JOB ORDER CONTRACT (JOC) FOR SLURRY & PAVING SERVICES
Solicitation number
IFB 080-2540101-AC
Issued by
Orange County, San Francisco City, California

About this file

This document is an Invitation for Bid (IFB) issued by the County of Orange, California's OC Public Works Procurement Services for a Job Order Contract (JOC) for Slurry & Paving Services. The contract will be a usage contract with a maximum amount of $500,000, effective for one year from April 13, 2024, or until the total contract amount is reached. Bidders must possess a current California C-12 Contractor's license and be registered with the Department of Industrial Relations. A mandatory pre-bid webinar is scheduled for December 5, 2023, at 10:00 AM, with all questions due by December 8, 2023, at 2:00 PM. Electronic bids are due on December 13, 2023, at 2:00 PM through the County's online bidding system, OpenGov.

The contract requires bidders to submit two adjustment factors: one for normal working hours (7:00 AM to 5:00 PM) and another for other than normal working hours (5:01 PM to 6:59 AM). The County may award the contract to multiple contractors, and bidders must provide a bid bond of at least 10% of the total contract amount. Successful bidders will be required to furnish a performance bond and a payment bond, each equal to 100% of the contract amount. The contract includes provisions for job order development, quote submission, and detailed requirements for work performed, including safety protocols, permit requirements, and compliance with prevailing wage laws. Contractors must self-perform 20% of the work for 'A' and 'B' licenses and 75% for 'C' licenses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

County of Orange, OC Public Works IFB # 080-2540101-AC

Job Order Contract (JOC) for Slurry & Paving Services

2540101 Page 1 of 68

OC PUBLIC WORKS

Procurement Services

601 N. Ross St., 4th Floor

Santa Ana, CA 92701

Date: November 29, 2023

INVITATION FOR BIDS

BID MUST BE RECEIVED

BEFORE:

December 13, 2023 / 2:00 PM PDT

DATE / TIME

IFB 080-2540101-AC

BID NUMBER

2540101

FILE FOLDER NUMBER

COVER PAGE

Procurement Services

Regular Office Hours:

8:00 AM. to 5:00 PM

Monday through Friday

The office is closed between

12:00 PM and 1:00 PM

The County of Orange, OC Public Works, (“County”) is requesting competitive sealed bids from qualified firms, (“Bidder”) for Job Order Contracting (“JOC”) for Slurry & Paving Services. The awarded contract, (“Contract”), will be a usage Contract between the County and awarded Bidder (“Contractor”) in accordance with the Model Contract, attached hereto and incorporated herein, and Scope of Work attached hereto and incorporated herein by this reference as Attachment A. The proposed Contract shall be effective for one (1) year, or until the total Contract amount is reached. The Contractor shall possess a current State of

California C-12 Contractor’s license issued by the California State Contractor’s License Board.

BIDS ARE DUE ON OR BEFORE THE DATE AND TIME SPECIFIED ABOVE.

THERE WILL BE A MANDATORY PRE-BID MEETING ON DECEMBER 5, 2023 AT 10:00 AM.

ALL QUESTIONS/REQUESTS FOR INTERPRETATION MUST BE RECEIVED BEFORE 2:00 PM ON DECEMBER 8, 2023.

ELECTRONIC BID OPENING DATE: December 13, 2023 AT 2:00 PM.

BIDS WILL BE VALID FOR 180 DAYS AFTER CLOSING DATE.

All questions and inquiries related to this IFB must be directed to: Amanda Casas, County Deputy Purchasing

Agent (“DPA”), OC Public Works/Procurement Services, via the OpenGov at the: County’s online bidding system under the bid page for this solicitation.

Respondents are not to contact other County personnel with any questions or clarifications concerning this

IFB. OC Public Works/Procurement Services will provide all official communication concerning this IFB. Any

County response relevant to this IFB other than through or approved by OC Public Works/Procurement Services is unauthorized and will be considered invalid.

I have read and understand and agree to the terms and conditions herewith, and I am submitting a bid in response to this solicitation.

Date: ____________________ Company Name:

*Authorized Signature Print Name Title

*Authorized Signature Print Name Title

* If the Bidder is a corporation, (2) two signatures are required: one (1) signature by the Chairman of the Board, the President or any Vice

President; and one (1) signature by the Secretary, any Assistant Secretary, the Chief Financial Officer or any Assistant Treasurer. The signature of one person alone is sufficient to bind a corporation, as long as he or she holds corporate offices in each of the two categories described above. For County purposes, proof of such dual office holding will be satisfied by having the individual sign the instrument twice, each time indicating his or her office that qualifies under the above described provision. In the alternative, a single corporate signature is acceptable when accompanied by a corporate resolution demonstrating the legal authority of the signator to bind the corporation.

RETURN THIS COVER PAGE WITH YOUR BID

https://opengov.com/products/procurement/suppliers/

2540101 Page 2 of 68

I. GENERAL INFORMATION

1. Important Notice: The County of Orange has attempted to provide all information available. It is the responsibility of each Bidder to review, evaluate, and where necessary, request any clarification prior to submission of a bid. If any person contemplating submitting a bid in response to this IFB is in doubt as to the true meaning of any part of the solicitation documents attached hereto or finds discrepancies in or omissions from the specifications, they must submit a written request for clarification/interpretation to the DPA via OpenGov at the: County’s online bidding system under the bid page for this solicitation. If clarification or interpretation of this solicitation is considered necessary by County, a written addendum shall be issued and the information will be posted on

OpenGov at the: County’s online bidding system. Any interpretation of, or correction to, this solicitation will be made only by addendum issued by the County DPA. It is the responsibility of each Bidder to periodically check the County’s on-line bid system to ensure that they have received and reviewed any and all addenda to this solicitation. The County will not be responsible for any other explanations, corrections to, or interpretations of the documents, including any oral information.

All questions or requests for interpretation must be received by the time and date specified on the bid cover page.

2. OC Public Works/Procurement Services regular business hours are 8:00 AM to 12:00 PM and 1:00

PM to 5:00 PM, Monday through Friday. OC Public Works/Procurement will be closed on the following County holidays:

November 10, 23 & 24, 2023

December 25, 2023

January 1, 2024

3. Orange County does not require and neither encourages nor discourages the use of lobbyists or other consultants for the purpose of securing business.

II. GENERAL INSTRUCTIONS AND PROVISIONS

1. Before submitting a bid, Bidders shall carefully examine the solicitation contents, including the

Contract Terms and Conditions and Scope of Work. Bidders shall include in their bid response a monetary sum to cover the cost of all items included in the Contract

2. This Invitation for Bids consists of the Cover Page and the following Attachments and Exhibits:

Section I General Information

Section II General Instructions and Provisions

Section III W-9 Requirements

Section IV County Contract Terms and Conditions, including:

Attachment A, Scope of Work;

Exhibit A, Gordian License and User Agreement;

Attachment B, Contractor’s Pricing

Exhibit 1 Company Profile & References

Exhibit 2 Non-Collusion Affidavit

Exhibit 3 Labor & Material Bond

Exhibit 4 Faithful Performance Bond

Exhibit 5 Iran Contracting Act Certification Form

Exhibit 6 Campaign Disclosure Form

2540101 Page 3 of 68

Exhibit 7 Contractor Safety Responsibility form

Exhibit 8 Contractor Safety – Activity Checklist (Contractor will provide prior to the issuance of each task order)

3. Mandatory Pre-Bid Meeting Webinar: All Bidders must be in attendance at the Pre-Bid Webinar

Meeting in order to continue in the bidding process. The Pre-Bid Webinar Meeting will be conducted one time only. Attendance will be taken at the webinar meeting, in the beginning and the end of the meeting. Attendance during entire webinar is required.

i. PRE-BID INFORMATION

DATE: DECEMBER 5, 2023

TIME: 10:00AM – NO ONE WILL BE ADMITTED AFTER 10:10AM

ii. Please RSVP your attendance by sending an email to Amanda.casas@ocpw.ocgov.com by closed of business day on December 4, 2023.

iii. The purpose of the Pre-Bid Meeting will be to discuss the Job Order Contract (JOC) concept, and discuss JOC from a Contractor’s perspective. For Contractors who are new to the JOC process a training workshop will be part of the Pre-Bid Meeting.

▪ The County strongly encourages a responsible managing officer from the Contractor’s office to attend this meeting.

4. Bid Submittal: This is a fully electronic Invitation for Bid (IFB). Bidders must submit their bid on

County’s online bidding system to be considered responsive. All bid documents specified in Section

II of the IFB shall be uploaded electronically and bidders shall utilize OpenGov to provide their overall factor from Line 5 of the Award Formula on Attachment B of the Model Contract. Only electronic bids will be accepted, no exceptions. Once the Bid Due Date and Time has lapsed, bidders, the public and County staff are able to immediately see the results on OpenGov.

All bids are due no later than the due date and time specified within this solicitation. Late bids will not be accepted regardless of reason.

5. Responsive Bids shall include the following completed submittals:

i. Bid Cover Page: Dated and signed by Contractor’s authorized representative (note special requirements for Corporations)

ii. Attachment B: Contractor’s Pricing (2 pages, individual scores & award formula)

iii. Exhibit 1: Company Profile and References

iv. Exhibit 2: Non-Collusion Affidavit

v. Bid Bond in an amount not less than 10% of the total Contract amount

vi. Exhibit 5: Iran Contracting Act Certification Form

vii. Exhibit 6: Campaign Disclosure Form

viii. Exhibit 7: Safety Responsibility Form

6. Bid Cover Page: The Cover Page of a responsive bid must include the date and company legal name and must be signed by person(s) with authority to bind the Bidder. If the Bidder is a corporation, then the signature of two corporate specific officers are required as follows: (1) signature by the

Chairman of the Board, the President or any Vice President; and one (1) signature by the Secretary, any Assistant Secretary, the Chief Financial Officer or any Assistant Treasurer. The signature of one person alone is sufficient to bind a corporation, as long as he or she holds corporate offices in each of the two categories described above. For County purposes, proof of such dual office holding will

2540101 Page 4 of 68 be satisfied by having the individual sign the instrument twice, each time indicating his or her office that qualifies under the above described provision. In the alternative, a single corporate signature is acceptable when accompanied by a corporate resolution demonstrating the legal authority of the signator to bind the corporation. An unsigned or improperly signed bid submission is grounds for rejection of the bid and disqualification from further participation in this IFB process.

7. Pricing (Attachment B):

i. Adjustment Factors quoted shall be firm for the full term of the Contract.

ii. Bidder shall utilize Attachment B, Contractor’s Pricing, to provide all-inclusive Adjustment

Factors for Services in accordance with the requirements of the Scope of Work for the full term of the Contract. All items shall be properly filled in. The completed form shall be without alterations, interlineations, or erasure marks.

iii. Bids shall be submitted for Adjustment Factors as stated in the specifications; bids upon other bases will not be considered. Bids that do not reference all addenda or that are not submitted on the prescribed forms may be rejected.

iv. Each Bidder must submit two (2) Adjustment Factors in order to be considered responsive. The first Adjustment Factor is to be applied to work anticipated to be performed during Normal

Working Hours (7:00 AM to 5:00 PM). The second Adjustment Factor is to be applied to work anticipated to be performed during Other Than Normal Working Hours (Overtime) (5:01 PM to 6:59 AM). It will be the responsibility of the winning Bidder to comply with all applicable

Prevailing Wage laws.

v. The Construction Task Catalog® is priced at a net value of 1.0000. The bid shall be "net", (i.e., 1.0000) or an adjustment "decrease from" (e.g., 0.9500) or "increase to" (e.g., 1.2000) the Unit

Prices listed in the Construction Task Catalog®. Bidders who submit separate Adjustment

Factors for individual line items in the Construction Task Catalog® will be considered non-responsive and the bid will be rejected.

vi. The Bidder’s Adjustment Factors must contain allowances for overhead, profit, bond premiums, insurance, mobilization, Quote development, shop drawings and submittals, overtime and holiday pay, and all contingencies in connection therewith, as no additional allowance will be made later.

vii. Any change in the applicable minimum hourly wage rates during the contract period shall not affect the Unit Price to be paid by the County for work performed under the contract.

viii. Bids will be considered on the following criteria: Lowest responsible bidder using Adjustment

Factors. For the purposes of determining the low bid, the Normal Working Hours Adjustment

Factor shall be multiplied by .80, the Other Than Normal Working Hours Adjustment Factor shall be multiplied by .20, these two numbers will be summed for a composite bid, and the lowest composite bid will be considered the low bid. Please utilize second page of Attachment

B and submit with your bid.

8. Company Profile & References (Exhibit 1): Bidder shall utilize the forms provided in Exhibit 1 of this solicitation to satisfy this requirement.

9. No person, firm or corporation shall be allowed to make or file or be interested in more than one bid, for the Job Order Contract. A person, firm or corporation who has submitted a sub-bid to a Bidder, or who has quoted prices on materials to a Bidder, is not hereby disqualified from submitting a sub-bid or quoting prices to other Bidders.

10. Bonds: Bonds shall be secured from an admitted surety company authorized to conduct surety insurance in California and satisfactory to County Counsel and County Risk Management and in accordance with the General Conditions.

2540101 Page 5 of 68

i. Bid Bond: Bidder will be required to furnish a bid bond in an amount not less than 10% of the total Contract amount. Original bid security documents shall be received at the following address before 2:00 p.m. on the bid closing date or submittals shall be deemed non-responsive:

County of Orange/County Administration South Building

601 N. Ross St., 4th Floor

Santa Ana, CA 92701

Attn: Amanda Casas

ii. Labor and Material Payment Bond and a Faithful Performance Bond (Exhibits 3 & 4):

The successful Bidder, immediately upon award, will be required to furnish a Faithful

Performance Bond and a Labor and Material Payment Bond in an amount of $500,000.

11. Non-Collusion Affidavit (Exhibit 2):

i. Pursuant to Public Contract Code, Section 7106, each Bidder must execute and submit with their bid a Non-collusion Affidavit. Bidder shall utilize Exhibit 2 of this solicitation to satisfy this requirement.

ii. The County may require that the principal Contractor shall, before awarding any subcontract, secure a Non-collusion Affidavit from the proposed subcontractor.

12. Contractor’s License: No bid may be considered from a Bidder who, at the time the bids are opened, is not licensed to perform the project in accordance with Division 3, Chapter 9, of the Business and

Professions Code of the State of California (see California Business and Professions Code, Section

7000, et seq). However, if federal funds are involved, the Bidder must be properly licensed at the time of award (Public Contract Code 20103.5).

13. Bidders shall be required to meet any other legal, license or certificate requirements that are necessary to enable them to perform the services specified in this solicitation.

14. Bidders shall take all responsibility for any errors or omissions in their bids. Any discrepancies in numbers or calculations shall be interpreted to reflect the lowest price to the County.

15. The County shall not be liable for any expenses incurred by potential Bidders in the preparation or submission of their bids. Pre-contractual expenses are not to be included in the Contractor’s Pricing

Sheet. Pre-contractual expenses are defined as, including but not limited to, expenses incurred by

Bidder in:

i. Preparing its bid in response to this IFB;

ii. Submitting that bid to the County;

iii. Negotiating with the County any matter related to the bid; and,

iv. Any other expenses incurred by the Bidder prior to the date of the award and execution, if any, of the Contract.

16. Bid Protest & Appeal: Any bidder, respondent, or contractor who alleges an error or impropriety in the solicitation or award of a contract may submit a grievance or protest to the awarding department and the following procedures will apply.

2540101 Page 6 of 68

a. Procedure

Prior to the filing of an Agenda Staff Report (ASR) for award of Contract, the DPA shall send a

Notice of Intent to Award a Contract to all participating vendors and submit a copy to the Clerk of the Board. This Notice shall initiate the protest period as follows:

1) Bidders will have five (5) business days from the date of the notice in which to file a protest concerning the award of the Contract.

2) Protests relating to a proposed Contract award which are received after the five (5) business day deadline will not be considered by the County.

3) During the five (5) business day period, bid information is subject to public disclosure.

4) Upon expiration of the five (5) business day period or proper resolution of a protest/appeal, the department may move forward with the Contract award or if necessary, filing the item for approval by the Board of Supervisors.

b. Protest Process

1) In the event of a timely protest, the County shall not proceed with the solicitation or award of the Contract until the DPA, or the Director renders a decision on the protest.

2) Upon receipt of a timely protest, the DPA will within ten (10) business days of the receipt of the protest, issue a decision in writing which shall state the reasons for the actions taken.

3) The County may, after providing written justification to be included in the procurement file, make the determination that an immediate award of the Contract is necessary to protest the substantial interest of the County. The award of a Contract shall in no way compromise the protestor’s right to protest procedures outlined herein.

4) If the protestor disagrees with the decision of the DPA, the protestor may submit a written appeal to the Office of the Director requesting an appeal, in accordance with the process stated below.

c. Appeal Process

1) If the protesting Bidder wishes to appeal the decision of the DPA, the protesting bidder must submit, within three (3) business days from receipt of the DPA’s decision, a written appeal to the Office of the Director.

2) Within fifteen (15) business days, the Office of the Director will conduct a third-party review of all materials in connection with the grievance, assess the merits of the protest and provides a written determination that shall contain his or her decision.

3) The decision of the Director will be final and there shall be no right to any administrative appeals of this decision.

17. Acceptance/Rejection/Award

i. Bids are not to be marked as confidential or proprietary. The County may refuse to consider any bid so marked. Bids submitted in response to this IFB may become subject to public disclosure. The County shall not be liable in any way for disclosure of any such records.

Additionally, all bids shall become the property of the County.

ii. Bid packages will be reviewed by the County for responsiveness to all requirements. The County has the right to reject any bid deemed unresponsive or lacking the resources or experience to adequately perform the services described herein, and is therefore not a responsible bidder.

2540101 Page 7 of 68

iii. Only those responsible, responsive bids meeting all solicitation requirements and specifications shall be further reviewed for consideration for award. Award shall be based on the lowest, responsive, responsible bid.

Please take notice, non-acceptance of County of Orange terms and conditions will result in a bid being deemed non-responsive. The County will not accept any other terms, conditions, or provisions contrary to those contained within this solicitation.

iv. Final award determination based upon the lowest responsive, responsible bid, may also include a review of successful Bidder’s qualifications, experience, and resources; Bidder’s ability to meet the requirements and perform the services specified in this solicitation; Bidder’s references and past performance; and Bidder’s acceptance of County of Orange terms and conditions.

v. Awarded Contractor will be required to sign a Contract upon award. If Contractor is a corporation, signature will be provided in accordance with the corporation’s code as specified in this solicitation.

18. Rights Reserved to County: The County reserves the right to:

i. Waive, at its discretion, any irregularity or formality, which the County deems immaterial.

ii. Make multiple awards to Bidders for services requested in this solicitation, at its sole discretion, to serve the best interests of the County.

ii. Accept or reject all bids received as a result of this solicitation at its sole discretion and to solicit for new bids, as the best interests of the County may require;

iii. Withdraw or cancel this solicitation at any time without prior notice and furthermore makes no representation that any Contract will be awarded to any bidder responding to this solicitation;

III. W-9 REQUIREMENTS

1. Department of the Treasury, Internal Revenue Service Form W-9 Requirement: Effective June

3, 2006, all Contractors, entering into a contract with the County, who are not already established in the Countywide Accounting and Personnel System (CAPS) as an Auditor-Controller vendor, will be required to submit to the County a federal Form W-9, or form W-8 for foreign vendors. The County will inform the Contractor, at the time of award, if the Form W-9, or W-8, will be required.

In order to comply with this County requirement, within ten days of notification of selection of award of Contract but prior to official award of Contract, the selected Contractor agrees to furnish to the contract administrator, the County DPA, or the agency/department deputy purchasing agent the required W-9 or W-8.

2540101 Page 8 of 68

IV. COUNTY OF ORANGE MODEL CONTRACT

JOB ORDER CONTRACT (JOC) [TBD]

FOR

SLURRY & PAVING SERVICES

This Job Order Contract [TBD] for Slurry & Paving Services (“Contract”) is made and entered into as of the date fully executed by and between County of Orange, a political subdivision of the State of

California; (“County”), and [TBD], (“Contractor”), which are sometimes individually referred to as “Party”, or collectively referred to as “Parties”.

RECITALS

WHEREAS, County and Contractor are entering into this Contract for Slurry & Paving Services under a Usage Contract; and, WHEREAS, County solicited Slurry & Paving Services as set forth herein, and Contractor has represented that it is qualified and capable to provide Slurry & Paving Services to the County as further set forth herein; and, WHEREAS, Contractor agrees to provide Slurry & Paving Services to the County as further set forth in the Scope of Work, attached hereto as Attachment A and incorporated herein; and, WHEREAS, County agrees to pay Contractor the fees as further set forth in Contractor’s Pricing, attached hereto as Attachment B and incorporated herein;

NOW, THEREFORE, the Parties mutually agree as follows:

DEFINITIONS

DEFINITIONS: The following terms shall have the definitions as set forth below:

1. Adjustment Factor: The Bidder’s competitively bid price adjustment to the unit prices published in the Construction Task Catalog®.

2. Brief Scope of Work: The initial Scope of Work developed by the County Project Manager and is utilized to provide adequate information to schedule the Joint Scope Meeting.

3. Best Management Practices (BMPs): As used herein, a BMP is defined as a technique, measure, or structural control that is used for a given set of conditions to manage the quantity and improve the quality of stormwater runoff in a cost-effective manner. Specific BMPs are found within the County’s

LIP in the form of Model Maintenance Procedures and BMP Fact Sheets (the Model Maintenance

Procedures and BMP Fact Sheets contained in the DAMP/LIP shall be referred to hereinafter collectively as "BMP Fact Sheets") and contain pollution prevention and source control techniques to eliminate non-stormwater discharges and minimize the impact of pollutants on stormwater runoff.

4. Construction Task Catalog® (CTC): A comprehensive listing of specific construction related tasks identified by the County together with a specified unit of measurement and unit price. The price published in the CTC for a specific construction or construction-related task. The unit prices are fixed for the Term of this Contract. Each unit price is comprised of the labor, equipment and materials costs to accomplish that specific task.

5. DAMP/LIP: To assure compliance with the Stormwater Permits and water quality ordinances, the

County Parties have developed a Drainage Area Management Plan (DAMP) which includes a Local

Implementation Plan (LIP) for each jurisdiction that contains Best Management Practices (BMPs) that parties using properties within Orange County must adhere to.

2540101 Page 9 of 68

6. Detailed Scope of Work: The complete description of services to be provided by the Contractor under an individual Job Order. Developed by the Contractor, after the Joint Scope Meeting and submitted for approval to the County Project Manager.

7. Final Acceptance: All Work has been completed and accepted by the County. The Contractor has provided all required close-out documentation and items as required by the Detailed Scope of Work for the specific Job Order, and these items and have accepted and approved by the County

8. Job Order Authorization (JOA): Issued upon acceptance of quote and the duration schedule, stating that the quote is a firm fixed price. Must be issued prior to issuance of a Notice to Proceed.

9. Job Order Notice To Proceed (NTP): The document prepared by the County, based on the approved

Job Order Quote, and issued to the Contractor which provides the specific instructions, specific bid items, and the duration to complete the approved Detailed Scope of Work.

10. Job Order Quote (Quote): Contractor’s irrevocable offer to perform Work associated with a Job

Order and refers to the Contractor prepared document quoting a firm fixed-price and schedule for the completion of a specific Scope of Work. The Contractor’s Quote must be on forms provided by the

County and in an electronic version compatible with the County’s systems. The Quote may also contain approved drawings, Work schedule, permits, or other such documentation as the County might require for a specific Job Order.

11. Joint Scope Meeting: A meeting at the Job Order location, attended by the Contractor and County and any other interested parties to outline the Scope of Work for the Task.

12. Non-Pre-Priced (NPP) Tasks: The units of Work that are not included in the CTC but are still within the general Scope of Work requested by the County under the Contract.

13. Normal Working Hours: means between the hours of 7:00 AM to 5:00 PM, Monday through Friday, inclusive. Saturdays, Sundays, and County holidays are excluded.

14. Other Than Normal Working Hours: means Work done between the hours of 5:01 PM to 6:59 AM, on week days and any times during Saturday, Sunday, and County holidays.

15. Project: The Work to be performed by Contractor on behalf of County pursuant to this Contract as described in individual Job Orders.

16. Request for Quote (RFQ): The County’s Request for Quote for a specific Job Order.

17. Stormwater Permit: The Santa Ana and San Diego Regional Water Quality Control Boards have issued National Pollutant Discharge Elimination System permits ("Stormwater Permits") to the

County of Orange, the Orange County Flood Control District and cities within Orange County, as co-permittees (hereinafter collectively referred to as "County Parties") which regulate the discharge of urban runoff from areas within the County of Orange, including from all County facilities on which

Work within Contract is being performed. These permits are referred to as Stormwater Permits.

18. Work: The Work shall include, without limitation, all labor, materials, apparatus, supplies, services, facilities, utilities, transportation, manuals, warranties, training, and the like, necessary for the

Contractor to faithfully perform and complete all of its obligations under the Contract.

2540101 Page 10 of 68

ARTICLES

1. Scope of Contract: This Contract, including Attachments, specifies the contractual terms and conditions by which the Contractor will provide Slurry & Paving Services under a Usage Contract, as set forth in the Scope of Work identified as Attachment A to this Contract.

2. Term: Following the Contract’s award by the Board of Supervisors, this Contract shall become effective April 13, 2024, if executed with all necessary signatures by this date, or upon the date of execution of all necessary signatures if execution occurs after April 13, 2024 (“Date of

Commencement”); and shall be effective for one (1) year from the Date of Commencement or until the maximum Contract amount is expended, whichever occurs first, or unless otherwise terminated.

3. Contingency of Funds: Contractor acknowledges that funding or portions of funding for this

Contract may be contingent upon state budget approval; receipt of funds from, and/or obligation of funds by, the state of California to County; and inclusion of sufficient funding for the services hereunder in the budget approved by County’s Board of Supervisors for each fiscal year covered by this Contract. If such approval, funding or appropriations are not forthcoming, or are otherwise limited, County may immediately terminate or modify this Contract without penalty.

4. County's Representatives:

A. The Contract will be under the general direction of the Board of Supervisors. OC Public Works is the authorized representative of the Board of Supervisors and, under the Board of

Supervisors, has complete charge of the Contract, and shall exercise full control of the Contract, so far as it affects the interest of the County.

B. The provisions in this Article or elsewhere in this Contract regarding approval or direction by the County, Board of Supervisors, or OC Public Works, or action taken pursuant thereto are not intended to and shall not relieve the Contractor of responsibility for the accomplishment of the Work, either as regards sufficiency or the time of performance, except as expressly otherwise provided herein.

C. County’s Contract Administrator is the County's exclusive contact agent to the Contractor with respect to this Contract during construction and until the completion of the Contract. The

County will assign Project Managers for individual Job Orders. The County may utilize the services of an Architect in relation to some, but not all Job Orders.

D. The County's communications with the Contractor and Architect shall be exclusively through the County's Project Manager.

E. County Project Manager shall at all times have access to the Work whenever it is in preparation or progress. The Contractor shall provide safe facilities for such access.

F. The County and County Project Manager shall not be responsible for or have control or charge of the construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, and will not be responsible for the

Contractor's failure to carry out the Work in accordance with the Contract documents.

G. The County and County Project Manager shall not be responsible for the failure of the

Contractor to plan, schedule, and execute the Work in accordance with the approved schedule or the failure of the Contractor to meet the Contract completion dates or the failure of the

Contractor to schedule and coordinate the Work of his own trades and subcontractors or to coordinate with others separate Contractors.

H. The County will not be responsible for the acts or omissions of the Contractor, or any subcontractor, or any Contractor's or subcontractor's agents or employees, or any other persons performing any of the Work.

2540101 Page 11 of 68

I. County Project Manager has the authority to disapprove or reject Work on behalf of the County when, in the County Project Manager’s opinion, the Work does not conform to the Contract documents.

J. Whenever, in County Project Manager’s reasonable opinion, it is considered necessary or advisable to insure the proper implementation of the intent of the Contract documents, County

Project Manager has the authority to require special inspection or testing of any Work in accordance with the provisions of the Contract documents whether or not such Work shall then be fabricated, installed or completed.

K. County Project Manager has the authority to require special inspection or testing of the Work.

However, neither County Project Manager’s authority nor any decision made by the Project

Manager in good faith whether to exercise or not to exercise such authority shall give rise to any duty or responsibility of the County to the Contractor, or any subcontractor, or any of their agents, or employees, or any other person performing any portion of the Work.

L. County Project Manager has the authority and discretion to call, schedule, and conduct job meetings to be attended by the Contractor, representatives of his subcontractors and the

Architect and his consultants, to discuss such matters as procedures, progress, problems, and scheduling.

M. County Contract Administrator will establish procedures to be followed for processing all submittals, Change Orders, Invoices, other project reports, documentation and test reports.

N. County Project Manager will issue Job Order if required.

O. County Project Manager will review and process all Invoices by the Contractor.

5. Contractor:

A. Composition: If the Contractor is comprised of more than one legal entity, each such entity shall be jointly and severally liable hereunder.

B. Superintendent: The Contractor shall maintain on site, at all times during the construction activities, a dedicated competent Superintendent. In addition to a General Superintendent and other administrative and supervisory personnel required for the performance of the Work, the

Contractor shall provide specific coordinating personnel as reasonably required for interfacing of all the Work required for the total project, all satisfactory to County Project Manager. The superintendent shall not be changed except with consent of County Project Manager, unless the superintendent proves to be unsatisfactory to the Contractor and ceases to be in his employ, in which case he shall be replaced within 24 hours by a superintendent acceptable to County

Project Manager. The superintendent shall represent the Contractor in his absence and all directions given to him shall be binding as if given to the Contractor.

If Contractor elects to appoint a Contractor’s Project Manager, all relevant provisions of the above paragraph shall also apply to Contractor’s Project Manager. If Contractor elects to not appoint a Contractor’s Project Manager, any references to “Contractor’s Project Manager” in this Contract shall be deemed to be referring to Superintendent.

C. Licenses and Certificates: Contractor shall, at all times during the term of this Contract, maintain in full force and effect such licenses as may be required by the State of California or any other governmental entity for Contractor to perform the duties specified herein and provide the services required pursuant to this Contract. Contractor shall strictly adhere to, and obey, all governmental rules and regulations now in effect or as subsequently enacted or modified, as promulgated by any local, state, or federal governmental entities.

2540101 Page 12 of 68

D. Superintendent and County Project Manager: The Contractor shall provide County Project

Manager with complete Work history profiles of management staff associated with this Project for County Project Manager review.

6. Usage: Unless otherwise specified herein, no guarantee is given by the County to the Contractor regarding usage of this Contract. Usage figures, if provided, are approximate, based upon the last usage. The Contractor agrees to supply services and/or commodities requested, as needed by the

County of Orange, at prices listed in the Contract, regardless of quantity requested.

7. Reports/Meetings: The Contractor shall develop reports and any other relevant documents necessary to complete the services and requirements as set forth in this Contract. The County’s Project Manager and the Contractor’s Project Manager will meet at a County designated location to discuss the

Contractor’s performance and progress under this Contract, at the request of the County’s Project

Manager. If requested by County, the Contractor’s Project Manager and other project personnel shall attend all meetings. The Contractor shall provide such information that is requested by the County for the purpose of monitoring progress under this Contract.

8. Conflict of Interest: The Contractor shall exercise reasonable care and diligence to prevent any actions or conditions that could result in a conflict with the best interests of the County. This obligation shall apply to the Contractor; the Contractor’s employees, agents, and relatives;

subcontractors; and third parties associated with accomplishing work and services hereunder. The

Contractor’s efforts shall include, but not be limited to establishing precautions to prevent its employees or agents from making, receiving, providing or offering gifts, entertainment, payments, loans or other considerations which could be deemed to appear to influence individuals to act contrary to the best interests of the County.

9. Ownership of Documents: The County has permanent ownership of all directly connected and derivative materials produced under this Contract by the Contractor. All documents, reports and other incidental or derivative Work or materials furnished hereunder shall become, and remain, the sole property of the County and may be used by the County as it may require without additional cost to the County. None of the documents, reports and other incidental or derivative Work or furnished materials shall be used by the Contractor without the express written consent of the County.

10. Title to Data: All materials, documents, data or information obtained from the County data files or any County medium furnished to the Contractor in the performance of this Contract will at all times remain the property of the County. Such data or information may not be used or copied for direct or indirect use by the Contractor after completion or termination of this Contract without the express written consent of the County. All materials, documents, data or information, including copies, must be returned to the County at the end of this Contract.

11. Contractor’s Personnel: Contractor warrants that all Contractor personnel engaged in the performance of Work under this Contract shall possess sufficient experience and/education to perform the services requested by the County. County expressly retains the right to have any of the Contractor personnel removed from performing services under this Contract. Contractor shall effectuate the removal of the specified Contractor personnel from providing any services to the County under this

Contract within one business day of notification by County. County shall submit the request in writing to the Contractor’s Project Manager. The County is not required to provide any reason, rationale or additional factual information if it elects to request any specific Contractor personnel be removed from performing services under this Contract.

12. Publication: No copies of sketches, schedules, written documents, computer based data, photographs, maps or graphs, including graphic art Work, resulting from performance or prepared in connection with this Contract, are to be released by Contractor and/or anyone acting under the supervision of Contractor to any person, partnership, company, corporation, or agency, without prior written approval by the County, except as necessary for the performance of the services of this

2540101 Page 13 of 68

Contract. All press contacts, including graphic display information to be published in newspapers, magazines, etc., are to be administered only after County approval.

13. News/Information Release: The Contractor agrees that it will not issue any news releases or make any contact with the media in connection with either the award of this Contract or any subsequent amendment of, or effort under this Contract. Contractors must first obtain review and approval of said media contact from the County through the County’s Project Manager. Any requests for interviews or information received by the media should be referred directly to the County. Contractors are not authorized to serve as a media spokespersons for County projects without first obtaining permission from the County Project Manager.

14. Errors and Omissions: All reports, files and other documents prepared and submitted by Contractor shall be complete and shall be carefully checked by the professional(s) identified by Contractor as

Project Manager and key personnel attached hereto, prior to submission to the County. Contractor agrees that County review is discretionary and Contractor shall not assume that the County will discover errors and/or omissions. If the County discovers any errors or omissions prior to approving

Contractor's reports, files and other written documents, the reports, files or documents will be returned to Contractor for correction. Should the County or others discover errors or omissions in the reports, files or other written documents submitted by Contractor after County approval thereof, County approval of Contractor's reports, files or documents shall not be used as a defense by Contractor in any action between the County and Contractor, and the reports, files or documents will be returned to

Contractor for correction.

15. Audits/Inspections: Contractor agrees to permit the County’s Auditor-Controller or the Auditor-

Controller’s authorized representative (including auditors from a private auditing firm hired by the

County) access during normal working hours to all books, accounts, records, reports, files, financial records, supporting documentation, including payroll and accounts payable/receivable records, and other papers or property of Contractor for the purpose of auditing or inspecting any aspect of performance under this Contract. The inspection and/or audit will be confined to those matters connected with the performance of the Contract including, but not limited to, the costs of administering the Contract. The County will provide reasonable notice of such an audit or inspection.

The County reserves the right to audit and verify the Contractor’s records before final payment is made.

Contractor agrees to maintain such records for possible audit for a minimum of three years after final payment, unless a longer period of records retention is stipulated under this Contract or by law.

Contractor agrees to allow interviews of any employees or others who might reasonably have information related to such records. Further, Contractor agrees to include a similar right to the County to audit records and interview staff of any subcontractor related to performance of this Contract.

Should the Contractor cease to exist as a legal entity, the Contractor’s records pertaining to this

Contract shall be forwarded to the surviving entity in a merger or acquisition or, in the event of liquidation, to the County’s Project Manager.

16. State Funds- Audits: When and if state funds are used in whole or part to pay for the goods and/or services under this Contract, the Contractor agrees to allow the Contractor’s financial records to be audited by auditors from the state of California, the County of Orange, or a private auditing firm hired by the state or the County. The County or state shall provide reasonable notice of such audit.

Pursuant to and in accordance with Section 8546.7 of the California Government Code, in the event that this Contract involves expenditures of Public funds aggregating in excess of Ten Thousand

Dollars ($10,000), the parties shall be subject to the examination and audit of the Auditor General of the State of California for a period of three (3) years after final payment under this Contract.

2540101 Page 14 of 68

The Contractor shall maintain records for all costs connected with the performance of this Contract including, but not limited to, the costs of administering the Contract, materials, labor, equipment, rentals, permits, insurance, bonds, etc., for audit or inspection by County, State, or any other appropriate governmental agency during the three (3) year period.

17. Hazardous Conditions: Whenever the Contractor’s operations create a condition hazardous to traffic or to the public, the Contractor shall provide flagmen and furnish, erect and maintain control devices as are necessary to prevent accidents or damage or injury to the public at Contractor’s expense and without cost to the County. The Contractor shall comply with County directives regarding potential hazards.

Emergency lights and traffic cones must also be readily available at all times and must be used in any hazardous condition. Emergency traffic cones must be placed in front of and behind vehicles to warn oncoming traffic.

Signs, lights, flags, and other warning and safety devices shall conform to the requirements set forth in Chapter 5 of the current traffic manual, Traffic Control for Construction and Maintenance Work

Zones, published by the state of California Department of Transportation. The Contractor shall take proper safety and health precautions to protect the Work, the workers, the public, and the property of others. The Contractor shall also be responsible for all materials delivered and Work performed until completion and acceptance of the entire construction Work, except for any completed unit of construction thereof which theretofore may have been accepted.

18. Conditions Affecting the Work: The Contractor shall be responsible for having taken steps reasonably necessary to ascertain the nature and location of the Work, and the general and local conditions, which can affect the Work or the cost thereof for any Job Order. Any failure by the

Contractor to do so will not relieve him from responsibility for successfully performing the Work without additional expense to the County. The County assumes no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of this Contract, unless such understanding or representations by the County are expressly stated in the Contract.

19. County's Property On Site: All fixtures, crops, trees, and all other personal property of the County located at the job site which are removed in the course of construction of the project remain the property of the County unless express provision to the contrary is made in the Contract between the

Parties, and the Contractor shall exercise reasonable care to prevent loss or damage to said property and shall deliver promptly such property to the place designated by the County.

20. Protection: The Contractor shall take proper safety and health precautions to protect the Work, the workers, the public, and the property of others. Contractor shall comply with the provisions of the

Construction Safety Orders issued by the State Division of Occupational Safety & Health. He shall also be responsible for all materials delivered and Work performed until completion and acceptance of the entire construction Work, except for any completed unit of construction thereof which until completion and acceptance of the entire construction Work, except for any completed unit of construction thereof which theretofore may have been accepted.

The Contractor shall maintain continuously adequate protection of all his Work from damage and shall protect the County's property from injury or loss arising in connection with this Contract. He shall make good any such damage, injury or loss, except such as may be directly due to errors in the

Contract documents or caused by agents or representatives of the County. He shall adequately protect adjacent property as provided by law and the Contract documents, and shall maintain reasonable security of the site at all times. He shall limit visitors to the site to those necessary for construction and inspections. Visitors for other purposes shall be referred to OC Public Works. Contractor's and subcontractors' employees shall possess means of identification at all times as required by OC Public

Works while on the job site.

2540101 Page 15 of 68

In an emergency affecting the safety of life or of the Work or of adjoining property, the Contractor, without special instruction or authorization from the A-E or County, is hereby permitted to act at his discretion to prevent such threatened loss or injury. He shall so act if directed or instructed by OC

Public Works. Any dispute as to compensation claimed by the Contractor on account of emergency

Work shall be determined by agreement as hereinafter set forth.

OC Public Works may notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately correct such conditions. Such notices, when delivered to the Contractor or his representative at the site of the

Work, shall be deemed sufficient for said purpose. Failure of receipt of such notice from OC Public

Works shall not relieve the Contractor of responsibility.

If the Contractor fails or refuses to comply promptly, OC Public Works may issue an order stopping all or part of the Work until satisfactory corrective action has been taken. No part of the time lost due to any such stop order shall be made the subject of claim for extension of time or for excess costs or damages to the Contractor. The Contractor will be responsible for ensuring that his subcontractors comply with the provisions of this Clause.

Contractor shall comply with County’s Safety and Loss Prevention Policy and Procedure #306

(“Contractor Safety Responsibilities”) and submit a copy of its Injury and Illness Prevention Program

(IIPP), Jobsite Safety Inspection Checklist, and Contractor Safety-Activity Checklist to the designated County Procurement staff as part of the solicitation and/or contract process.