Final Location Sheet D5 Sweeping 1-9-25 Version.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Eq Rental Highway Sweeping D-5
Solicitation number
RFB-605-2500000376-2
Issued by
Breckinridge County, Kentucky

About this file

This is a location sheet detailing highway sweeping work requirements for District 5 in Kentucky, covering multiple routes across Jefferson, Bullitt, and Shelby counties. The document outlines specific sweeping locations, frequencies, and mileage for various interstate highways (I-65, I-64, I-264, I-265, I-71) and state routes (KY 841), with work descriptions including sweeping of curblines, bridges, barrier walls, rest areas, and overhead bridges. The contract specifies a maximum completion time of 21 calendar days for full sweeping cycles and 5 calendar days for designated partial sweeping cycles, with locations requiring either 3, 6, or 12 cycles per year.

The total sweeping mileage is broken down by location, with detailed measurements for each segment and anticipated total miles per year. Notable segments include I-264 with the highest annual mileage at 553.32 miles (46.11 miles per cycle), and specific sections managed by LSIORB (Louisville-Southern Indiana Ohio River Bridges). The work encompasses various types of sweeping, including rest area maintenance, full-width sweeping, and specific structural elements like bridges and barrier walls, with some sections requiring sweeping of all paved areas outside the roadway.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Highway Sweeping Work Location Sheet
District 5
RouteCountyProject NumberFromToSweeping Miles (Miles Paid)Anticipated # of Cycles/YRAnticipated Total Miles/YR (Sweeping Miles X # of cycles)Work Description including incidentals
3 Cycle Locations
(Miles measured from begin to end of RA Ramps)
I-65BullittFE01 015-0065Rest Area Exit RampRest Area Entrance Ramp0.69832.094Sweep all pavement areas at the Rest Area
112-114(MP 113.650)(MP 112.952)
I-64ShelbyFE01 106-0064Rest Area Exit RampRest Area Entrance Ramp0.7232.16Sweep all pavement areas at the Rest Area
028-029(MP28.250)MP28.970
Subtotal1.418
6 Cycle Locations
(Miles for length of cleaning ONLY)
KY 841JeffersonFE01 056-0841US 31WI-65
000-010(MP 0.000)(MP 10.000)2.45614.7Sweep curblines, bridges & barrier walls
I-265JeffersonFE01 056-0265I-65I-7112.833676.998Sweep curblines, bridges & barrier walls (Added 5.278 miles for new barrier wall and bridges along IMOVE project)
010-035(MP 10.000)(MP 35.000)
Subtotal15.283
12 Cycle Locations
(Miles for Centerline Mile, Cardinal and Non-Cardinal paid seperately; all other work incidental according to contract and descriptions below)
I-264JeffersonFE01 056-0264I-64I-7146.1112553.32Sweep curblines , Bridges, barrier walls and
000-024(MP 0.000)(MP 23.055)overhead bridges at KY 864, KY 1703, KY 1932
I-64 , US 60 and US 42
I-64JeffersonFE01 056-0064Mellwood Bridge (Eastside)0.047 mile West of Browns Lane10.34812124.176Sweep all bridges and tunnels
006-012(MP 6.701)(MP 11.875)
I-64JeffersonFE01 056-00640.700 mile East of I-2641.0 miles West of I-2659.94612119.352Sweep curblines , Bridges, barrier walls and
012-018(MP 12.943)(MP 17.916)overhead bridges at Blankenbaker Parkway
(KY 913)
I-64JeffersonFE01 056-0064English Station Rd BridgeShelby Co Line8.80212105.624Sweep curblines, bridges & barrier walls
019-024(MP 19.573)(MP 23.974)
I-65BullittFE01 015-0065Hardin Co Line0.672 mile North of Hardin Co Line1.3441216.128Sweep curblines, bridges & barrier walls
103-104(MP 103.308)(MP 103.980)
I-65BullittFE01 015-0065Beginning of the Roadway BridgeEnd of the Railroad Bridge0.274123.288Sweep curbline of the railroad bridge and the roadway bridge
112-113(MP 112.517)(MP 112.654)
I-65BullittFE01 015-00650.2 Mile South of KY 4800.2 Mile North of KY 443.0881237.056Sweep curblines, bridges, barrier walls and
115-117(MP 115.321)(MP 116.865)the overhead bridges at KY 44, KY 245 and KY1526
I-65BullittFE01 015-0065Beg. Of Barrier WallEnd of Barrier Wall0.138121.656Sweep the barrier wall ( NORTHBOUND ONLY)
118-119(MP 118.180)(MP 118.042)
I-65JeffersonFE01 056-00650.8 Mile North of the0.245 Mile South of the14.77812177.336Sweep curblines, bridges, barrier walls and
123-132Bullitt County LinePhillips Lane Bridgeoverhead bridges at I-265, KY 1065, KY 1631
(MP 123.900)(MP 131.289)and all ramp bridges at I-265
I-71JeffersonFE01 056-0071I-64I-2649.93212119.184Sweep bridges and curblines
000-005(MP 0.000)(MP 4.966)
I-64ShelbyFE01 106-0064Beg. Of Barrier WallEnd of Barrier Wall17.80212213.624Sweep curblines, bridges barrier walls and
023-033(MP 23.974)(MP 32.875)overhead bridges at KY 1848 and KY 55
I-65JeffersonFE01 056-00650.254 Mile South of theSouth End Ali Bridge8.58212102.984Sweep all paved areas outside of roadway
131-136Phillips Lane Bridge(MP 135.58)
(MP 131.289)
I-64JeffersonFE01 056-0064Sherman Minton BridgeRiver Road Bridge9.97612119.712Sweep all paved area outside of roadway
000-005(MP 0.000)(MP 4.988)

Subtotal 141.12

Sweeping Paid for by LSIORB

I-64JeffersonFE01 056-0064River Road BridgeMellwood Bridge (Eastside)3.4261241.112Sweep all paved area outside of roadway
005-007(MP 4.988)(MP 6.701)
I-65JeffersonFE01 056-0065South End Ali BridgeNorth End of River Bridges3.4761241.712Sweep all paved areas outside of roadway
136-138(MP 135.58)(MP 137.318)

Subtotal 6.902

Maximum time to complete a Full Sweeping Cycles : 21 Calendar Days
Maximum time to complete a Designated Partial Sweeping Cycle: 5 Calendar Days