Firing Range combined Synopses_Solicitation.pdf

PDF 2 MB Posted

Attached to
Indoor Firing Range Comprehensive Abatement and Follow-up Abatement
Solicitation number
47PH0821R0002
Issued by

View the file

Other files

File Type Posted
Questions and Answers.pdf PDF
Picture 1.pdf PDF
Picture 4.pdf PDF
Picture 3.pdf PDF
Picture 5.pdf PDF
Drawing.pdf PDF
Picture 2.pdf PDF
Past Performance Form.pdf PDF
SF1449 Indoor Firing Range Abatement.pdf PDF
Price proposal.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Indoor Firing Range Comprehensive Abatement and Follow-up Abatement John Shaw U.S. Courthouse

1 | P a g e

Indoor Firing Range Comprehensive Abatement and Follow-up Abatement

John Shaw U.S. Courthouse

Lafayette, Louisiana

COMBINED

SYNOPSES/SOLICITATION

TECHNICAL AND PRICE PROPOSAL DUE

4:00 PM CST, January 28, 2021

2 | P a g e

TABLE OF CONTENTS

Attention to Offeror

Statement of Work…

Clauses and Provisions

Evaluation Factors for Award…

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.

3 | P a g e

ATTENTION TO OFFEROR

The U. S. General Services Administration (GSA), Region 7 is procuring Indoor Firing Range

(IFR) Comprehensive Abatement and Follow-up Abatement at John Shaw U.S. Courthouse IFR in Lafayette, LA. This requirement will be a Total Small Business set-aside. The contractor shall provide all labor, personnel, management, supervision, materials, supplies, and other items or services necessary to provide IFR Comprehensive Abatement and Follow-up Abatement. The

Government will award a contract resulting from this combined synopses/solicitation to the responsible offeror with the Lowest Price Technically Acceptable (LPTA) offer that conforms to the solicitation on a "Pass" or "Fail" basis. The NAICS Code is 562910 (Remediation Services) and the size standard is $20.5 Million.

Proposals are due by 4:00P.M. (CST) on January 28, 2021 and shall be submitted via email to

Trevor Simon, Contracting Officer (CO) at trevor.simon@gsa.gov. No paper copies of the solicitation will be distributed. All offerors will be responsible for obtaining the solicitation and any subsequent amendments from beta.sam.gov.

Electronic Submission of Proposals: Offers must be received by the email address of the GSA

Point of Contact (POC) listed herein on or before the date and time established for receipt of offers. The date and time of receipt will be established according to the Government computer system’s documentation showing the exact official time of receipt by the GSA POC listed herein and not by the time the electronic proposal was sent by the Offeror or received by the GSA server. It is the Offeror’s responsibility to ensure proposals are complete and submitted early enough to be received by the GSA POC before the deadline, and to confirm receipt before the deadline. Proposals or portions of proposals which are received by the GSA POC later than the time noted within will be rejected and will not be considered.

NOTE: The maximum file size is 25 MB. GSA has occasionally experienced delays in delivery of emails from the GSA server to an email account. Therefore contractors/offerors need to plan accordingly.

WARNING: Consistent with GAO case law on the issue of “late-is-late rule” related to electronically submitted proposals, GSA will strictly comply with and enforce FAR 52.215-

1(c)(3)(ii)(A). Pursuant to GAO’s application of FAR 52.215-1(c)(3)(ii)(A), an electronically submitted proposal that is received late will not be considered unless (1) it is received before award is made, (2) the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition and (3) it was received at the initial point of entry to the

Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals. FAR 52.215-1 (c)(3)(ii)(A)(1).

In accordance with 13 CFR 125.6, in order to be awarded a small business set-aside contract, a small business concern must agree that the concern will perform at least 50 percent of the cost of the contract incurred for personnel with its own employees.

mailto:trevor.simon@gsa.gov

4 | P a g e

Any and all questions regarding this solicitation shall be submitted via email to the CO, at trevor.simon@gsa.gov. It is the potential offer’s responsibility to monitor these avenues for release of any future amendments to the solicitation.

Please read the entire solicitation. The following information is highlighted for your attention:

1. This solicitation number 47PH0821R0002 is issued as a Request for Proposal (RFP).

2. The solicitation document incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2020-02 (AUG 2020).

3. This will be a total small business set-aside with NAICS Code 562910 (Remediation Services) and the size standard of $20.5 Million.

4. Be sure to read FAR Provisions 52.212-1 Instructions to Offerors – Commercial Items and 52.212-2 Evaluation – Commercial Items.

5. Prime Contractor/Subcontractor Arrangement and/or Contractor Team Arrangement

(CTA) - Offerors shall identify any contractor teaming arrangement(s) or Prime

Contractor/Subcontractor Arrangement(s) in their offer. The Offeror must clearly explain the portion of effort to be performed by each contractor. If a CTA is to be used, the Offeror must provide a signed copy of the CTA with their offer.

6. All contractor personnel working under this contract must be U.S. Citizens with no felony convictions.

7. Site visit will ONLY be conducted on at10:00 A.M. (CST) on January 13, 2021.

8. All questions regarding this solicitation are due no later than January 20, 2021.

9. Offers must be received by 4:00 P.M. (CST) on January 28, 2021 along with signature on all amendments to this solicitation.

SUBMIT TECHINCAL AND PRICE PROPOSALS to: trevor.simon@gsa.gov.

mailto:%20trevor.simon@gsa.gov.

mailto:%20trevor.simon@gsa.gov.

5 | P a g e

STATEMENT OF WORK

Indoor Firing Range (IFR) Comprehensive Abatement and

Follow-up Abatement

John Shaw U.S. Courthouse

800 Lafayette Street

Lafayette, Louisiana (LA) 70501

7/08/2020

1. SUMMARY

The Contractor shall furnish all necessary labor, material, equipment, travel, and supervision to accomplish the following work for the General Services Administration (GSA), at the John Shaw

U.S. Courthouse, 800 Lafayette Street, Lafayette, LA 70501. All work shall be performed in accordance with the following specifications.

Contractor shall visit the site and perform a thorough site inspection. The contractor shall inspect the site to become familiar with the existing conditions relating to the work to be performed and the difficulties and restrictions to the work to be performed.

The base and options includes all comprehensive abatement, preventative maintenance and testing services in accordance with Statement of Work (SOW). A follow-up abatement shall be performed six months after the completion of the comprehensive abatement.

The Government reserves the right to order none or any combination of the line item. No minimum quantity for the line item is guaranteed by the Government.

2. SCOPE

ABATEMENT:

A. Comprehensive and Follow-up Requirements

All abatements, maintenance, equipment specifications (including quantity, type, and manufacturer’s specifications of filters in place) shall be documented by the Range Master in the IFR Maintenance and Report Log book.

All Comprehensive Maintenance and IFR cleaning personnel shall be trained and certified in accordance with regulatory lead hazards and Comprehensive Maintenance personnel shall also be trained and certified in accordance with applicable local environmental cleanup requirements.

The IFR ventilation system shall be on during all maintenance and cleanings.

Place walk-off sticky mats just outside of all access/exit doors to the IFR.

Collect spent brass shells in 2 to 5 gallon sealable bucket(s) labeled “brass only”. Collect spent lead in 2 to 5 gallon sealable bucket(s) labeled “lead only”. Store buckets in a secure area (i.e. bullet trap room if available) until the disposal/recycling pickup.

Inspect, clean and maintain firearm accidental discharge clearing trap per manufacturer’s recommendations.

6 | P a g e

Abatement of the range areas will be done in a sequential manner to minimize the spread of dust (i.e. from clean to less clean - start cleaning from the control room side moving towards the backstop and backstop access area.

Wet wipe with a lead specific cleaner all surfaces in the firing range, control room, gun cleaning area, storage room, secured storage room, and backstop service room (if present) including; but not limited to walls, baffles, ceilings, firing lane partitions, target rails, backstop, bullet trap, doors and knobs, light switches, countertops, shelves, exhaust filter frames/housings, ducting, etc.

Floors and surfaces that are not smooth and, consequently, cannot be wet wiped shall be

HEPA vacuumed. This will include all noise reduction insulation (i.e. walls and ceiling).

HEPA vacuum all areas within 15 feet outside of bullet trap access door and any range exit doors.

Verify that all alarms and fan interlocks are working properly and document any issues on Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement notes section.

Inspect signage, lighting, targeting systems, storage areas, and cleaning facilities associated with the IFR. Repair if possible, any signage, lighting, storage areas, and cleaning facilities.

Clearly document any identified damage or items needing repair on Table 4 - Inspection

Checklist for Post-IFR Comprehensive and Follow-up Abatement notes section.

Steel type bullet trap/collector Type Backstop (if applicable) o Inspect the baffles and the steel bullet backstop and trap and/or Granular Rubber.

Apply thin coat of all-purpose oil to primary impact surface of bullet trap.

o Note any missing parts, chips, cracks, or dents larger than 2 inches or stray bullet holes.

o Report any damage on Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement notes section and to the Project Manager (PM)/Contracting Officer Representative (COR).

Dura Block Type backstop (if applicable) o Inspect the Granular Rubber for excessive damage, o Replace heavily damaged Granular Rubber, and o Move lightly to moderately damaged Granular Rubber to perimeters of backstop.

Completion of IFR HVAC System Evaluation and Maintenance (Comprehensive Maintenance Only). This task will only be incorporated if there is no other IFR HVAC maintenance program in place (i.e. GSA). (Refer to Table 6 - HVAC Annual Maintenance Tasks and Table 7 - HVAC Filter Change-Out Maintenance Tasks).

IFR Exhaust Filters (Comprehensive maintenance Only) o Determine the pressure drop for each filter level including pre-filter and HEPA filter.

o If there are no pressure sensors installed to measure pressure differential before/after filter levels, sensors must be installed or portable monitors used.

The installed pressure sensors shall feed to the DDC of the IFR (if applicable).

If only one (1) pressure differential sensor is installed to measure the pressure drop of both the pre-filters and final filters and the pressure drop is significant, replace the pre-filters and check full pressure drop of both filter sections combined.

o Measure full volumetric exhausted airflow (cfm).

Calculate airflow (cfm) for each HEPA filter. Use this number to compare to filter manufacturer’s pressure drop vs. airflow volume to determine

7 | P a g e change out requirements.

o Replace HVAC filters (pre-filters and/or HEPA) only if there indicates a pressure drop more than twice the manufacturer’s pressure drop for the designed air flow (i.e. 1” wg @ 2400 cfm for HEPA filters).

o Filters requiring replacement per above will be replaced by GSA-furnished filters that meet the specifications of USMS Publication 64, Section A10.2. The filters shall consist of a pre-filter stage of a minimum MERV 8 rating followed by a final filtration stage.

Final HEPA filter(s) shall have a minimum MERV 17 rating (99.97% capture efficiency at 0.3µ IEST type A).

o Wet wipe the inside of the exhaust filter housing if potential exists for contamination

B. Verification of Comprehensive Abatement and Follow-up Abatement

The contractor is responsible to provide services of an independent Certified Industrial Hygienist

(CIH) to conduct proper surface sampling protocol to complete the following:

Collect surface wipe samples based upon the table below, as a minimum of 15 locations and an adequate quantity of Quality Assurance/Quality Control samples.

Sampling locations and sample results criteria are detailed in table 1.

Send all samples for analysis to a laboratory approved by the American Industrial Hygiene

Association and recognized by the National Lead Laboratory Accreditation Program

(NLLAP) as being proficient in lead in dust analysis.

Surface contamination by lead shall be evaluated using ASTM E1728-03 methods.

Abatement Criteria: If any of the wipe sample analyses indicate levels exceeding the clearance standard as described in the above table, the Contractor shall clean that area again where those surface samples were taken and have the surfaces sampled again by the

Independent Air Monitor Consultant and verified until the clearance standards are met.

C. Measurements and Evaluations (Comprehensive Only)

The contractor is also responsible to provide services of a CIH to conduct proper airflow and pressure measurements and evaluations based upon applicable protocol to complete the following:

Measure and document all pressure differentials (pd) between the different zones (as applicable by IFR design) using as a reference, the Figure 1 – Indoor Firing Range Top-view

Zones, Sensor and Vent Locations as an example of pd reading locations. Record these pd’s on the Figure 2 – Lead Sample References, Sampling Locations and PD Template and include in final report.

Measure and document airflows using procedures described in the following section.

Document and/or sketch those tests for 1) each lanes respective three firing positions, 2) mid-lane locations, midway between firing lines and bullet trap for each firing lane, and 3) mid-lane locations within 6 feet of front of bullet trap for each firing lane and document the results in the Figure 3 – Air Flow Pattern and Velocity Templates and include in final report.

Evaluate and document air flow patterns at each lane’s respective three (3) firing positions.

It is mandatory to lock out tag out all potential energy sources which may cause the exhaust fans to turn on while workers are in the fan housing.

8 | P a g e

Document those results on Figure 3 – Air Flow Pattern and Velocity Templates and include in final report.

Verify that all alarms and fan interlocks are working properly and document any issues on the Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement.

Inspect signage, lighting, targeting systems, storage areas, and cleaning facilities associated with the IFR. Repair if possible any signage, lighting, storage areas, and cleaning facilities.

Clearly document any identified damage or items needing repair on the Table 4 - Inspection

Checklist for Post-IFR Comprehensive and Follow Up Abatement notes section.

Complete, initial and sign Table 4 - Inspection Checklist for Post-IFR Comprehensive and

Follow-up Abatement.

D. Air Pathway Testing and Airflow Velocity Procedures (Comprehensive Only)

Smoke testing and airflow velocities of the lane’s shooting positions shall be conducted in a standard procedure. The following procedures shall be followed as closely as possible:

Sampler shall position their bodies as would a shooter at each lane and each of the three shooting positions – standing, kneeling, and prone.

The sampler shall locate the smoke generator at the locations where the guns will be discharged (i.e. hold smoke generator with arms outstretched in front of shooter for approximately 10 seconds) for each of the locations and positions listed in #1 above. Allow for normalization of position (about 10 seconds) before recording smoke movement in sketch.

Please provide a sketch of the smoke movement from each lane and the 3 positions.

o Ideal sketch will use three colors, one color each for the shooters/samplers positions.

o Green color indicating standing position, blue indicating kneeling position, and red indicating prone position.

o Smoke movement lines should be sketched onto the diagrams provided.

o These sketched lines should start on the diagrams from the shooting location (estimate) and be drawn through to the perspective where the smoke disappears or becomes too diluted to observe. The length of the sketched lines should proportionally estimate the actual length and direction(s) the smoke traveled onto the provided diagram (i.e. a 4’ actual is equal to about 1/2” on diagram).

Record airflow velocities (fpm) in the breathing zone of the shooter (or sampler) for each of the lanes/positions indicated in #1 above. Breathing zone is identified as within approximately 1 foot of the nose/mouth, preferably to the side in this case.

Downrange airflow velocities (fpm) (mid-range and in front of backstop) should be taken in the middle of each lane, approximately midway from the floor to the bottom of the ceiling baffles.

Supply air volumetric measurements (cfm) should be taken at the outside air supply vent using applicable procedures for accurate measurements.

Exhaust air volumetric measurements (cfm) should be taken at the final outside air exhaust vent using applicable procedures for accurate measurements.

o If this is not a single pass HVAC system (i.e. with return air ducting, shared ventilation with other areas, etc.) please note on Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement notes section.

9 | P a g e

E. Final Comprehensive Maintenance Report

The contractor must submit a final report package to the PM/COR using Attachment A. The

PM/COR shall provide the local USMS representative (i.e. Range Master) and the USMS HQ

OSSH’s IFR Coordinator, the following information prior to allowing use of the firing range.

The firing range shall not be used until approval by authority of the USMS HQ as represented by final signature on the Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up

Abatement. Copies of the following shall be maintained in the sites Maintenance Log.

Tasks completed.

Completed and fully approved and signed Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement including condition of the baffles, bullet trap, lighting, alarms, fan interlock, targeting system, etc., Sample reference and sampling locations documented on Figure 2 – Lead Sample References, Sampling locations and PD Template.

Laboratory certifications along with final samples analyses report.

Pressure differential readings for each zone while ventilation is operating documented on Figure 2 – Lead Sample References, Sampling Locations and PD Template.

CIH completed Figure 2 – Lead Sample References, Sampling Locations and PD Template and Figure 3 – Air Flow Pattern and Velocity Templates.

Brand, model #, quantity and specifications (i.e. manufacturers cfm and pressure drop) for any filters installed.

Weight and price of lead and brass recyclable metals with proof that the total amount was recycled and value refunded to government.

Legibly completed and signed manifest for hazardous waste with weights and disposition of waste specified.

Results of any TCLP testing done and description of tested items for hazardous waste (if applicable).

Completed Table 6 - HVAC Annual Maintenance Tasks and Table 7 - HVAC Filter Change- Out Maintenance Tasks if applicable (i.e. not GSA maintained).

F. Final Follow-up Abatement Report

The contractor must submit a final report package to the PM/COR using Attachment A. The

PM/GSA shall provide the local USMS representative (i.e. Range Master) and the USMS HQ

OSSH’s IFR Coordinator, the following information prior to allowing use of the firing range.

Copies of the following shall be maintained in the sites Maintenance Log.

Tasks completed.

Completed Table 4 - Inspection Checklist for Post-IFR Comprehensive and Follow-up

Abatement including condition of the baffles, bullet trap, lighting, alarms, fan interlock, targeting system, etc., including weight (lbs.) of lead contaminated wastes and lead and brass recyclable metals collected during this housekeeping.

CIH completed Figure 2 – Lead Sample References, Sampling Locations and PD Template for diagramed sample references and sampling locations only.

10 | P a g e

Laboratory certifications along with final samples analyses report.

G. Environmental

IFR produces various levels of recyclable materials and/or hazardous waste. The principle hazardous waste includes lead contaminated materials. All efforts shall be made to reduce the monthly hazardous waste stream to less than 220 pounds. Generators of less than or equal to 220 pounds per month of hazardous waste are considered Conditionally Exempt Small Quantity

Generator under current EPA standards. Conditionally Exempt Small Quantity Generator is typically subject to lower levels of regulations than those of Small or Large Quantity Generators.

Hazardous waste may include lead contaminated HVAC filters, Dura blocks, target debris, tacky mats, lead contaminated soiled rags, disposable wipes, HEPA vacuum filters, HEPA vacuum dirt container, used personal protective equipment, etc. HEPA filters and Dura blocks represent the largest quantity by weight of contaminated wastes as spent lead bullets and shell casings are recycled.

Disposition of Collected Spent Lead and Shell Casings - Comprehensive Maintenance o Spent lead bullets and shell casings shall be recycled.

o Cleaning contractor(s) shall collect the spent lead bullets and shell casings and deliver to a recycling facility.

o Cleaning contractor(s) shall sell the spent lead bullets and shell casings and deduct the proceeds from the cleaning invoice.

o An official receipt of sale for the recycled lead bullets and shell casings shall be provided as evidence of recycling and value deducted from cleaning invoice.

Disposition of Collected Spent Lead and Shell Casings – Follow-up Abatement o Collect spent brass shells in 2 to 5 gallon sealable bucket(s) labeled “brass only”.

Collect spent lead in 2 to 5 gallon sealable bucket(s) labeled “lead only”. Store buckets in a secure area (i.e. bullet trap room if available) until the disposal/recycling pickup.

H. Recycling

All efforts shall be used to minimize weight of hazardous waste generated. To that goal, all efforts shall be made to recycle all rubber components of the target range backstop including

Dura blocks, granulated rubber, rubber bladders, etc. All efforts shall be made to change out

HEPA filters only when necessary and as prescribed in this document.

I. Hazardous Waste

Collect lead contaminated HVAC filters, target debris, tacky mats, soiled rags, disposable wipes, HEPA vacuum filter, HEPA vacuum dirt container, used personal protective equipment, and all other contaminated waste and store in a solid container durably labeled

“lead contaminated waste.” This containers label shall also identify the weight of the wastes and the date of generation to use for calculating generation rates.

These wastes shall be either delivered to or picked up by a certified hazardous waste transport, storage, and disposal facility during Comprehensive maintenance.

11 | P a g e

These wastes shall be properly packaged, labeled and temporarily stored until the next disposal if collection was done during follow up abatement.

Weight of all lead contaminated wastes shall be documented on the Table 4 - Inspection

Checklist for Post-IFR Comprehensive and Follow-up Abatement.

3. WORK RESTICTIONS

CONTRACTOR USE OF PREMISES: During the abatement period the contractor shall limit use of the premises to the work area indicated by the General Services Administration (GSA)

PM, to allow for Government occupancy and public use. The following guidance shall be adhered to:

1. Prior to abatement, provide a written list of employees and subcontractor employees that will be working within the building during the contract period to the PM/COR.

2. Keep entrances serving the premises clear and available at all times to the Government, Government employees, and visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time required for storage of materials and equipment on site.

4. Space on the premises will be made available for the contractor’s storage and related activities, provided that its use will not interfere with the operation of the Government.

Arrange and gain approval for the use of this space through the PM/COR.

5. Use of the loading dock facilities will be shared with Government activities on a first-come-first-served.

6. No apparatus with an open flame, grinding that creates sparks, or grinding that creates excessive dust is allowed to be used within the facility without prior receipt of a burn permit. Burn permits should be requested through the PM/COR.

PERIOD OF PERFORMANCE:

The period of performance is one 1-year base and three 1-year option periods.

PERFORMANCE OF WORK:

A. Work is to begin after issuance of the Notice to Proceed (NTP). Access to work site shall be coordinated with the PM/COR once the NTP is issued as well as providing hours to allow a schedule to be generated.

B. Work is expected to be complete during the schedule provided and approved by

PM/COR. Clearances and containment removal is expected to be completed within same work schedule provided and approved by PM/COR.

All work shall be scheduled through the PM/COR at a minimum of two weeks advance notice.

Work shall be performed in a manner to avoid disruption of court proceedings.

12 | P a g e

4. QUALITY REQUIREMENT

All work performed to accomplish the work specified herein shall be in strict compliance with the manufacturers’ written recommendations and all nationally or locally recognized governing bodies. Contractor shall without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of this work. If two codes are in conflict, the most stringent will be applied.

All work to be performed under this contract shall be executed in a careful and orderly manner by workmen skilled in their respective trades or class of work. The work shall consist of furnishing and installing all new work and doing all necessary removing, patching, filling-in, repairing, and altering of existing work specified to be performed. The materials and methods of application for new work and for patching, filling-in, and repairing shall be similar and equal quality in its new state and shall be installed in compliance with standard trade practices.

All work shall be completed in compliance with Building Standards. Lists of Building Standards are available in the Field Office upon request from the PM/COR

5. TEMPORARY FACILTIES AND CONTROLS

UTILITY SHUTDOWN: All utility (electrical, water, sanitary, sprinkler, or HVAC) shutdowns must be scheduled with the PM/COR, at a minimum of seventy-two (72) hours in advance, and may be required to be completed after hours.

6. EXECUTION REQUIREMENTS

All work must be performed by the contractor unless noted otherwise.

WORKMANSHIP STANDARDS: The contractor shall ensure that personnel performing tasks required under this contract are skilled and knowledgeable in the methods and craftsmanship needed to produce journeymen level of workmanship. Any work performed by the contractor that is found to be faulty or fails to meet acceptable standards shall be removed and replaced by the contractor at no additional cost to the Government.

1. Manufacturer's Instructions: Where installations include manufactured products, comply with manufacturer's applicable installation instructions and recommendations to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in the contract documents.

2. Specialists: Where the individual sections of the specifications require specialists to perform the work, comply with the requirements specified. The assignment of a specialist shall not relieve the contractor of installation in accordance with all manufacturers’ written instructions and all nationally or locally recognized governing bodies.

13 | P a g e

3. Measurement Verification: It is the contractor’s responsibility to verify all dimensions and job site conditions, and order sufficient material to perform the job. Contractor shall be responsible for the accuracy of the measurements of total square footage.

CLEAN-UP: The contractor shall be responsible for removal and legal disposal of all debris created by the work specified herein from the premises. The contractor shall clean up the immediate area on a daily basis and must keep the area safe at all times.

7. CLOSEOUT

SUBSTANTAL COMPLETION: Is defined as that state when the contractor has complied with the contract requirements, except for minor deviations, and the project is sufficiently complete and capable of being occupied and used by the Government for the intended purpose.

INSPECTION PROCEDURES: On receipt of the contractor’s request for inspection, the

PM/COR or government designated representative will either proceed with the inspection or advise the contractor of unfilled requirements. If the contractor is aware of any unfilled requirements prior to the inspection, the contractor shall provide a list of incomplete items with a reason work is not complete. The PM/COR will notify the contractor once the project is substantially complete. This does not relieve the contractor from correcting all punch list items.

The Government may withhold funds until all items on the punch list have been successfully completed.

8. RECORD DOCUMENTS

Contractor is required to provide record documents as noted below:

1. Lead Sampling Locations - Comprehensive & Follow-up Abatement (see Table 1, page

65)

2. Inspection Checklist for Post-IFR Comprehensive and Follow-up Abatement

(see Table 4, page 68 -69)

FINAL CLEANING: Employ experienced workers or professional staff for final cleaning.

Clean each surface or unit to the condition expected in a normal, commercial cleaning and maintenance program. Comply with the manufacturer’s instructions. Remove all temporary protection or facilities installed for the protection of new work and all barriers erected around the construction area for dust control, noise, fall protection, or any other barrier that was required for construction.

9. SUSTAINABLE DESIGN REQUIREMENTS

GENERAL PHILOSOPHY: GSA is committed to the purchase and use of environmentally sustainable products and services. “Green purchasing” is the procurement of sustainable products and services that contain recycled/recovered material(s); are bio-based and/or non-ozone-depleting; are energy-efficient or water-efficient (are certified ENERGY STAR and/or

14 | P a g e

Water Sense); contain chemicals that are less ozone-depleting or hazardous; or have other sustainable attributes.

REQUIREMENTS FOR CONTRACTOR: The contractor is required to consider and use “green

(sustainable) products” if at all possible when providing any goods and/or services to the GSA.

The only three (3) exceptions to the requirements for “green products” are:

1. Unavailability.

2. Products meeting the requirements do not satisfy performance requirements.

3. The green product is only available at an unreasonable price.

Any exception must be documented and discussed with the Contracting Officer (CO) listed below prior to submission of your offer. In the case of unreasonable pricing, the price of the green product must be furnished and compared to the price of the product proposed for use. If you have questions regarding this please contact the CO.

Sustainability:

• Green Purchasing:

• The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement

Compilation can be found at https://sftool.gov/greenprocurement. The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.

• The use of the following standards (“Key Sustainable Product” or “KSP” standards) is mandatory for all contracts and task orders. See https://sftool.gov/green-products/1037/key-sustainable-products for more details.

• Nylon Carpet: NSF-140 Platinum or Cradle to Cradle Bronze.

• Resilient Flooring (e.g. vinyl and linoleum): NSF-332 (any level) or

Cradle to Cradle (any level)

• Interior Latex Paint: Master Painters Institute (MPI) Extreme Green or

Green Seal 11.

• Acoustical Ceiling Tiles: > 15% post-consumer recycled content.

• Water-Consuming Equipment: Water Sense Certified.

A. For each KSP listed, the Contractor shall submit proof of compliance to the CO or his designee prior to the installation of the product or material. The CO’s designee shall verify compliance.

B. If the KSP materials listed above are 1) not reasonably available within a reasonable period of time; 2) fail to meet the performance standards set forth in the specification or fail to meet reasonable performance standards of GSA; or 3) are available only at an unreasonable price, only then can the Contractor use other types of products. In these cases the Contractor shall select products and materials, to the extent possible, which are the safest and most environmentally friendly. Exemptions must be submitted in writing and can only be approved by the CO.

15 | P a g e

10. SUBMITTALS AND ABATEMENT

SUBMITTALS: The contractor shall submit via email the following to Technical Advisor, Jennifer Zenuch and PM/COR, Ryan S. Smith listed in paragraph 12.

1. A comprehensive work plan detailing the work to be accomplished, chronology, safety and health plan.

2. Contaminated materials sampling, packaging, transport and disposal plan; recyclable metals packaging, transport and name of recycling facility(s).

3. Standard Operating Procedures (SOPs) for IFR abatement

4. Past personal air sampling (Personally Identifiable Information (PII) redacted) per OSHA

29 CFR 1910.1025(d).

11. SECURITY

11.1 Department of Homeland Security (DHS) Directive-12 (HSPD-12) requires all Federal Executive departments and agencies to conduct personnel investigations, adjudicate the results, and issue identity credentials to all Federal contractors who require routine access to Federal buildings.

11.2 Contractor’s employees requiring routine access for work on this project will be required to undergo an HSPD-12 background investigation.

11.3 The contractor is responsible for the HSPD-12 requirements and to provide the HSPD-12 information requests in a timely manner in order so as not to delay this project.

11.4 Failure to fully comply with the HSPD-12 security directives or the security mandates set forth by DHS may result in the immediate removal of the offending employee and/or contractor from the job site.

12. POINTS OF CONTACT

Contracting Officer (CO) Trevor Simon

Office: 817-978-0122

Cell: 817-505-3393 trevor.simon@gsa.gov

Building Manager Dennis Crozier

Office: 225-389-0304

16 | P a g e

Cell: 225-315-0459

Dennis.crozier@gsa.gov

Project Manager/ Contracting Officer’s Representative (PM/COR) Ryan S Smith

Office: 504-218-2937

Cell: 504-421-8935

Ryan.s.smith@gsa.gov

Technical Advisor Jennifer Zenuch

Office: 504-589-6094 x120

Cell: 504-415-9463

Jennifer.zenuch@gsa.gov

Independent Air Monitor Consultant USPHS/FOH

TBD

mailto:Dennis.crozier@gsa.gov mailto:Jennifer.zenuch@gsa.gov

17 | P a g e

CLAUSES AND PROVISIONS

The following Federal Acquisition Regulation clauses are hereby incorporated into any resultant contract:

FAR 52.252.2 Clauses Incorporated by Reference (Feb 1998) this contract incorporates one or more clauses by reference with the same force and effect as if they were given in full text. Upon request, the

Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far and https://www.acquisition.gov/browse/index/gsam

CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE:

FAR 52.202-1 Definitions (Jun 2020)

FAR 52.204-7 System for Award Management (Oct 2018)

FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(Jun 2020)

FAR 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014)

FAR 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations – Representation

(Nov 2015)

FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

FAR 52.212-1 Instructions to Offerors - Commercial Items (Jun 2020)

FAR 52.212-4 Contract Terms and Conditions – Commercial Items (Oct 2018)

FAR 52.217-8 Option to Extend Services (Nov 1999)

FAR 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or

Transactions Relating to Iran—Representation and Certification (Jun 2020)

FAR 52.246-4 Inspection of Services -- Fixed-Price (Aug 1996)

FAR 52.249-4 Termination for Convenience of the Government (Services) (Short Form) (Apr

1984)

(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site

Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.

(2) Site visits will be conducted on January 13, 2021 at 10:00 AM (CST).

https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/browse/index/gsam

18 | P a g e

CLAUSES AND PROVISIONS INCORPORATED BY FULL-TEXT:

52.204-13 – System for Award Management Maintenance (Oct 2018)

(a) Definition. As used in this clause--

“Electronic Funds Transfer (EFT) indicator” means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management

(SAM) records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.

“Registered in the System for Award Management (SAM) database” means that—

(1) The Contractor has entered all mandatory information, including the unique entity identifier and the EFT indicator (if applicable), the Commercial and

Government Entity (CAGE) code, as well as data required by the Federal

Funding Accountability and Transparency Act of 2006 (see subpart 4.14), into the SAM database;

(2) The Contractor has completed the Core, Assertions, Representations and

Certifications, and Points of Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal

Revenue Service (IRS). The Contractor will be required to provide consent for

TIN validation to the Government as a part of the SAM registration process; and

(4) The Government has marked the record “Active”.

“System for Award Management (SAM)” means the primary Government repository for prospective Federal awardee and Federal awardee information and the centralized

Government system for certain contracting, grants, and other assistance-related processes. It includes—

(1) Data collected from prospective Federal awardees required for the conduct of business with the Government;

(2) Prospective contractor-submitted annual representations and certifications in accordance with FAR subpart 4.12; and

(3) Identification of those parties excluded from receiving Federal contracts, certain subcontracts, and certain types of Federal financial and non-financial assistance and benefits.

19 | P a g e

“Unique entity identifier” means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.

(b) If the solicitation for this contract contained the provision 52.204-7 with its

Alternate I, and the Contractor was unable to register prior to award, the Contractor shall be registered in SAM within 30 days after award or before three days prior to submission of the first invoice, whichever occurs first.

(c) The Contractor shall maintain registration in SAM during contract performance and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement. The Contractor is responsible for the currency, accuracy and completeness of the data within SAM, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in SAM after the initial registration, the Contractor is required to review and update on an annual basis, from the date of initial registration or subsequent updates, its information in SAM to ensure it is current, accurate and complete.

Updating information in SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(d)(1)(i) If a Contractor has legally changed its business name or "doing business as" name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in subpart 42.12, the

Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to—

(A) Change the name in SAM;

(B) Comply with the requirements of subpart 42.12 of the FAR; and

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor shall provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (d)(1)(i) of this clause, or fails to perform the agreement at paragraph (d)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the

Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in SAM record to reflect an assignee for the purpose of assignment of claims (see FAR subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM.

Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the

"Suspension of Payment" paragraph of the EFT clause of this contract.

(3) The Contractor shall ensure that the unique entity identifier is maintained with the entity designated at www.sam.gov for establishment of the unique entity http://www.sam.gov/ https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-42#FAR_Subpart_42_12 https://www.acquisition.gov/far/part-42#FAR_Subpart_42_12 https://www.acquisition.gov/far/part-32#FAR_Subpart_32_8 http://www.sam.gov/

20 | P a g e identifier throughout the life of the contract. The Contractor shall communicate any change to the unique entity identifier to the Contracting Officer within 30 days after the change, so an appropriate modification can be issued to update the data on the contract.

A change in the unique entity identifier does not necessarily require a novation be accomplished.

(e) Contractors may obtain additional information on registration and annual confirmation requirements at https://www.sam.gov.

(End of Clause)

52.212-2 -- Evaluation -- Commercial Items (Oct 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

Experience on Similar Projects

Past Performance

Price

Technical and past performances, when combined, are equal to cost or price [Contracting

Officer state, in accordance with FAR 15.304, the relative importance of all other evaluation factors, when combined, when compared to price.]

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The

Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

(End of Provision)

52.212-3 -- Offeror Representations and Certifications -- Commercial Items (Nov 2020)

The Offeror shall complete only paragraph (b) of this provision if the Offeror has completed the annual representations and certification electronically in the System for Award

Management (SAM) accessed through https://www.sam.gov. If the Offeror has not completed the annual representations and certifications electronically, the Offeror shall complete only paragraphs (c) through (v)) of this provision.

(a) Definitions. As used in this provision— https://www.sam.gov/ https://www.sam.gov/

21 | P a g e

"Covered telecommunications equipment or services" has the meaning provided in the clause

52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment.

Economically disadvantaged women-owned small business (EDWOSB) concern means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13

CFR part 127. It automatically qualifies as a women-owned small business eligible under the

WOSB Program.

Forced or indentured child labor means all work or service—

(1) Exacted from any person under the age of 18 under the menace of any penalty for its nonperformance and for which the worker does not offer himself voluntarily; or

(2) Performed by any person under the age of 18 pursuant to a contract the enforcement of which can be accomplished by process or penalties.

Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.

Immediate owner means an entity, other than the offeror, that has direct control of the offeror.

Indicators of control include, but are not limited to, one or more of the following: ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.

Inverted domestic corporation, means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).

Manufactured end product means any end product in product and service codes (PSCs) 1000-

9999, except—

(1) PSC 5510, Lumber and Related Basic Wood Materials;

(2) Product or Service Group (PSG) 87, Agricultural Supplies;

(3) PSG 88, Live Animals;

(4) PSG 89, Subsistence;

(5) PSC 9410, Crude Grades of Plant Materials;

(6) PSC 9430, Miscellaneous Crude Animal Products, Inedible;

(7) PSC 9440, Miscellaneous Crude Agricultural and Forestry Products;

https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title6-section395&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title6-section395&num=0&edition=prelim

22 | P a g e

(8) PSC 9610, Ores;

(9) PSC 9620, Minerals, Natural and Synthetic; and

(10) PSC 9630, Additive Metal Materials.

Place of manufacture means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.

Predecessor means an entity that is replaced by a successor and includes any predecessors of the predecessor.

Reasonable inquiry has the meaning provided in the clause 52.204-25, Prohibition on

Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

Restricted business operations means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174).

Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—

(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;

(2) Are conducted pursuant to specific authorization from the Office of Foreign Assets

Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;

(3) Consist of providing goods or services to marginalized populations of Sudan;

(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;

(5)…

This is the start of the file's text. The full file is on GovTribe.