Falcon_Field_Planning_RFQ_2027.docx

DOCX document 39 KB Posted

Attached to
RFQ Airport Consulting Services- Planning Services
Solicitation number
PE-66888-NONST-2027-000000008
Issued by
Fayette County, Georgia

About this file

This is a Request for Qualifications (RFQ) issued by the Peachtree City Airport Authority for professional airport planning and environmental services at Atlanta Regional Airport – Falcon Field in Georgia. The Authority seeks to select one qualified aviation consulting firm to provide on-call services including Airport Layout Plan (ALP) updates, environmental assessment or categorical exclusion documentation, land acquisition planning support, and program coordination. Specific anticipated projects span fiscal years 2027 through 2031 and include Runway RSA and TSA improvements with ALP updates ($475,000 total project cost), Runway 13 easement acquisition and obstruction removal ($754,000), Area B and C environmental documentation ($125,000), and acquisition of miscellaneous TTF properties ($4,000,000). Written questions are due December 2, 2026 at 12:00 p.m. Eastern Time, with Statements of Qualifications due December 16, 2026 at 12:00 p.m. Eastern Time. Shortlist notices and interviews are scheduled for January 7 and 14, 2027, with anticipated selection and agreement execution between January 19 and February 27, 2027. The Master Agreement term is five years from the effective date, with individual assignments to be negotiated through separate written task orders. No minimum amount of work is guaranteed under this agreement.

Consultant fees, overhead rates, and hourly rates must not be included in the Statement of Qualifications submission. Responding firms must hold current Georgia Department of Transportation (GDOT) Area Class 1.08 Airport Master Planning prequalification and maintain required professional licenses throughout performance. Responding firms must also identify qualified environmental specialists and any additional discipline-specific approvals. The Authority will obtain an independent fee estimate and perform cost or price analysis before negotiating compensation with the highest-ranked firm; if negotiations fail, they will be formally terminated before proceeding with the next-ranked firm. This RFQ is independent of the Authority's separately issued Engineering, Architectural, and Construction Services RFQ; firms seeking both must submit separate responses to each. Work is funded through Federal, State, or local funding sources, with GDOT coordination required for State funding consideration. The procurement must comply with 49 U.S.C. 47107(a)(17), 40 U.S.C. Chapter 11, 2 CFR Part 200, FAA AC 150/5100-14E with Change 1, Georgia law, and applicable DBE requirements under 49 CFR Part 26. Responses must be submitted as four paper copies in a sealed envelope to Hope Macaluso at 7 Falcon Drive, Peachtree City, GA 30269.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Qualifications Airport Planning and Environmental Services Atlanta Regional Airport Falcon Field Peachtree City Airport Authority Peachtree City Georgia 1 Invitation and agreement term The Peachtree City Airport Authority invites Statements of Qualifications from qualified aviation consulting firms to provide professional on-call airport planning and environmental services for Atlanta Regional Airport - Falcon Field. The Authority intends to select one consultant team under this RFQ and execute a separate Master Agreement for these services.

The anticipated Master Agreement term is five years from [AGREEMENT EFFECTIVE DATE], ending [AGREEMENT EXPIRATION DATE]. Assignments will be negotiated individually through written task orders. Attachment A identifies specific FY2027-2031 CIP projects reasonably expected to be initiated within five years of the agreement effective date. Some services may not be required; no minimum amount of work is guaranteed.

This solicitation is independent of the Authority’s Engineering Architectural and Construction Services RFQ. A firm seeking both must submit a separate response to each; each will have its own evaluation, ranking, negotiation, agreement, and procurement file.

2 Solicitation schedule

Milestone
Date and time
Advertisement and RFQ release
NOVEMBER 18, 2026
Written questions due
DECEMBER 2, 2026, at 12:00 p.m. Eastern Time
Responses and addenda issued
DECEMBER 9, 2026, at 3:00 p.m. Eastern Time
Statements of Qualifications due
DECEMBER 16, 2026, at 12:00 p.m. Eastern Time
Shortlist notice and interviews
JANUARY 7, 2027/ JANUARY 14, 2027
Anticipated selection and agreement
JANUARY 19, 2026 / FEBRUARY 27, 2027

The published schedule and any changes will be communicated by written addendum. Eastern Time means the local time in Peachtree City on the applicable date.

3 Scope of professional services Services are limited to the planning and environmental components of the named projects in Attachment A. This agreement does not include preliminary or final engineering design, construction bidding, or construction administration and inspection.

Airport planning and ALP updates Prepare the ALP updates associated with the runway RSA and TSA improvements; perform the planning and obstruction analyses associated with the Runway 13 easement acquisition and obstruction removal. Provide inventories, facility and land-use analyses, alternatives evaluation, and agency coordination needed for those assignments.

Environmental studies and documentation Prepare the Area B and C environmental assessment or categorical exclusion documentation, supporting resource studies, alternatives analysis, agency consultation, public involvement, and mitigation coordination as applicable. FAA and other responsible agencies determine the required level of review and make environmental decisions.

Land acquisition planning support For the FY2031 TTF property acquisition, provide acquisition planning, land-use and environmental due diligence, and ALP or property exhibit coordination only as needed and authorized. Real estate appraisal, review appraisal, negotiation, relocation, and legal services require appropriately qualified providers and a compliant procurement method.

Program coordination Provide project funding applications and CIP support directly associated with Attachment A assignments. Standalone DBE program administration and unrelated financial, legal, or real estate services are not awarded through qualifications-based selection under this RFQ. Coordinate technical inputs with the separately selected engineering consultant.

4 GDOT prequalification and licensing For State funding consideration, the responding firm must hold current GDOT Area Class 1.08 Airport Master Planning prequalification. Identify qualified environmental specialists and any additional discipline-specific approvals required for the assigned work.

Provide current approval evidence, expiration dates, and a matrix identifying the prime or subconsultant performing each discipline. Each provider must hold the qualifications required for its assigned work; a prime firm’s approval does not qualify an unapproved subconsultant. Maintain required approvals and Georgia professional licenses throughout performance. The Authority will verify status with GDOT before award and task authorization.

5 Statement of Qualifications requirements Submit four paper copies in a sealed envelope or box to Hope Macaluso, A.A.E., Peachtree City Airport Authority, 7 Falcon Drive, Peachtree City, GA 30269. Clearly mark the package “Airport Planning and Environmental Services RFQ” and include the submitting firm’s name. Responses must be received by the deadline in Section 2; late responses will not be considered.

Organize the response in the following order. Do not include consultant fees, overhead rates, hourly rates, or other pricing in the SOQ or interview. Historical project budgets may be included only to demonstrate experience and cost control.

1. Firm and team. Identify the legal entity, authorized contact, firm size, proposed subconsultants, responsibilities, and current GDOT prequalification and professional licenses.

2. Personnel and organization. Provide an organization chart, project manager and key staff resumes, discipline roles, availability, and office responsible for performance.

3. Comparable experience. Describe relevant projects completed or substantially performed within the last five years at comparable airports, including scope, team role, dates, outcomes, schedule performance, and cost control.

4. Approach to the CIP. Explain the approach to Attachment A, project dependencies, regulatory coordination, operational safety, and the division of responsibilities between planning and engineering.

5. Capacity and service. Summarize current workload, staffing commitments, support offices, response capability, and ability to meet schedules. Explain relevant knowledge of FAA and GDOT aviation programs.

6. References and disclosures. Provide at least three current airport client references with contact name, agency, phone, and email. Disclose actual or apparent conflicts, prior involvement relevant to this RFQ, and any competitive advantage. Acknowledge each addendum.

6 Predetermined evaluation criteria Eligibility and responsiveness are evaluated first. Responsive SOQs will be scored on a 100-point scale using the following maximum points. The same criteria and weights apply to shortlist and final evaluation.

Criterion
Maximum points
Comparable airport project experience
25
Key personnel and technical qualifications
25
Understanding and approach to the identified CIP work
20
Capacity availability and schedule performance
15
Past performance quality and cost control
10
Service delivery and coordination capability
5

Technical qualifications include airport planning, ALP development, environmental documentation, resource studies, and public and agency coordination. Office location is requested to assess service delivery; no local office or residency preference is established. DBE participation is administered under applicable requirements and is not assigned qualification points.

7 Separate qualifications based selection process

1. Selection panel. The Authority will appoint a panel of at least three members, including a professional knowledgeable in the services sought. Members will disclose conflicts and follow written standards of conduct. The criteria and evaluation method will be established before advertisement.

2. Public notice and screening. The Authority will publicly advertise this RFQ, review timely SOQs for responsiveness and required qualifications, and document all eligibility decisions. It will evaluate this solicitation separately from the companion RFQ.

3. Shortlist. The panel will identify three to five best-qualified firms when sufficient qualified responses are received. If fewer than three qualified firms respond, the Authority will document the circumstances and coordinate the next steps with GDOT before proceeding. Firms not shortlisted will receive written notice.

4. Interviews and references. Shortlisted firms will be interviewed or further evaluated using Section 6. If interviews are held, each firm will receive at least seven days’ notice and the same format and opportunity. The panel may omit formal interviews if SOQs and documented reference checks provide sufficient information. No price information will be requested during ranking.

5. Final ranking. Each panelist will score each firm from zero to the maximum points for each criterion. The panel’s average total score establishes the ranking. The final evaluation supersedes the preliminary shortlist score and considers SOQs, reference checks, and interviews if conducted. Ties are resolved by higher scores for comparable experience, then key personnel, then project approach; any remaining tie requires a documented panel determination based on those criteria.

6. Scope and fee negotiations. The Authority will negotiate a detailed scope and fair and reasonable compensation only with the highest-ranked firm. It will obtain an independent fee estimate and perform the required cost or price analysis before agreeing to compensation. If negotiations fail, they will be formally terminated in writing before negotiations begin with the next-ranked firm; simultaneous fee competition is prohibited.

7. Award and notification. Subject to Authority approval and required funding-agency review, the Authority will execute a separate planning Master Agreement. Unsuccessful firms will be notified in writing no later than five days after selection and contracting are completed.

8 Procurement documentation and GDOT submission The Authority will retain a separate procurement file for this solicitation containing advertisements and publication evidence; the RFQ and addenda; questions and answers; all SOQs; prequalification checks; panel appointments and conflict disclosures; shortlist decisions; individual and consolidated scores; interview and reference records; the final ranking and selection report; notices; the independent fee estimate and fee analysis; negotiation records; approvals; and the executed agreement.

Upon completion of selection, the Authority will submit the procurement documentation to GDOT, including the advertisements, RFQ, all submittals, shortlist and evaluation records, and executed agreement. Records will be retained for the applicable Federal, State, grant, audit, and litigation retention periods. The Authority will coordinate its anticipated selection schedule with GDOT Project Manager Lew Walker at LeWalker@dot.ga.gov.

9 Solicitation and contract conditions Governing requirements Selection and contracting will comply with 49 U.S.C. 47107(a)(17), applicable qualifications-based selection principles in 40 U.S.C. Chapter 11, 2 CFR Part 200 including 200.318 through 200.327 as applicable, FAA AC 150/5100-14E with Change 1, applicable Georgia law, and funding-agency requirements. Qualifications-based procurement is limited to eligible professional services; unrelated services require an appropriate separate procurement method.

Task orders and scope control Attachment A defines the projects and service boundaries of this procurement. Work may span multiple years, task orders, and Federal, State, or local funding sources. Each task order must identify its scope, deliverables, schedule, negotiated fee, funding, and required approvals before work begins. New or materially different projects require a new procurement unless a permitted addition has all required written GDOT and FAA approvals. The Authority reserves the right to procure listed services separately.

GDOT reports that the current agreement expires in February 2027. No task order or work authorization executed after an agreement’s expiration is eligible for Department funding under the supplied guidance. New work will not be authorized under an expired agreement. Any continuation of previously authorized work beyond the agreement term requires contract and funding-agency authorization; no automatic extension is created.

Nondiscrimination and DBE requirements The consultant and subconsultants shall comply with applicable nondiscrimination requirements and 49 CFR Part 26 for federally assisted contracts. Applicable DBE requirements, any approved contract goal, certification requirements, and documentation of commitments or good faith efforts will be stated in the solicitation addenda or contract documents as required before the applicable commitment deadline. Certified DBE firms must meet the applicable Georgia Unified Certification Program requirements. Failure to meet applicable contractual nondiscrimination and DBE obligations may constitute a material breach.

Conflicts and equal access Firms must disclose involvement in preparing this RFQ or its requirements, current related assignments, and actual or apparent conflicts. The Authority will apply applicable restrictions on firms that prepared procurement requirements and address unfair competitive advantage before selection. Current project information material to competition will be made available equally through addenda.

Questions submissions and reservations Direct written questions and site visit requests only to Hope Macaluso, A.A.E., Aviation Director, at hope@kffc.org, 7 Falcon Drive, Peachtree City, GA 30269; phone 770-487-2225. Written answers affecting the RFQ will be issued to all interested firms by addendum. Unauthorized solicitation-related contact with Authority officials, selection panel members, or Airport employees may result in disqualification.

The Authority may reject any or all submissions, request clarifications, or waive minor informalities consistent with applicable law and equal treatment. Firms bear their response and presentation costs. The Authority assumes no responsibility for late, improperly addressed, or incorrectly identified submissions.

Attachment A Anticipated planning projects Source: Atlanta Regional Airport - Falcon Field Capital Improvements Plan, FY2027-2031, supplied file dated October 15, 2025. The first column gives fiscal year and local priority. Descriptions retain the CIP project identity with expanded abbreviations where helpful. Costs are the total budget for the listed CIP row, not consultant fees or the budget for the component assigned by this RFQ. A shared project cost is not additive across the two RFQs.

Years and budgets are anticipated and depend on funding, approvals, project readiness, and the five-year initiation limit in Section 1. A CIP listing is not a funding commitment or authorization to duplicate previously contracted work. Reimbursement items and FY2026 entries are addressed separately below.

FY and priority
CIP project and services under this RFQ
Total CIP cost

Runway RSA and TSA Improvements with ALP Updates - Design Services: ALP update, planning coordination, and related agency submissions only. Engineering design is separately procured.

$475,000

Runway 13 Easement Acquisition 1.79 plus or minus Acres and Obstruction Removal - Planning Design Bid and Construction Services: Planning, obstruction and land-use analyses, and related environmental coordination only. Engineering design, bidding, construction services, and real estate transactions are separate.

$754,000

Area B and C - Environmental EA or CatEx Services: Environmental assessment or categorical exclusion documentation and supporting studies, consultation, public involvement, and mitigation coordination as applicable.

$125,000

Acquire Miscellaneous Land TTF Properties - Land Acquisition Services: Planning and environmental due diligence, acquisition planning, and ALP or property exhibit coordination only if required and authorized. The CIP does not identify a separate planning fee; property purchases and standalone real estate services are excluded.

$4,000,000

The planning and environmental components of mixed CIP entries will be scoped and priced separately from engineering services. The total CIP costs above include other phases and, for acquisition projects, land costs. No full airport master plan or unrelated noise study is added solely by this procurement.

Attachment A Project boundaries and status Reimbursements and prior year work

FY and priority
CIP item and treatment
Total CIP cost
Reimbursement for FY2027-2029 DBE Plan Update. Reimbursement only; no automatic new DBE plan assignment. Any standalone DBE administration requires an appropriate procurement.
$12,000
Reimbursement - Terminal Auto Parking Area Expansion Design and Construction. No new planning assignment.
$1,430,341
Reimbursement - Upper Ramp Lower Ramp North Ramp Design. No new planning assignment.
$250,000
Area C Access Road Utilities - Bid and Construction Reimbursement. No new planning assignment.
$2,000,000

The CIP includes two FY2026 entries outside this solicitation horizon: Air Traffic Control Tower siting, environmental EA or CatEx, design and FCT Tower Feasibility Study reimbursement ($763,882), and Runway RSA and TSA Improvements EA and mitigation permitting ($200,000). They are not represented as new FY2027-2031 assignments. Any remaining unperformed work must be assessed against its existing agreement and procured or authorized through a compliant action.

Engineering projects and conditional coordination The remaining FY2027-2031 CIP entries concern tower construction, runway rehabilitation, RSA and EMAS construction, MALSR and edge lights, apron and refueler parking expansion, fuel farm replacement, Area C roads and utilities, Taxiway A, Area B and Hangar B-3 relocation, wildlife fencing, ramps, and Hangar Area A taxilanes. Their design, bid, and construction services belong to the separate engineering RFQ.

The Area B and C environmental assignment may support the named Area B and C development projects. This relationship does not create a separate environmental study for every engineering project. Any additional environmental or planning assignment must have a defined project scope and satisfy Section 9 before authorization. Environmental conclusions must remain independent of engineering design and implementation decisions.

Reference documents GDOT Consultant Selection - Atlanta Regional-Falcon Field Airport, email dated October 29, 2026, pages 1-2.

Atlanta Regional Airport - Falcon Field Capital Improvements Plan, supplied FY2027-2031 file dated October 15, 2025, page 1.

FAA AC 150/5100-14E with Change 1, Architectural, Engineering, and Planning Consultant Services for Airport Grant Projects: https://www.faa.gov/documentLibrary/media/Advisory_Circular/AC_150_5100-14E_with_chg_1.pdf GDOT Consultant Prequalification Manual, Revision 2.10, September 6, 2024, and current consultant status search: https://www.dot.ga.gov/GDOT/Pages/EngineeringConsultantQualification.aspx Atlanta Regional Airport Falcon Field | Planning RFQ | 1

File details come from the government source that posted it. Updated .