FSS III Questions and Answers dtd 18 Jun 26.pdf

PDF 42 KB Posted

Attached to
Facility Support Services III - Request For Information (RFI)
Solicitation number
FA9101FSSIII_RFI2
Issued by

About this file

This is a Questions and Answers document dated 18 June 2026 addressing an upcoming federal contract opportunity designated FSS III. The document does not address specific required products or services, but rather provides preliminary acquisition information in response to industry inquiries.

The Government is conducting the FSS III acquisition to replace the current contract, FSS II (FA9101-19-C-1000), which was awarded to Akima Intra-Data, LLC. The current contract has an eight-year total anticipated value of $152,871,144.00, exclusive of Collective Bargaining Agreements and Service Contract Labor Standard wage adjustments; funding is incremental and subject to change. The acquisition strategy is still under development, with the Government finalizing details for a Small Business set-aside. A formal Request for Proposal (RFP) is projected for issuance in the first quarter of Fiscal Year 2027 (Q1 FY27), though this timeframe is an estimate for planning purposes only and subject to change. All official updates regarding the acquisition timeline and solicitation will be posted on SAM.gov.

View the file

Other files

File Type Posted
FSS III RFI 2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Number Reference Document Page/Paragraph # Question Answer 1 RFI 1 - Current Contract N/A Who is the current contractor? FSS II, FA9101-19-C-1000, was awarded to

Akima Intra-Data, LLC 2 RFI 1 - Current Contract N/A What is the current contract amount? The current contract is being incrementally funded; thus, the current amount changes frequently. The 8 year period as a total anticipated amount of $152,871,144.00 exclusive of Collective Bargaining Agreements and Service Contract Labor Standard wage adjustments.

3 RFI 1 - Current Contract N/A If you are unable to provide the current contract amount, what is the current budget your agency has for this project?

See the answer to question 2.

4 RFI 1 N/A Is the acquisition strategy still being developed?

Yes, the Government is currently finalizing the acquisition strategy. It has been determined that this requirement will be set aside for Small Business. Additional details regarding the finalized acquisition strategy will be made available when the formal Request for Proposal (RFP) is posted on SAM.gov.

5 RFI 1 N/A Is there a projected timeframe for when the solicitation will be issued?

The Government currently anticipates issuing the formal Request for Proposal (RFP) in the first quarter of Fiscal Year 2027 (Q1 FY27).

Please note that this projected timeframe is an estimate for planning purposes only and is subject to change. All official updates regarding the acquisition timeline and the solicitation itself will be posted on SAM.gov.

FSS III

Solicitation #:

Questions and Answers Date: 18 June 2026

Q&A for Industry

File details come from the government source that posted it. Updated .