This is a Statement of Work (SOW) for the manufacture and delivery of domestically-produced 55-gallon monopropellant production drums/containers conforming to NSN 8140-01-054-6702.

The contractor shall manufacture 208 drums in accordance with drawing 7263829 Rev NR and specification A-A-58020A, Type II, Class 4 for steel drums with polyethylene inserts. The drums must meet performance-oriented packaging (POP) requirements per 49 CFR 178.600 for UN6HA1/Y1.2/100 and UN1A2/Y1.2/100 designations. The contractor is responsible for performing required UN testing per 49 CFR Parts 173 and 178, with two copies of the test report (CDRL A001) due at or prior to first delivery. The contractor must provide certifications of compliance for materials and certifications of conformance to all applicable drawings and specifications, with one copy accompanying each shipment and one copy mailed to Code M24JT at the delivery location. Final inspection and acceptance will be performed by the Government at NSWC IHD. Drums shall be packaged per ASTM D3951 specification with four units per 48" x 48" pallet, single-stacked and stretch-wrapped, and shipped via dedicated tractor-trailer regardless of shipment size. Delivery is to Indian Head, MD 20640-5125 no later than 20 weeks following contract award. Documentation deliverables, including two copies of material certifications and two copies of conformance certifications, are due with the shipment. Technical points of contact will be provided after award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

Monopropellant Production Drums /CONTAINERS, DWG 7263829 REV NR

1.0 ITEM

Domestically manufactured 55-gallon Monopropellant Production Drums /Containers, NSN 8140-01-

054-6702, in accordance with drawing 7263829 Rev. NR and specification A-A-58020A, Type II, Class

4.

2.0 55-GALLON DRUM REQUIREMENTS

The 55-gallon drum shall be manufactured domestically.

georgekearnycontainer@gmail.com

2.1 Specifications

Document Number Document Title

A-A-58020 Drums, Shipping, Steel with Polyethylene Insert

ASTM D2000

Standard Classification System for Rubber Products in Automotive

Applications

49 CFR 100-199 Code of Federal Regulations; Title 49 Transportation

ASTM D3951 Standard Practice for Commercial Packaging

2.2 Drawings

Document Number Document Title

7263829 Rev NR Monopropellant Production Drums /CONTAINER

3.0 REQUIREMENTS

3.1 General

The Contractor shall manufacture, inspect/test, package, and deliver the required number of

Monopropellant Production Drums /Containers in accordance with drawing 7263829 Rev NR and per the applicable documents listed in Section 2.0.

3.2 Monopropellant Production Drums /Container Manufacture

The drums shall be manufactured in accordance with drawing 7263829 Rev NR and specification A-A-

58020A, Type II, Class 4 for steel with polyethylene insert shipping drums.

3.3 Certification

mailto:georgekearnycontainer@gmail.com

The containers shall meet the performance oriented packaging (POP) requirements of 49 CFR 178.600 for

UN6HA1/Y1.2/100 and UN1A2/Y1.2/100 as specified in drawing 7263829 Rev NR, Notes 2D, 2E, and 3

(Critical). The manufacturer shall perform the required UN testing per 49 CFR Parts 173 and 178 and specification A-A-58020A Section 4.2. The manufacturer shall provide two (2) copies of the test report, CDRL A001, at the time of the first container delivery to NSWC IHD technical point of contact per specification A-A-58020A Section 5. The manufacturer shall provide one (1) copy of the certification of conformance to the UN test requirements.

As part of the quality control requirement, the Contractor shall provide Certification of Compliance for material and Certification of Conformance to drawings and specifications listed herein. The containers shall conform to the requirements of Drawing 7263829 Rev NR, ASTM-D-3951, and specification A-A-

58020A. The Contractor shall specify the contract number and container lot(s) or deliveries covered by the certificate of compliance for the material. Further, the Contractor shall provide all relevant certifications for material to provide proof that the material is in accordance with drawing 7263829 Rev

NR. Certifications of Compliance/Conformance shall be provided by the Contractor, one (1) copy to accompany each shipment (in the packing list envelope) and one (l) copy mailed to arrive at time of receipt of each shipment. Mark all certificates to the attention of Code M24JT.

3.4 Inspection/Acceptance.

Final inspection and acceptance of the Monopropellant Production Drums /Containers will be performed at NSWC IHD by the Government. The objective of the inspection is to provide verification of conformance to applicable drawing requirements (dimensions and notes), specifications, and contract requirements. The Government shall verify, through inspection, certification, audit, or test or any combination, the dimensional, material, and/or note conformance to drawing 7263829 Rev NR.

3.5 Packaging and Shipment

Contractor shall package the Monopropellant Production Drums /Containers for shipment in accordance with specification ASTM D3951. Monopropellant Production Drums /Containers shall be palletized four per pallet, single stacked and stretch wrapped on pallets. The pallets shall be 48” x 48” to ensure that the containers do not overhang the edge and to prevent damage to the containers during shipment. All shipments shall be on a dedicated tractor-trailer, no matter how small the shipment. A label shall be placed on the shrink-wrap around each palletized assembly containing the following information:

“Monopropellant Production Drums/Container”, drawing number with revision, manufacturer name, contract number including call number and contract line-item number (CLIN), quantity per pallet, and weight.

4.0 DELIVERABLES

Documentation deliverables as specified herein shall be delivered to the Technical Points of Contact, for review and approval/acceptance:

Technical Points of Contact:

Provided after award

Monopropellant Production Drums /Containers shall be delivered to the Receiving Office, for inspection and approval/acceptance:

Delivery Address:

Full address provided after award

Indian Head, MD 20640-5125

4.1 Deliverables Schedule (Each subsequent order shall be an option)

This SOW consists of multiple options, as outlined in the table below.

Deliverables

Deliverable Quantity Due

Monopropellant

Production Drums

/Containers

208 No later than 20 weeks following award of contract.

Certification of

Material

2 Two copies with Monopropellant

Production Drums /Container shipment

Certification of

Conformance*

2 Two copies with Monopropellant

Production Drums /Container shipment

UN Test Report, CDRL A001

2 Two copies prior to or at the time of the

Monopropellant Production Drums

/Container shipment

*Contractor to provide Certificates of Conformance to the requirements of Drawing 7263829 Rev NR, specification ASTM-D-3951, and specification A-A-58020A, and UN test requirement.

File details come from the government source that posted it. Updated .