This document is an addendum to the Florida Fish and Wildlife Conservation Commission's (FWC) Solicitation No. FWC 22/23-119, "Buoy System Services". The addendum provides answers to questions from prospective bidders regarding the scope of work, including the storage and transportation of 13 buoys and down lines. The solicitation is seeking competitive bids for buoy system inspection and maintenance services in accordance with the specifications. Bidders must submit their responses no later than 2:00 PM (ET) on Friday, July 14, 2023.

The addendum clarifies that the cost of storing the 13 buoys and down lines, as well as the off-water work to transport and unload them, should be included in the flat rate for the Riviera Beach portion of the project. The document also confirms that the FWC will not reimburse the contractor for these storage costs.

View the file

Other files

File Type Posted
FWC 2223-119 Exhibit D.pdf PDF
FWC 22.23-119 Final ITB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Fish and Wildlife Conservation Commission

Commissioners

Rodney Barreto

Chairman Coral Gables

Steven Hudson Vice Chairman Fort Lauderdale

Gary Lester Oxford

Albert Maury Coral Gables

Gary Nicklaus Jupiter

Sonya Rood St. Augustine

Robert A. Spottswood Key West

Office of the

Executive Director

Dr. Thomas H. Eason

Acting Executive Director

Jessica Crawford

Chief of Staff

850-487-3796

850-921-5786 FAX

Finance and Budget Office

(850) 488-6551

Mana gin g fish and wildlife resourc e s for their long-te rm well-b ei n g and the benefi t of peopl e .

620 South Meridian Street

Tallahassee, Florida 32399-1600 Voice: 850-488-4676

Hearing/speech-impaired:

800-955-8771 (T)

800 955-8770 (V)

MyFWC.com

DATE: JULY 3, 2023

ADDENDUM NO.: 1

BID NO.: FWC 22/23-119

BID TITLE: BUOY SYSTEM SERVICES

UPDATE: QUESTIONS & ANSWERS

The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s

(FWC) Solicitation No. FWC 22/23-119, “Buoy System Services”.

All responses to the subject solicitation must be received no later than 2:00

PM (ET) on Friday, July 14, 2023.

A response received after the exact time specified will not be considered.

Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in

Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875

Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.

Sincerely, Ruth Heggen

FWC Procurement Manager

FWC 22/23-119 ADDENDUM #1 2

BEGIN ADDENDUM #1

Item #1 –Questions and Answers

Question #1: Can you please provide Exhibit D- Standard Tech Specs with addendum-this was the only exhibit that was not able to be opened to view.

Answer #1: A copy of Exhibit D has been uploaded as a separate document to the Vendor

Information Portal.

Question #2: In section 5.1.3, contractor shall be responsible for the storage of the 13 buoys and down lines. Will the commission reimburse the contractor for the storage costs (square footage of warehouse space)?

Answer #2: No, the cost should be included in the flat rate for Riviera Beach. Please see

SOW Section 2.3 Buoy System Maintenance.

Question #3: There are other costs involved, including but not limited to the off water work to safety transport and unload the 13 buoys and down lines to the storage facility and remobilize them to the project area in the Spring. OR Do we estimate the cost and include it in our price for the Riviera Beach portion of the project?

Answer #3: The cost should be included in the flat rate for Riviera Beach.