firing-range-lead-maintenance-tasks_.pdf

PDF 59 KB Posted

Attached to
Pittsburgh Bureau of Police Firing Range Lead Remediation
Solicitation number
2022-IFB-291
Issued by
Allegheny County, Pennsylvania

About this file

This document details the Firing Range Lead Maintenance Tasks for the Pittsburgh Bureau of Police Firing Range Lead Remediation project, involving comprehensive lead recovery and site restoration services. The scope of work is divided into three primary phases: (1) Mobilization, Site Set-Up, and Plan Preparation, which includes site access control, utility location, and necessary permit acquisition; (2) Excavation, Screening, and Recycling, involving soil excavation from the backstop berm to a depth of 0.5-3.0 feet, screening 80-90% of lead bullets and fragments larger than 1/4"-3/8", and shipping recovered lead to a licensed recycler; and (3) Range Restoration, which includes returning screened soil to the original berm, reshaping the landscape, and reinstalling a two-course railroad-tie retaining wall.

The project includes a unique financial component where the contractor will provide the customer with lead transport documentation, a recycling certificate, and a minimum of 50% of the recycled lead's value. Additional specifications require careful site management, including preparing work, health & safety, and waste management plans, establishing temporary site access, and decontaminating equipment before demobilization. The project appears focused on environmental remediation and lead recovery at the Pittsburgh Police Department's firing range, with an emphasis on thorough material processing, recycling, and site restoration to the original landscape configuration.

View the file

Other files

File Type Posted
Pittsburgh_Bureau_of_Police_Firing_Range_Lead_Remediation.pdf PDF
firing-range_2.JPG JPG image
firing-range_3-aerial.png PNG image
firing-range_1.JPG JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRING RANGE LEAD MAINTENANCE TASKS

I. MOBILIZATION, SITE SET-UP, AND PLAN PREPARATION

• Mobilize personnel and equipment to project site

• Prepare work plan

• Prepare health & safety plan

• Prepare waste management plan

• Complete site walk-through with customer representative to confirm excavation processing areas

• Establish temporary access, site access control, and traffic control; place appropriate signage

• Set up processing area and equipment

• Obtain approvals and permits as necessary (City can provide city fee waiver forms.)

• Locate utilities

• Vegetation removal if applicable

• Protect or remove railroad-tie retaining walls if applicable

II. EXCAVATION, SCREENING, AND RECYCLING

• Excavate estimated depth of 0.5-3.0 feet of soil from the backstop berm or deeper if the concentration of bullets appears economically feasible to recover at deeper depths

• Screen 80%-90% or more (weight percent) of the lead bullets & bullet fragments greater than 1/4"-3/8" from the lead-impacted range materials

• Contain and securely store recovered lead for shipment

• Ship recovered lead to a licensed lead recycler

• Provide customer with lead transport documentation, certificate of recycling, and a minimum of 50% of the value of the recycled lead

III. RANGE RESTORATION

• Return screened soil to original berm

• Replace oversized materials to range at a mutually agreed-upon location as necessary

• Re-install processed soils on the main berm and backstops, reshape to mirror original slope.

• Supplement soil for backstop berm as needed

• Purchase and install two-course railroad-tie retaining wall along the bottom of the backstop berm on the main berm.

• Decontaminate equipment before demobilization