Final_RFB_785_2600000643_6_SO_FORM.PDF
PDF 280 KB Posted
- Solicitation number
- RFB 785 2600000643 6
- Issued by
- Webster County, Kentucky
About this file
RFB-275-26 Willisburg Lake Dam Rehabilitation Project - Scope of Work
This is a Scope of Work document for the Commonwealth of Kentucky's RFB-275-26 Willisburg Lake Dam Rehabilitation Project. The project encompasses comprehensive rehabilitation of Willisburg Lake Dam, including structural repairs, spillway improvements, and associated infrastructure upgrades. The scope of work outlines detailed specifications for construction activities, material requirements, and quality standards to be met by the selected contractor. Bidders must submit responses by the specified due date, with site visits and pre-bid meetings available to familiarize contractors with project conditions and requirements. The contract will be awarded to the lowest responsive and responsible bidder meeting all technical and qualification criteria. The contract term extends for the duration of construction activities as detailed in the project schedule, with provisions for potential change orders and contract modifications as necessary during project execution.
The pricing structure requires bidders to submit fixed-price bids for all work outlined in the scope, with payment contingent upon satisfactory completion of work stages and inspections. The project is funded through state appropriations and may be subject to prevailing wage requirements applicable to public works projects in Kentucky. Bidders should note any qualifications, certifications, or experience requirements specified for contractor eligibility. The Commonwealth of Kentucky reserves the right to reject any or all bids and is not obligated to award the contract to the lowest bidder if the bid does not represent the best value to the state. Additional contract terms, insurance requirements, bonding, and compliance obligations are detailed in the associated bid documents and solicitation materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2600000643_3_SO_FORM.PDF | ||
| Addendum Three.pdf | ||
| Addendum Two.pdf | ||
| Addendum Five.docx | DOCX document | |
| Final_RFB_785_2600000643_5_SO_FORM.PDF | ||
| Addendum Four Emars.pdf | ||
| Final_RFB_785_2600000643_2_SO_FORM.PDF | ||
| Final_RFB_785_2600000643_1_SO_FORM.PDF | ||
| Final_RFB_785_2600000643_4_SO_FORM.PDF | ||
| Addendum One.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document ID: RFB 785 2600000643 Page: 1
Commonwealth of Kentucky
SOLICITATION MODIFICATION
Modification: Yes Version #: 6
TITLE: RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Date Issued:
08/17/2026 Record Date:
08/17/2026
Solicitation Closes Date:
08/31/2026 Time:
13:30
Solicitation No:
RFB 785 2600000643
Reason for Modification
Addendum Five
Online Bidding Prohibited: No
For Information Call:
Susan Ward 502-226-0335
Bid Receiving Location:
Bid Receiving
See Terms & Conditions for Bid Submission Instructions
Other KY
Vendor Customer Number:
Vendor Name:
Phone Number:
Fax Number:
Email Address:
Ordering
Address:
City, State, Zip:
Contact Name:
Contact Email:
Contact Phone Number:
Payment
Address:
City, State, Zip:
Contact Name:
Contact Email:
Contact Phone Number:
Ownership Type
__ Sole Proprietorship __ Partnership __ Corporation __ Other_________________________
SIGNATURE OF AUTHORIZED AGENT IS REQUIRED UNLESS RESPONSE
IS SUBMITTED ELECTRONICALLY. FAILURE TO SIGN SHALL RENDER
THE BID INVALID.
Signature X_________________________________________ FEIN#____________________ Date____________
All offers subject to all terms and conditions contained in this solicitation.
Document ID: RFB 785 2600000643 Page: 2
Line Items
Commodity Group: Default Commodity Group
Line CL Description Quantity UOM Unit Cost Line Total or Contract Amnt
1 RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Comm Code Comm Description Manufacturer Model # Manuf Part #
92678 Remediation Services, Environmental (Including Rehabilitatio
Extended Description
***ONLY ONLINE BIDS WILL BE ACCEPTED FOR THIS RFB.***
Emailed and hard copies delivered by any method WILL NOT BE ACCEPTED.
On this line, Bidders must enter $0.00 for Contract Amount in the e-procurement system. Actual Contract Amount must be entered on "Official Bid Document" and submitted as an attachment in the e-procurement system. Vendors should review and update, if necessary, all addresses and contact persons for their account prior to bid submission. This information will carry forward to a contract if awarded, therefore please ensure all information is correct.
** Entire Official Bid Document and Bid Bond (if required) should be combined as one PDF and uploaded**
The Base BID Work shall include construction of a reinforced concrete auxiliary spillway with two, 8 feet by 16 feet, precast concrete culverts through the dam crest to serve as the spillway inlet with a reinforced concrete stepped chute along the downstream slope that discharges into a reinforced concrete stilling basin at the toe of the dam. A reinforced concrete floodwall with concrete cutoff shall be constructed along the upstream crest of the dam along KY-555 with rockfill placed along the upstream slope of the dam. A rockfill stability berm shall be constructed along the downstream slope. The BASE BID Work further includes a new low-level drawdown valve in the dry well of the riser structure, replacement of the existing low level drawdown valve, and remediation of concrete cracking and seepage in the existing principal spillway culvert. In addition, the City of Springfields raw water intake will be abandoned and new raw water intake lines installed within the principal spillway culvert. A Contractor designed Water Diversion Plan is required. The BASE BID Work will also consist of site preparation, erosion and sedimentation control, slope construction and protection, construction access, selective demolition, earthwork, temporary shoring, traffic control and maintenance, storm drainage, and site grading and restoration work. Demolition Work shall include demolition of existing storm sewer infrastructure, raw water lines, concrete ditches, KY 555 within the footprint of the new auxiliary spillway, existing valves and operators at the intake structure, partial demolition of the principal spillway culvert and wingwalls, and abandonment of existing embankment piezometers. The CONTRACTORs Work shall also include site safety, water control, site security, traffic control, and site cleanup.
Shipping Information Division of Water
300 Sower Blvd, 3rd Floor
Frankfort KY 40601
Billing Information Division of Water
300 Sower Blvd, 3rd Floor
Frankfort KY 40601
Document ID: RFB 785 2600000643 Page: 3
Submission Checklist
The following items will be required to be submitted with bid:
Item
REQUEST FOR BID NO. RFB-275-26
Rehabilitation of Willisburg Lake Dam Kentucky Division of Water Energy and Environmental Cabinet Washington County, Kentucky
Project Description
The Base BID Work shall include construction of a reinforced concrete auxiliary spillway with two, 8 feet by 16 feet, precast concrete culverts through the dam crest to serve as the spillway inlet with a reinforced concrete stepped chute along the downstream slope that discharges into a reinforced concrete stilling basin at the toe of the dam. A reinforced concrete floodwall with concrete cutoff shall be constructed along the upstream crest of the dam along KY-555 with rockfill placed along the upstream slope of the dam. A rockfill stability berm shall be constructed along the downstream slope. The BASE BID Work further includes a new low-level drawdown valve in the dry well of the riser structure, replacement of the existing low level drawdown valve, and remediation of concrete cracking and seepage in the existing principal spillway culvert. In addition, the City of Springfield’s raw water intake will be abandoned and new raw water intake lines installed within the principal spillway culvert. A Contractor designed Water Diversion Plan is required. The BASE BID Work will also consist of site preparation, erosion and sedimentation control, slope construction and protection, construction access, selective demolition, earthwork, temporary shoring, traffic control and maintenance, storm drainage, and site grading and restoration work.
Demolition Work shall include demolition of existing storm sewer infrastructure, raw water lines, concrete ditches, KY 555 within the footprint of the new auxiliary spillway, existing valves and operators at the intake structure, partial demolition of the principal spillway culvert and wingwalls, and abandonment of existing embankment piezometers. The CONTRACTOR’s Work shall also include site safety, water control, site security, traffic control, and site cleanup.
SITE VISIT INFORMATION:
There will be a site visit on this project. Interested contractors are encouraged to attend. The site visit will be held on 6/18/2026 at 10:00 A.M. Eastern Time. The site visit will be held at Willisburg Lake Dam, meeting will be at Willisburg Marina (Don's Marina) 11528 KY-555, Willisburg, KY 40078.
ALL PROCUREMENT QUESTIONS SHALL BE DIRECTED TO BUYER OF RECORD FOR THIS
PROJECT.
IMPORTANT: Site visit participants shall follow any applicable health and safety guidelines for all Commonwealth of Kentucky construction projects.
PROJECT CONTACTS:
Consultant: Robert Hatton, Stantec Consulting Services, robert.hatton@stantec.com, (859) 422-3000 Agency: Glen Alexander, Division of Water, glen.alexander@ky.gov, (502) 782-6874 Purchasing Agent: Susan Ward, Division of Engineering and Contract Administration, Susan.Ward@ky.gov, (502) 226-0335
OBTAINING PLANS AND SPECIFICATIONS:
For all project information and documents go to: https://www.stateofkyplanroom.com. For customer service you may contact Lynn Imaging, Phone 1-800-888-0693. There is no charge for plans and specifications. Contractor will need to download bid documents, specifications, and drawings. If contractors want a hard copy, they can choose
Document Phase Document Description Page 4
2600000643 Final RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Total Pages: 5 https://www.stateofkyplanroom.com to pay for this option. Contractors that receive plans and specifications from other sources will not be registered as a planholder and will not receive addenda.
ELECTRONIC BID SUBMITTAL:
Solicitation responses (“bid”) shall be received by electronic submission through the Commonwealth’s eProcurement system.
Please be advised: Bids shall not be accepted via postal carrier (USPS, UPS, FED EX, etc.) nor can bids be hand delivered.
Response must contain all information required by the Solicitation and be executed by an authorized agent of the Bidder, affirmed by electronically submitting the bid through the eProcurement system. All bid documents shall be complete when the bid is submitted.
To bid, all bidders SHALL be registered in the Commonwealth eProcurement System via the Vendor Self Service (VSS) System at https://vss.ky.gov . Allow 24 – 48 hours to complete Vendor Registration. Vendors must be logged in to their Vendor Self Service account to submit a response. The Customer Resource Center is not able to complete registrations and activate accounts on the same day. Closing dates will not be extended for Vendors not registered by the date/time of the bid closing. Vendor Self Registration Guides are provided at https://vss.ky.gov under “Download Vendor Forms and Quick Reference Guides.”
All bidders are cautioned to begin their electronic submission in sufficient time to complete before the closing date and time. Delays due to inability to register, document upload impediments, or technical difficulties shall not be justification for acceptance of a late bid or proposal. If you need assistance, please contact the
Customer Resource Center (CRC)
- Email at Finance.CRCGroup@ky.gov;
- Locally at 502-564-9641 or toll-free 877-973- HELP (4357).
Online bid responses must be in an “Accepted” status prior to the closing date and time of the solicitation. The assigned date and time stamp from the eProcurement system generated at the time of final acceptance and formal submission by the vendor shall establish the date and time the bid was submitted. A bid may be modified or withdrawn electronically through VSS prior to the bid closing date and time.
Please be advised, VSS will not allow submission of an online response after the published date and time for closing.
Bidders shall attach the Official Bid Document and Bid Bond (if required) as a single combined attachment when submitting their electronic bids.
All results will be posted to https://www.stateofkyplanroom.com after the bid opening and review. If additional information is needed from the successful bidder, the buyer may be in contact.
There will be a public bid reading by conference call on the bid opening date at 3:00 P.M., Eastern Time.
The dial in number is (502) 782-2663 Conference ID# 240522018# Participant code is 75309#
Document Phase Document Description Page 5
2600000643 Final RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Total Pages: 5 https://vss.ky.gov/ https://vss.ky.gov/ mailto:Finance.CRCGroup@ky.gov https://www.stateofkyplanroom.com/
File details come from the government source that posted it. Updated .