About this file

This is a Request for Bid (RFB) issued by the Commonwealth of Kentucky Transportation Cabinet Division of Purchases on behalf of the Division of Traffic Operations for the procurement of steel strain poles that are FHWA-eligible. The solicitation RFB 605 2700000232 seeks 320 total steel strain poles in four different heights: 80 units of 30-foot poles, 200 units of 32-foot poles, 20 units of 34-foot poles, and 20 units of 38-foot poles. All poles must be sourced from manufacturers already listed on the state's Qualified Products List (QPL) prior to the bid closing date. The solicitation employs a two-phase competitive sealed bid process conducted as a reverse auction through eBridge. Phase 1, closing on December 11, 2026 at 1:30 PM Eastern Time, requires vendors to submit unpriced technical offers including manufacturer information and compliance documentation. Phase 2 occurs during an online reverse auction event scheduled for December 29, 2026 at 11:00 AM, during which only qualified bidders from Phase 1 may submit pricing. The anticipated award date is January 15, 2027. Delivery must occur within 120 calendar days, with penalties of one percent per day assessed for late delivery. Poles will be unloaded at the KYTC Division of Traffic Operations Transportation Warehouse in Frankfort, Kentucky by state forces.

Pricing is to be submitted on an F.O.B. Destination Freight Prepaid and Allowed basis, with the vendor responsible for all freight charges. Award will be made on a best-value basis with price as the sole evaluation criterion (100 points). All poles must comply with AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals (2013-6th Edition) and must be manufactured entirely in the United States in compliance with Buy America and Build America, Buy America Act requirements. Vendors must provide comprehensive documentation including Certificate of Authority from the Kentucky Secretary of State (if applicable), Certificate of Insurance with minimum $1,000,000 per occurrence coverage, welding certificates, mill certifications, and both a Non-Collusion Certification and Buy America/BABA Materials Certificate of Compliance. The contract is funded by the Federal Highway Administration, and all steel materials, manufacturing processes, and galvanizing must occur in the United States. Vendors must register in the Commonwealth's eProcurement System (VSS) prior to submission, and all bids remain valid for 90 calendar days following the closing date. The solicitation allows for no substitutions or exceptions to specifications without Commonwealth approval.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document ID: RFB 605 2700000232 Page: 1

Commonwealth of Kentucky

SOLICITATION

Modification: No Version #:

TITLE: Steel Strain Pole - FHWA Eligible

Date Issued:

11/19/2026 Record Date:

11/19/2026

Solicitation Closes Date:

12/11/2026 Time:

13:30

Solicitation No:

RFB 605 2700000232

Online Bidding Prohibited: No

For Information Call:

LATASHA CHENAULT

502-782-5673

Bid Receiving Location:

Bid Receiving

See Terms & Conditions for Bid Submission Instructions

Other KY

Vendor Customer Number:

Vendor Name:

Phone Number:

Fax Number:

Email Address:

Ordering

Address:

City, State, Zip:

Contact Name:

Contact Email:

Contact Phone Number:

Payment

Address:

City, State, Zip:

Contact Name:

Contact Email:

Contact Phone Number:

Ownership Type

__ Sole Proprietorship __ Partnership __ Corporation __ Other_________________________

SIGNATURE OF AUTHORIZED AGENT IS REQUIRED UNLESS RESPONSE

IS SUBMITTED ELECTRONICALLY. FAILURE TO SIGN SHALL RENDER

THE BID INVALID.

Signature X_________________________________________ FEIN#____________________ Date____________

All offers subject to all terms and conditions contained in this solicitation.

Document ID: RFB 605 2700000232 Page: 2

Line Items

Commodity Group: Default Commodity Group

Line CL Description Quantity UOM Unit Cost Line Total or Contract Amnt

1 30 ft steel strain poles 80.00000 EA

Comm Code Comm Description Manufacturer Model # Manuf Part #

55085 Traffic Signal Poles, Standards, and Brackets

Extended Description KYTC Warehouse (T-04-0020)

FOR INTERNAL USE ONLY

2 32 ft steel strain poles 200.00000 EA

KYTC Warehouse (T-04-0030)

3 34 ft steel strain poles 20.00000 EA

KYTC Warehouse (T-04-0040)

Document ID: RFB 605 2700000232 Page: 3

4 38 ft steel strain poles 20.00000 EA

KYTC Warehouse (T-04-0051)

Shipping Information KYTC Division of Traffic Operations - Transportation Warehouse

1239 Wilkinson Blvd

Frankfort KY 40601

Billing Information KYTC Division of Traffic Operations

200 Mero Street 3rd Floor Frankfort KY 40622

Document ID: RFB 605 2700000232 Page: 4

Submission Checklist

The following items will be required to be submitted with bid:

Item Price

ELECTRONIC BID SUBMISSION

Bid responses shall be received by electronic submission in the eProcurement system.

Link: https://vss.ky.gov

An electronic bid shall be authorized by the proper agent of the firm by the act of submitting it electronically through the eProcurement system.

Bid information MUST be completed online. Response must contain all required information for the Solicitation.

All bidders MUST be registered in the Commonwealth eProcurement System via the Vendor Self Service System at https://vss.ky.gov.

Allow 24 – 48 hours to complete Vendor Registration. Vendors must be logged in to their Vendor Self Service (VSS) account in order to submit a response. Registrations completed the day of bid closing must be completed by the Vendor in the VSS portal. The Customer Resource Center is not able to complete registrations and activate accounts on the same day. Closing dates will not be extended for Vendors not registered by the date/time of the bid closing. Vendor Self Registration Guides are provided at https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx

All bidders are cautioned to begin their electronic submission in sufficient time to complete before the closing date and time. Delays due to technical difficulties or document upload impediments shall not be justification for acceptance of a late bid or proposal. Vendor attention to this advisory is encouraged. If you need assistance, please contact the Customer Resource Center (CRC) by email at Finance.CRCGroup@ky.gov or phone 502-564-9641 or toll-free 877-973-HELP (4357).

BID PRICES SUBMITTED ON COMPANY QUOTE FORMS ARE DISCOURAGED. COMPANY TERMS AND

CONDITIONS AND/OR SALES AND USE AGREEMENTS OFTEN CONFLICT WITH STANDARD SOLICITATION

REQUIREMENTS AND MAY RESULT IN REJECTION OF BID OFFER.

Online bid responses must be in an “Accepted” status and shall be assigned a date and time stamp from the eProcurement system at the time of final acceptance and formal submission by the vendor. The system will not allow submission of an online response after the published date and time for closing.

An offer may be modified or withdrawn by electronic or written notice ONLY if received prior to the bid closing date and time. An electronic offer may be modified by applying the appropriate electronic signature and following the procedure in the state’s eProcurement signature.

BID SUBMISSION CHECKLIST:

The vendor MUST include the following with the bid submission. If the items below are not submitted with the bid, the Commonwealth MUST deem the bid non-responsive and SHALL NOT be considered for award.

_____ BID INFORMATION – COMPLETED (See Section 5.00)

_____ _PHASE 1 – OFFERS WITHOUT PRICING (Attachment G Bid Sheet, Delivery, Pole Manufacturer Name and Address)

All other items MUST be submitted prior to award however, vendors are strongly encouraged to include with bid submission.

_____ CERTIFICATE OF AUTHORITY – REGISTRATION WITH SECRETARY OF STATE BY FOREIGN

ENTITY (See Section 2.12)

_____ REQUIRED AFFIDAVIT(S) (See Attachments A, B, C, etc. as applicable)

_____ CERTIFICATE OF INSURANCE (See Section 1.01)

_____ WELDING CERTIFICATE (Upon Request)

Document Phase Document Description Page 5

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 https://vss.ky.gov https://vss.ky.gov https://emars311.ky.gov/webapp/vssprdonline3111d/AltSelfService https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx mailto:Finance.CRCGroup@ky.gov

_____ NON COLLUSION CERTIFICATION (Section 1.02 E)

_____ BUY AMERICA/BABA (Section 1.02 F)

PLEASE READ THIS SOLICITATION AND ITS INSTRUCTIONS IN ITS ENTIRETY.

This is a Request for Bid (RFB).

Vendors shall comply with the terms and conditions stated in the solicitation.

Any efforts to negotiate these terms and conditions SHALL NOT be accepted and SHALL cause the bid to be deemed non-responsive.

Vendors should review and comply with the general bidding requirements listed under “Procurement Laws, Preference, Regulations and Policies” and “Response to Solicitation” located on the eProcurement Web page at https://finance.ky.gov/eProcurement/Pages/procurement-laws-regulations-and-policies.aspx and https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx respectively. The vendor must comply with all applicable statutes, regulations and policies related to this procurement.

Specifications – Reverse Auction

This RFB will be conducted as a Multistep Competitive Sealed Bid in accordance with 200 KAR 5:375 also referred to as a REVERSE AUCTION.

The Commonwealth has partnered with eBridge to host this bidding event on its Web-Based Bidding Platform. Vendors who have not previously registered must register with eBridge by emailing tara.obannon@ebridgeglobal.com

Review the Attachment (eBridge Bid Instructions). The awarded supplier is obligated to pay a transaction fee to eBridge pursuant to the Terms and Conditions accepted upon placement of initial bid.

This RFB will consist of two phases.

Phase 1: VENDORS SHALL SUBMIT UNPRICED OFFERS per instruction in Section 3.04. Prices will be accepted only from bidders whose unpriced technical offer is found acceptable during Phase 1. Vendor/ Manufacturers MUST submit the attached bid sheet with the QPL Number and Pole Manufacturer Name and Address.

Prior to Phase 2 vendors will be emailed a copy of the current drawings noted on the QPL. Vendors will be asked to confirm that the drawings on the QPL are the most current version. If emailed drawings are not most current version, an update may be submitted until 12/21/2026. Vendors shall submit pricing in Phase 2 according to the confirmed drawings on the QPL.

Phase 2: PRICES WILL ONLY BE ACCEPTED IN THE SECOND PHASE DURING THE ONLINE REVERSE AUCTION BIDDING EVENT. If only one (1) responsive bid is received, the online reverse auction will be cancelled and the Division of Purchases, will request pricing from the vendor via email. The criteria that will be used to evaluate the offers at the conclusion of the online bidding event are located in section 5.00.

Document Phase Document Description Page 6

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 https://finance.ky.gov/eProcurement/Pages/procurement-laws-regulations-and-policies.aspx mailto:tara.obannon@ebridgeglobal.com

Section 1 - Specifications – Commodity

The Kentucky Transportation Cabinet Division of Purchases issues this solicitation on behalf of the Division of Traffic Operations to award a one- time contract for: Steel Strain Poles

1.00 - Specifications of Commodity

The specifications below are in reference to AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals, 2013-6th Edition with current interims and need to be followed in the drawings and calculations.

Drawings and calculations are required to be stamped by a Professional Engineer licensed in the Commonwealth of Kentucky.

Qualified Products List (QPL) of Materials

All vendors bidding on this Steel Strain Pole solicitation shall only bid poles on the QPL. Poles bid shall be on the QPL prior to the bid closing date. Vendors bidding poles not on the QPL shall not be considered for award. Vendors should allow 10 days from the date submittals are received by the Division of Purchases to be placed on the QPL.

The final submittals and drawings on the Materials QPL shall be attached to the resulting contract.

To view manufacturers currently on the QPL please go to the Division of Materials website below.

http://transportation.ky.gov/materials/pages/List-Of-Approved-Materials.aspx

If you wish to add poles to the preapproved materials list, please contact Latasha Chenault at Latasha.Chenault@ky.gov with the Division of Purchases at 502-782-5673.

Vendor should submit the name and address of the pole manufacturer on Attachment G with the bid submission. If the vendor fails to submit this information the bid shall be rejected as non-responsive. Upon receipt of the drawings and calculations the manufacturer shall be the same as on the bid submission.

All poles shall be manufactured per the approved final drawings and calculations attached to the resulting contract.

KYTC reserves the right to inspect poles upon delivery prior to making payment. Vendor will be required to correct any poles not conforming to the specifications and final drawings and calculations.

General: Pole shall be designed such that the span wire attachment height is 2’ below pole top. The couplings shall have a threaded steel plug and shall be installed in the coupling. See attached drawings for permissible pole clamp assemblies and required pole clamp hardware.

No round poles shall be accepted and poles with more than 16 sides shall not be accepted.

TRAFFIC POLES. Pole diameter and wall thickness shall be calculated in accordance with the AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals, 2013-6th Edition with current interims.

Provide poles and arms that conform to:

ASTM A595, grade A or B with minimum yield strength of 55 ksi, ASTM A572, minimum of grade 55, or

ASTM A53.

Provide poles, anchor bolts, base plates, and all other hardware that are hot dip galvanized per ASTM A123, A153.

Fasteners galvanizing can conform to ASTM F2329.

Provide base plates that conform to ASTM A36 for grade 36 or ASTM 572 for grade 50.

Document Phase Document Description Page 7

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 http://transportation.ky.gov/materials/pages/List-Of-Approved-Materials.aspx mailto:Latasha.Chenault@ky.gov

Ensure transverse plates have a thickness # 2 inches. Provide a base plate for the vertical pole that fits inside a 36 in diameter concrete base. The maximum anchor bolt circle shall not be more than 24.5 inches. The maximum anchor bolt diameter shall not be more than 2.25 inches. The bottom pole diameter shall not be less than 16.25 inches at the base of the pole and the hand hole shall be a minimum of at least the pole base diameter above the base plate.

Provide mill certifications as proof of compliance with the specifications upon request. Provide poles that are anchor-based. Provide poles that are hot-dipped galvanized inside and out. For anchor bolt design, pole forces shall be positioned in such a manner to maximize the force on any individual anchor bolt regardless of the actual anchor bolt orientation with the pole. Provide poles that are furnished complete with fully galvanized anchor bolts and hardware.

The pole handhole shall be 25 inches by 6.5 inches. The handhole cover shall be removable from the handhole frame.

On the frame side opposite the hinge, provide a mechanism on the handhole cover/frame to place the Department's standard padlock. The handhole frame shall have two stainless studs installed opposite the hinge to secure the handhole cover to the frame which includes providing stainless steel wing nuts and washers. The handhole cover shall be manufactured from 0.25-inch-thick galvanized steel (ASTM 153) and have a neoprene rubber gasket that is permanently secured to the handhole frame to ensure weather-tight protection. The hinge shall be manufactured from 7-gauge stainless steel or approved equal to provide adjustability to ensure a weather-tight fit for the cover. Provide a copper, stainless steel or brass grounding lug installed 180 degrees from the handhole opening and that is accessible from the handhole.

There shall be a 4” by 6” Arc FLASH/Shock Hazard Warning sticker installed on the center of the door. The sticker shall be Metalcraft PLY695 Prem STYLEMARK Label with .007 thickness, with UV white polycarbonate material, and with MC53FL pressure sensitive adhesive. The sticker shall have two colors of black and custom color orange.

See example attached at the header.

Provide welding that is in accordance with sections 1 through 8 of the AWS D1.1 structural welding code. Vendors shall submit the manufacturer’s welding certificate with the drawings and calculations for verification prior to award of contract. Use tackers and welders that are qualified in accordance with the code. Provide a tube that contains only one longitudinal seam weld. Provide tube longitudinal seam welds that are free of cracks and excessive undercuts, performed with automatic processes. Visually inspect all welds. Longitudinal welds suspected to contain defects shall be magnetic particle inspected by the manufacturer.

Provide calculations and drawings that are stamped by a Professional Engineer licensed in the Commonwealth of Kentucky. Provide materials and products that are manufactured in the United States of America. All tables are found in the AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals, 2013-6th Edition with current interims. Include a shop drawing specifying the pole height, bolt circle diameter, bolt diameter, and detailed drawings showing the handhole cover assemblies with all Contracts.

Steel Strain Poles. Provide two, 2-inch blind half couplings installed 3 feet from top of pole. Provide steel strain poles with two (2) pole clamp assemblies suitable for attaching messenger cable. Each clamp assembly shall include a minimum of one 5/8-inch bolt that conforms to ASTM A325, ASTM A449, or A490 with a minimum tensile load of 17,050 lbs).

There shall be galvanized rigid steel plugs for each blind half coupling and shall be installed into couplings when delivered.

Provide steel strain poles with a permanently affixed label 6 feet from the bottom of the base plate on the outside with the following information:

manufacturer height minimum stringing tension at yield order number, and maximum deflection rate.

As stated above, the best evaluated bidder shall provide detailed calculations of the pole. The detailed calculations shall be certified by a Professional Engineer licensed in the Commonwealth of Kentucky. The detailed calculations shall include, but not be limited to, the following calculations:

Group II load combinations as listed in table 3-1.

Document Phase Document Description Page 8

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30

For group load II, which have wind loads, provide calculations for each Controlling "worst case" (wind is blowing in the same direction as the wire) wind direction on pole that controls any aspect of the design (anchor bolts, pole sizing, etc.). Loads shall be positioned to produce maximum effect. (Wind load is applied in the same direction as the tension).

Anchor Bolts shall be designed for the orientation that would provide the maximum stress on any individual bolt.

All structural properties for poles, anchor bolts and base plates. This includes the poles diameter, thickness, section modulus, moment of inertia, and cross-sectional area.

Calculations for each member shall include loads, section properties, member forces (axial, shear, bending, and torsion), member deflections (angular and linear), member stresses (actual and allowable), and the combined stress ratio (csr).

Anchor Bolts. The anchor bolt design shall follow the AASHTO Specifications and NCHRP Report 494 Section

2.4 for anchorage into concrete. Use anchor bolts that conform to the requirement of ASTM F 1554. Hooked anchor bolts shall be Grade 55. Headed anchor bolts may be Grade 55 or 105.

Anchor bolts shall be fully galvanized. Provide each anchor bolt with 2 galvanized hex nuts as well as two flat washers. Provide nuts that equal or exceed the proof load of the bolt’s strength. Provide bolts that are hot dip galvanized to the requirements of either ASTM A 123 (fabricated products) or ASTM A 153 (hardware items).

Protect anchor bolt threads from damage during shipping. Provide mill test reports on anchor bolts. Provide steel strain poles with a minimum of four fully galvanized anchor bolts. There shall be two steel templates (one can be used for the headed part of the anchor bolt when designed in this manner) provided per pole. Templates shall be contained within a 26.5-inch diameter. All templates shall be fully galvanized (ASTM A 153). Anchor bolt lengths should be based on NCHRP Report 494 Section 2.4.5.5 using #8 bars for the foundation reinforcing steel. The headed anchor bolt assembly shall be contained within 26.5-inch diameter. Minimum edge distance for bolt holes shall follow Table J3.4 of AISC Steel Construction Manual.

Packaging: The anchor bolts for each individual pole shall be banded together and shrink-wrapped. Anchor bolts and bottom of the pole base shall be marked per the color code and inscribed with a designated letter to readily determine which anchor bolts/pole go with which pole (letter shown below). This color code and letter shall be applied on the anchor bolts not the outside shrink-wrap. There shall be two galvanized steel templates provided per pole and each template shall be marked per the color code and inscribed with a designated letter.

Except for the anchor bolts, all hardware (including the pole cap) shall be packaged in a plastic bag for storage with the pole. The plastic bag shall have the color code and designated letter clearly marked. There shall be a laminated picture of the supplied with all hardware to show what is in the hardware bag or installed on the anchor bolts. The poles shall be delivered banded together in multiplies of four poles and all poles shall be staggered and squared off for ease of moving around the pole yard. All pole doors shall be secured before loaded on its transport to our warehouse.

Delivery: Poles will be unloaded at the shipping destination by state forces. Rail shipments are not acceptable.

Inscribed Letter added:

28-foot poles “A” “Blue” 30-foot poles “B” “Red” 32-foot poles “C” “Orange” 34-foot poles “D” “Yellow” 36-foot poles “E” Black” 38-foot poles “F” “Brown” 40-foot poles “G” “Purple”

1.01- Required Insurance Coverage The awarded vendor(s) shall be responsible for maintaining, and not reducing, the following insurance coverages, types, and limits of liability. Further awarded vendor shall be able to produce evidence of insurance in compliance with (C) through the entire contract:

Document Phase Document Description Page 9

A. Commercial General Liability Insurance in accordance with minimum limits of liability of $1,000,000.00 per occurrence, $2,000,000.00 aggregate. The Commonwealth, in the Request for Solicitation, may require higher limits depending on the type of solicitation.

B. Additional Types of Insurance

1. Automobile Liability Insurance (If Applicable) Automobile Liability Insurance is required for delivery, onsite training, services or events in all situations where the Contractor must drive to any property where Commonwealth operations occur. With regard to delivery, if the items requested in this solicitation will be delivered by the awarded Contractor or Subcontractor, proof of Automobile Liability Insurance must be provided prior to award. If items will be delivered by common courier (USPS, FedEx, UPS, Old Dominion Freight Line, etc.), this requirement does not apply.

The Contractor or Subcontractor must provide a certificate of insurance coverage for any vehicle used in performance of this contract, whether owned, non-owned, or hired, or other vehicles utilized by the Contractor or Subcontractor.

Said policy of insurance to have a minimum coverage limit of $1,000,000.00 per occurrence combined single limit for bodily injury, including death, and property damage.

This requirement does not apply if the Contractor does not own, lease, or hire any automobiles to be used in connection with performance under any Contract resulting from this Solicitation.

C. Evidence of Insurance Coverage

The successful bidder shall provide evidence of insurance coverage as required. Failure to do so shall constitute a material breach of this Contract and may result in immediate cancellation of the Contract.

For all required insurance coverages, during the course of the Contract, the awarded vendor shall not be self-insured or utilize a Captive Insurer or a fronting policy that shifts risk back to the awarded vendor without prior written approval by the Office of the Controller of the Commonwealth.

Further, the awarded vendor shall not utilize an insurer or similar entity not in good standing with the Insurance Commissioner to fulfill the insurance requirements of the contract without prior written approval by the Office of the Controller of the Commonwealth.

Such approvals may require additional financial review, proof of funds, or bonding requirements sufficient for the risk associated with the services covered by the Contract, and approval or rejection is within the sole discretion of the Commonwealth’s Office of the Controller.

Contractor shall furnish the Certificate of Insurance prior to award and shall, upon request of the Commonwealth at any time during the contract term, provide a current, valid Certificate of Insurance.

Contractor and/or its insurer shall provide immediate notice of nonrenewal or cancellation of coverage during the course of the Contract.

All Certificates of Insurance must be signed by an authorized representative of the insurance agency, shall be in compliance with the laws of the Commonwealth of Kentucky, and shall be placed with a licensed resident or non-resident agent who represents insurance companies authorized to do business in Kentucky. The insurer shall have an AM Best rating of B+ or higher. Visit www.ambest.com for verification. Failure to meet this requirement may result in the bid being deemed non-responsive. A list of authorized companies can be found at https://insurance.ky.gov/ppc/ Company/Default.aspx.

A Certificate of Insurance (COI) on an ACORD form shall include the following:

# The certificate holder shall be listed as:

Kentucky Transportation Cabinet Division of Purchases

200 Mero Street, 4th Floor Frankfort, Kentucky 40622

Document Phase Document Description Page 10

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 http://www.ambest.com https://insurance.ky.gov/ppc/Company/Default.aspx https://insurance.ky.gov/ppc/Company/Default.aspx

# Certificate of Insurance must contain the following language in the Description of Operations box:

“The Commonwealth and its agents are Additional Insureds for the contract resulting from the solicitation. Additional insured protection afforded is on a primary and non-contributory basis.”

# The contract number in the Description of Operations box.

D. Subcontractors

If the contract allows for Subcontractors and utilizes Subcontractors, prior to the commencement of any work by a Subcontractor.

# The primary Contractor’s Certificate of Insurance must identify coverage that meets or exceeds the insurance requirements defined in this contract and that covers Subcontractor and its work in support of the Contract or the Subcontractor must submit and maintain a Certificate of Insurance that also meets or exceeds the insurance requirements of the Primary Contractor defined in this contract, with an Additional Insured Endorsement.

# KYTC reserves the right to request copies of all Subcontractor’s Certificate(s) of Insurance at any time.

1.02 - Federal Language

Funds from the Federal Highway Administration will be used to make payment against the resulting contract. The following clauses shall apply:

A. KYTC Standard Specifications

Except as provided herein, conform to all requirements of the Transportation Cabinet’s Current Standard Specifications for Road and Bridge Construction. Section references herein are to the Cabinet’s Current Standard Specifications for Road and Bridge Construction.

The Standard Specifications can be found at: https://transportation.ky.gov/Construction/Pages/Kentucky-Standard- Specifications.aspx

B. FHWA 1273

https://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf

C. PROJECT WAGE RATES

Wage Rates (Davis Bacon) do not apply because this contract is for commodities and not services.

D. PROHIBITION ON TELECOMMUNICATIONS EQUIPMENT OR SERVICES

In accordance with the FY 2019 National Defense Authorization Act (NDAA), 2 CFR 200.216, and 2 CFR 200.471, Federal agencies are prohibited, after August 13, 2020, from obligating or expending financial assistance to obtain certain telecommunications and video surveillance services and equipment from specific producers. As a result of these regulations, contractors and subcontractors are prohibited, on projects with federal funding participation, from providing telecommunication or video surveillance equipment, services, or systems produced by:

Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities)

Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities)

E. NON COLLUSION CERTIFICATION

Per KRS 45A.325, “Any agreement or collusion among bidders or prospective bidders which restrains, tends to restrain, or is reasonably calculated to restrain competition by agreement to bid at a fixed price, or to refrain from bidding, or otherwise, is prohibited.”

Per 23 USC 112 (c) “The Secretary shall require as a condition precedent to his approval of each contract awarded by competitive bidding pursuant to subsection (b) of this section, and subject to the provisions of this section, Document Phase Document Description Page 11

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 https://transportation.ky.gov/Construction/Pages/Kentucky-Standard-Specifications.aspx https://transportation.ky.gov/Construction/Pages/Kentucky-Standard-Specifications.aspx https://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf https://www.law.cornell.edu/definitions/uscode.php?width=840&height=800&iframe=true&def_id=23-USC-1264422296-293024739&term_occur=999&term_src= a sworn statement, executed by, or on behalf of, the person, firm, association, or corporation to whom such contract is to be awarded, certifying that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract.”

The attached Non-Collusion Certification must be submitted to Division of Purchases prior to award of contract.

F. BUY AMERICA REQUIREMENT AND BUILD AMERICA, BUY AMERICA (BABA) ACT

1.0 BUY AMERICA REQUIREMENT

Follow the “Buy America” provisions as required by Title 23 Code of Federal Regulations § 635.410. Except as expressly provided herein all manufacturing processes of steel or iron materials including but not limited to structural steel, guardrail materials, corrugated steel, culvert pipe, structural plate, prestressing strands, and steel reinforcing bars shall occur in the United States of America, including the application of:

• Coating,

• Galvanizing,

• Painting, and

• Other coating that protects or enhances the value of steel or iron products.

The following are exempt, unless processed or refined to include substantial amounts of steel or iron material, and may be used regardless of source in the domestic manufacturing process for steel or iron material:

• Pig iron,

• Processed, pelletized, and reduced iron ore material, or

• Processed alloys.

The Contractor shall submit a certification stating that all manufacturing processes involved with the production of steel or iron materials occurred in the United States.

Produce, mill, fabricate, and manufacture in the United States of America all aluminum components of bridges, tunnels, and large sign support systems, for which either shop fabrication, shop inspection, or certified mill test reports are required as the basis of acceptance by the Department.

The use of foreign steel and iron materials may only be under the following conditions:

1) When the materials are not permanently incorporated into the project; or

2) When the delivered cost of such materials used does not exceed 0.1 percent of the total Contract amount or $2,500.00, whichever is greater.

The Contractor shall submit to the Engineer the origin and value of any foreign material used.

2.0 BUILD AMERICA, BUY AMERICA (BABA)

The Contractor shall comply with the Federal Highway Administration (FHWA) Buy America Requirement in Title 23 Code of Federal Regulations § 635.410 and all relevant provisions of the Build America, Buy America (BABA) Act, contained within the Infrastructure Investment and Jobs Act (IIJA), Pub. L. No. 117-58, §§ 70901-52 enacted November 25, 2021. The BABA requires iron, steel, manufactured products and construction materials used in infrastructure projects funded by federal financial assistance to be produced in the United States. The Contractor shall comply with Title 2 C.F.R. § 184.

Document Phase Document Description Page 12

A) Iron and Steel Requirements. BABA permits FHWA participation in the Contract only if domestic steel and iron will be used on the Project. To be considered domestic, all steel and iron used, and all products manufactured from steel and iron must be produced in the United States and all manufacturing processes, including application of coating, for these materials must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating was applied. This requirement does not preclude a minimal use of foreign steel and iron materials, provided the cost of such materials does not exceed 0.1% of the total contract amount under the Contract or $2,500.00 whichever is greater.

B) Construction Material Requirements. BABA permits FHWA participation in the Contract only if all “construction materials”, as defined in the IIJA and OMB Memorandum M-24-02, are produced in the United States.

The Buy America preference applies to the following materials incorporated into infrastructure projects:

• non-ferrous metals

• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables)

• glass (including optic glass)

• fiber optic cable

• optical fiber

• lumber

• engineered wood

• drywall

C) Manufactured Products Requirements. All manufactured products incorporated into the project must comply with the following:

1) All manufactured products used in Federal-aid projects must have final assembly occur in the United States to be considered Buy America compliant.

2) Effective with the October 2026 letting, in addition to the requirement specified in paragraph 1), the cost of the components of the manufactured product that are mined, produced or manufactured in the United States must be greater than 55% of the total cost of all components of the manufactured product. Each manufactured item must be classified into one of the following categories: iron or steel product, manufactured product, construction material or another product category as specified by law or in 2 CFR Part 184. Items shall not be classified into multiple categories.

3.0 ADDITIONAL BABA ACT REQUIREMENTS.

A) De Minimis Waiver. The De Minimis Costs portion waives the application of the requirements of the BABA Act for construction materials and manufactured products under a single financial assistance award when the total value of the non-compliant products is no more than the lesser of $1,000,000 or 5% of the total applicable costs for the project. Applicable costs are defined as the costs of all steel, iron, manufactured products and construction materials. Cement and cementitious materials; aggregates such as stone, sand, or gravel; and binding agents and additives, standing alone, should not be included in the determination of total applicable project costs. The De Minimis waiver cannot be applied to a single item exceeding $1,000,000 in value.

If the Contractor seeks to utilize the waiver, the entire administrative burden lies solely with the Contractor, including all documentation and tracking of actual costs of steel, iron, manufactured products and construction materials to ensure that the 5% threshold is not exceeded. Records must be retained for at least five (5) years after receipt of the Contractor’s Final Release Letter.

Additionally, the Contractor shall notify the Engineer in writing of the intent to utilize the waiver prior to purchasing any De Minimis material and/or products. This written notice shall include the estimated cost of the De Minimis

Document Phase Document Description Page 13 material and/or products and the estimated total applicable costs for the project. Any noncompliant items outlined in the project specific Utilities and Rail Certification Note shall also be included.

B) Certification. Prior to the issuance of the Notice to Proceed, the Contractor shall submit a Department approved Build America, Buy America Certificate, certifying compliance with all applicable requirements. Once submitted, the Contractor is bound by the Certification. A false certification is a violation of 18 U.S.C. § 1001 and may result in criminal penalties. The Contractor bears the burden of proof of compliance.

In addition to the required Contractor certification, each manufacturer and/or supplier shall submit a certification to certify materials or supplies are in compliance with the applicable domestic material content procurement preferences found in the Buy America Act requirements (23 CFR 635.410) and the BABA Act (BABA) requirements (2 CFR part 184). The individual completing this form takes full responsibility for the information included in the form. The manufacturer/supplier shall utilize the AASHTO Domestic Materials Self-Certification Form.

C) Project Specific Waiver. At the Contractor’s request, the Cabinet may, but is not obligated to, seek a waiver of Buy America requirements if grounds for the waiver exist under 23 C.F.R. § 635.410(c) or will comply with the applicable Buy America requirements if a waiver of those requirements is not available or not pursued by the Cabinet. The time associated with the project specific waiver process will be considered non-compensable. Refer to the Federal Highway Administration’s Buy America webpage for more information.

4.00 DEFINITIONS.

A) Construction Materials. Pursuant to the definition in 2 CFR 184.3, construction materials are articles, materials or supplies that consist of only one of the following items. Minor additions of articles, materials, supplies or binding agents to a construction material do not change the categorization of a material as a “construction material”. All manufacturing processes for the construction material must occur in the United States.

• non-ferrous metals;

• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);

• glass (including optic glass);

• optical fiber;

• lumber;

• engineered wood; or

• drywall.

Not included: primarily iron or steel items; a manufactured product; cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives.

“All manufacturing processes” is defined as the final manufacturing process and the immediately preceding manufacturing stage for the construction material.

B) Manufactured Products. Pursuant to the definition in 2 CFR 184.3, manufactured products means articles, materials, or supplies that have been:

• (i) processed into a specific form and shape; or

• (ii) combined with other articles, materials, or supplies to create a product with different properties than the individuals’ articles, materials, or supplies.

An article, material, or supply classified as a manufactured product may include components that are construction materials, iron or steel products.

Document Phase Document Description Page 14

C) Iron and Steel. Pursuant to the definition in 2 CFR 184.3, iron or steel products means articles, materials, or supplies that consist wholly or predominantly of iron or steel or a combination of both. •

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such a bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the iron or steel components.”

The Certificate of Compliance must be submitted to Division of Purchases prior to award of contract.

G. DISADVANTAGED BUSINESS ENTERPRISE PROGRAM

DBE requirements do not apply because this contract is for commodities and not services.

Section 2 - Terms and Conditions of the Contract

2.00 - Executed Contract

The Contractor shall not deliver any items until a valid Contract has been fully executed. The Contract shall represent the entire agreement between the parties. Prior negotiations, representations, or agreements, either written or oral, between the parties hereto relating to the subject matter hereof shall be of no effect upon this Contract.

2.01 - Contract Components and Order of Precedence

The Commonwealth’s acceptance of the offer indicated by the issuance of an Award by the KYTC Division of Purchases shall create a valid contract consisting of the following:

1. The written contract between the Parties;

2. Any Addenda to the Solicitation;

3. Any provisions of the Solicitation and all attachments thereto;

4. The Bidder’s response to the Solicitation, and

5. The Kentucky Revised Statutes KRS 45A.

In the event of an inconsistency between provisions of the solicitation, the inconsistency shall be resolved by giving precedence in the following order: (a) the Specifications; (b) other provisions of the Solicitation, whether incorporated by reference or otherwise; (c) Contract or Master Agreement Terms and Conditions; (d) FAP 110-10-00 – General Conditions and Instructions for Solicitations and Contracts.

2.02 - Changes and Modifications to the Contract

During the period of the contract, a modification shall not be permitted in any of its conditions and specifications, unless the contractor receives electronic or written approval from the KYTC Division of Purchases. If the contractor finds at any time that existing conditions make modification in requirements necessary, the contractor shall report the matter promptly to the KYTC Division of Purchases for consideration and decision. All contract modifications shall be subject to the provisions of 200 KAR 5:311.

2.03 - Basis of Shipment

Document Phase Document Description Page 15

Quotations of unit prices on this solicitation shall be F.O.B. Destination Freight Prepaid and Allowed to the receiving agency. The vendor shall be fully responsible for all shipments and freight charges involved to the ordering agency. The responsibility for filing freight claims lies with the vendor.

2.04 - Notices

The Division of Purchases Buyer identified below shall be the sole point of contact throughout the procurement process. All communications, oral and written (regular, express, or electronic mail) concerning this procurement shall be submitted to:

Latasha Chenault

Division of Purchases

Kentucky Transportation Cabinet

Phone: 502-782-5673

E-mail: Latasha.Chenault@ky.gov

From the issue date of this solicitation until a Contractor(s) is selected and the selection is announced, Offerors are not permitted to communicate with any Commonwealth staff concerning this solicitation

After the award of a contract, all programmatic communications are to be made to the Agency Contact Person identified in the contract document with a copy to the Division of Purchases Buyer.

After the Award of a contract, all communications of a contractual or legal nature are to be made to the KYTC Division of Purchases Buyer.

2.05 - Delivery

Delivery greater than 120 calendar days may be deemed non-responsive. See Attachment G – Bid Sheet to enter delivery days.

The Vendor agrees that when delivery is not made within the contracted due date, one percent (1%) per day shall be deducted from the Vendor’s invoice for each day the Vendor fails to meet the contracted delivery date.

The Vendor is not responsible for and shall not be penalized for delays in its delivery when caused by factors or events outside Vendor’s control, including but not limited to acts or omissions of the Commonwealth or third parties, acts of civil or military authority, civil disturbance, war, terrorism, pandemics, explosions, fire, floods, tornadoes or other natural disasters or acts of God.

2.06 - Inspection

All supplies, equipment and services shall be subject to inspection or tests by the Commonwealth prior to acceptance. In the event supplies, equipment or services are defective in material or workmanship or otherwise not in conformity with specified requirements, the Commonwealth shall have the right to reject the items or services or require acceptable correction at the vendor’s expense.

Document Phase Document Description Page 16 mailto:Latasha.Chenault@ky.gov

2.07 – Payments

The Commonwealth will make payment within thirty (30) working days of receipt of Contractor's invoice and of acceptance of goods and/or services except when the agency has transmitted a rejection notice to the vendor in accordance with KRS 45.453 and KRS 45.454. For the purpose of this provision, a working day is any weekday except for Commonwealth employee holidays up to the agency close of business. The Commonwealth may make a partial payment of goods or services that it has received according to the terms of the contract.

Payments are predicated upon successful completion and acceptance of the described work, services, supplies, or commodities, and delivery of the required documentation. Invoices for payment shall be submitted to the agency contact person or agency representative and, except Personal Service Contract invoices, shall include the following information, as applicable:

(1) Contract and/or delivery order number;

(2) Name of Contractor Entity or Individual;

(3) Contractor designated point of contact;

(4) Unique Invoice Number;

(5) Invoice Date;

(6) Item numbers;

(7) Descriptions of goods or services provided;

(8) Sizes of goods provided;

(9) Quantities provided;

(10) Unit prices; and

(11) Extended totals (unit price x quantity) for invoiced line items.

For Personal Service Contracts, invoices must be submitted on the Personal Service Contract Invoice form established by the Government Contract Review Committee, available at:

https://apps.legislature.ky.gov/moreinfo/contracts/PSC%20INVOICE%20FORM.pdf

The Commonwealth will make a good faith effort to notify the Contractor within fifteen (15) working days of the Contractor’s failure to submit a proper invoice or a dispute of the goods or services provided. The Contractor shall address the Commonwealth’s concerns within ten (10) calendar days and resubmit a corrected invoice with a new invoice number for payment. If the Contractor has not rectified the problem with the invoice or the good or service within the ten (10) calendar day correction period, any revised submitted invoice shall be considered a new invoice with a new date of submission for calculation of any late payment penalty.

If the Commonwealth has not notified the Contractor of any issue with the invoice or the goods and/or services and the Contractor has not received payment by the twenty-fifth (25th) business day after the Contractor submitted the invoice, the Contractor should notify its Commonwealth contract representative that its invoice is still pending payment.

Except as otherwise explicitly provided in the contract, payments shall be issued to the Contractor within thirty (30) working days of receipt of Contractor's invoice or of acceptance of goods and/or services. In the event of an invoice payment dispute between the Contractor and purchasing agency, the Contractor shall first attempt resolution of the dispute via submission to the purchasing agency in accordance with the payment dispute process posted on the Finance and Administration Cabinet website, located at:

https://finance.ky.gov/office-of-the-secretary/office-of-general-counsel/Pages/procurement-and-protest-resources.aspx

If submission to the purchasing agency fails to resolve the payment dispute, the Contractor may submit a contract dispute regarding payment to the Finance Secretary for resolution. In accordance with KRS 45.454, and except as provided by KRS 371.405, there shall be payable to the Contractor a penalty of one-percent (1%) on any undisputed amount each month or fraction thereof owing to the Contractor after 30 working days following the receipt of the goods or services and receipt of the invoice unless otherwise agreed between the Commonwealth and the Contractor. After a resolution is determined, the purchasing agency shall begin to assess penalties due the Contractor and remit the penalty payment to the Contractor within ten (10) working days.

Document Phase Document Description Page 17

2700000232 Final Steel Strain Pole - FHWA Eligible Total Pages: 30 https://apps.legislature.ky.gov/moreinfo/contracts/PSC%20INVOICE%20FORM.pdf https://finance.ky.gov/office-of-the-secretary/office-of-general-counsel/Pages/procurement-and-protest-resources.aspx https://finance.ky.gov/office-of-the-secretary/office-of-general-counsel/Pages/procurement-and-protest-resources.aspx

2.08 - Post Contract Agreements

This contract will constitute the entire agreement between the State and awarded contractor. Unless contractually provided, the Commonwealth shall not be required to enter into nor sign further agreements, leases, company orders or other documents to complete or initiate the terms of the contract. Any such documents so obtained will be non-binding on the State and be cause for breach of contract.

2.09 – Ethics Compliance

Contractor certifies that contractor and its employees will not offer or provide gifts to KYTC employees in excess of $25.00 in any single calendar year as defined in KRS 11A.045 (1) and KYTC General Administration and Personnel Policy GAP-808. Moreover, contractor certifies that contractor and its employees will not offer any ticket to a sporting event to a KYTC employee without being reimbursed the face value amount for said ticket as defined in KRS 11A.045 (2).

It is agreed and understood that non-compliance with the above provisions may result in the suspension of vendor procurement participation, contract termination, and/or debarment.

2.10 - Termination of Contracts

A contract may be terminated for default by the vendor, for the convenience of the Commonwealth, or for lack of appropriation in accordance with 200 KAR 5:312.

2.11 - Endorsements

The Contractor shall not refer to the Award of Contract in commercial advertising in such a manner as to state or imply that the firm or its services are endorsed or preferred by the Commonwealth of Kentucky.

2.12 - Registration with the Secretary of State by a Foreign Entity

Pursuant to KRS 45A.480(1)(b), an agency, department, office, or political subdivision of the Commonwealth of Kentucky shall not award a state contract to a person that is a foreign entity required by KRS 14A.9-010 to obtain a certificate of authority to transact business in the Commonwealth (“certificate”) from the Secretary of State under

KRS 14A.9-030.

For all foreign entities required to obtain a certificate of authority to transact business in the Commonwealth, if a copy of the certificate is not received within the time specified by the Division of Purchases, the foreign entity’s solicitation response may be deemed non-responsive. If the foreign entity is not required to obtain a certificate as provided in KRS 14A.9-010, the foreign entity should identify the applicable exception in its solicitation response.

Foreign entity is defined within KRS 14A.1-070.

Vendors are required to remain in active and good standing during the life of the contract.

Businesses can register with the Secretary of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .