Answers_to_Solicitation_Questions_FERC-16-Q-0018.pdf.docx

DOCX document 51 KB Posted

Attached to
Rock Erosion Technical Services to Update FERC’s Engineering Guidelines for the Evaluation of Hydropower Projects, Arch Dam Chapter
Solicitation number
FERC16Q0018
Issued by

About this file

FERC-16-Q-0018 Answers to Solicitation Questions_FERC-16-Q-0018.pdf.docx

View the file

Other files

File Type Posted
FERC-16-Q-0018_1.docx DOCX document
FERC-16-Q-0018.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Answers to Solicitation FERC-16-Q-0018 Questions

Question # 1: Is this a follow-on requirement? If so, could you please provide the incumbent contract number for this opportunity? If not, is this a new requirement?

FERC Answer: This is not a follow-on requirement, it is a new requirement.

Question # 2: In the section on Additional information (page 23), first line, there is confusion on the page limit. Please see below and clarify. It currently says …. to twenty (10) pages …

FERC Answer: The correct page limit is ten (10) pages.

Question # 3: The website shown below appears out of service. Please provide a substitute.

FERC Answer: Registration in SAM is required per FAR 52.212-4(t); therefore, paragraph (C)(2) of FAR provision 52.204-16 -- COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (NOV 2014) is not necessary because a CAGE code will be assigned as a result of obtaining the required SAM registration, as indicated in paragraph (C)(1) of the same provision.

image1.jpeg

File details come from the government source that posted it. Updated .