FMO26224 Pump House Roof SOW.pdf
PDF 46 KB Posted
- Solicitation number
- BD-27-1069-MILDV-10000-135511
- Issued by
- Bristol County, Massachusetts
About this file
This Statement of Work (SOW) is issued by the Massachusetts Army National Guard (MAARNG) for a pump house roof replacement project at the Rehoboth Armory. The project involves the complete removal and replacement of the existing roof (approximately 27' x 17') due to age, weather damage, and water leaks that interfere with system performance. The scope of work includes all permitting, labor, materials, equipment, and supervision necessary to remove and dispose of the existing roofing and rafters (to be treated as asbestos-containing material); furnish and install new decking, blocking, and finger joint pine trim; install new insulation or recovery board; and install a new 0.060 PVC adhered membrane roofing system with a 20-year materials and labor warranty from the manufacturer. Work will be performed at 13 Fire Tower Road, Rehoboth. Contractors must attend a mandatory site assessment walk-through with the Point of Contact (Brian Hicks) or Construction Facilities Management Office (CFMO) representative prior to submitting a proposal. The estimated project completion timeline is no more than 12 weeks from the project award date. Contractors must submit a firm, fixed-price proposal in PDF format that includes a detailed project schedule with key milestones and completion dates.
The estimated project cost is $65,000, with pricing that includes a $15,000 asbestos abatement cost if necessary. The scope includes comprehensive asbestos-containing material (ACM) remediation services, requiring the contractor to conduct a pre-demolition survey with sampling and analysis by a Massachusetts Division of Labor Standards certified Asbestos Inspector. All suspect bulk samples must be submitted to an AIHA and NVLAP accredited laboratory for analysis using Polarized Light Microscopy with Dispersion Staining methodology, with results available within 72 hours. The contractor is responsible for removal and disposal of all excess and scrap materials in accordance with Local, State, and Federal Regulations. No set-asides are indicated in this solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bidders Instructions Pumphouse Roof Replacement Rehoboth Armory.pdf | ||
| Non-Collusion 1~54.pdf | ||
| Authorized Signatory1.pdf | ||
| FMO26224 FORM FOR GENERAL BID.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW Acceptance Form
Project_________________________________________ Project Number:__________
Location:_______________________________________ Facility Number:__________
Problem // Issue Description
Scope of Work:
POC Name/Email/Phone:_______________________________________
Initial Qualifications: ________________________________________
Estimated Project Cost: ______________
Environmental State Quartermaster (If State-Share) CFMO Approved
Approve Approve Approve
Hold Hold Hold
*Share with Chief Procurement officer for Review.
| Project: Pumphouse Roof Replacement |
| Project Number: FMO26224 |
| Location: MAARNG Armory Rehoboth |
| Facility Number: 25178 |
| Problem Issue Description: The scope covered by this Statement of Work (SOW) consists of the removal and replacement of the Pump House Roof (roughly 27'x17') due to a combination of age, weather damage and leaks. Water leaks from the damaged roof can leak onto the system, freeze and interfere with system performance |
| Scope of Work: The work shall be conducted by Contract. The work performed by the Contractor shall include all permitting, labor, materials, equipment, and supervision necessary to remove and dispose of the existing roofing and rafters (treat as asbestos containing material); furnish and install new decking and blocking; replace existing trim with finger joint pine; furnish and install new insulation or recovery board for structure; furnish and install new .060 PVC adhered membrane roofing system; furnish and install heat weldable material and; upon completion, roofing manufacturer will issue a 20 year materials and labor warranty. Work to be performed at the Rehoboth Army National Guard Armory (13 Fire Tower Road). Work will include but is not limited to: a firm proposal |
that is approved by the designated Construction Facilities Management Office (CFMO) representative, permitting, site preparation, any required fabrication, removal/disposal of the existing roof and installation of the new roof as noted above. The Contractor will be responsible for the removal and disposal of any and all excess/scrap material in accordance with (IAW) Local, State, and Federal Regulations. The contractor shall provide a detailed project schedule outlining key milestones and completion dates in a PDF format. Estimated Project Completion shall be no more than 12 weeks from Project Award date. Attendance for a site assessment (walk-through) will be required for any Contractor submitting a proposal. The site assessment shall be conducted with the POC and/or CFMO representative. When submitting the proposal, provide a firm, fixed price for the removal and disposal of the old roof and installation of the new one, inclusive of all permitting, labor, materials, equipment, and overhead costs.
ACM Remediation:
Contractor will perform an evaluation of the building to identify the presence of Asbestos Containing Material (ACM) that may impact construction, quantify the volumes and locations of hazardous materials, provide options for addressing the hazardous materials, and provide permitting obligations, cost estimates, coordination issues and abatement timelines. Specified details regarding the proposed scope of services are presented below.
A) Collect representative samples of all accessible materials along with additional samples of materials suspected to be ACM. Suspected ACM will be quantified and classified according to:
1. Type (e.g. surfacing, thermal system insulation and/or miscellaneous.
2. Encapsulated material, condition (good, fair, poor) and
3. Potential to become disturbed.
B) Document all findings on a Potential ACM Inventory Sheet. Accessible suspect building materials will be sampled and analyzed using standard procedures and methodologies.
C) The building survey will be conducted by a Massachusetts Division of Labor Standards certified Asbestos Inspector(s) to satisfy the inspection requirements of 40 CFR Part 61.
D) Collected suspect bulk samples will be submitted under a chain‐of‐custody to an American Industrial Hygiene Association (AIHA) and National Voluntary Laboratory Accreditation Program (NVLAP) accredited and federal and state licensed laboratory for Polarized Light Microscopy with Dispersion Staining (PLM/DS) analysis in accordance with the Environmental Protection Agency (EPA) "Interim Method for the Determination of Asbestos in Bulk Insulation Samples" (EPA‐600/4‐82‐020). Analysis will be performed under a 72‐hour turnaround time.
E) Upon completion of Pre‐Demolition Survey activities and receipt and review of laboratory results, a final report will be prepared summarizing the investigation findings. The final report will include laboratory results, locations of ACMs, LBPs, and Regulated Materials identified. The final report will also include tables quantifying ACM, LBPs, and Regulated Materials, as well as costs estimates for the removal of identified materials
| POC NameEmailPhone: Brian Hicks <brian.s.hicks10.nfg@army.mil> |
| Initial Qualifications: Pricing includes $15K Abatement cost (if nec) |
| Estimated Project Cost: $65,000 |
| Check Box1: Off |
| Check Box2: Off |
| Check Box3: Off |
| Check Box4: Off |
| Check Box5: Off |
| Check Box6: Off |