIES

23 21 23 – HVAC PUMPS

23 25 00 – HVAC WATER TREATMENT

23 31 00 – HVAC DUCTS AND CASINGS

23 33 00 – AIR DUCT ACCESSORIES

23 33 19 – DUCT SILENCERS

23 34 23 – HVAC POWER VENTILATORS

23 36 00 – AIR TERMINAL UNITS

23 37 00 – AIR OUTLETS AND INLETS

23 51 00 – BREECHINGS, CHIMNEYS, AND STACKS

23 52 16 – CONDENSING BOILERS

23 72 23 – PACKAGED AIR-TO-AIR ENERGY RECOVERY UNITS

23 81 26.13 – SMALL-CAPACITY SPLIT-SYSTEM AIR CONDITIONERS

23 82 00 – CONVECTION HEATING AND COOLING UNITS

REFERENCE SPECIFICATION(S) - (Include portions of the Work specified as noted

015000 – TEMPORARY FACILITIES & CONTROLS

014533 – CODE-REQUIRED SPECIAL INSPECTIONS

033000 – CAST-IN-PLACE CONCRETE

078400 – FIRESTOPPING

079200 – JOINT SEALANTS

083100 – ACCESS DOORS & PANELS

312301 – EXCAVATION, FILLING, AND GRADING

312302 – EXCAVATING AND BACKFILLING FOR UTILITY CONSTRUCTION

safety program.

2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark

Construction Superintendents

3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.

4. Obtain permits required to complete the Work of this bid category.

5. MEP Contractors are required to submit MEP Cost Breakdown as a start-up submittal for approval.

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

6. Coordinate design of system material and equipment routing with other Trade

Contractors as required to avoid conflicts.

a. This Trade Contractor shall develop shop drawings equal to scale as that to be used by other Trade Contractors in which conflicts have potential to occur. Drawing scale shall be coordinated prior to start of shop drawings.

b. Shop drawings shall be extensively and thoroughly coordinated with each Trade Contractor with which conflicts have potential to occur to the extent required to eliminate conflicts prior to fabrication and installation.

c. Conflicts encountered during fabrication and installation which could have been foreseen through a more extensive coordination effort shall be corrected by this bid category.

d. All costs for modifications which are a result of conflicts with items noted in the Contract Documents shall be born by this bid category.

e. In the event of conflict with items indicated in shop drawings of other

Trade Contractors and not in the Contract Documents, the cost shall be shared equally by the Trade Contractors involved.

7. Material bends and offsets in addition to those indicated in the documents associated with the Work of this bid category and required to avoid installation conflicts. Contract Documents shall not be interpreted to include all bends and offsets required to avoid conflicts.

8. Hangers, supports, unistrut or miscellaneous steel required for a complete installation.

9. Coordinate openings required to accommodate installation of equipment prior to enclosure of spaces by other Trades.

10. Coordinate roof and other opening dimensions and locations required with

Structural and other Contractors.

11. Remove temporary covers over mechanical openings installed by others prior to performing the Work (including cutting metal deck or burning of welds).

Maintain openings in safe manner.

12. Furnish sleeves as needed and not indicated in the Documents for installation by others. Provide layout and assistance with placement.

13. Furnish, for installation by others, access panels as required for this Work but not indicated in the documents. Confirm type of panel required with Clark

Construction Company prior to ordering.

14. Access panels as required in duct to access in-duct coils or other equipment.

15. HVAC Work as described in specification section “Temporary Facilities and

Controls”.

16. Gas piping connection for temporary heat.

17. Mechanical and plumbing insulation.

18. Roof curbs associated with the Work of this bid category.

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

19. Provide and install roof drains as indicated in the documents. Coordinate with with other Trades.

20. All plumbing and gas piping within building to +/- 5’-0 outside of building including connection point. Include tie-ins to existing buildings.

21. Concrete housekeeping pads for mechanical equipment required and not indicated in the documents.

22. Support steel required for mechanical equipment and not indicated in the documents.

23. Pumps and associated variable frequency drives.

24. Disconnects and motor starters for mechanical equipment as indicated in the documents.

25. Electrical Work from electrical disconnects to equipment is the responsibility of this bid category.

26. Control and/or low voltage wiring of equipment. Electrical Contractor shall have a single point connection only.

27. Coring as required to perform the Work of this bid category.

28. Fire stopping of penetrations associated with the Work of this bid category.

29. Seal all penetrations through roof, walls & floors.

30. Temperature controls including raceways, wiring, complete commissioning and user training.

31. Aluminum pipe enclosures and supports.

32. Coordinate floor drain elevations with Clark Construction Company and other

Trades.

33. Protect floor drain elevations and locations during concrete pours. Protect floor drains from debris during the construction process.

34. Commissioning of mechanical and plumbing systems as indicated in the

Documents. Coordinate with Owner’s Commissioning Agent as required.

35. Testing and balancing of system. Submit final test and balance reports in a timely manner as not to delay other project requirements.

36. Complete check, test and start up of mechanical systems. Provide written plan and documentation to Clark Construction Company of check, test and start of each component of the system.

37. Identification, labeling and tagging system equipment, piping, duct, etc.

38. Framed identification charts in mechanical rooms providing valve and major equipment information.

39. Perform complete flushing, disinfecting, cleaning, and testing of mechanical and plumbing systems and equipment.

40. Participate in fire alarm testing process as it relates to the Work of this bid category.

41. Train Owner’s representative(s) on proper start-up, operation and maintenance of all mechanical systems. Provide video recording of training for Owner.

42. Paint touch-up of factory finished equipment.

43. Complete chemical treatment of system.

002416-5

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

44. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.

45. Warranty and guarantee start date shall be the project Substantial Completion date.

46. All utility shut downs and tie ins must be completed on 2nd shift/weekend work with approval from Clark Construction Company and Owner in advance.

47. This trade shall include mechanical and plumbing work for the construction phase egress plan shown on drawing A0.3 and MP1.8.

48. Furnish, install, and remove at a later date, temporary water meter with backflow preventor at mechanical room riser to be used during construction.

49. Control wiring, connections, and programing of Duct Detectors for code required operations of equipment.

50. This contractor is responsible for all gas piping as indicated in the documents, including outside of +/- 5’ of the building.

51. Excavation, backfill and compaction associated with the Work of this bid category.

52. Restore grade to condition that existed prior to start of the Work.

Bid Category 26A-Electrical JUNE 2026

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

BID CATEGORY 26A - Electrical

GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of

BASE SPECIFICATION(S) - (Include all Work specified or reasonably inferred)

26 00 05 – SES BASIC ELECTRICAL REQUIREMENTS

26 05 26 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 – HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33.13 – CONDUIT FOR ELECTRICAL SYSTEMS

26 05 33.16 – BOXES FOR ELECTRICAL SYSTEMS

26 05 33.23 – SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS

26 05 36 – CABLE TRAYS FOR ELECTRICAL SYSTEMS

26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 05 73 – POWER SYSTEMS STUDIES

26 09 23 – LIGHTING CONTROL DEVICES

26 22 00 – LOW-VOLTAGE TRANSFORMERS

26 24 16 – PANELBOARDS

26 27 26 – WIRING DEVICES

26 28 13 – FUSES

26 28 16.16 – ENCLOSED SWITCHES

26 43 00 – SURGE PROTECTIVE DEVICES

26 51 00 – INTERIOR LIGHTING

26 56 00 – EXTERIOR LIGHTING

27 11 16 – COMMUNICATIONS CABINETS, RACKS, AND FRAMES

27 13 23 – COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING

27 15 16 – COMMUNICATIONS COPPER HORIZONTAL CABLING

27 41 16 – INTEGRATED AUDIO VIDEO SYSTEMS

27 51 16 – PUBLIC ADDRESS & CLOCK SYSTEMS

28 00 00 – SECURITY SYSTEMS

28 46 00 – FIRE DETECTION AND ALARM

REFERENCE SPECIFICATION(S) - (Include portions of the Work specified as noted

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

014533 – CODE-REQUIRED SPECIAL INSPECTIONS

26 05 05 – SELECTIVE DEMOLITION FOR ELECTRICAL

033000 – CAST-IN-PLACE CONCRETE

078400 – FIRESTOPPING

079200 – JOINT SEALANTS

083100 – ACCESS DOORS AND PANELS

087100 – DOOR HARDWARE

312301 – EXCAVATION, FILLING, AND GRADING

312302 – EXCAVATION AND BACKFILLING FOR UTILITY CONSTRUCTION

313219 – GEOTEXTILE FABRIC

321116 – GRANULAR SUBBASE

321123 – AGGREGATE BASE COURSES

321500 – AGGREGATE SURFACING

safety program.

2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark

Construction Superintendents

3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.

4. Obtain permits required to complete the Work of this bid category.

5. MEP Contractors are required to submit MEP Cost Breakdown as a start-up submittal for approval.

6. Coordinate design of system material and equipment routing with other Trade

Contractors as required to avoid conflicts.

a. This Trade Contractor shall develop shop drawings equal to scale as that to be used by other Trade Contractors in which conflicts have potential to occur. Drawing scale shall be coordinated prior to start of shop drawings.

b. Shop drawings shall be extensively and thoroughly coordinated with each Trade Contractor with which conflicts have potential to occur to the extent required to eliminate conflicts prior to fabrication and installation.

c. Conflicts encountered during fabrication and installation which could have been foreseen through a more extensive coordination effort shall be corrected by this bid category.

d. All costs for modifications which are a result of conflicts with items noted in the Contract Documents shall be born by this bid category.

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

e. In the event of conflict with items indicated in shop drawings of other

Trade Contractors and not in the Contract Documents, the cost shall be shared equally by the Trade Contractors involved.

7. Coordinate openings required to accommodate installation of equipment prior to enclosure of spaces by other Trades.

8. Hangers, supports, unistrut or misc. steel required for a complete installation.

9. Equipment support structures as required.

10. Furnish only, for installation by others, access panels as required for this Work but not indicated in the documents. Confirm type of panel required with Clark

Construction Company prior to ordering.

11. Concrete housekeeping pads for electrical equipment required and not indicated in the documents.

12. Fire stopping of penetrations associated with the Work of this bid category.

13. Excavation, backfill and compaction associated with the Work of this bid category.

14. Warning tape in trenches above conduit and wire.

15. Restore grade to condition that existed prior to start of the Work.

16. Furnish sleeves as needed and not indicated in the Documents for installation by others. Provide layout and assistance with placement.

17. Cut/Cap/Make safe for electrical demo as required.

18. Coring as required to perform the Work of this bid category.

19. Firestopping of penetrations associated with the Work of this bid category.

20. Seal all penetrations through roof, walls & floors.

21. Provide and install door position switches as required for doors.

22. Complete wiring for door hardware provided by others.

23. Perform final hook up of equipment furnished by Owner and others. Coordinate rough in location with equipment supplier and Clark Construction Company.

24. Electrical Work associated with fire protection system equipment (e.g. tamper and flow switches, etc.) installed by Fire Protection Contractor.

25. Electrical identification and labeling.

26. Obtain permits required to complete the work of this bid category.

27. Electrical work as described in specification section 015000 “Temporary

Facilities and controls”

28. Electrical connections for temporary heat

29. Site electrical work is the responsibility of this contractor.

30. Site lighting including light pole bases.

31. Include directional drilling under service road behind the Davis Building for power feeds to the sanitary force main pump station.

32. Backfill material for underground utilities under concrete and asphalt shall match road sections in the civil documents.

33. Fire Alarm system. Coordinate tie in requirements with other trades.

34. Provide and install duct detectors as required.

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

35. Remove spoils from the site and backfill in accordance with the plans and specifications requirements.

36. Furnish and install starters and disconnects for equipment by others as indicated in the documents.

37. Install variable speed drives furnished by others including conduit and wiring.

38. Install TVs and brackets provided by Owner. Coordinate required in-wall backing with other trades.

39. Train Owner’s representative(s) on proper start-up, operation and maintenance of all mechanical systems. Provide video recording of training for Owner.

40. Include any patching needed.

41. Deliver, unload and place in storage specified maintenance materials when and where as directed by Clark Construction Company.

42. Warranty and guarantee start date shall be the project Substantial Completion date.

43. This trade shall include work for the construction phase egress plan shown on drawing A0.3 Include revised lighting layout with battery back up emergency lights, exit signs and additional horn strobe fire alarm devices for code compliance. This trade shall include rework of the egress corridor to return to previous condition at the end of the project.

44. All utility shut downs and tie ins must be completed on 2nd shift/weekend work with approval from Clark Construction Company and Owner in advance.

Mandatory Bid Alternates:

1. Costs for the following alternative scope items must be provided with your bid.

2. Refer to Section 012300 ALTERNATES for more information.

3. Any applicable mark-up, OH&P, management costs, and/or general conditions costs must be accounted for in the alternate cost

a. Alternate #3: Demolition of electrical feed and conduit to existing chicken coop as shown on C1.0.

Bid Category 31-Mass Grading JUNE 2026

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

BID CATEGORY 31A - Sitework, Utilities, Landscaping & Asphalt Paving

GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Bid Category. This Bid Category Trade Contractor shall be responsible to perform all work reasonably interpreted to be included in its scope of

BASE SPECIFICATION - (Include all Work specified or reasonably inferred)

00 24 13 – SCOPE OF WORK GENERAL NOTES

014126 – PERMIT REQUIREMENTS

014516.02 – DENSITY AND AGGREGATE TESTING

015726 – DUST CONTROL

0017123.16 – CONSTRTUCTION STAKING BY CONTRACTOR

024113.13 – PAVEMENT REMOVAL

311001 – CLEARING AND REMOVAL OF MISCELLANEOUS STRUCTURES

312301 – EXCAVATING, FILLING, AND GRADING

312302 – EXCAVATING AND BACKFILLING FOR UTILITY CONSTRUCTION

312500 – SOIL EROSION AND SEDIMENTATION CONTROL

312319 – GEOTEXTILE FABRIC

313700 – RIPRAP

321116 – GRANULAR SUBBASE

321123 – AGGREGATE BASE COURSES

321216 – HMA PAVING

321500 – AGGREGATE SURFACING

321723 – PAVEMENT MARKINGS

328423 – UNDERGROUND SPRINKLERS

329119 – TOPSOIL FOR LANDSCAPING & CONSTRUCTION

329200 – NATURAL TURF & SODDING

329200 – TURF ESTABLISHMENT

329300 – PLANTS

329400 – LANDSCAPE MAINTENANCE & WARRANTY STANDARDS

330500 – ADJUSTING STRUCTURES

331100 – WATER MAIN (Genesee County)

333100 – SANITARY SEWER (Genesee County)

334400 – STORM SEWERS

REFERENCE SPECIFICATION - (Include portions of the Work specified as noted

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

012100 – ALLOWANCES

014533 – CODE-REQUIRED SPECIAL INSPECTIONS

017123.16 – CONSTRUCTION STAKING BY CONTRACTOR

024119 – SELECTIVE DEMOLITION

033000 – CAST-IN-PLACE CONCRETE

042000 – UNIT MASONRY

231123 – NATURAL GAS PIPING, VALVES AND ACCESSORIES

321300 – CONCRETE CURB AND GUTTER, SIDEWALK, AND MISC. PAVMT.

safety program.

2. Contractor Supervisor/Foreman must attend weekly meetings held by Clark

Construction Superintendents

3. Furnish and install all labor, materials, and equipment necessary to provide all work as shown on the drawings and in the specifications for this bid package. All work to be per the plans and specifications and as required by Code.

4. Obtain permits required to complete the Work of this bid category.

5. Verify on-site and surrounding grades are in accordance with the Documents prior to start of the work. Report discrepancies to Clark Construction Company in writing.

6. Verify location of existing utilities prior to performing the work. Hand dig as required to avoid contact with underground utilities.

7. Maintain streets and public areas free of dirt, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads.

8. Remove debris and/or spoils from the site in a timely manner.

9. Import and export of soil material, cut and fill, grading, and compaction to achieve grades required by the documents.

10. Site grading to plus or minus 1/10 of a foot of design to balance.

11. All subbase is the responsibility of this bid category.

12. Pumping water to perform the work of this bid category.

13. Provide, maintain, and coordination location of dumpsters for demolition.

14. Legal disposal of materials off site.

15. Provide erosion control for entire project, including soil permit, installation, maintenance, storm water operator and removal at completion of project.

16. Topsoil raking and removal of rocks, stones and debris.

17. Clean-up on a daily basis.

18. Broom cleaning of hard surfaces.

19. Initial staking/support of plantings.

20. Final connection of irrigation system to water supply.

21. Weed control and fertilizer per specifications.

22. Temporary watering as required until irrigation system is fully functioning.

BID CATEGORY SPECIFIC NOTES

ADDENDUM NO. 03

23. Tree removal, clearing and grubbing.

24. Protect existing structures and/or trees and landscaping to remain.

25. Construct building pad including import material, placement, grading, and compaction.

26. Strip, stockpile and re-spread topsoil at a later date as directed by Clark

Construction Company. Include remobilization.

27. Grade, seed and mulch areas disturbed outside of construction limits as a result of the work of this bid category.

28. Proof rolling of sub-grade as required prior to placement of stone base, asphalt, concrete or other materials.

29. Perform water, sanitary and storm tie-in to public utility system in accordance with requirements of authorities having jurisdiction.

30. Extend utility piping to connect to building systems to 5’-0” from the building line. Coordinate with building Trade Contractors and other design documents the exact location and elevation of connection prior to performing the Work. Report discrepancies to Clark Construction Company in writing.

31. Install drainage structures such that Subgrade will drain completely by gravity.

Final adjustments of the drainage structures shall be performed by this bid category at a later date just prior to placement of finished surfaces and as directed by Clark Construction Company. Final adjustments shall include required excavation, backfill and compaction.

32. Coordinate and perform final adjustments of valve boxes and other utilities prior to placement of finished surfaces by others.

33. Dust control for the duration of the Work of this bid category.

34. Restore disturbed grade to condition that existed prior to performing the Work.

35. Underdrain system as indicated in documents.

36. Grade, seed and mulch areas disturbed outside of the building area as a result of the Work of this bid category.

37. Clean dirt and debris out of storm water system upon completion of the project when directed by Clark Construction Company.

38. All site demolition including asphalt and concrete indicated in the drawings.

39. Verify telephone riser is abandoned prior to demolition. If riser is determined to be active, notify Clark Construction Company for final direction from Owner.

40. Temporary fencing, gates, laydown areas, and site development as indicated on the site logistics plan. Include restoration of site area upon project completion.

Topsoil to be stripped and stockpiled on site for laydown area development per logistics plan

a. Gravel…

This is the start of the file's text. The full file is on GovTribe.