- Request for Bids - Fairgrounds Shower Building
- Solicitation number
- 2024-02-12.02
- Issued by
- Rusk County, Wisconsin
About this file
This is a Request for Sealed Bids issued by Rusk County, Wisconsin for the construction of a shower building at the County Fairgrounds. The project involves constructing a new shower facility with specifications detailed in attached drawings and notes labeled Addendum A. All permits and utilities are the responsibility of the contractor. Site visits can be arranged by contacting Gary Shilts, Facilities Manager, at 715-415-5529. Sealed bids are due by March 7, 2024 at noon, to be submitted to Gary Shilts at 311 E Miner Ave, Ladysmith, WI 54848 (Clerks Office). Bids will be opened on March 8, 2024 during the next Property Meeting, with the bid award scheduled for March 26, 2024 at the County Board Meeting. Construction is to begin April 15, 2024, with substantial completion targeted for July 12, 2024, a punch list due July 15, 2024, and final construction completion by July 26, 2024.
Liquidated damages may be assessed if work is not completed before the County Fair on August 5-12, 2024, with the contractor responsible for supplying eight temporary shower and restroom facilities, including labor, mobilization, demobilization, stock supplies, and all hookups and disconnects. No pricing terms, set-asides, or funding source information is specified in the bid document. Questions regarding the project can be directed to Gary Shilts at gshilts@ruskcountywi.us.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Sealed Bids Rusk County Fairgrounds Shower
Building
- See Attached Drawings/Notes labeled Addendum A
- All Permits/Utilities By Contractor
- Contact Gary Shilts Facilities Manager for a site visit 715- 415-5529
- Send sealed bids to Gary Shilts 311 E Miner Ave.
Ladysmith Wi. 54848 (Clerks Office)
- Sealed bids due by 3/7/2024 Noon
- Bids open 3/8/2024(Next Property Meeting)
- Bid Awarded 3/26/2024 (County Board Meeting)
- Construction to Begin 4/15/2024
- Substantially Complete 7/12/2024
- Punch List 7/15/2024
- Construction Completion 7/26/2024
- Liquidated Damages May Apply If Work Not Complete Before Fair 8/5/2024 8/12/2024 ( Which Would Include
Being Responsible For Supplying 8 Temp.
Shower/Restrooms, Labor, Mobilization, Demobilization, Stock Supplies, Hookups, Disconnects, Etc.