This document is a set of Special Contract Requirements for a road maintenance project in the Twin Falls District, Idaho, under the Bureau of Land Management. The work involves maintenance/improvements to approximately 11.2 miles of naturally surfaced existing road, including reshaping, grading, and surfacing with a 6-inch layer of compacted aggregate material. Key details include:
The performance period is 80 calendar days from the Notice to Proceed. The contractor is responsible for mobilization, traffic control, site preparation, materials testing, and other incidental work. Applicable specifications are FP-14 Standard Specifications with several modifications detailed in the Special Contract Requirements. The contractor will be paid per cubic yard of surface aggregate material delivered and placed. Specific project requirements cover grading, compaction, drainage, and project-specific environmental protection measures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L2624R0005_Amd_0001.pdf | ||
| Site_Inspection_Tour_1510-56_0001.pdf | ||
| BIL_-_Big_Bend_Crossing_Road_Maintenance_Access_Map.pdf | ||
| Sol_140L2624R0005.pdf | ||
| SF-24_Bid_Bond.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Contract Requirements TWIN FALLS DISTRICT, ID
BIL - Big Bend Crossing Road Maintenance Bureau of Land Management
SPECIAL CONTRACT REQUIREMENTS
FOR THE CONSTRUCTION, RECONDITIONING,
AND SURFACING OF ROADS PROJECTS
Description of Work
The work to be done under this contract includes all labor, supervision, transportation, equipment, tools, supplies, and materials necessary for maintenance/improvements of road to specified dimensions and furnishing, loading, hauling, placing, shaping, watering, compaction, and testing of surfacing aggregate material to follow FP 14 Table 703-2 Gradation B.
Road shall be graded and compacted to the typical sections template (Section 301 Figure 1 Typical
Cross Section, page 20). Material must be a combination of screened/crushed material with a gradation of B (Subbase) according to Standard Specifications for Construction of Roads and Bridges on Federal
Highway Projects, FP 14, Table 703-2. Approximately 11.2 miles of reshaping and grading of naturally surfaced existing road and surfacing the existing road with material Provided by the contractor and approved by the CO. Road travel width shall be 12’ wide and surface course should be placed with a compacted thickness of at least 6 inches as shown on the plans. Prior to placement of road surfacing material, the road prism and ditches shall be reconditioned, and the ditches shall be cleaned. Surfacing shall take place in the quantities shown on the Bid Schedule, at the location shown on the Project Map.
Work includes mobilization, traffic signing, site preparation, watering, grading, materials testing, compaction and finish work. There has been one mobilization allocated for this project. The contractor shall be responsible for all costs associated with additional mobilizations. The roads to the project site, after leaving the pavement, are rough and difficult roads and any damage caused to existing roads must be repaired. Any repairs or maintenance needed due to damage done to the roads during mobilization will be the contractor’s responsibility.
Project Location
See attached map. North end of project is located approximately 30 miles from Castleford, ID. Travel west on Balance Rock road to Crows Nest road (gravel road) which begins at the Y intersection with
Castleford Glenns Ferry road. Travel approx. 15 miles to intersection of Clover road, turn south on
Clover road and travel 4.8 miles, turn east and travel 3 miles to the project northern point, Lat.
42.518112°, Long.-115.253585°. Project is 11.2 miles, southern point Lat. 42.363512°, Long.
-115.201581°.
Performance Period
80 Calendar Days from Notice to Proceed (NTP).
Local conditions (weather conditions, road conditions, etc.) that may affect work are included in the performance period. Contractor shall coordinate work hours with the Contracting Officer’s
Representative (COR) / Contracting Officer 48 hours in advance of beginning work.
Applicable Standard Specifications
The General Requirements (Division 100) and the applicable sections of Divisions 150 through 700 of the Federal Highway Administration’s "Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14, U.S. Customary Units" of the U.S. Department of Transportation, Federal Highway Administration apply to this project as modified by these Special Contract
Requirements and Contract Clauses contained in the contract. Unless otherwise noted, all reference headings in these Special Contract Requirements refer to divisions, sections, subsections, articles or paragraphs of the Standard Specifications, FP-14. The Contractor shall keep a copy of FP-14 on site during all construction for this project.
The FP-14 is a separately published book by the Federal Lands Highway. To download FP-14 or to obtain a hard copy, visit:
http://flh.fhwa.dot.gov/resources/pse/specs/fp-14.htm
Applicable Standard Specifications
Section 151 – Mobilization
Section 201 – Clearing and Grubbing
Section 203 – Removal of Structures and Obstructions
Section 212 – Linear Grading
Section 607 – Cleaning, Relaying, and Repairing Existing Drainage Structures
Section 635 – Temporary Traffic Control
Section 703 – Aggregate
Section 725 – Miscellaneous Material
Specific Project Supplemental Specifications
Preface
Section 101 – Terms, Format, and Definitions
Section 102 – Bid, Award, and Execution of Contract
Section 103 – Scope of Work
Section 104 – Control of Work
Section 105 – Control of Material
Section 106 – Acceptance of Work
Section 107 – Legal Relations and Responsibility to the Public
Section 108 – Prosecution and Progress
Section 109 – Measurement and Payment
Section 156 – Public Traffic
Section 204 – Excavation and Embankment
Section 209 – Structure Excavation and Backfill
Section 301 – Untreated Aggregate Courses
Section 303 – Road Reconditioning http://flh.fhwa.dot.gov/resources/pse/specs/fp-14.htm
PREFACE
Delete the Preface and substitute the following:
These Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects are issued primarily for constructing roads and bridges on Federal Highway projects under the direct administration of the Bureau of Land Management. These specifications are cited as "FP-14" indicating
"Federal Project" Standard Specifications issued in 2014 and contain both United States Customary and
Metric units of measure.
When designated in a contract, the FP-14 becomes part of the contract and binding upon all parties to the contract. Construction contracts of the Bureau of Land Management are also governed by the following regulations:
● Federal Acquisition Regulation (FAR), Title 48, Code of Federal Regulations, Chapter 1
The FAR regulations are not included in the FP-14. A complete copy of the FAR is available from the
Superintendent of Documents, Congressional Sales Office, U.S. Government Printing Office, Washington, DC 20402.
U.S. Customary units of measure are used in the FP-14 as provided in the November 25, 2008, Memorandum from Jeffrey F. Paniati entitled Update on Metric Use Requirements for FHWA Documents. Metric units are noted in parentheses following the U.S. Customary Units. The references to Metric or Metric units apply only when the project or portion of the project expressly calls for Metric units of measure.
DIVISION 100
GENERAL REQUIREMENTS
Section 101. – TERMS, FORMAT AND DEFINITIONS
101.01 Meaning of Terms. Add the following:
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03 Abbreviations. Add the following to (a) Acronyms:
ABA
ADA
AIA
ASCE
ASCII
BLM
FTMS
GSA
MIL
NFPA
PCA
USFS
USGS
Architectural Barriers Act
Americans with Disabilities Act
American Institute of Architects
American Society of Civil Engineers
American Standard Code for Information Interchange
Bureau of Land Management
Federal Test Method Standard
General Services Administration
Military Specifications
National Forest Products Association
Portland Cement Association
United States Forest Service
United States Geological Survey
Add the following to (b) U.S. Customary unit abbreviations and symbols:
hr mp ppm
Hour
Milepost
Parts Per Million
101.04 Definitions. Delete the definitions for the following terms:
Bid
Bidder
Modify the following definitions as follows:
Contract Time – Delete this definition and substitute the following:
Period of Performance (POP) – The specified time allowed for completion of contract work.
Notice to Proceed – Delete this definition and substitute the following:
Notice to Proceed – Written notice from the Contracting Officer to the Contractor to begin the contract work.
Add the following:
Maximum Particle Size – The smallest sieve opening through which all particles in the material will pass.
Neat Line – A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road – Temporary construction access built along the route of the project.
Protected Streamcourse – A drainage shown on the plans that requires designated mitigation measures.
Right-of-Way – A general term denoting (1) the privilege to pass over land in some particular line
(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2)
Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Utilization Standards – The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Section 102. – BID, AWARD, AND EXECUTION OF CONTRACT
Delete this section in its entirety.
Section 103. – SCOPE OF WORK
103.02 Disputes. Delete in its entirety.
103.03 Value Engineering. Delete in its entirety.
103.04 Contractor Records. Delete in its entirety.
103.05 Partnering. Delete in its entirety.
Section 104. – CONTROL OF WORK
104.01 Authority of the Contracting Officer (CO). Delete in its entirety.
104.02 Authority of Inspectors. Delete in its entirety.
104.03 Specifications and Drawings.
(c) As-built drawings. Modify the first sentence to read as follows: Use one set of Contractor-provided plans exclusively for as-built drawings.
(d) Submittals. Add this section:
1. Scale certification.
2. Daily Logs
3. Method for determining Cubic yards delivered.
4. Section 105.02 (c)
5. Section 301 Gradation Test Results
104.04 Coordination of Contract Documents. Delete in its entirety and replace with the following:
The only staking which will be performed by the Government is to indicate sections where work is to begin and where work is to end. All other required staking shall be the responsibility of the Contractor.
Segments shown on the map indicate areas where work may be performed.
Section 105. – CONTROL OF MATERIAL
105.02(a) Delete in its entirety.
105.02(b) Delete in its entirety.
105.05 Delete in its entirety.
105.05(a). Delete in its entirety.
105.05(b). Delete in its entirety.
Section 106. – ACCEPTANCE OF WORK
106.05 Statistical Evaluation of Work and Determination of Pay Factor. Delete in its entirety, including all references to Statistical Evaluation. All references to Section 106.05 shall be replaced with references to Section 106.04 Measured or Tested Conformance.
Section 107. – LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
107.01 Laws to be Observed. Delete in its entirety.
107.02 Protection and Restoration of Property and Landscape. Delete in its entirety.
107.03 Bulletin Board. Delete in its entirety.
107.05 Responsibility for Damage Claims. Delete in its entirety.
107.06 Contractor’s Responsibility for Work. Delete in its entirety.
107.09 Legal Relationship of the Parties. Delete in its entirety.
107.10 Environmental Protection.
(e) Project Specific Environmental Protection. Add this section:
During the time period of August 1 – October 30, work (equipment use) shall be limited to the hours of
6 AM to 6 PM.
Prior to mobilizing equipment to the site, all mechanical equipment and vehicles shall be cleaned of all vegetation (stems, leaves, seeds, and all other vegetative parts) in order to minimize the transport of invasive plant species.
Section 108. – PROSECUTION AND PROGRESS
Delete this section in its entirety.
Section 109. – MEASUREMENT AND PAYMENT
109.03 Weighing Procedures and Devices.
(c) Project weighing system. Add the following:
Manual scales may be used if approved in writing by the CO and if the method of weighing meets all other contract requirements. Loader scales may be used if approved in writing by the CO and if the method of weighing meets all other contract requirements. Scales shall be accurate to within 2% of actual weight. For aggregates weighed for payment, adjust scale weights of material to deduct the daily average moisture content in excess of 2 percentage points over optimum moisture as determined by AASHTO T 99 or the designated compaction method. If moisture determination is necessary, determine the daily average moisture content in accordance with AASHTO T 255, from not less than three representative samples of aggregate taken at random intervals each day that aggregate is being weighed.
109.06 Pricing of Adjustments. Delete in its entirety.
109.07 Eliminated Work. Delete in its entirety.
109.08 Progress Payments. Delete in its entirety.
109.09 Final Payment. Delete in its entirety.
Section 156. – PUBLIC TRAFFIC
Replace Section 156 in its entirety with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
See FAR Clause 52.236-13 Accident Prevention.
Material
156.02 Conform to the following Section:
Temporary traffic control ………………………………………………… 635
Construction Requirements
156.04 Accommodating Traffic During Work. Perform work in a manner that ensures the safety and convenience of the public and protects the residents and property adjacent to the project. Accommodate public traffic on roads
156.05 Maintaining Roadways During Work. Maintain roadways as follows:
(a) Maintain intersections with trails, roads, streets, businesses, parking lots, residences, garages, farms, and other features.
(b) Snow removal to facilitate the work is the Contractor’s responsibility.
(c) Maintain a dust-free traveled way such that visibility and air quality are not affected, and a hazardous condition is not created.
(d) Remove accumulations of soil and other material from traveled way.
(e) Do not allow water to pond on the traveled way; and
(f) Maintain the roadway, detours, and diversions in a safe and acceptable condition.
If corrective action is requested and the corrective action is not taken immediately, the condition may be corrected, and the cost of the corrective action deducted from monies due the Contractor.
156.06 Maintaining Roadways During Non-Work Periods. Maintain roadways and traffic control for public traffic during periods when work is not in progress.
156.08 Nighttime Operations. Perform construction operations during the hours of daylight (one-half hour after sunrise to one-half hour before sunset). Only as permitted by the CO.
Section 204. – EXCAVATION AND EMBANKMENT
204.03 Material. Delete in its entirety, and replace with the following:
204.03 Material. Conform to the following Subsections:
Water ……………………………………………725.01(c)
204.06 (d) Pioneer Roads. Add this section:
Road pioneering, slash disposal, and grubbing of sage brush may proceed concurrently with excavation. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway. Maintain drainage during pioneering operations.
Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments.
Place snow or ice in a manner to prevent resource damage.
204.11 (b) Compaction Delete in its entirety, and replace with the following:
(A) Aggregate. Place material by end dumping or belly dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until there is no visible evidence of further consolidation from the roller. Make at least three complete passes over every square foot of the placed material.
(B) Subgrade Compaction. While grading roadway to specified dimensions adjust the moisture content of existing materials to obtain a mass that will not visibly deflect under the load of the grading, hauling, and spreading equipment. Operate compaction equipment over the full width of the roadway until there is no evidence of further consolidation from the roller. Make, at a minimum, three complete passes over every square foot of the graded roadway.
Section 209. – STRUCTURE EXCAVATION AND BACKFILL
209.07 Foundation Preparation Delete the third paragraph and replace with the following:
Backfill and compact with backfill material. If using approved road subbase for backfill, use any compaction method according to subsection 209.10.
209.09 Backfill Add the following to Subsection 209.09(a):
(a) General.
Backfill without damaging or displacing the culvert or structural plate structure. Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.
209.10 Compacting Delete in its entirety and replace with the following:
Compact the embankment using one of the following methods as specified. If in situ material or other backfill material is requested and approved by the CO, compaction Method 1 is required.
(a) Compaction Method 1. Use AASHTO T 27 to determine the quantity of material retained on a No. 4
(4.75-millimeter) sieve. Compact as follows:
(1) More than 80 percent retained on a No. 4 (4.75-millimeter) sieve. Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation:
(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds (180 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.
(b) Eight roller passes of a 20-ton (20-metric ton) compression-type roller; or
(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.
Increase the compactive effort for layers deeper than 12 inches (300 millimeters) as follows:
• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roll passes in Subsection 209.10(a)(1)(a), by four passes: or
• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roll passes in Subsection 209.10(a)(1)(b) and (c), by eight passes.
(2) 50 to 80 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to
AASHTO M 145. Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content. Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 (4.75-millimeter) sieve. Multiply this number by the percentage of material passing a No. 4 (4.75-millimeter) sieve and add 2 percent to determine the optimum moisture content of the material.
Use nonvibratory rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet(1 meter) per second. Compact each layer of material full width according to Subsection
209.10(a)(1).
(3) Less than 50 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. For material classified A-1 or A-2-4, determine the maximum density according to
AASHTO T 99, Method C.
Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.
Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to
AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.
(b) Compaction Method 2. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate roller compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Ensure rollers meet the following requirements:
(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch (4.5 kilogram/millimeter) of width of the compression roll or rolls.
(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration, specifically designed to compact the material on which it is used.
(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi (550
Kilopascals).
(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 pounds per inch (4.5 kilogram/millimeter) of width of roller drum.
(c) Compaction Method 3. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer until there is no visible evidence of further consolidation. Make at least three complete passes.
(d) Compaction Method 4. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer.
(e) Compaction Method 5. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact the complete surface with a bucket of an excavator larger than 39,000 pounds (18 metric ton) Gross Vehicle Weight using a minimum of three blows. Overlap compaction by ½ width of bucket.
(f) Compaction Method 6. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact using an approved mechanical tamper until visible displacement ceases with a minimum of three complete passes.
When compacting with rollers or hauling and spreading equipment is not practical, use approved mechanical tampers for a minimum of three complete passes.
Section 301. – UNTREATED AGGREGATE COURSES
301.03 General. Replace this subsection in its entirety with the following:
Prepare the surface on which the aggregate course is placed according to Section 303. Material to be placed is a 2 inch minus aggregate or an approved equal material. Rolling and watering is required. Water is not provided by the Government. Material shall be placed to a depth and width as shown on Figure 1 –
Typical Cross-Section.
301.04 Mixing and Spreading. Delete the first sentence of the first paragraph and add the following:
Determine the adequate moisture content to obtain the necessary compaction results according to field trial. Obtain approval (of adequate moisture content) by the Contracting Officer prior to rolling. Water is a scarce resource in this area and the Contractor will not be asked to make more than one pass per section which is being rolled but the roller shall not operate on any section of road which has not had at least one pass with the water tender or has been wetted by rain. No other additives will be required.
301.05 Compacting. Replace this subsection in its entirety with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors. Blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. Compact the aggregate using the following methods as specified:
Aggregate Compaction. Operate rollers and compact as specified in Subsection 204.11(b)(A).
Subgrade Compaction. Operate rollers and compact as specified in Subsection 204.11(b)(B).
(Refer to 204.11 (b) Compaction, Special Contract Requirements above)
301.06 Surface Tolerance. Replace this subsection in its entirety with the following:
Remove irregularities and shape to a uniform surface.
301.08 (b) Delete in its entirety.
Table 301-1 Modify as follows:
Remove all Sampling, Testing, and Acceptance Requirements rows except for the first row titled
“Subbase, base, or surface coarse aggregate”.
Delete “Fractured Faces” from row titled “Subbase, base, or surface coarse aggregate” and
“Characteristic” column
Delete “2 per day per stockpile” from row titled “Subbase, base, or surface coarse aggregate” and
“Sampling Frequency” column
And Replace with the Following:
“1 per 1000 Cubic Yards.”
301.09 Measurement. Replace this subsection in its entirety with the following:
The quantity to be paid for will be the cubic yards of Surface Aggregate delivered by the hauling vehicle at the point of delivery according to Section 109. Measuring of material shall be at the Contractor's expense. A daily log and truck count for each load of material shall be furnished by the Contractor to the
Contracting Officer. Daily log and truck counts shall include individual records for each truck, at minimum providing; truck identification, total volume hauled for each day, the time at loading and dumping, and point of delivery of each load.
FP14 301 (1) Surface Course . . .. Cubic Yard
Figure 1. – Typical Cross-Section
303 – ROAD RECONDITIONING
Replace Section 303 in its entirety with the following:
Description
303.01 Work. Contractor shall furnish all labor, equipment, materials, and incidentals necessary to improve selected aggregate surfaced, natural surfaced, or two-track roads which includes shaping two-track or unimproved roads to be crown and ditch roads. Work requires the use of a water tender and compaction equipment.
Construction Requirements
303.02 Blading and Shaping. Prepare the surface as shown on Typical Cross-Section provided in the plans. This includes maintaining and/or constructing ditches, crown, and furrow ditches into an existing two-track or unimproved road. Improvements shall be completed when adequate moisture is present. A water tender shall be required to deliver water to the section of road requiring improvement. The
Contractor shall provide enough water to the area being improved such that the material can be formed into a ball through pressure applied by one’s hand. A roller shall also be required for use on areas being improved. The road shall be improved to keep drainage functional (including ditch cleaning of branches, large rocks, and/or other water drainage blockers and annual cleaning of the culverts to remove branches, large rocks, and sediment greater than 2 inches in depth) and to keep the road prism to an acceptable level to allow a prudent driver to safely negotiate the road in a passenger car. End product shall be in compliance with the following:
a. Shall be constructed to achieve positive drainage in all places using the road geometry shown in the typical Cross-Section (Figure 1).
b. Roads shall have a travel way width of 12’. Any deviation must be approved by the
Contracting Officer (CO).
c. Shall be compacted with water and compaction effort such that the surface is a hard smooth durable surface.
303.04 Drainage. Grade the ditches to the typical sections (Figure 2) and construct new furrow ditches where required to maintain ditch drainage or as directed by the Contracting Officer (CO).
303.06 Compaction. Shape and compact the traveled way and shoulders using one of the methods described in Subsection 204.11.
303.10 Payment. The accepted quantities will be paid at the price per unit of measurement for the
Section 303 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.
Figure 2 - Typical Furrow Ditch