Fuel Containment Scope of Work Final.docx

DOCX document 254 KB Posted

Attached to
Replace Fuel Dispenser Reel and Containment (Station Pascagoula)
Solicitation number
70z02925QNEW00000022
Issued by

About this file

This is a Scope of Work document for a comprehensive fuel dispensing system replacement project at U.S. Coast Guard Station Pascagoula in Pascagoula, Mississippi (Project Number 29378105, scheduled for February 2026). The contractor must furnish all labor, tools, equipment, and materials to replace the fuel dispenser reel and secondary containment system, including removal and disposal of existing equipment. Key work requirements include replacing secondary containment boxes for both gasoline and diesel dispensers with new stainless-steel units, replacing all mechanical inline safety devices and pressure relief valves with stainless-steel parts, replacing fuel filters at main tanks and dispensers, installing new nozzles and hoses for both fuel types, replacing existing hose reels with new stainless-steel reels, and providing new covers for hose reels and dispensers. Material specifications require 304 or 316 stainless steel for most components, aluminum piping options, brass solenoid valves with Viton seals, single-element inlet filters rated to 40 GPM, and 1-1/2" inlet swivel hose reels with capacity for over 125 feet of 1" hose.

The contractor must maintain the installation schedule with a 30 calendar-day performance period, working Monday through Friday from 7:30 a.m. to 3:30 p.m., and coordinate all staging and laydown areas with Coast Guard representatives. The contractor is responsible for providing proper fuel cleanup kits, fuel spill supply kits (booms and mats), temporary toilet facilities, waste disposal in compliance with federal and state hazmat requirements, and must submit personnel rosters, project schedules, safety plans, product data, and operation and maintenance manuals for approval. All personnel must carry valid government-issued identification compliant with the Real ID Act. The contractor must provide training to unit personnel on equipment operation before project completion and obtain approval from the Contracting Officer's Representative before interrupting any utilities or working beyond normal hours. Site contact is MKC Ben MacPhee at Benjamin.L.Macphee@uscg.mil or (228) 769-5606.

View the file

Other files

File Type Posted
SF1442 (AutoRecovered).docx DOCX document
Wage Determinations.txt TXT text file
Construction Clauses (Mar) 2025.odt ODT document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

Replace Fuel Dispenser Reel and Containment

AT

UNITED STATES COAST GUARD

Station Pascagoula, Pascagoula, MS

PROJECT NUMBER 29378105

February 2026

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1. GENERAL DESCRIPTION

1.1.1. General Work Requirements

The project involves a comprehensive replacement of the fuel dispensing system's key components. This includes upgrading safety features by replacing all mechanical inline safety devices and pressure relief valves with new stainless-steel parts. The secondary containment boxes for both gasoline and diesel dispensers will also be replaced with new stainless-steel units.

The project includes the replacement of all fuel filters at the main tanks and dispensers, as well as new nozzles and hoses for both gasoline and diesel dispensers. The existing hose reels will be replaced with new stainless-steel reels, and new covers will be provided for both the hose reels and the dispensers.

Furnish all labor, tools, equipment, and materials for a new fuel dispenser reel and containment for Station Pascagoula.

A. Contractor shall provide, install and test new fuel dispensing reel and new containment for proper operation and make sure there are no leaks.

B. Contractors shall remove and dispose of the existing reel and containment.

C. This summary is not all inclusive and delineates only those work items deemed as major to the contract. Ancillary work items necessary to attain the completed project, shall be included in the contract as inherent to the work.

1.1.2. SPECIFIC WORK REQUIREMENTS

A. Qualifications

(1) The installation shall be performed by a contractor with certifications and qualifications in the state of Mississippi.

B. Additional Performance Requirements

(1) Contractor shall be responsible for disposing of the existing reel and containment.

(2) Contractors shall have proper fuel cleanup kits/materials readily available.

(3) Dispensers: Remove the existing gasoline and diesel dispensers. The units will be reused and reinstalled upon completion of the containment box replacement.

(4) Containment Boxes: Replace the secondary containment boxes for both the gasoline and diesel dispensers with new stainless-steel units and all associated hardware.

(5) Safety Devices: Replace all mechanical inline safety devices and pressure relief valves for both the gasoline and diesel tanks with new stainless-steel parts and associated hardware.

(6) Filtration: Replace all fuel filters at both the main tanks and at the gasoline and diesel dispensers.

(7) Dispenser Components: Replace all gasoline and diesel dispenser nozzles and hoses.

(8) Hose Reels: Replace the existing gasoline and diesel hose reels with new stainless-steel reels and all associated hardware.

(9) Covers: Provide new hose reel covers and dispenser covers

1.1.2.1

Specifications
Component
Specification
Piping & Conduit
All 304SS or ALUMINUM
Frame & Top
304 Stainless steel (Powder Coated)
Doors & Panels
316 Stainless steel
Solenoid Valve
Brass with Viton seals
Hose Reel
1-1/2" inlet swivel with 1-1/2"

Capacity: In excess of 125' of 1" hose

Inlet Filter
Single element, rated to 40 GPM

1.1.3. SPECIAL WORK REQUIREMENTS

A. Comply with Federal, State and Local hazmat requirements, including the Coast Guard Unit itself.

B. Coordinate all staging and laydown areas with the Coast Guard prior to work starting.

1.2. TEMPORARY FACILITIES OR UTILITIES

A. The contractor shall provide temporary toilet facilities for their personnel.

1.3. PROJECT PERFORMANCE PERIOD

A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.

B. The total contract performance period is 30 calendar days.

1.4. LOCATION

The work is located at:

U.S. Coast Guard Station Pascagoula 108 Singing River Island Pascagoula, 39595, Mississippi Arrangements for visiting the site may be made by contacting:

MKC Ben MacPhee Email: Benjamin.L.Macphee@uscg.mil Telephone: (228) 769-5606

1.5. DRAWINGS ACCOMPANYING SPECIFICATION

There are no drawings accompanying this specification.

1.6. WORK HOURS

1.6.1. Normal Working Hours

A. Perform all work at the site from Monday through Friday from 7:30am to 3:30 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.

B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.

1.7. SPECIFIC ENVIRONMENTAL REQUIREMENTS

There are no specific environmental requirements. References can be made to the guidelines set forth by the National Response Center, Emergency Response Guidebook and EPA Incident Management Handbook, if needed, for fuel spill containment.

1.8. SAFETY PROGRAM

1.8.1. General

The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.

1.9. AVAILABILITY OF UTILITY SERVICES

A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.

(1) Electricity

(2) Potable Water

B. The contractor shall provide temporary toilet facilities for their personnel.

1.10. UNDERGROUND AND CONCEALED UTILITIES

A. Any utility locations provided are diagrammatic, not exact.

B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area as applicable. Mark the surface of the ground where existing underground utilities are discovered as applicable.

1.11. UTILITY OUTAGES

Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).

1.12. CONTRACTOR USE OF PREMISES

The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight. Provide proper fuel spill supply kits, such as booms and mats, in case of a spill into the water.

1.13. CLEANUP

The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.

1.14. ENVIRONMENTAL

1.14.1. Protection of the Environment

The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment and/or containment of fuel spills in or near bodies of water.

1.14.2. Generated Waste

A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with Federal, State and Local requirements.

B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with all applicable federal, state, and local laws and ordinances.

C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.

1.15. DISPOSITION OF MATERIALS

A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.

1.16. STORM PROTECTION

The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.17. RECEIPT OF MATERIALS

The Contractor is responsible to receive all equipment, materials, and supplies.

1.18. DELIVERY AND STORAGE

The Contractor is responsible for the proper transport and storage of all equipment and materials.

1.19. SECURITY

A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.

B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.

C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.

1.20. FINAL INSPECTION AND ACCEPTANCE

A. Electronically submit a written request for final acceptance to the Coast Guard.

1.21. WARRANTIES

A. Endorse all warranties or guarantees to the Government.

1.22. TRAINING

A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.

1.23. SUBMITTALS

A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.

1.24. SUBMITTAL LIST

A. ROSTER OF PERSONNEL

(1) As required by the paragraph titled Security.

B. PROJECT SCHEDULE

(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.

C. SAFETY PLAN

(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.

D. PRODUCT DATA

(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.

1.24.2. OPERATION AND MAINTENANCE MANUALS

A. Submit electronically and provide the following:

(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;

(2) Warranty information;

(3) Test procedures;

(4) Results of all testing and commissioning procedures;

(5) Performance data;

(6) A control sequence describing start-up, operation and shut-down instructions;

(7) Installation instructions;

(8) Maintenance instructions;

(9) Operating instructions;

(10) Parts list.

-- End of Section --

Section 01 11 00 image1.jpeg