Form C - Bidder Price Response.pdf
PDF 84 KB Posted
- Solicitation number
- BD-27-1206-40000-40000-132307
- Issued by
- Massachusetts
About this file
This is a Bidder Price Response Form for RFP 103-26 Fire Alarm Maintenance, Service and Repair with the Massachusetts Bay Transportation Authority (M.B.T.A.). The procurement is for comprehensive testing, repair, and maintenance services of the M.B.T.A.'s fire alarm systems over a three-year contract term. All work must comply with the Notice to Bidders and Technical Specification F-1 accompanying the proposal. Bidders must submit responses for all line items to be considered responsive, as the contract will be awarded in its entirety.
The pricing response consists of four itemized components: Item 1 requires a total monthly testing fee multiplied by 12 months across the three-year term; Item 2 addresses additional services for repair, upgrade, and maintenance at an hourly rate applied to 3,640 estimated hours per year over three years; Item 3 covers overtime calls at an hourly rate applied to 1,456 estimated hours per year over three years; and Item 4establishes an additional parts allocation of $75,000 annually totaling $225,000 over the three-year period. Items 2, 3, and 4 are designated as estimates subject to operational needs with no guaranteed quantities, though all quoted prices must remain firm throughout the contract term. The basis of award is the sum of all four items.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form C - Pricing Response
The undersigned proposes to furnish all supervision, labor, parts, equipment, and materials to test, repair, and maintain the M.B.T.A. Fire Alarm Systems. This shall be in strict accordance with the Notice to Bidders and Technical Specification F-1 that accompanied this proposal.
Item 1: Total Monthly Testing Fee x 12 months x 3 years = $ ____________
Item 2: Additional Services - Repair / Upgrade / Maintain
Hourly Cost $________ x 3640 hours per year x 3 years = $ __________
Item 3: Overtime Calls
Hourly Cost $_______x 1456 hours per year x 3 years = $ _____________
Item 4: Additional Parts
$75,000 per year x 3 years = $ 225,000.00
BASIS OF AWARD IS ITEM 1+ ITEM 2 + ITEM 3 + ITEM 4 = $______________
A. It is understood and agreed that Item 2,3, and 4 are estimates and will depend upon operational needs and that the Authority does not guarantee these quantities.
B. It is understood and agreed that the quoted prices, designated as Item 1,2,3,and 4, will remain firm for the contract term.
C. The contract will be awarded in its entirety, therefore, incomplete bids will be considered unresponsive.