Questions & Answers

Public Safety Tower Project FEMA Region 1

1.) Would your technical team consider reusing the existing conduits by installing a pad poured around the existing conduits and placing a lockable NEMA enclosure over the conduits to create a dry lightning arrestor patch panel that will be bonded to exiting tower grounding and a lateral grounding system in shaded area if required. Yes, we can add conduits just on top of existing to increase capacity if required.

FEMA has no intentions of leaving any cabling in the conduit. The existing underground conduit will be sealed in place after this project is completed as a temporary solution until FEMA can have it removed at a later date.