FLYINGFISH (WPB 87) Sewage and Grey water Specifications.pdf
PDF 128 KB Posted
- Solicitation number
- 70Z028-23-Q-0000082
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 87-WPB_601_1_1_-_R Drawing.pdf | ||
| Commercial Supplies and Services Clauses Provisions FAC 2022-04.doc | DOC document | |
| 15-4543.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC FLYINGFISH (WPB-87) DOCKSIDE AVAILABILITY FY2023
18 (REV-1)
59301_ESD_0921_FLT
REC_59301_FLT_87’ WPB (ALL) (1017)
WORK ITEM 1: Grey Water Holding Tanks, Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – TANKS
TYPE OF TANK LOCATION CAPACITY - 95% (gallons) LOW SUCTION (Gallons)
Grey Water (stainless steel, uncoated)
Below Hold Deck between Frames 8 and 9, 3-7-1-W
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
19 (REV-1)
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.3.1 Plug all inlet and outlet piping in the tank(s) to prevent contaminants from entering. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Piping.
Pump(s).
Stateroom berthing locker.
Toilet (to be removed by CG personnel).
Speed log.
3.2 Plug log. The Contractor must keep a written record of all plugs put in any tank vents. A separate list must be kept for each tank being entered.
3.2.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.2.2 The plug log must be available to the Coast Guard Inspector when the inspector is performing his close-out inspection on each tank.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.3 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.4 Service disruption. When grey water is disrupted due to Contractor repairs, the Contractor must refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.
3.5 Cleaning. The Contractor must accomplish the following for the tank(s) listed. The Contractor must refer to Coast Guard Drawing 87 WPB 601-001 for guidance.
3.5.1 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations
3.5.2 Cleaning requirements. Remove manhole cover(s). Clean all tank structure’s interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths.
Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all
20 (REV-1)
Federal, state, and local regulations. Clean all tank vent lines. Remove and clean the eductors and level switches inside of the tank(s). Reinstall the eductors and level switches upon completion of tank cleaning.
Use new gaskets and o-rings to install/reinstall all removed/disturbed components.
3.6 Inspection. The Contractor must visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit the “Tank and Void Assessment Form” via CFR (see paragraph 4.2 of the Work Item titled “General Requirements”). Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:
Tank structural condition.
Inaccessible areas.
Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (not applicable for stainless steel tanks).
Tank level indicator (TLI), vacuum and/or float switch condition.
Suction and discharge piping and vent line condition.
Fastener material (stainless steel) and condition.
Zinc anode condition (remaining percentage).
3.7 Control panel assembly. The Contractor must open and vacuum clean the control panel assembly.
Inspect the control panel assembly for any indications of overheating or loose wiring or connections.
Submit a CFR
3.8 Closing. The Contractor must notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330.
3.8.1 Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Existing undamaged fasteners may be reused. For purpose of bid, assume 10% of existing fasteners will require renewal. Renew all nylon insert/nylock nuts.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.9 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.9.1 The Contractor must adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.
3.9.2 The Contractor must verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.
3.9.3 Upon completion of testing and, in the presence of the Coast Guard Inspector, the Contractor must pump tank(s) to the limit of the ship’s installed pumps.
21 (REV-1)
4. NOTES
This section is not applicable to this work item.
22 (REV-1)
59302_ESD_0922_FLT
REC_59301_FLT_87’ WPB (ALL) (1017)
WORK ITEM 2: Sewage Holding Tanks, Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – TANKS
TYPE OF TANK LOCATION CAPACITY - 95% (gallons) LOW SUCTION (Gallons)
Sewage (stainless steel, uncoated) Hold Deck between Frames 6 and 8, 3-7-0-W 363
1.2 Government-furnished property.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
23 (REV-1)
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.3.1 Plug all inlet and outlet piping in the tank(s) to prevent contaminants from entering. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Piping.
Pump(s).
Stateroom berthing locker.
Toilet (to be removed by CG personnel).
Speed log.
3.2 Plug log. The Contractor must keep a written record of all plugs put in any tank vents. A separate list must be kept for each tank being entered.
3.2.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.2.2 The plug log must be available to the Coast Guard Inspector when the inspector is performing his close-out inspection on each tank.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test - initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.4 Service disruption. When sewage collection service is disrupted due to contractor repairs, the Contractor must refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.
3.5 Cleaning and inspection requirements. The Contractor must accomplish the following for the tank(s) listed in paragraph 1.1 (Intent), referring to Coast Guard Drawing 87 WPB 601-001 for guidance:
3.5.1 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations
3.5.2 Cleaning requirements. Remove manhole cover(s). Clean all tank structure’s interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths.
Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations. Clean all tank vent lines. Remove and clean the eductors and level
24 (REV-1)
switches inside of the tank(s). Reinstall the eductors and level switches upon completion of tank cleaning.
Use new gaskets and o-rings to install/reinstall all removed/disturbed components.
3.5.3 Inspection. Visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.
Submit the “Tank and Void Assessment Form” via CFR (see paragraph 4.2 of the Work Item titled “General Requirements”). Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:
Tank structural condition.
Inaccessible areas.
Condition of tank coating, including measurements, percentage, location, and type of coating failure (not applicable for stainless steel tanks).
Tank level indicator (TLI), vacuum and/or float switch condition.
Suction and discharge piping and vent line condition.
Fastener material (stainless steel) and condition.
Zinc anode condition (remaining percentage).
3.5.4 Control panel assembly. Open and vacuum clean the control panel assembly. Inspect the control panel assembly for any indications of overheating or loose wiring or connections. Submit a CFR
3.6 Closing. The Contractor must notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330.
3.6.1 Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Existing undamaged fasteners may be reused. For purpose of bid, assume 10% of existing fasteners will require renewal. Renew all nylon insert nuts.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.7 Operational test, post repairs. After completion of work, the Contractor must accomplish the following in the presence of the Coast Guard Inspector, and submit a CFR:
3.7.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.
3.7.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.
3.7.3 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tank(s) to the limit of the ship’s installed pumps.