This is an Invitation to Bid (ITB) issued by the Town of Woodstock, Virginia for the Water Treatment Plant Third Floor Wall Reinforcement project. The Town seeks qualified bidders to furnish all labor, materials, equipment, and services to install steel bracing that reinforces the existing third-floor masonry wall of the Woodstock Water Treatment Plant located at 145 Broadview Lane. The work includes furnishing and installing steel channel bracing, angle clips, shear tabs, base plates, bar-joist bracing, Hilti anchors, and connections as detailed in engineering drawings signed and sealed by Painter-Lewis, P.L.C. (dated October 7, 2026, job number 2502016). A mandatory pre-bid meeting and site visit is required on November 17, 2026 at 10:00 AM at the project site. Sealed bids are due by December 14, 2026 at 10:00 AM local time, with a public bid opening at the Town Office in Woodstock. The question deadline is November 30, 2026 at 11:00 AM. The contract is expected to begin with a notice to proceed on or before December 31, 2026, with substantial completion required by May 31, 2027 and final completion within thirty days thereafter. Bidders must submit a written schedule within ten days of notice to proceed.
This is a lump-sum contract with payment on a monthly basis for work completed, based on an approved schedule of values. The Town will pay approved invoices within forty-five days of receipt. Bidders must meet minimum qualifications including continuous operation for at least five years, a valid Virginia Class A or Class B contractor license, and no pending litigation that would materially affect performance. Bidders must provide proof of authority to transact business in Virginia, three project references for similar structural steel or masonry reinforcement work completed within the past five years, and a sample Certificate of Insurance. Required insurance coverage includes Workers' Compensation, Comprehensive General Liability of not less than $1,000,000 combined single limit per occurrence, and Automobile Liability of $500,000 minimum combined single limits. The work is restricted to the plant's operating hours (7:00 AM to 3:00 PM, Monday through Friday, excluding Town holidays), and the plant will remain operational throughout the project. Award will be made to the lowest responsive and responsible bidder. Bids are valid for forty-five days from submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF WOODSTOCK, VIRGINIA
INVITATION TO BID
Water Treatment Plant Third Floor Wall Reinforcement
ITB Number: FY27_ITB_003
Issue Date: November 4, 2026
Bid Due Date: December 14, 2026 at 10:00 AM Local Time
SECTION 1 — BIDDER CONTACT INFORMATION
Complete all fields. This cover sheet must be signed and returned with your bid.
Legal Name of Firm (as listed on W-9)
DBA / Trade Name (if applicable)
Street Address City, State, ZIP
Primary Contact Name Title
Phone Number Email Address
SECTION 2 — ATTESTATIONS
By signing this cover sheet, the authorized representative of the firm named above attests and certifies to the following:
□ Years in Business: The firm has been in continuous operation as a legal business entity for a minimum of five (5) years. Year business established: ___________
□ No Pending Litigation: The firm has no current pending litigation that would materially affect its ability to perform the services described in this ITB, and no judgments have been entered against the firm in the past three (3) years that remain unsatisfied.
□ Licensure: The firm holds all business and contractor licenses required by the Commonwealth of Virginia to perform the work described in this ITB and will maintain such licenses in good standing throughout the term of the contract.
SECTION 3 — ADDENDA ACKNOWLEDGMENT
The Town will complete this table as each addendum is issued and will distribute an updated cover sheet with each addendum. Bidders must initial each row to acknowledge receipt, and should confirm with the Town's website or eVA immediately prior to submission that no additional addenda have been issued. Bids submitted without acknowledgment of all issued addenda may be deemed non-responsive. If no addenda have been issued as of the bid due date, write "None" in the table below.
Addendum No. Date Issued Subject / Description Initial
SECTION 4 — AUTHORIZED REPRESENTATIVE SIGNATURE
The undersigned, being duly authorized to act on behalf of the firm identified above, certifies that all information provided in this bid is true, accurate, and complete, that all attestations in Section 2 are correct, and that the firm agrees to be bound by the terms and conditions of this ITB and any resulting contract.
Printed Name of Authorized Representative
Title
Signature of Authorized Representative
Date
This cover sheet must be signed and submitted as the first page of your bid. Unsigned bids will be deemed non-responsive.
Invitation to Bid (ITB) Water Treatment Plant Third Floor Wall Reinforcement This Invitation to Bid (ITB) plus the resulting contract shall be consistent with and governed by the Town's procurement policy and has been prepared in accordance with the Virginia Public Procurement Act's competitive sealed bidding process (Va. Code § 2.2-4302.1).
The Town’s Point of Contact for this project is:
Travis Hoffman Town of Woodstock 135 N. Main St.
Woodstock, VA 22664 Ph: (540) 459-3045 Email: thoffman@woodstockva.gov
Potential Bidders are required to submit all questions in writing via email directly to the listed point of contact no later than Monday, November 30, 2026 at 11:00 AM Local Time. Written responses, including the questions, will be provided to all Bidders via an official Addendum and posted on the Town's website and eVA.
I. Project Background The Town of Woodstock (‘Town’) is soliciting bids from qualified bidders to reinforce the wall on the third floor of the Woodstock Water Treatment Plant (WTP) located at 145 Broadview Lane, Woodstock, Virginia.
The WTP is a three-story structure and the wall needs reinforcement for stabilization. Engineering specifications are signed and sealed by Painter-Lewis, P.L.C., dated October 7, 2026 (10-7-2026), job number 2502016, titled “THIRD LEVEL WALL REINFORCEMENT DETAILS” and are included as supporting documents to this ITB.
II. Procurement Schedule The Town reserves the right to modify this schedule. Any changes will be issued via addendum.
ITB Issued Wednesday, November 4, 2026 Pre-Bid Meeting / Site Visit (Mandatory) Tuesday, November 17, 2026, at 10:00 AM Deadline for Questions Monday, November 30, 2026 at 11:00 AM Local
Time Final Addendum Issued (if needed) Tuesday, December 8, 2026 Bid Due Date / Public Bid Opening Monday, December 14, 2026 at 10:00 AM Local
Time
The public bid opening will be held at the Town Office, 135 North Main Street, Woodstock, Virginia 22664, at the date and time listed above as the Bid Due Date. Bids will be opened and read aloud publicly at that time and place.
III. Mandatory Pre-bid Meeting A mandatory pre-bid meeting for clarification on the specifications will be held on November 17, 2026 at 10:00 A.M. at the Woodstock Water Treatment Plant located at 145 Broadview Lane, Woodstock, VA 22664.
Attendance at the mandatory pre-bid meeting is a condition of bidding. Each bidding firm must be represented by an owner, employee, or authorized representative, who must sign in with the Town representative as a record of attendance. Bids from firms that did not attend the mandatory pre-bid meeting and sign in will be rejected.
Bidders are requested to have questions written out with a copy to be handed to the point of contact for recording purposes. Questions raised at the meeting, and the Town’s answers, will be issued in writing by addendum following the meeting. Oral statements made at the meeting are not binding on the Town.
IV. Project scope and requirements The Contractor shall furnish all labor, materials, equipment, transportation, and supervision to install steel bracing that reinforces the existing third-floor masonry wall of the Woodstock Water Treatment Plant, as shown on the engineering drawings.
Governing Drawings The work shall be built in accordance with the drawings titled “THIRD LEVEL WALL REINFORCEMENT DETAILS,” Sheet S1, signed and sealed by Painter-Lewis, P.L.C., job number 2502016, dated October 7, 2026, which are attached to this ITB. This section summarizes the work.
Where this section and the drawings differ on a technical requirement, the drawings control.
Substitutions.
Products named on the drawings, including the Hilti anchors, establish the required type and quality.
A bidder that wants to use an equal product must submit a written substitution request, with product data, to the point of contact by the question deadline. Substitutions approved by the Town after review by the engineer of record will be issued by addendum. No other substitutions will be accepted.
Work included
• Furnish and install the steel channel bracing, angle clips, shear tabs, base plates, bar-joist bracing, anchors, and connections shown on the drawings.
• Verify all field dimensions and existing conditions before fabrication, including dimensions marked “V.I.F.” (verify in field) on the drawings.
• Before fabrication, submit shop drawings and product data for structural steel and anchors to the Town for review by the engineer of record.
• Install all manufactured products in accordance with the manufacturer’s specifications.
• Obtain and pay for all required building permits and inspections, and schedule inspections with the building official.
• Protect all existing construction shown “to remain,” including the roofing system, steel deck, bar joists, masonry wall, and floor slab.
• Warrant all workmanship and materials for one (1) year from the Town’s final acceptance of the work.
Site conditions and restrictions
• The Water Treatment Plant will remain in operation throughout the project. The Contractor shall not interrupt plant operations or compromise the integrity of any part of the plant outside the work area.
• NO MATERIAL, DUST, OR DEBRIS MAY ENTER THE SECOND FLOOR
LAB. The Contractor shall provide and maintain protection to prevent it.
• Work is limited to the plant’s operating hours, 7:00 A.M. to 3:00 P.M., Monday through Friday, excluding Town holidays.
• The Contractor shall move all materials, tools, equipment, and personnel to and from the third-floor work area. The Town representative will identify the access route at the pre-bid meeting.
• Welding or cutting requires advance notice to the Town representative. The Contractor shall provide fire protection and a fire watch during and after hot work as required by applicable fire codes.
• The Contractor shall plan and schedule the work with the designated Town representative and shall follow all applicable safety standards and building codes.
Cleanup
• At the end of each workday, the Contractor shall clear debris from the work area so plant staff can operate and reach equipment on the third floor.
• On completion, the Contractor shall remove all debris, trash, waste, surplus materials, tools, and equipment and leave the site clean.
V. Contract Time Time is of the essence. The Town expects to issue a written notice to proceed on or before December 31, 2026.
• Schedule: Within ten (10) days after the notice to proceed, the Contractor shall submit a written schedule showing submittals, fabrication lead time, and on-site work dates.
• Substantial completion: on or before May 31, 2027. The work is substantially complete when it is finished except for minor punch-list items and has passed the building official’s final inspection.
• Final completion: within thirty (30) calendar days after substantial completion, with all punch-list items done, the site clean, and closeout documents delivered.
• Time extensions: The contract time may be extended only by written change order, for delays beyond the Contractor’s control and without its fault or negligence. The Contractor must request an extension in writing within ten (10) days after the delay begins.
VI. Payment Terms This is a lump-sum contract. The bid price includes all labor, materials, equipment, permits, fees, insurance, and other costs needed to complete the work.
• Schedule of values: Within ten (10) days after the notice to proceed, the Contractor shall submit a breakdown of the lump sum by major part of the work for the Town’s approval.
• Progress payments: The Contractor may submit one application for payment per month for work completed, based on the approved schedule of values. Each invoice must include the Town’s purchase order number and be sent to the Town’s point of contact.
• Payment timing: The Town will pay approved invoices within forty-five (45) days after receipt of a proper invoice, as provided in Code of Virginia § 2.2-4352. The Town will notify the Contractor of any defect or impropriety that would prevent payment within twenty (20) days after receipt of the invoice.
• Final payment: Final payment will be made after final completion and after the Contractor delivers the building official’s final inspection approval, the written warranty, and a written release of claims from the Contractor and its subcontractors.
VII. Minimum Qualifications Bidders must demonstrate that they have the resources and capability to provide the materials and services as described herein. Bidders must submit the documentation listed under Bid Submission Requirements, which the Town will use to determine whether a bidder is responsible.
The following criteria shall be met to be eligible for this contract:
1. Provide evidence of a contractor’s certificate of registration, whether resident or nonresident of
Commonwealth of Virginia, as required by the following:
a. Registered Commonwealth of Virginia Contractor: Minimum of a Class B. Include a copy of the Contractors License in your bid.
2. A Certificate of Insurance will be required from the selected vendor; please refer to General
Terms and Conditions for complete instructions. Please include a sample of your Certificate of Insurance with your bid.
3. The bidder has been in continuous operation as a legal business entity for at least five (5) years before the bid due date.
4. The bidder has no pending litigation that would materially affect its ability to perform the work described in this ITB, and no judgments entered against it in the past three (3) years that remain unsatisfied.
VIII. Selection of Contractor Award will be made to the lowest responsive and responsible bidder, as those terms are defined in Virginia Code § 2.2-4301. In determining whether a bidder is responsible, the Town will consider the documentation required under Minimum Qualifications and Bid Submission Requirements, including the bidder’s license, references, and record on similar projects.
The approving authority for this ITB is the Town of Woodstock, Virginia. This ITB does not commit the Town of Woodstock to award a contract or to pay costs or expenses incurred in the preparation of responses to this ITB. The Town of Woodstock reserves the right, at any time prior to award of the contract, to reject any and all bids, or any part thereof, to make no award, and/or to issue a new ITB, or make modifications, corrections, or additions to the information contained herein. Offerors are cautioned this is an ITB, not a request for proposal.
IX. Bid Submission Requirements Sealed bids must be received by hand delivery, mail, or electronic submission through eVA, at or before 10:00 A.M., local time, on December 14, 2026.
If hand delivering or mailing a sealed bid response, the bid must be submitted in a sealed envelope, marked with the ITB title, “Water Treatment Plant Third Floor Wall Reinforcement” to the project point of contact by the listed bids due date (no email or faxed bids will be accepted). Bids received after the bid due date and time will NOT be accepted or considered. The time of receipt shall be determined by the time stamp in Town Office.
If submitting electronically via eVA, Bidder should refer to the online bidding instructions available at the following link: https://www.youtube.com/watch?v=KSxcAkOekW0. To submit a bid through eVA the Bidder must be a registered vendor in eVA. If Bidder encounters any issues submitting an online bid through eVA, Bidder shall contact eVA Customer Care for assistance. The time of receipt for bids submitted electronically through eVA shall be determined by the time clock included in the eVA submittal system.
FAXED OR E-MAILED BIDS ARE NOT ACCEPTABLE.
https://www.youtube.com/watch?v=KSxcAkOekW0
Prior to submitting a bid, it is the Bidders responsibility to check the Town’s website https://www.woodstockva.gov/bids or eVA for any addenda associated with this ITB.
Any costs or expenses of any kind incurred by an offeror in preparing or submitting bids are the Bidders sole responsibility. The Town of Woodstock will not reimburse any offeror for any costs or expenses incurred because of the preparation of this ITB.
Each bid must include the items below.
Required with the bid
1. Cover sheet, completed and signed by an authorized representative and acknowledgment of every addendum issued.
2. Attachment A: Bid Form, completed and signed by an authorized representative, including the total bid price and all unit prices. A bid without a completed and signed Bid Form will be rejected.
3. Attachment B: Proof of Authority to Transact Business in Virginia. Pursuant to Code of Virginia § 2.2-4311.2, a bidder organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 of the Code of Virginia shall include in its bid the identification number issued to it by the State Corporation Commission (“SCC”). A bidder that does not provide this information shall not receive an award unless a waiver is granted under § 2.2-4311.2(C).
Responsibility Information
Include the following with the bid. If any item is missing, the Town may request it, and the bidder must provide it within three (3) business days of the request or the bid may be rejected as non-responsible.
1. Project Manager: name, company mailing address, email address, office phone number, and mobile phone number if available.
2. References: three (3) projects completed within the past five (5) years involving structural steel or masonry reinforcement, preferably in occupied or operating facilities. For each, give the project name and location, dates of work, contract value, and contact information for an owner’s representative familiar with the work.
3. Virginia Contractor License: a copy of a valid Virginia Class A or Class B contractor license.
4. Proof of Insurance: a sample Certificate of Insurance showing the coverage required under General Terms and Conditions, item H. The selected bidder must provide a current certificate before the contract is signed.
5. Material Lead Time: the expected lead time for structural steel and anchors after shop drawings are approved.
6. Plant Protection: a brief statement (one page or less) of how the bidder will keep material, dust, and debris out of the second-floor lab and avoid disrupting plant operations.
X. General Terms and Conditions A. Unless canceled or rejected, a responsive bid from the lowest responsible bidder shall be accepted as submitted.
B. This document will form part of the contract between the successful bidder and the Town.
https://www.woodstockva.gov/bids.aspx
The terms of this document are subject to the Invitation To Bid, which shall control in the event of conflict.
C. This solicitation is subject to the provisions of the procurement policy for the Town and any revisions thereto, which are hereby incorporated into this contract in their entirety. A copy of the manual is available for review at the Town Office.
D. This solicitation and any resulting contract shall be governed in all respects by the laws of the Commonwealth of Virginia and any litigation with respect thereto shall be brought in the courts of the Commonwealth. The contractor shall comply with all applicable federal, state and local laws, rules and regulations.
E. All documents, including electronic copies, submitted in response to this solicitation shall become the property of the Town. All documents, including electronic copies, prepared in conjunction with, and relating to, the work detailed in this solicitation and resulting Contract shall become the property of the Town upon final payment of all fees to the Contractor as set forth in the contract.
F. The successful Bidder (Contractor) shall assume full responsibility for the complete effort as required by this ITB. The selected Bidder shall be the sole point of contact for the Town regarding all contractual responsibilities.
G. By submitting their bids, bidders certify to the Town that they will conform to the provisions of the Federal Civil Rights Act of 1964, as amended, as well as the Virginia Fair Employment Contracting Act of 1975, as amended, where applicable, the Virginians With Disabilities Act, the Americans With Disabilities Act and 2.2-4311 of the Virginia Public Procurement Act.
H. By signing and submitting a bid or proposal under this solicitation, the bidder or offeror certifies that if awarded the contract, it will have the following insurance coverage at the time the contract is awarded. The bidder or offeror further certifies that the contractor and any subcontractors, at any tier, will maintain this insurance coverage during the entire term of the contract and that all insurance coverage will be provided by insurance companies authorized to sell insurance in Virginia by the Virginia State Corporation Commission.
a. Worker’s Compensation: Coverage is compulsory for employers of three or more employees, to include the employer. Contractors who fail to notify the Town of increases in the number of employees that change their workers’ compensation requirements under the Code of Virginia during the course of the contract shall be in noncompliance with the contract.
b. Comprehensive General Liability Insurance: The Contractor shall maintain during the life of the Contract comprehensive general liability insurance as shall protect them and the Town of Woodstock and its officers, agents, and employees from claims for damages for personal injury, including death, as well as from claims for property damage, which may arise from operations under the Contract, whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amount of such insurance shall be not less than a combined single limit of $1,000,000.00 per occurrence on bodily injury and property damage and $1,000,000.00 aggregate on completed operations.
c. Automobile liability insurance with minimum combined single limits of $500,000.00 per occurrence. This insurance shall include bodily injury and property damage for owned vehicles, non-owned vehicles, and hired vehicles.
I. No Bidder shall modify, revise, edit or make any unauthorized change(s) to the original Invitation To Bid (ITB). The Official solicitation document and the addenda(s) are the documents posted on the Town of Woodstock’s web site and/or eVA. Any such violation as stated above may result in rejection of the bid. In addition, violations may result in the debarment of the offeror by the Town of Woodstock.
J. If any prospective (bidder/offeror) has questions about the specifications or other solicitation documents, the prospective (bidder/offeror) should contact the person whose name appears on the face of the solicitation no later than the question deadline stated in this ITB. Any revisions to the solicitation will be made only by addendum issued by the buyer.
K. Any bid resulting from this solicitation shall be valid for (45) days. At the end of the (45) days the bid may be withdrawn at the written request of the Bidder. If the bid is not withdrawn at that time it remains in effect until an award is made or the solicitation is canceled.
L. The Town may make such reasonable investigations as deemed proper and necessary to determine the ability of the bidder to perform the services/furnish the goods and the bidder shall furnish to the Town all such information and data for this purpose as may be requested. The Town reserves the right to inspect bidder’s physical facilities prior to award to satisfy questions regarding the bidder’s capabilities. The Town further reserves the right to reject any bid if the evidence submitted by, or investigations of, such bidder fails to satisfy the Town that such bidder is properly qualified to carry out the obligations of the contract and to provide the services and/or furnish the goods contemplated therein.
M. The Town shall not be in default for any failure in the performance of this agreement in accordance with its terms if such failure arises out of causes beyond its reasonable control and without the fault of or negligence of the Town. Such causes may include but are not restricted to acts of God or the public enemy, fires, flood, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, but in every case the failure to perform must be beyond the reasonable control and without the fault or negligence of the Town.
N. In case of failure to deliver goods or services in accordance with the contract terms and conditions, the Town, after due oral or written notice, may procure them from other sources and hold the contractor responsible for any resulting additional purchase and administrative costs. This remedy shall be in addition to any other remedies which the Town may have.
O. The Town may terminate any agreement resulting from this solicitation at any time, for any reason or for no reason, upon thirty days’ advance written notice to the Contractor. In the event of such termination the Contractor shall be compensated for services and work performed prior to termination.
P. The contractor shall be responsible for all property damage, accidents, injury, death, and other liabilities incurred while performing contractual duties for the Town and will hold the Town harmless for all resulting damages. This duty of indemnification shall include the right of the Town to select its legal counsel.
Q. Changes can be made to the contract in any of the following ways:
a. The parties may agree in writing to modify the scope of the contract. An increase or decrease in the price of the contract resulting from such modification shall be agreed to by the parties as a part of their written agreement to modify the scope of the contract.
b. The Town delegated agent may order changes within the general scope of the contract at any time by written notice to the Contractor. Changes within the scope of the contract include, but are not limited to, things such as services to be performed, the method of packing or shipment, and the place of delivery or installation. The Contractor shall comply with the notice upon receipt. The Contractor shall be compensated for any additional costs incurred as the result of such order and shall give the Town a credit for any savings.
R. It is mutually understood and agreed that the Contractor shall not assign, transfer, convey, sublet, or otherwise dispose of this contract or his right, title, or interest therein, or his power to execute such contract, to any other person, firm, or corporation, without the previous written consent of an authorized representative of the Town of Woodstock; but in no case shall consent relieve the Contractor from his obligations or change the terms of the contract.
S. All parties performing services for the Town shall comply with all Occupational Safety and Health Administration (OSHA), State Occupational Health Standards, and any other applicable rules and regulations. All parties shall be held responsible for the training, supervision, and safety of their employees. Any unsafe acts or hazardous conditions that may cause injury or damage to any persons or property within and around the worksite areas under this contract shall be remedied per the regulatory agency’s guidelines.
T. The Town shall not indemnify or hold harmless any Contractor or other third party. The Town does not waive any right or release any party from liability, whether on its own behalf or on behalf of any boards, employees, or agents. The Town does not waive the right to trial by jury for any cause of action arising from the contract and shall not submit any contract claim to binding arbitration or mediation. The Town shall not be liable to Contractor for any special, punitive, or exemplary damages arising from the performance of the contract, including, but not limited to, incidental damages, and lost profit and lost wages, even if such special damages are reasonably foreseeable. Any provision(s) in the contract contrary to these statements is/are hereby deleted and rendered void.
U. All bids submitted shall have included in price the cost of any business or professional licenses, permits or fees required by the Town of Woodstock or the Commonwealth of Virginia. The bidder must have all necessary licenses to perform the services in Virginia and, if practicing as a corporation, be authorized to do business in the Commonwealth of VA.
V. Pursuant to Code of VA 2.2-4311.2 subsection B, a bidder organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 is required to include in its bid the identification number issued to it by the State Corporation Commission (SCC). Any bidder that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title 13.1 or Title 50 or as otherwise required by law is required to include in its bid statement describing why the bidder is not required to be so authorized. Link to the SCC site is http://www.scc.virginia.gov.
W. Drug-free workplace (Code of Virginia § 2.2-4312). During the performance of this contract, the Contractor agrees to (i) provide a drug-free workplace for the Contractor’s employees;
(ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor. For the purposes of this section, “drug-free workplace” means a site for the performance of work done in connection with a specific contract awarded to a contractor in accordance with the Virginia Public Procurement Act, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.
X. Immigration Reform and Control Act (Code of Virginia § 2.2-4311.1). The Contractor does not, and shall not during the performance of the contract for goods and services in the Commonwealth, knowingly employ an unauthorized alien as defined in the federal Immigration Reform and Control Act of 1986.
Y. Prompt payment of subcontractors (Code of Virginia § 2.2-4354). The Contractor shall be liable for the entire amount owed to any subcontractor with which it contracts, except amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the subcontract. Payment by the Town to the Contractor shall not be a condition precedent to payment to any lower-tier subcontractor. Within seven (7) days after receipt of amounts paid to the Contractor by the Town for work performed by a subcontractor, the Contractor shall either (a) pay the subcontractor its proportionate share of the payment received, or (b) notify the Town and the subcontractor, in writing, of its intention to withhold all or part of the subcontractor’s payment and the reason for nonpayment. The Contractor shall pay interest to the subcontractor on all amounts owed that remain unpaid after seven (7) days following receipt of payment from the Town, except amounts withheld as allowed above.
Unless otherwise provided under the terms of this contract, interest shall accrue at the rate of one percent per month. Individual contractors shall provide their social security numbers, and proprietorships, partnerships, and corporations shall provide their federal employer identification numbers. The Contractor shall include in each of its subcontracts a provision requiring each subcontractor to include or otherwise be subject to the same payment and interest requirements with respect to each lower-tier subcontractor. The Contractor’s obligation to pay interest to a subcontractor is not an obligation of the Town.
ATTACHMENT A
BID FORM
ITB – Water Treatment Plant Third Floor Wall Reinforcement
In compliance with and subject to your Invitation for Bids and the documents therein specified, all of which are incorporated herein by reference, the undersigned bidder proposes to furnish all labor, equipment, and materials and perform all work necessary for construction of this project, in accordance with the Scope of Work in the ITB dated Nov. 4, 2026, as prepared by the Town of Woodstock for the consideration of the following amount:
Total Bid for all activities ($): ___________________________________
Unit prices for changes in the work. The following unit prices include all labor, materials, equipment, overhead, and profit. They will be used only to price additions to or deletions from the work ordered by written change order. They will not be used to determine the lowest bidder.
Item Unit Unit price ($) Additional steel channel assembly, complete as shown in the Standard Condition detail on Sheet S1 (channel, angle clips, base plate, anchors, and bar-joist bracing), installed
Each _______________
Additional wall anchor (sleeve anchor as shown on Sheet S1), installed Each _______________
By signing below, we hereby confirm that, if awarded the contract for the Water Treatment Plant Third Floor Wall Reinforcement project, we have the capability and resources to complete the project.
The undersigned understands that time is of the essence and agrees that the date for substantial completion of the entire project shall be on or before May 31, 2027 based on a notice authorizing work to proceed on or before December 31, 2026.
Bidder Name: _____________________________________________
Authorized Signature: _____________________________ Date: __________________
Title: __________________________________________________
Address: _______________________________________________
Phone: _____________________ Email: ________________________________
ATTACHMENT B
PROOF OF AUTHORITY TO TRANSACT BUSINESS IN VIRGINIA
THIS FORM MUST BE SUBMITTED WITH YOUR BID.
Pursuant to Virginia Code § 2.2-4311.2, a bidder organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 of the Code of Virginia shall include in its bid the identification number issued to it by the State Corporation Commission ("SCC"). Any bidder that is not required to be authorized to transact business in the Commonwealth shall include in its bid a statement describing why authorization is not required.
NOTE: The SCC number is NOT your federal ID number or business license number.
Please check the applicable box:
A. [ ] Bidder is a Virginia business entity organized and authorized to transact business in Virginia by the SCC. SCC Identification Number: _____________________
B. [ ] Bidder is an out-of-state (foreign) business entity authorized to transact business in Virginia by the SCC. SCC Identification Number: _____________________
C. [ ] Bidder is not required to be authorized to transact business in Virginia for the following reason(s):
Legal Name of Company (as on W-9)
Authorized Signature
Print Name and Title
Date
PHOTOGRAPHS OF THIRD FLOOR AREA
Exhibit 1
EXAMPLE OF OFFSET OF WALL REQUIRING STABILIZATION
WALL WITH LEVEL
WALL AREA DIFFERENTIAL
| I. Project Background |
| II. Procurement Schedule |
| III. Mandatory Pre-bid Meeting |
| IV. Project scope and requirements |
| V. Contract Time |
| VI. Payment Terms |
| VII. Minimum Qualifications |
| VIII. Selection of Contractor |
| IX. Bid Submission Requirements |
| X. General Terms and Conditions |
| Legal Name of Firm as listed on W9: |
| DBA Trade Name if applicable: |
| Street Address: |
| City State ZIP: |
| Primary Contact Name: |
| Title: |
| Phone Number: |
| Email Address: |
| Years in Business The firm has been in continuous operation as a legal business entity for a minimum of five 5: Off |
| No Pending Litigation The firm has no current pending litigation that would materially affect its ability to perform: Off |
| years Year business established: |
| Licensure The firm holds all business and contractor licenses required by the Commonwealth of Virginia to: Off |
| undefined: |
| undefined_2: |
| undefined_4: |
| Total Bid for all activities: |
| Each: |
| Each_2: |
| Bidder Name: |
| Date: |
| Title_2: |
| Address: |
| Phone: |
| Email: |
| reasons 1: |
| reasons 2: |
| Legal Name of Company as on W9: |
| Print Name and Title: |
| Date_2: |
| SCC Number: |
| SCC Number 2: |
| Business status: Off |
| Date Issued_af_date: |
| Sub/Desc: |
| Inital: |
File details come from the government source that posted it. Updated .