FMO26281 HVAC Upgrade - Mini Split Installation Westfield AASF #2 (MA National Guard)
Solicitation number
BD-27-1069-MILDV-10000-135319
Issued by
Massachusetts

About this file

This is a Scope of Work acceptance form for a state and local contract opportunity involving the Massachusetts Army National Guard Construction Facilities Management Office (CFMO) for an HVAC upgrade project at the Westfield facility (AASF#2, Facility Number 25D10, Project Number FMO26281). The project requires installation of two 5-ton outdoor compressor/condenser units with eight indoor air handlers to provide heating and air conditioning to four rooms: GSE Room #903 (25'x40', A/C only), Supply Room #301-302-303 (40'x50', A/C only), Sheet Metal Shop Room #202 (30'x50', heat and A/C), and Engine Repair Shop Room #206 (50'x25', heat and A/C). All rooms feature 17' to 20' sloped/open ceilings. The awarded contractor must conduct a thorough site assessment, install refrigerant lines, electrical communications wiring, condensate drains, and power supplies while adhering to OSHA and Massachusetts State construction and safety regulations. The contractor must also perform comprehensive testing, restore disturbed surfaces, properly dispose of debris, and provide detailed installation documentation and maintenance guidelines. Site visits require a Real ID or US Passport, with standard working hours from 7:30 AM to 3:30 PM, coordinated through the CFMO representative and site Operations Manager. The contractor must submit a detailed project schedule in PDF format and conduct a final walkthrough prior to project commencement.

The estimated project cost is $55,000. The equipment must utilize R-454B refrigerant and comply with all State and Federal environmental regulations. Warranty requirements mandate a minimum of five years for compressors and sealed system components, and one year for all other parts and labor, commencing upon final CFMO acceptance of successful installation, testing, and startup. The project involves secure outdoor mounting with protective bollards, weather-tight seals, and proper condensate drainage to prevent water damage. No set-asides are indicated in the document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW Acceptance Form

Project_________________________________________ Project Number:__________

Location:_______________________________________ Facility Number:__________

Problem // Issue Description

Scope of Work:

POC Name/Email/Phone:_______________________________________

Initial Qualifications: ________________________________________

Estimated Project Cost: ______________

Environmental State Quartermaster (If State-Share) CFMO Approved

Approve Approve Approve

Hold Hold Hold

*Share with Chief Procurement officer for Review.

Project: HVAC Upgrade - Mini Split Installation
Project Number: FMO26281
Location: AASF#2 - Westfield
Facility Number: 25D10
Problem Issue Description: The Engine Repair Shop and the Sheet Metal Shop are lacking heat and A/C, while the Supply and GSE Rooms are lacking A/C. These shops currently lack adequate climate controls which poses significant risk to the operation and preservation of critical equipment and the health and safety of site personnel. The issue may also negatively impact operational readiness.
Scope of Work: Awarded contractor shall conduct a thorough site assessment to understand the existing conditions and requirements for the installation of two (2) 5-Ton outdoor Compressor/Condenser Units supporting multiple (8) indoor air handlers. One Unit will support both heat and A/C while the other will support A/C only. All supporting Refrigerant Lines, Communication Wiring (electrical), Condensate Drains and Power Supplies are to be included in the assessment. All work must follow OSHA and MA State construction and safety regulations. Room sizes and requirement details as follows:

GSE Room #903 – 25’x40’ (A/C only).

Supply Room #301-302-303 (all one room) – 40’x50’ (A/C only).

Sheet Metal Shop Room #202 – 30’x50’ (heat and A/C).

Engine Repair Shop Room #206 – 50’x25’ (heat and A/C).

All rooms have 17’ to 20’ sloped/open ceilings.

Contractor will ensure that the units are of a reputable brand, utilizing R-454B refrigerant and are compliant with all State and Federal Environmental regulations.

Contractor will ensure safe and secure physical (outdoor pad) mounting of each unit along with the installation of protective bollards.

Contractor will ensure weather-tight seals preventing air and water leakage.

Contractor will ensure proper condensate drainage for each unit to eliminate water damage.

Contractor will ensure proper and safe electrical connections for each unit that meet all City, County and State codes.

Contractor will perform thorough testing of each unit to confirm proper operation and heating/cooling performance including; heating/cooling output verification and refrigerant charge validation.

Contractor will restore any disturbed surfaces to their pre-installation condition (walls, ceilings, insulation etc).

Contractor will ensure that all debris, packaging and any other associated items are properly disposed of in accordance with State and Federal regulations.

Contractor will provide all detailed installation documents, operations manuals, warranty information and preventative maintenance guidelines.

Warranty requirements must include at least five (5) years for the Compressors and all other sealed system parts, and one (1) year for all other parts and labor. Warranty period will commence upon final CFMO acceptance of successful installation, testing and start up.

Contractor will coordinate with the Massachusetts Army National Guard (MAARNG) Construction Facilities Management Office (CFMO) to schedule a site visit. A Real ID or US Passport will be required in order to enter this site.

Standard site working hours are from 7:30AM through 3:30PM. Daily access will be coordinated with the CFMO representative and the site Operations Manager.

Selected Contractor will submit a detailed project schedule to the CFMO in PDF format, and perform a final walk through with the CFMO representative and the site Operations Manager prior to starting the project.

POC NameEmailPhone: Brian Hicks <brian.s.hicks10.nfg@army.mil>
Initial Qualifications:
Estimated Project Cost: $55,000