This is a Questions and Answers document for Federal Acquisition Regulation (FAR) solicitation FA670326Q0015 concerning fiber optic cable installation at the Dobbins Air Reserve Base (ARB) Air Traffic Control (ATC) Tower.
The document clarifies key requirements and constraints for offerors: site visit attendance is not mandatory; a Georgia low-voltage/electrical contractor license is not specifically required; bid, payment, and performance bonds are not required; and prime contractors may utilize qualified licensed fiber/low-voltage subcontractors subject to small business requirements. Personnel performing fusion splicing and optical testing must hold fiber certifications such as FOA/CFOT, BICSI, or manufacturer certifications. The installation involves routing single-mode fiber from the first floor to the observation deck through existing multimode conduit pathways. The existing multimode/fiber panel on the observation deck should be utilized if available; otherwise, a new Line Interface Unit (LIU) must be installed on the observation deck connecting to existing paths. Armored fiber must be protected from weather per commercial best practices. Service loops of 15 feet are required at both ends, with the observation deck loops integrated with existing infrastructure using outdoor-rated labeling, and first-floor loops coiled and labeled on the rack. Exact rack unit positions and labeling conventions will be determined at installation. Personnel require escorted access at all times, with operating hours Monday through Friday 8 a.m. to 11 p.m. and Saturday through Sunday 8 a.m. to 4 p.m.; a personnel list is required. Multimode fiber disposal must be removed and delivered to 94th Computer Squadron for proper handling. Wage determination 2015-4471 revision 37 applies, with FAR 52.222-41 or equivalent to be added in Amendment 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS__Dobbins_ARB_ATC_Fiber_Installation.pdf | ||
| Contract - FA670326P0020.pdf | ||
| WD 2015-4471 Rev 37 17 Aug 26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers for FA670326Q0015 fiber optic cable at the Dobbins ARB ATC Tower
1 Question Is attendance at a site visit mandatory for offerors? If so, please confirm the scheduled date/time and any visitor-access submission deadline.
Answer No
2 Question Is a Georgia low-voltage/electrical contractor license specifically required for this fiber installation scope, and if so, which classification is acceptable?
Answer no
3 Question Are bid, payment, or performance bonds required for this acquisition?
Answer No
4 Question May the prime contractor perform through a qualified licensed fiber/low-voltage subcontractor, subject to all applicable smallbusinesssubcontracting/limitations requirements?
Answer Yes
5 Question For FA670326Q0015, the RFQ lists wage determination 2015-4471 revision 37, which we have recovered, but we did not find FAR 52.222-41 in the 15-page RFQ clause inventory.
Answer 52.222-41 or its equivilent will be added in Amendment 2
6 Question Does identified vacant or slightly filled conduit run from the first floor in the ATC Tower to the observation deck?
Answer yes there is a path from the 1st floor to the observation deck utilizing the multimode path that exist.
7 Question Can we view the blueprint of the ATC Tower including all floors (1-7, roof)?
Answer No
8 Question Can another Site Visit be scheduled to see the pathway of the conduit on all floors (1-7) to determine the orientation of the closets on each floor and if floor penetrations have to be done?
Answer No to site visit
9 Question . Which rack will house the LIU on the observation deck?
Answer if available utilize the existing multimode/fiber panel on the observation deck. If no room inside install new LIU on the observation deck connecting to the existing path for connection to system
10 Question Will the current MaxCell be used to install new single mode fiber?
Answer if available utilize the existing multimode/fiber panel on the observation deck. If no room inside install new LIU on the observation deck connecting to the existing path for connection to system
11 Question Will armored fiber be required?
Answer it will need to protected from any weather by fiber approved commercial best practices.
12 Question The rack at the observation deck was not identified for the rack-mounted LIU. Will this be addressed?
Answer if available utilize the existing multimode/fiber panel on the observation deck. If no room inside install new LIU on the observation deck connecting to the existing path for connection to system
13 Question Exact Rack Locations – Please confirm the exact rack units (RU positions) for LIU installation on both floors.
Answer will be accomplished at time of installation.
14 Question Pathway Capacity Verification – Are the existing conduit/cable tray/riser pathways confirmed to have available capacity? If not, provide pathway drawings or authorize installation of innerduct/J-hooks.
Answer Yes
15 Question Approved Fiber Route – Provide any existing route drawings or confirm contractor-proposed routing is acceptable.
Answer none available
16 Question Labeling Convention – Confirm required labeling format beyond ANSI/TIA-606-C (e.g., color codes, naming schema).
Answer will be accomplished at time of installation.
17 Question Access Requirements – Clarify any ATC Tower restrictions, quiet hours, or operational constraints.
Answer Personnel will be escorted at all times. Cab access and quiet hours will be determined by airfield operations at the time. Operating hours are Mon - Fri 8am to 11pm. Sat - Sun 8am to 4pm. No holidays. Personnel list will be required.
18 Question Environmental Disposal Requirements – Provide Dobbins ARB environmental guidelines for MM fiber disposal.
Answer remove mm fiber from location and deliver to 94CS for disposal.
19 Question Service Loop Locations – Confirm exact service loop placement areas for the required 15 ft loops at both ends.
Answer on obversation deck, integrate with existing loops, marking this new single mode with outdoor rated labeling. On 1st floor, leave nice coils on the rack labeled.
20 Question Are personnel performing the fusion splicing and OTDR/OLTS testing required to hold any specific fiber certification, such as FOA/CFOT, BICSI, or a manufacturer certification?
Answer yes, anyone of those would work.