Summary of City of Sherman, Texas Annual Concrete Work Services IFB (PW-IFB4006-27)
This Invitation for Bid (IFB) document is issued by the City of Sherman, Texas, soliciting sealed bids from qualified contractors to provide on-call concrete work services on an as-needed basis at various locations throughout the city. The scope of work includes sidewalk repair and installation, curbs, ADA compliance upgrades, and related flatwork, with all labor, equipment, and materials to be furnished in accordance with TXDOT Standards and Specifications. The IFB was advertised on November 3 and 10, 2026, with a question deadline of November 12, 2026, at 10:00 a.m., and answers provided by November 13, 2026, at 4:00 p.m. Sealed bids are due on November 18, 2026, at 2:00 p.m., with City Council approval estimated for December 21, 2026, and a contract start date of January 1, 2027. The contract is an annual agreement with an initial one-year term commencing on the Effective Date, followed by up to four additional one-year renewal options, contingent upon mutual written agreement between the City and the awarded vendor. Contractors must submit bids through Public Purchase, in person at City Hall (220 W Mulberry, Sherman, TX 75090), or by courier, with prices held firm for a minimum of 90 days from the bid closing date.
The evaluation criteria for award includes 40 percent pricing, 30 percent references, 25 percent ability to perform the requested services (verified through references), and 5 percent past experience with municipal government. All pricing must be F.O.B. Destination, Sherman, Texas, with all delivery and packaging costs included. The City expects payment within thirty days of receipt of invoice, unless supporting documentation has been requested or a dispute arises. Contractors are required to provide General Liability insurance with a minimum of $1,000,000 per occurrence and $2,000,000 in the aggregate, Workers' Compensation and Employers Liability coverage, Automobile Liability insurance, and Umbrella/Excess Liability coverage of $2,000,000. The City retains the right to terminate the contract at any time with thirty days' notice for convenience or immediately upon breach. The contract is subject to cancellation if funds are not approved in the City's next fiscal year, which closes September 30th, as state law prohibits municipal commitment of funds beyond the fiscal year. Contractors must complete three contractor references and submit the Texas Ethics Commission Form 1295 (Certificate of Interested Parties) online prior to contract execution.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Sherman PO Box 1106 Sherman, TX 75091-1106
PW-IFB4006-27
Annual Concrete Work Services
Expected Timeline:
Advertise November 3 and 10, 2026
Question Deadline November 12, 2026 at 10 am
Questions Answered November 13, 2026 at 4 pm
IFB Submission Deadline November 18, 2026 at pm
Estimated Council Approval December 21, 2026
Estimated Contract Start January 1, 2027
CITY OF SHERMAN, TEXAS
Bidder must submit their bid response utilizing the following:
1) Public Purchase at https://www.publicpurchase.com
2) In person at City Hall, 220 W Mulberry, Sherman, TX 75090 or
3) By courier, delivered to 220 W Mulberry, Sherman, TX 75090
Bid responses shall not be submitted by facsimile, email or other type of submission other than the stated deliveries.
Prices quoted must be held for a minimum of ninety (90) days from date of bid closing. In the case of estimated requirements, the prices shall remain firm during the term of the contract. Discount from list or clauses that are known as “escalator” or “cost-plus” responses shall not be accepted.
In the case of estimated requirements, the quantities appearing are estimated as realistically as possible. However, the City reserves the right to increase, decrease, or delete any item or items being furnished while continuing to pay the price quoted regardless of quantity.
Bids must be submitted on units specified, extended and show total. In the event of discrepancies in extension, unit prices shall govern.
F.O.B./Damage: Items shall be bid F.O.B. Destination, delivered to the designated municipal facility and shall include all delivery and packaging costs. The City assumes no liability for goods delivered in damaged or unacceptable condition. The successful bidder shall handle all claims with carriers, and in the case of damaged goods, shall ship replacement goods immediately upon notification of City staff.
Bids subject to unlimited price increases shall not be considered. The City reserves the right to solicit bids for larger projects.
The enclosed INVITATION FOR BID (IFB) and accompanying specifications are for your convenience in bidding for the City of Sherman.
Bids may be submitted as follows:
City of Sherman Finance Dept.
• P.O. Box 1106 Sherman, TX 75091-1106
• Electronically at www.publicpurchase.com
• By delivery at City Hall, address listed above.
Bids will be received by the City of Sherman, Sherman, Texas, at the Finance Department, Attention: Carla Hommel, City Hall, 220 W Mulberry St, Sherman, Texas 75092-1106, until the hour 2:00 PM on the 18TH day of November, 2026, at which time bids duly delivered and submitted will be considered.
QUESTION AND ANSWER PERIOD
Questions will be received by email only. All questions MUST be sent to carlah@cityofsherman.com by November 12, 2026 at 10 am. Answers will be issued by addendum by November 13, 2026 at 4 pm.
https://www.publicpurchase.com/ http://www.publicpurchase.com/ mailto:carlah@cityofsherman.com
The award is intended to be included on the agenda of a regularly scheduled meeting of the City Council.
Each bid delivered to the City shall be sealed and clearly marked “PW-IFB4006-27 Concrete Work Services” on the exterior of the bid. Electronic submittals may only be made through Public Purchase at https://www.publicpurchase.com. No email or faxed bids will be accepted. Each bid shall be manually signed and dated by a person having the authority to bind the firm in a contract. Bids that are not signed and dated will be rejected.
Please note that all bids must be received at the designated location or through Public Purchase by the deadline shown. Bids received after the deadline will not be considered for the award of the contract and shall be considered void and unacceptable. The bid submission deadline is scheduled for 2:00 p.m., November 18, 2026, at which time the sealed bids will be opened.
Any bid received after stated closing time will be returned unopened. If bids are sent by mail to the Finance Department, the bidder shall be responsible for actual delivery of the bid before the advertised date and hour for opening of bids. If the mail is delayed by the postal service, courier service, or an ISP (Internet Service Provider), beyond the date and hour set for the bid opening, bids thus delayed will not be considered.
Bidders should carefully examine all terms, conditions, specifications, Evaluation Criteria, supplied agreement, and related documents. Should a bidder find discrepancies in, or omissions from, the specifications or related documents, or should there be doubt as to their meaning, the City of Sherman Finance Department should be notified immediately for clarification prior to submitting the bid. In the event of any conflict between the terms and conditions of these requirements and the specifications, the specifications shall govern. In the event of any conflict of interpretation of any part of this overall document, the City of Sherman’s interpretation shall govern.
Information concerning the bid specifications or bid process/procedures may be submitted in writing to Carla Hommel, Purchasing Agent, at carlah@cityofsherman.com, or via phone at (903) 487-5976.
Until the final awarding by the City of Sherman, said City reserves the right to reject any and/or all bids, to waive technicalities, to re-advertise, and proceed otherwise when the best interests of said City will be realized hereby.
ADDENDA
It is the responsibility of the vendor to check for addenda. Addenda will be posted to:
www.ci.sherman.tx.us and to www.publicpurchase.com.
ANNUAL CONTRACT FUNDING
The city operates on a fiscal year that ends on September 30th. Because state law mandates that a municipality may not commit funds beyond a fiscal year, this bid is subject to cancellation if funds for this service are not approved in the next fiscal year.
BID CONSIDERATION / TABULATION
Until final award of the Contract, the city reserves the right to reject any or all bids, to waive technicalities, https://www.publicpurchase.com/ mailto:carlah@cityofsherman.com http://www.ci.sherman.tx.us/ http://www.publicpurchase.com/ and to re-advertise for new bids, or proposed to do the work otherwise in the best interests of the City.
BRAND NAMES
If items for which bids have been called for have been identified by a “brand name or equal” description, such identification is intended to be descriptive, but not restrictive, and is to indicate the quality and characteristics of products that will be satisfactory. Bids offering “equal” products will be considered for award if such products are clearly identified in the bids and are determined by the City to be equal in all material respects to the brand name products referenced. Unless the bidder clearly indicates in their bid that they are offering an “equal product”, their bid shall be considered as offering a brand name product referenced in the Proposal Schedule.
CHANGES OR ALTERATIONS
No part of this bid may be changed/altered in any way. Vendors must submit written requests to change any specifications/conditions with their proposal. Changes made without submission of a written request, and approval by the City, will result in disqualification.
COMPLETING INFORMATION
Bidder must fill in all information asked for in the blanks provided under each item EXCEPT for the agreement. Only the awarded respondents shall be required to complete the agreement. Failure to comply may result in rejection of the Bid at the City’s option.
CONTRACT CLAUSE
All bidders understand and agree that the vendor’s bid response will become a legally binding contract upon acceptance in writing by the City. This contract may be superseded only if replaced with a more extensive contract that is agreed to by both parties.
DELIVERY
The City reserves the right to demand bond or penalty to guarantee delivery by the date indicated. If order is given and the Bidder fails to furnish the materials by the guaranteed date, the City reserves the right to cancel the order without liability on its part. All prices are to be F.O.B. Sherman, Texas all freight prepaid.
DELIVERY DATE
Delivery date is an important factor to the City and may be required to be a part of each bid. The City of Sherman considers delivery time to be that period elapsing from the time the individual order is placed until that order or work thereunder is received by the City at the specified delivery location. The delivery date indicates a guaranteed delivery at Sherman, Texas. Failure of the bidder to meet guaranteed delivery dates or service performance could affect future City orders.
Whenever the Contractor encounters any difficulty which is delaying or threatens delaying timely performance (including actual or potential labor disputes), the Contractor shall immediately give notice thereof in writing to the City, stating all relevant information with respect thereto. Such notice shall not in any way constitute a basis for an extension of the delivery or performance schedule or be construed as a waiver by the City of any rights or remedies to which it is entitled by law or pursuant to provisions herein.
Failure to give such notice, however, may be grounds for denial of any request for an extension of the delivery or performance schedule because of such delivery.
INSURANCE
Deductibles, of any type, are the responsibility of the vendor/contractor.
MISCELLANEOUS
Except as to any supplies or components which the specifications provide need not be new, all supplies and components to be provided under this contract shall be new (not used or reconditioned, and not of such age or so deteriorated as to impair their usefulness or safety), of current production and of the most suitable grade for the purpose intended. If at any time during the performance of this contract the Contractor believes that the furnishing of supplies or components which are not new is necessary or desirable, they shall notify the City immediately, in writing, including the reasons therefore and proposing any consideration which will flow to the City if authorization to use supplies or components is granted.
Successful bidder(s) agrees to extend prices to all entities that have entered or will enter into joint purchasing inter-local cooperation agreements with the city of Sherman. As such, the city of Sherman has executed an inter-local agreement with certain other governmental entities authorizing participation in a cooperative purchasing program. The successful vendor may be asked to provide product/services, based upon the bid price, to any other participant in the forum.
The responding bidders are financially responsible for their own preparation of their bid document response and any/all meetings or appointments associated with this bid. The City does not assume any financial liability in a bidder’s cost for their bid response.
The City operates on a fiscal year that ends on September 30th. State law mandates that a municipality may not commit funds beyond a fiscal year; this bid is subject to cancellation if funds for this commodity are not approved in the next fiscal year.
Termination for Default: The City reserves the right to enforce the performance of this contract in any manner prescribed by law or deemed to be in the best interest of the city in the event of breach or default of this contract. The City reserves the right to terminate this contract within ten (10) days in the event the successful bidder fails to 1) meet delivery schedules or 2) otherwise fails to perform in accordance with these specifications. Breach of contract or default authorizes the City to, among other things, award another to another bidder, purchase elsewhere and charge the full increase in cost and handling to the defaulting bidder.
Termination for convenience: The City reserves the right to terminate any resulting contract from this bid for convenience, by supplying the awarded bidder with at least thirty (30) days’ notice.
Venue: Bidder shall comply with all Federal and State laws and City ordinances and Codes applicable to the bidders’ operation under this contract. These specifications and the contract resulting here from shall be fully governed by the laws of the State of Texas, and shall be fully performable in Grayson County, Texas, where venue for any proceeding arising hereunder will lie.
The apparent silence of these specifications as to detail or to the apparent omission from it of detailed description concerning any point shall be regarded as meaning that only the best commercial practices are to prevail.
PAYMENT TERMS & CONDITIONS
All bids shall specify terms and conditions of payment, which will be considered as part of, but not control, the award of bid. City review, inspection, and processing procedures ordinarily require thirty (30) days after receipt of invoice, materials or service. Bids which call for payment before the elapse of 30 days from receipt of invoice, or cash discounts given on such payment, will be considered only if in the opinion of the City the review, inspection and processing procedures can be completed as to the specific purchases within the specified time.
It is the intention of the city of Sherman to make payment on completed orders within thirty (30) days of receiving invoicing unless unusual circumstances arise. Invoices shall be fully documented as to labor, materials and equipment provided.
REJECTION OF BIDS
The City reserves the right to reject any or all bids or to waive technicalities at its option when in the best interests of said City. Bids will be considered irregular if they show any omissions, alteration of form, additions, or conditions not called for, unauthorized alternate bids or irregularities of any kind. However, the City reserves the right to waive any irregularities and to make the award in the best interests of the City.
The City reserves the right to reject any or all bids, and all bids submitted are subject to this reservation.
Bids may be rejected, among other reasons, for any of the following specific reasons:
• Bids received after the time limit for receiving bids as stated in the advertisement.
• Proposal containing any irregularities.
• Bids submitted via fax or email.
• Unbalanced value of any items.
Bidders may be disqualified and their bids not considered, among other reasons, for any of the following specific reasons:
• Reason for believing collusion exists among the Bidders.
• Reasonable grounds for believing that any Bidder is interested in more than one Proposal for the work contemplated.
• The Bidder being interested in any litigation against the City.
• The Bidder being in arrears on any existing contract or having defaulted on a previous contract.
• Lack of competency as revealed by a financial statement, experience and equipment, questionnaires, etc.
• Uncompleted work, which in the judgment of the City will prevent or hinder the prompt completion of additional work if awarded.
REQUEST FOR NON-CONSIDERATION
Bids deposited with the City cannot be withdrawn prior to the time set for opening bids. Requests for non-consideration of bids must be made in writing to the Finance Department and received by the City prior to the time set for opening bids. After other bids are opened and publicly read, the Proposal for which non-consideration is properly requested may be returned unopened. The Proposal may not be withdrawn after the bids have been opened, and the Bidder, in submitting the same, warrants and guarantees that this bid has been carefully reviewed and checked and that it is in all things true and accurate and free of mistakes and that such bid will not and cannot be withdrawn because of any mistake committed by the Bidder.
SALES TAX
The total for each bid submitted must include any applicable taxes. Although the City is exempt from most City, State, or Federal taxes, this is not true in all cases. It is suggested that taxes, if any, be separately identified, itemized, and stated on each bid. The City cannot determine for the bidder whether the bid is taxable to the City. The bidder through the bidder’s attorney or tax consultant must make such determination. Bills submitted for taxes after the bids are awarded will not be honored.
PROPOSAL TERMS
The City of Sherman reserves the right to reject any, or all, bids received because of this IFB. If a bid is selected, it will be the most advantageous regarding price, quality of service, the independent contractor's qualifications and capabilities to provide the specified service, and other factors which the City of Sherman may consider.
Bids must be signed by an official authorized to bind the independent contractor to its provisions for a period of at least ninety (90) days. In the event it becomes necessary to revise any part of the IFB, addenda will be provided. Responses should be prepared simply and economically providing a straightforward, and concise description of the independent contractor's ability to meet the requirements of the IFB.
The price quotations from the contractor stated in this response will not be subject to any price increase from the closing date of this IFB to the mutually agreed date of contract.
The City of Sherman reserves the right to increase or decrease the number of services based upon annual budget constraints with fifteen (15) days’ notice.
The City of Sherman reserves the right to award a separate contract to separate vendors for each item/group or to award one contract for the entire IFB. The bidder agrees to indemnify and hold harmless from any claim involving patent right infringement or copyrights on goods supplied.
CONTRACT
Contract Period/Renewal Terms: This is an annual contract beginning XXXXXXXXX. The City shall allow for one (1) initial annual term from XXXXX to XXXX, allowing for up to four (4) additional one (1) year renewal options. Renewal options are not guaranteed and are based solely upon the written agreement between both the City and awarded vendor. Either party dissenting will terminate the contract in accordance with its initial specified term.
COOPERATIVE PURCHASING
As permitted under the Texas Local Government Code, Chapter 791.025, other government entities may wish to also participate under the same terms and conditions contained in this contract (Interlocal Agreement). Each entity
EVALUATION PROCESS
All submitted proposals will be reviewed by the City of Sherman for compliance with the specified IFB requirements. The selection committee will select which responses meet the requirements and those shall receive further evaluation.
Based on the firm’s response to the IFB requirements, the selection committee will determine the top firm(s) capable of meeting the needs of the City for such services. The City may invite the top firm(s) for an interview before considering a contract. Once the firm has been selected, the City will submit an agreement to the City Council for approval. The following evaluation criteria will be considered by the selection committee.
BEST VALUE EVALUATION CRITERIA
40% Pricing 30% References
25% Ability to perform the requested services (verified through references) 5% Past experience with a municipal government
(remainder of page intentionally left blank)
SPECIFICATIONS
The City of Sherman, Texas is soliciting sealed bids from qualified contractors to provide on-call concrete work services on an as-needed basis. The successful bidder will be responsible for providing the services at various locations throughout the city. The scope of work includes, but is not limited to, sidewalk repair and installation, curbs, ADA compliance upgrades, and any other related flatwork.
The resulting contract shall consist of furnishing all labor, equipment, and materials necessary to perform concrete construction and repair in accordance with the TXDOT Standards and Specifications.
SCOPE OF WORK
The contractor shall make measurements and determine all quantities and amounts of work done under the contract. The contractor shall provide the services required according to the bid form and pricing submitted.
No payment shall be made for any materials or work performed outside of the intended work area.
No payment shall be made for any materials wasted. Any work that is not compliant with the quantity and scope of the contract shall not be paid unless previously approved by the City designee.
Any material (concrete) that is removed from the work site shall be disposed of at a city appointed location. Disposal of used concrete shall be at no expense to the contractor. Any dirt removal shall be disposed of at a city appointed location at no cost to the contractor.
Contractor shall not charge the City for any additional supplies, material or labor that was overestimated.
All on-call work shall be completed by a mutually agreed upon schedule by the City and contractor.
Contractor shall be responsible for any traffic control and barricades required for on-call work.
However, the City may provide cones, barricades, etc. at the request of the contractor. It is the contractor’s responsibility to effectively barricade and secure the work area in order to eliminate pedestrian access and protect pedestrians from work-site hazards as appropriate.
Contractor shall ensure the project location is left in a clean and tidy condition. The contractor shall be responsible for repairing any affected areas during the project. Any damages caused to the area by the contractor shall be repaired or replaced by the contractor at no expense to the City. This shall include, utilities, pavements, sidewalks, structures, etc. Incidental landscaping repair and backfill around the concrete associated with the work shall be completed by the contractor.
BID WORKSHEET
1 Remove, dispose, and replace existing 4” concrete sidewalk, 1-50 square yards
SY
2 Remove, dispose, and replace existing 4” concrete sidewalk, 51-200 square yards
SY
3 Construct new 4” sidewalks with headers, dowels, expansion joints, excavation and disposal of soil 1-50 square yards
SY
4 Construct new 4” sidewalks with headers, dowels, expansion joints, excavation and disposal of soil 51-200 square yards
SY
5 All other concrete flatwork not described by sidewalk, curb, or ADA ramp
SY
6 Remove, dispose, and replace existing curb, all types LF
7 Construct new curbs, all types LF
8 Remove, dispose, and replace existing concrete ADA wheelchair ramp, all types
EA
9 Install new concrete ADA wheelchair ramp with headers, dowels, expansion joints, and integral color, all types
EA
10 Concrete saw cutting LF
Contractor References
References must be for similar services
Customer Name: ___________________________________________________________
Address: _________________________________________________________________
Contact: ____________________________ Telephone #: __________________________
Email: ______________________________
Scope of work performed: ____________________________________________________
Length of Service: __________________________________________________________
Contact: ____________________________ Telephone #: __________________________
Email: ______________________________
Contact: ____________________________ Telephone #: __________________________
Email: ______________________________
CERTIFICATE OF INTERESTED PARTIES – FORM 1295 In 2015, the Texas
Legislature adopted House Bill 1295, which added section 2252.908 of the
Government Code. The law states that a governmental entity may not enter certain contracts with a business entity unless the business entity submits a disclosure of interested parties to the governmental entity at the time the business entity submits the signed contract to the governmental entity. The law applies only to a contract of a governmental entity that either (1) requires an action or vote by the governing body of the entity before the contract may be signed or (2) has a value of at least
$1 million. The disclosure requirement applies to a contract entered on or after
January 1, 2016. Form 1295 must be completed online. The form is available from the Texas Ethics Commission by accessing the following web address:
https://www.ethics.state.tx.us/filinginfo/1295/. Print your completed Form 1295, have it signed. Submit your completed Form 1295 to your City of Sherman department contact.
**DO NOT COMPLETE THIS FORM ON THE ETHICS WEBSITE UNTIL
INSTRUCTED TO DO SO**
https://www.ethics.state.tx.us/filinginfo/1295/
SAM
PLE
Services Agreement Page 1 of 10 5029706
AGREEMENT FOR CONCRETE WORK SERVICES
The City of Sherman, Texas, a home-rule municipality (“City”), and Click or tap here to enter text., a Click or tap here to enter text. (LLC, Partnership, etc.) (“Contractor”), hereby enter into this Agreement for Concrete Work (“Agreement”). City and Contractor are sometimes referred to collectively as the “parties” or individually as a “party.”
WHEREAS City desires to engage Contractor to perform Concrete Work services under the terms and conditions of this Agreement.
NOW, THEREFORE, in consideration of the mutual agreements and covenants contained herein and other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the parties agree as follows:
1. Scope of Services.
Contractor shall provide the services and deliverables that are described in the Agreement
Documents (as defined below) and shall furnish all personnel, labor, equipment, supplies and all other items necessary to provide the services and deliverables as specified by the terms and conditions of the Agreement Documents (collectively, “Services”).
2. Compensation.
In exchange for Contractor’s performance of the Services in accordance with the
Agreement Documents, City agrees to pay Contractor in accordance with the Vendor
Pricing, attached hereto as Exhibit B. To the extent the terms of the Agreement Documents conflict with the Texas Prompt Payment Act, Chapter 2251 of the Texas Government Code, as amended (“Chapter 2251”) or Subchapter I of Chapter 271 of the Texas Local
Government Code, as amended (“Chapter 271”), the terms of Chapter 2251, Chapter 271 and the Agreement Documents shall control in that order.
City shall pay Contractor within thirty (30) days of receipt of each invoice, unless supporting receipts or other supporting documentation have been requested by City, in which case City shall pay the invoice as soon after receiving the supporting receipts or documentation as is reasonable; or unless a dispute arises as to any charge(s) contained in the invoice, in which case City shall pay the undisputed amount of the invoice within thirty
(30) days of receipt and shall pay the remaining amount, if any, of the invoice after resolution of the dispute as soon after resolution as is reasonable. Notwithstanding anything to the contrary in the Agreement Documents, City shall not be required to pay any invoice submitted by Contractor if Contractor is in breach of this Agreement.
Term.
The initial term of the Agreement shall be for a period of one (1) year, commencing on the
Effective Date (herein defined) of this Agreement. City shall have the option to extend this Agreement for up to two (2) additional terms of one (1) year each on the same terms and conditions of this Agreement by giving the Contractor written notice of its intent to extend prior to the expiration of the then-current one (1) year term.
Services Agreement Page 2 of 10 5029706
The parties agree that the continuation of this Agreement after the close of any given fiscal year of City, which closes on September 30th of each calendar year, shall be subject to City
Council approval. In the event that the City Council does not approve the appropriation of funds for this Agreement, the Agreement shall terminate at the end of the fiscal year for which funds were appropriated, and the parties shall have no further obligations hereunder, except that City shall be obligated to pay monies owed Contractor for Services it has provided pursuant to this Agreement through the end of that fiscal year provided that
Contractor is not in breach of this Agreement.
3. Agreement Documents.
The “Agreement Documents,” as that term is used herein, shall mean and include the following documents, and this Agreement expressly incorporates the same herein by reference for all purposes:
A. This Agreement;
B. Specifications, attached hereto as Exhibit A
C. Vendor Pricing, attached hereto as Exhibit B;
This Agreement shall incorporate the terms of the Agreement Documents in their entirety.
To the extent that Exhibit A or Exhibit B are in conflict with provisions of this Agreement or each other, the provisions of this Agreement, then the provisions of Exhibit A and
Exhibit B shall prevail in that order. Should disputes arise as to responsibilities and obligations set forth in the Agreement Documents, City’s interpretation and/or decision shall be final and binding.
4. Entire Agreement.
The Agreement Documents contain all representations, understandings, contracts and agreements between the parties regarding the subject matter of this Agreement. The
Agreement Documents supersede all oral or written previous and contemporaneous agreements, writings, understandings, representations, or contracts between the parties regarding the subject matter of this Agreement. This Agreement in no way modifies or supersedes any document executed by the parties prior to the Effective Date of this
Agreement which does not concern the subject matter of this Agreement. No amendment to the Agreement Documents shall be made except on the written agreement of the parties, which shall not be construed to release either party from any obligation of the Agreement
Documents except as specifically provided for in such amendment.
5. Required Insurance.
Contractor shall not start work under this Agreement until Contractor has obtained, at
Contractor’s expense, all of the insurance specified in, and required by, the Agreement
Documents. Contractor shall procure and keep in full force and effect the types and amounts of insurance specified below for and during all aspects and phases of Contractor’s work throughout the term of this Agreement at no expense to City. Contractor also shall comply with all other requirements set forth below.
Services Agreement Page 3 of 10 5029706
GENERAL INSURANCE REQUIREMENTS – Items
__X___ 1. Worker’s Compensation & $100,000 per injury, $300,000 per occurrence, Employers Liability and $100,000 per occupational disease.
___X__ 2. General Liability Minimum $1,000,000.00 each occurrence
Minimum $2,000,000.00 in the aggregate
__X___ 3. Automobile Liability Minimum $1,000,000.00 each occurrence
__NO___ 4. XCU Coverage Minimum $1,000,000.00 each occurrence
__NO___ 5. Professional Liability Minimum $1,000,000.00 each claim
__X___ 6. Umbrella Coverage or Excess An amount of $2,000,000.00
Liability
7. City and its officers, agents, representatives and employees named as additional insured on General Liability Policy, as provided above. This coverage is primary to all other coverage City may possess.
8. General Liability Insurance provides for a Waiver of Subrogation against City for injuries, including death, property damage, or any other loss to the extent that same is covered by the proceeds of the insurance. All insurance policies that are required to name City as an additional insured must be endorsed to read as primary and non-contributory coverage regardless of the application of other insurance.
9. Thirty (30) days’ notice of cancellation, non-renewal, or material change required. The words “endeavor to” and “but failure” (to end of sentence) are to be eliminated from the Notice of Cancellation provision on standard ACORD certificates.
10. Insurance company has a minimum rating of “A” by A.M. Best’s Key Rating
Guide, or other equivalent rating service(s).
11. The Certificate of Insurance must state the project title.
INSURANCE COMPANY QUALIFICATION – All insurance companies providing the required insurance shall be authorized to transact business in the State of Texas and shall have a minimum rating of “A” by A.M. Best’s Key Rating Guide, or other equivalent rating service(s).
Services Agreement Page 4 of 10 5029706
CERTIFICATE OF INSURANCE – A Certificate of Insurance and all applicable endorsement(s) evidencing the required insurance shall be submitted prior to commencing work under this Agreement. If the Agreement is renewed or extended by City, a Certificate of Insurance and all applicable endorsement(s) shall also be provided to City prior to the date the Agreement is renewed or extended.
6. No Prohibited Interest; Vendor Disclosure.
Contractor acknowledges and agrees that it is aware of, and will abide by, the no prohibited interest requirement of the City Charter. Contractor shall execute and deliver to City the
Affidavit of Ownership. Contractor acknowledges and agrees that the existence of a prohibited interest during the term of this Agreement will render this Agreement voidable.
Contractor further acknowledges and agrees that it also is aware of, and will abide by, the vendor disclosure requirements set forth in Chapter 176 of the Texas Local Government
Code, as amended. In this connection, Contractor shall execute and deliver to City the
Conflict-of-Interest Questionnaire, Form CIQ.
7. Indemnity.
CONTRACTOR HEREBY RELEASES AND SHALL DEFEND, INDEMNIFY AND HOLD HARMLESS CITY
AND ITS CITY COUNCIL MEMBERS, OFFICERS, AGENTS, REPRESENTATIVES AND EMPLOYEES
(COLLECTIVELY REFERRED TO AS “CITY” FOR PURPOSES OF THIS SECTION) FROM AND
AGAINST ALL DAMAGES, INJURIES (WHETHER IN CONTRACT OR IN TORT, INCLUDING
PERSONAL INJURY AND DEATH), CLAIMS, PROPERTY DAMAGES (INCLUDING LOSS OF USE),
LOSSES, DEMANDS, SUITS, ACTIONS, JUDGMENTS, LIENS, COSTS AND EXPENSES, INCLUDING
REASONABLE ATTORNEY’S FEES AND EXPENSES (INCLUDING ATTORNEY’S FEES AND EXPENSES
INCURRED IN ENFORCING THIS SECTION), THAT IN WHOLE OR IN PART ARISE OUT OF OR ARE
CONNECTED WITH GOODS AND/OR SERVICES PROVIDED BY CONTRACTOR, ITS OFFICERS,
AGENTS, REPRESENTATIVES, EMPLOYEES, SUBCONTRACTORS, LICENSEES, INVITEES OR ANY
OTHER THIRD PARTIES FOR WHOM CONTRACTOR IS LEGALLY RESPONSIBLE (COLLECTIVELY
REFERRED TO AS “CONTRACTOR” FOR PURPOSES OF THIS SECTION) PURSUANT TO THIS
AGREEMENT AND/OR THE NEGLIGENT, GROSSLY NEGLIGENT AND/OR INTENTIONAL
WRONGFUL ACT AND/OR OMISSION OF CONTRACTOR IN ITS/THEIR PERFORMANCE OF THIS
AGREEMENT, REGARDLESS OF THE JOINT OR CONCURRENT NEGLIGENCE OF CITY
(COLLECTIVELY, “CLAIMS”). THIS INDEMNIFICATION PROVISION AND THE USE OF THE TERM
“CLAIMS” IS ALSO SPECIFICALLY INTENDED TO APPLY TO, BUT IS NOT LIMITED TO, ANY AND
ALL CLAIMS, WHETHER CIVIL OR CRIMINAL, BROUGHT AGAINST CITY BY ANY GOVERNMENT
AUTHORITY OR AGENCY RELATED TO ANY PERSON PROVIDING SERVICES UNDER THIS
AGREEMENT THAT ARE BASED ON ANY FEDERAL IMMIGRATION LAW AND ANY AND ALL
CLAIMS, DEMANDS, DAMAGES, ACTIONS AND CAUSES OF ACTION OF EVERY KIND AND NATURE,
KNOWN AND UNKNOWN, EXISTING OR CLAIMED TO EXIST, RELATING TO OR ARISING OUT OF
ANY EMPLOYMENT RELATIONSHIP BETWEEN CONTRACTOR AND ITS EMPLOYEES OR
SUBCONTRACTORS AS A RESULT OF THAT SUBCONTRACTOR’S OR EMPLOYEE’S EMPLOYMENT
AND/OR SEPARATION FROM EMPLOYMENT WITH CONTRACTOR, INCLUDING BUT NOT LIMITED
TO ANY DISCRIMINATION CLAIM BASED ON SEX, SEXUAL ORIENTATION OR PREFERENCE,
RACE, RELIGION, COLOR, NATIONAL ORIGIN, AGE OR DISABILITY UNDER FEDERAL, STATE OR
LOCAL LAW, RULE OR REGULATION, AND/OR ANY CLAIM FOR WRONGFUL TERMINATION,
BACK PAY, FUTURE WAGE LOSS, OVERTIME PAY, EMPLOYEE BENEFITS, INJURY SUBJECT TO
RELIEF UNDER THE WORKERS’ COMPENSATION ACT OR WOULD BE SUBJECT TO RELIEF UNDER
Services Agreement Page 5 of 10 5029706
ANY POLICY FOR WORKERS COMPENSATION INSURANCE, AND ANY OTHER CLAIM, WHETHER
IN TORT, CONTRACT OR OTHERWISE.
IN ITS SOLE DISCRETION, CITY SHALL HAVE THE RIGHT TO APPROVE OR SELECT DEFENSE
COUNSEL TO BE RETAINED BY CONTRACTOR IN FULFILLING ITS OBLIGATION HEREUNDER TO
DEFEND AND INDEMNIFY CITY, UNLESS SUCH RIGHT IS EXPRESSLY WAIVED BY CITY IN
WRITING. CITY RESERVES THE RIGHT TO PROVIDE A PORTION OR ALL OF ITS OWN DEFENSE;
HOWEVER, CITY IS UNDER NO OBLIGATION TO DO SO. ANY SUCH ACTION BY CITY IS NOT TO
BE CONSTRUED AS A WAIVER OF CONTRACTOR’S OBLIGATION TO DEFEND CITY OR AS A
WAIVER OF CONTRACTOR’S OBLIGATION TO INDEMNIFY CITY PURSUANT TO THIS
AGREEMENT. CONTRACTOR SHALL RETAIN CITY-APPROVED DEFENSE COUNSEL WITHIN
SEVEN (7) BUSINESS DAYS OF CITY’S WRITTEN NOTICE THAT CITY IS INVOKING ITS RIGHT TO
DEFENSE OR INDEMNIFICATION UNDER THIS AGREEMENT. IF CONTRACTOR FAILS TO RETAIN
COUNSEL WITHIN SUCH TIME PERIOD, CITY SHALL HAVE THE RIGHT TO RETAIN DEFENSE
COUNSEL ON ITS OWN BEHALF, AND CONTRACTOR SHALL BE LIABLE FOR ALL COSTS
INCURRED BY CITY.
THE RIGHTS AND OBLIGATIONS CREATED BY THIS SECTION SHALL SURVIVE TERMINATION OF
THIS AGREEMENT.
8. Liability.
To the fullest extent permitted by law, Contractor shall be fully and solely responsible and liable for its own acts and omissions, including those of its officers, agents, representatives, employees, subcontractors, licensees, invitees and all other parties performing services for or on behalf of Contractor under this Agreement, and for any and all damage to
Contractor’s equipment and other property. City assumes no such responsibility or liability. City shall have no such responsibility or liability to either Contractor or its officers, agents, representatives, employees, subcontractors, licensees, invitees or other persons.
9. Compliance with Laws; Standard of Care.
Contractor shall comply with all federal, state and local laws, statutes, ordinances, regulations and policies, as they exist, may be amended or in the future arising, applicable to Contractor and its work. Contractor shall ensure that its officers, agents, representatives, employees, subcontractors, licensees, invitees and other parties performing services for or on behalf of Contractor under this Agreement comply with all applicable laws, statutes, ordinances, regulations and policies. If Contractor observes or is notified that the work under this Agreement is at variance with applicable laws, statutes, ordinances, regulations and policies, Contractor shall immediately notify City in writing. The contractor shall perform the Services in accordance with the prevailing standard of care by exercising the skill and care ordinarily utilized by professionals performing the same or similar services under the same or similar circumstances in the State of Texas.
10. Termination.
City is entitled to terminate this Agreement at any time for any reason or for no reason by giving Contractor at least thirty (30) days’ prior written notice of the termination date.
City is entitled to terminate this Agreement immediately on breach of any term or
Services Agreement Page 6 of 10 5029706 provision of the Agreement Documents by Contractor. If at any time during the term of this Agreement, Contractor shall fail to commence the work in accordance with the provisions of the Agreement Documents or fail to diligently perform the Services in an efficient, timely and careful manner and in strict accordance with the provisions of the
Agreement Documents, then City shall have the right to terminate this Agreement and complete the work in any manner it deems desirable, including engaging the services of other parties, if Contractor does not cure any such default after five (5) days written notice thereof. Any such act by City shall not be deemed a waiver of any other right or remedy of City.
If after exercising any remedy provided herein, the cost to City of the performance of the balance of the work under this Agreement is in excess of that part of the Contractor’s Fee which has not yet been paid to Contractor hereunder, Contractor shall be liable for and shall reimburse City for such excess, without waiver of any other right or remedy of
City.
The rights and remedies provided by this Agreement are cumulative, and the use of any one right or remedy by either party shall not preclude or waive its rights to use any or all other remedies. These rights and remedies are given in addition to any other rights the parties may have by law, statute, ordinance or otherwise.
11. Authority to Execute.
Each party represents and warrants to the other that it has the full power and authority to enter into and fulfill the obligations of this Agreement. The respective signatories to this
Agreement, by affixing their signatures hereto, warrant and represent that they have the authority to bind their respective parties as duly authorized representatives thereof.
12. Assignment.
Contractor agrees that neither this Agreement nor the work to be performed hereunder will be assigned or sublet without the prior written consent of City. Contractor further agrees that the assignment or subletting of any portion or feature of the work or materials required in the performance of this Agreement shall not relieve Contractor of its full obligations to
City as provided by this Agreement. All such approved work performed by assignment or subletting shall be billed through Contractor, and there shall be no third-party billing.
13. No Waiver of Immunity.
The parties acknowledge and agree that, in executing and performing this Agreement, City has not waived, nor shall be deemed to have waived, any defense or immunity, including governmental, sovereign and official immunity, that would otherwise be available to it against claims arising in the exercise of governmental powers and functions. By entering into this Agreement, the parties do not create any obligations, express or implied, other than those set forth herein.
14. Savings/Severability.
In the event that a term, condition or provision of this Agreement is determined to be invalid, illegal, void, unenforceable or unlawful by a court of competent jurisdiction, then
Services Agreement Page 7 of 10 5029706 that term, condition or provision shall be deleted and the remainder of the Agreement shall remain in full force and effect as if such invalid, illegal, void, unenforceable or unlawful provision had never been included in this Agreement.
15. Consideration.
This Agreement is executed by the parties without coercion or duress and for substantial consideration, the sufficiency of which is forever confessed.
16. Attorneys’ Fees.
If either party files any action or brings any proceeding against the other arising from this
Agreement, then as between City and Contractor, the prevailing party shall be entitled to recover as an element of its costs of suit, and not as damages, reasonable and necessary attorneys’ fees and litigation expenses both at trial and on appeal, subject to the limitations set forth in the TEX. LOC. GOV’T CODE § 271.153, as it exists or may be amended, if applicable.
17. Governing Law; Venue.
The laws of the State of Texas shall govern the interpretation, validity, performance and enforcement of this Agreement, without regard to conflict of law principles. This
Agreement is performable in Grayson County, Texas, and the exclusive venue for any action arising out of this Agreement shall be a court of appropriate jurisdiction in Grayson
County, Texas.
18. Binding Effect.
This Agreement shall be binding on and inure to the benefit of the parties and their respective heirs, executors, administrators, legal representatives, successors and assigns when permitted by this Agreement.
19. No Waiver.
Waiver by either party of any breach of this Agreement, or the failure of either party to enforce any of the provisions of this Agreement, at any time, shall not in any way affect, limit, or waive such party’s right thereafter to enforce and compel strict compliance.
20. Headings.
The headings of the various sections of this Agreement are included solely for convenience of reference and are not to be full or accurate descriptions of the content thereof.
21. Indemnity.
The parties agree that the indemnity provision set forth herein is conspicuous and the parties have read and understood the same.
22. Notice.
Any notice provided or permitted to be given under this Agreement must be in writing and may be served by depositing the same in the United States Mail, addressed to the party to be notified, postage pre-paid and registered or certified with return receipt requested; by electronic mail, with documentation evidencing the addressee’s receipt thereof; or by
Services Agreement Page 8 of 10 5029706 delivering the same in person to such party a via hand-delivery service, or to any courier service that provides a return receipt showing the date of actual delivery of the same to the addressee thereof. Notice given in accordance herewith shall be effective on receipt at the address of the addressee. For purposes of notification, the addresses of the parties shall be as follows:
If to Contractor, to: _______________________________
Attn: __________________________
Address: _______________________
Telephone: _____________________
Facsimile: ______________________
Email: _________________________
If to City, to: City of Sherman
Attn: Clint Philpott, Acting City Manager
220 W. Mulberry Street
Sherman, Texas 75090
Telephone: (903) 892-7201
Facsimile: (903) 892-7355
Email: clintp@cityofsherman.com
With a copy to:
Abernathy, Roeder, Boyd & Hullett, P.C.
Attn.: Ryan D. Pittman
1700 Redbud Blvd., Suite 300
McKinney, Texas 75069
Telephone: (214) 544-4000
Facsimile: (214) 544-4054
Email: rpittman@abernathy-law.com
23. Representations.
Each party states that they have carefully read this Agreement, know the contents hereof, have consulted with an attorney of their choice regarding the meaning and effect hereof and is signing the same solely of their own judgment.
24. Independent Contractor.
Contractor covenants and agrees that Contractor is an independent contractor and not an officer, agent, servant or employee of City; that Contractor shall have exclusive control of mailto:clintp@cityofsherman.com mailto:rpittman@abernathy-law.com
Services Agreement Page 9 of 10 5029706 and exclusive right to control the details of the work performed hereunder and all persons performing the same; that the doctrine of respondent superior shall not apply as between
City and Contractor, its officers, agents, employees, contractors, subcontractors and consultants; and that nothing herein shall be construed as creating a partnership or joint enterprise between City and Contractor.
25. Incorporation of Recitals.
The representations, covenants and recitations set forth in the foregoing recitals of this
Agreement are true and correct and are hereby incorporated into the body of this Agreement and adopted as findings of City and the authorized representative of Contractor.
26. Reference to Contractor.
When referring to “Contractor” herein, this Agreement shall refer to and be binding upon
Contractor, and its officers, directors, partners, employees, representatives, contractors, subcontractors, licensees, invitees, agents, successors, assignees (as authorized herein), vendors, grantees, trustees, legal representatives and/or any other third parties for whom
Contractor is legally responsible.
27. Reference to City.
When referring to “City” herein, this Agreement shall refer to and be binding upon City, its Council Members, officers, agents, representatives, employees and/or any other authorized third parties for whom City is legally responsible.
28. Miscellaneous Drafting Provisions.
This Agreement shall be deemed drafted equally by all parties hereto. The language of all parts of this Agreement shall be construed as a whole according to its fair meaning, and any presumption or principle that the language herein is to be construed against any party shall not apply. Headings in this Agreement are for the convenience of the parties and are not intended to be used in construing this document.
29. Multiple Counterparts.
This Agreement may be executed in a number of identical counterparts, each of which shall be deemed an original for all purposes. An electronic mail and/or facsimile signature will also be deemed to constitute an original if properly executed and delivered to the other party.
IN WITNESS WHEREOF, the parties have executed this Agreement and caused this
Agreement to be effective when all the parties have signed it. The date this Agreement is signed by the last party to sign it (as indicated by the date associated with that party’s signature below) will be deemed the effective date of this Agreement (“Effective Date”).
Services Agreement Page 10 of 10 5029706
CITY OF SHERMAN, TEXAS,
a home-rule municipality
By: ______________________________
Clint Philpott, Acting City Manager
Date:
ATTEST: APPROVED AS TO FORM:
Teri Fine, City Clerk Abernathy, Roeder, Boyd & Hullett, P.C.
Ryan D. Pittman, City Attorney
By: ______________________________
Printed Name: ________________________
Title: _______________________________
Date:
STATE OF TEXAS §
COUNTY OF __________ §
BEFORE ME, the undersigned authority, on this day personally appeared __________, known to me to be one of the persons whose names are subscribed to the foregoing instrument;
he/she acknowledged to me he/she is the ______________ (title) and duly authorized representative for ______________________________________, a Texas corporation, and that he/she executed said instrument for the purposes and consideration therein expressed.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this _____ day of
____________________, 20___.
Notary Public in and for the State of Texas
My Commission Expires:_______________
| PW-IFB4006-27 Specs |
| References |
| 1295 |
| Service Agreement 2.25.26 |
| By: ______________________________ |
| Clint Philpott, Acting City Manager |
| By: ______________________________ |
| Printed Name: ________________________ |