This is a solicitation for a construction project to modernize a mechanical room at a Federal Aviation Administration air traffic control facility. The solicitation seeks offers for furnishing all labor, equipment, and materials to modernize the mechanical room at the Jacksonville Air Route Traffic Control Center in Hilliard, Florida. The project is set aside for small businesses, with a price range of $250,000 to $500,000. Payment and performance bonds are required. A mandatory site visit will be held on June 21, 2022, with COVID protocols in place. Offers are due within 30 calendar days of the solicitation date. The solicitation will be posted on the Federal Business Opportunities website, and amendments will be posted there rather than distributed separately. Offerors must be registered in the System for Award Management to be eligible for award. Electronic submissions in PDF format are required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ZJX virtual survey.pdf | ||
| 697DCK-22-R-00410 amendment2.pdf | ||
| ZJX Panel Locations.pdf | ||
| 697DCK-22-R-00410amendment1.pdf | ||
| ZJX-D-1508555-Drawings.pdf | ||
| WagerateSJX.pdf | ||
| rfo697DCK-22-R-00410.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Aviation Administration
ZJX Air Route Traffic Control Center Hilliard, Florida
AHU 1-3 REPLACEMENT.
SPECIFICATION
April 2020
Specification number: FAA-ZJX-1508555
MODERNIZE THE AUTOWING MECHANICAL ROOM 111A REPLACE AHU 1,2,3 APRIL 2020
HILLIARD, FL FAA-ZJX-JCN 1508555
TABLE OF CONTENTS 00 01 10 - 1
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY
01 14 13 SITE ACCESS, CONSTRUCTION LIMITS
01 14 16 COORDINATION AND TESTING
01 33 00 SUBMITTALS
01 35 29 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES
01 73 29 CUTTING AND PATCHING
01 74 00 CLEANING
DIVISION 02 - EXISTING CONDITIONS
02 41 19 SELECTIVE STRUCTURE DEMOLITION
DIVISION 03 – CONCRETE (NOT USED)
DIVISION 05 - METALS (NOT USED)
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES (NOT USED)
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 13 PENETRATION FIRESTOPPING
DIVISION 09 – FINISHES (NOT USED)
DIVISION 10 – SPECIALTIES
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
23 00 00 BASIC MECHANICAL MATERIALS AND METHODS.
23 05 19 METERS AND GAGES FOR HVAC PIPING
23 05 23 GENERAL-DUTY VALVES FOR HVAC PIPING
23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 19 HVAC EQUIPMENT AND PIPING INSULATION
23 09 00 INSTRUMENTATION AND CONTROLS FOR HVAC
23 21 13 HYDRONIC PIPING
23 30 00 AIR DUCT ACCESSORIES
23 31 13 23 81 23
METAL DUCTS
COMPUTER ROOM AIR CONDITIONERS
DIVISION 26 - ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
TABLE OF CONTENTS 00 01 10 - 2
DIVISION 27 – COMMUNICATIONS (NOT USED)
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY (NOT USED)
DIVISION 31 – EARTHWORK (NOT USED)
DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)
APPENDIX A – FAA ORDER 1217H ELECTRICAL WORK, PREMISES WIRING
APPENDIX B – RECCOMENDED GRAPHICS FOR HVAC CONTROLS
END OF TABLE OF CONTENTS
GENERAL REQUIREMENTS 01 00 00-1
SECTION 01 00 00 GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 SCOPE
Scope - These specifications, together with referenced specifications, standards, construction drawings specified on the Contract Documents and the conditions of the Construction Contract cover the requirements of the Federal Aviation Administration (FAA) for the work associated with this project.
1.2 REPAIR AND PROTECTION
A. General: Upon completion of inspection, testing, sample taking and similar services, repair damaged construction and restore substrates and finishes.
B. Protect construction exposed by, or for quality control service activities, and repaired construction.
C. Contractor is responsible for, but not limited to, all repair and protection of existing equipment, systems and services, associated with or affected by the contract requirements and work area.
1.3 INDUSTRY STANDARDS
A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.
B. Publication Dates: Comply with the standards in effect as of the date of the Contract Documents.
C. Conflicting Requirements: Where compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different but apparently equal to the COR for a decision before proceeding.
1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to the COR for a decision before proceeding.
D. Copies of Standards: Each entity engaged in construction on the Project must be familiar with industry standards applicable to its construction activity. Copies of applicable industry standards are not bound with the Contract Documents.
1. Where copies of standards are needed to perform a required construction activity, the
Contractor shall obtain copies directly from the publication source and make them available on request.
E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where abbreviations and acronyms are used in the Specifications or other Contract
GENERAL REQUIREMENTS 01 00 00-2
Documents, they mean the recognized name of the trade association, standards-generating organization, authorities having jurisdiction, or other entity applicable to the context of the text provision. Refer to Gale Research's "Encyclopedia of Associations" or ‘Columbia Books' "National Trade & Professional Associations of the U.S.," which are available in most libraries.
1.4 RECORD DRAWINGS
The Government shall provide the Contractor with an electronic copy of the record drawings in .PDF format. During the course of construction, the addition of new graphics or text shall be in green; the removal of any text or graphics shall be in red. Any additional notes or general information shall be noted in blue. These “as-builts” shall be submitted to the FAA both in hard and soft copy; number of copies to be determined by the COR. As-Built progress shall be reviewed as part of each pay application submitted by the Contractor.
END OF SECTION 01 00 00
SUMMARY OF WORK 01 11 00 - 1
SECTION 01 11 00 SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Scope of Work - These specifications, together with the referenced specifications, standards, and drawings specified in the contract documents cover the requirements for all work associated with the following activities in the Control Wing attic located at the Jacksonville (ZJX) ARTCC located in Jacksonville, FL.
Contractor to provide labor and materials to replace three computer room units and two humidifiers.
The work shall include:
1. Removal and replacement of three nominal twenty ton chilled water computer room units.
2. Removal and replacement of two electrode steam generating humidifiers and distribution tubes.
3. Installation of new controls for the computer room units and humidifiers.
4. Preliminary and Final Testing and Balancing of the Autowing 1st Floor.
The General Contractor (GC) shall be expected to work during day times, 07:00 AM to 3:30 PM.
Extensive coordination between the GC and the COR shall be required at all times in order to maintain an operational facility. Prospective bidders are strongly recommended to perform a site visit to assess the actual conditions before submitting a bid. Site visits should be arranged thru the Contracting Officer’s Office.
B. FAA Holiday Moratorium - No work shall be scheduled or take place during the week of and the weekend preceding and following: Thanksgiving, Christmas, and New Year’s. Only emergency work to restore critical services to the Facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration of the project.
C. FAA Holidays Observed - The FAA also observes the following Holidays: : Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, and Veterans Day.
Any work required on any observed Holiday must be coordinated with the Contracting Officer Representative (COR) two weeks in advanced. The Holiday observances will not be counted against the contract construction duration of the project.
D. Intent of Specifications - This specification identifies all material, labor, and equipment required to perform this work. All work performed and all materials and equipment used are subject to approval by the Contracting Officer (CO) and /or the Contracting Officer Representative (COR). This shall include but is not limited to inspection, scheduling, reporting and submittals.
E. Title - Titles to division and sections of the specifications and notes and titles on drawings referring to subcontractors, division of work by trade, or type of work, are introduced merely for convenience in reading the specifications and drawings and do not imply any separate contractual arrangements of work assignments. Such separations into titled divisions and sections shall not operate to make the Government an arbiter to establish subcontract limits between the contractor and subcontractors, or between the subcontractors themselves.
William Luquette Rectangle
SUMMARY OF WORK 01 11 00 - 2
F. Contract Documents - The drawings form a part of the construction requirements for this project. The Contractor shall not use dimensions scaled from drawings. All dimensions shown on the drawings shall be field verified by the contractor prior to construction. Any discrepancies between the drawings and specifications and the existing conditions shall be referred to the CO for adjustment before any work affected is performed.
G. Precedence of Contract Documents - In the event of a difference between the following contract provisions, the order of precedence to determine which provision shall govern is:
1. Contract Clauses and Provisions
2. Project Specifications
3. Project Drawings
Any discrepancies between the contract provisions, the specifications and the contract drawings shall be referred to the CO for a written determination in accordance with Contract Clause entitled Order of Precedence.
H. Contracting Officer -The term "Contracting Officer" (CO) as used herein denotes the person designated to act on behalf of the Government in the performance of this contract. Where reference is made to "Federal Aviation Administration" (FAA), "Contracting Officer's Representative" (COR), or the like, this shall mean the Contracting Officer or his/her authorized representative.
I. Contractor Superintendence - In accordance with Contract Clause entitled SUPERINTENDENCE BY THE CONTRACTOR, the Contractor shall at all times during performance of this contract and until the work is completed and accepted, directly superintend the work or assign and have on site a competent superintendent with the authority to act for the Contractor. The Contractor shall submit a Project Organizational Chart with the key personnel identified and their qualifications for the Government’s review and approval. If, in the event the Contractor is not on site, on site activities shall cease immediately, or a competent superintendent with the authority to act for the Contractor must be appointed in writing to the CO and COR.
1.2 SPECIAL REQUIREMENTS
A. Asbestos Containing Materials - No new materials supplied by the contractor for this construction shall contain asbestos or lead-based products. The contractor shall verify that all materials, including those supplied by third parties, are asbestos free and/or lead-based free materials.
1. Contractor certification requirements. - The contractor shall provide to the Contracting Officer (CO) a signed and notarized document stating that to the best of his/her knowledge, no asbestos containing or lead-based materials were used during the construction, renovation, and/or modernization of this facility.
2. Safety Data Sheets. - The contractor shall submit Safety Data Sheets (SDS) with all submittals for review and approval by the Contracting Officer Representative. New materials found to contain asbestos and/or lead-based products will be automatically disapproved. Copies of all SDS sheets shall be provided to the facility FAA personnel for the building records. The contractor shall comply with all health and safety provisions outlined in each SDS and shall follow all OSHA guidelines regarding personnel protection.
3. Hazardous materials.- If the FAA COR suspects the presence of asbestos or lead-based products in the new materials, the FAA will sample the suspect material to verify that no asbestos containing material or lead-based material were used. If these materials are found to contain asbestos or lead-
SUMMARY OF WORK 01 11 00 - 3
based products, the cost of the survey and all subsequent removal/replacement of any hazardous materials shall be at the contractors’ expense.
B. Work plan and scheduling - Prior to the Contracting Officer issuing the Notice To Proceed (NTP), the contractor shall submit for approval a plan and schedule of his work.
C. Sequence of work - The contractor shall be responsible for scheduling all aspects of the work and coordinating among the different trades involved in the project. The Federal Aviation Administration (FAA) has developed a list of milestones that the contractor shall be required to meet.
D. Construction Activities and Milestones – Construction Activities and Milestones below shall be included in the submitted schedule. They are provided for guidance, but are not intended to direct how and when contract activities shall be ordered or take place in the submitted schedule.
1. Submittal Approval
2. Notice To Proceed
a) Scheduled by the FAA’s CO
3. Establish Protection Of Personnel And Equipment
a) Lockout Utilities
4. Installation and start up of AHU-2.
5. Installation and start up of AHU-3.
6. Installation and start up of AHU-1.
7. Installation of Humidifiers
8. Remove Personnel and Equipment Protection
a) Remove equipment lockout devices
9. Operator training on new CRU units and Humidifiers
10. Controls Training.
11. Deliver Closeout Documents
12. Contactor Acceptance Inspection
13. Close Job
E. Driveway Closures - Contractor shall maintain access to the loading dock at all times.
F. New Utility Work - Interface all existing utility work with new utility work as indicated in the plans and specifications.
END OF SECTION 01 11 00
SITE ACCESS CONSTRUCTION LIMITS 01 14 13 - 1
SECTION 01 14 13 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK
HOURS
A. Existing facility operations - Construction/demolition shall in no way interfere with Air Traffic Control
Operations. The ARTCC is a 24-hour, seven day a week facility. Extreme care shall be exercised so as not to cause any interference or interruption of service from this facility. Controller functions are vital to the safety of the flying public. It is absolutely mandatory that the contractor protect FAA personnel and existing FAA communication, electrical and mechanical equipment both inside and outside buildings from damage caused by impact, water, debris, dust or odor. The contractor shall have the overall responsibility for the performance and enforcement of all forms of protection within the ARTCC premises against any damages due to work performed under this contract. Any damages incurred, as a result of construction activity during the performance of this contract will be repaired/replaced immediately by the contractor at no cost to the
FAA.
Any work or activity that may impact the National Airspace System (NAS), such as work on critical equipment or circuits, will require coordination with the Contracting Officer Representative (COR). The COR will prepare and submit a work or activity specific “Risk Assessment” for the facility’s review and approval. This process may take one week to complete. Typically, this type of work or activity is performed from midnight to 05:00 am and/or on weekends.
B. Construction limits and access
1. Construction limits - The contractor shall confine operations, activities, storage of materials and employee parking within the designated areas, as indicated on the construction staging plan, or as designated by the COR. Additional space the contractor deems necessary shall be obtained off site, at no additional cost to the Government.
2. Access - Access route for the contractor, subcontractors, employees, deliveries, etc., shall be through the main gate, or as designated by the COR. Access to all, parking areas, and loading dock shall be kept unobstructed. If temporary access obstruction is unavoidable, the contractor shall advise the COR immediately. Vehicles transporting materials shall not be loaded beyond the capacity prescribed by federal, state, or local laws. Obstruction of existing roadways, driveways, to the ARTCC is strictly prohibited.
3. Damage to site - Damage to existing paving, lawns, curbs, sidewalks, and utilities caused by the contractor's activities shall be repaired immediately. Any damage to the building, interior or exterior, that are a result of the contractor’s activities shall be repaired. The contractor shall pay all costs of repairs. After notice to proceed and prior to the commencement of construction, the contractor and COR shall conduct joint inspections of the existing areas affected by the construction. Existing damage or defects shall be noted and will be used as the basis for determination of damages caused by the contractor's operations.
4. The Contractors’ employees may use the Cafeteria if properly badged/escorted.
C. Inspection of site by contractor - It is strongly urged that the contractor carefully examine the premises to determine the extent of work and the conditions under which it must be done.
SITE ACCESS CONSTRUCTION LIMITS 01 14 13 - 2
D. Government use and access to premises - The Government reserves the right to enter the construction area at any time for work inspection and for the operation of the facility.
E. Work hours - All work hours, shifts, and overtime work shall be coordinated with the COR. Before commencing construction, furnish to the COR a statement of hours per day and days per week to normally be worked and approximate number of persons on the job for a normal work shift.
F. Security requirements
1. Personnel List - Contractor shall provide the COR with a list of contractor personnel who require access to the ARTCC. The list shall be submitted immediately after contract award. The list shall be kept current during the project and shall include the following:
Full name, including middle initial Name of Employer Dates Anticipated On-Site Federal or State issued photo ID
2. Security Investigation and Identification - Contractor's personnel may be subject to security investigation by FAA. The contractor shall promptly complete all security forms provided by the CO.
Contractor's personnel shall report to the FAA security guard at entrance to the facility and submit proper identification when signing in to obtain an FAA badge which will be worn on an outside garment, above the waist and below the neck, facing forwards, at all times while on the ARTCC premises. This badge shall be returned daily to the security guard when leaving the premises, unless otherwise noted.
3. Vehicle Identification - Vehicle identification tags will be issued for contractor and contractor's employees' vehicles that require access into the ARTCC site. The identification tags shall be displayed in the windshield of the vehicle at all times when the vehicle is on the site. The contractor shall be responsible for the collection and return of all vehicle tags that are no longer required.
4. Escort Requirement - Contractor is responsible to provide an escort for his employees. This will required a security background investigation by the FAA. Contractor's personnel shall not violate any security regulations pertaining to the ARTCC facility. Violators may be removed from the premises with the right to reenter revocable. Contractor's day-to-day work schedules in the classified areas shall be so arranged to allow for minimum escort.
5. Right to Search - Current procedures at FAA facilities include the "right to search." If in the judgment of the FAA a cause to search a vehicle or the person of personnel exists, such search will be made.
6. Replacement of Lost Identification - The FAA will provide personnel badges and vehicle identification tags as described above. It is the contractor's responsibility to return these badges and tags daily and upon completion of the project. The contractor shall be liable to pay for any FAA badge or tag not returned or replaced at the completion of the work. The payment for lost I.D. will be $25.00 for each tag or badge not returned or replaced, except for temporary badges.
7. Physical Security - At the end of each workday, the contractor shall secure all construction areas by closing and locking all doors and gates. The contractor is responsible for the security of the staging area and shall provide the required measures at no additional expense to the government.
END OF SECTION 01 14 13
COORDINATION AND TESTING 01 14 16 - 1
SECTION 01 14 16 COORDINATION AND TESTING
A. Project Coordination - It shall be the duty of the Contractor to prepare a detailed schedule of work and work layout to resolve conflicts and to assure coordination of the work by different trades.
B. Daily Project Scope and Schedule - A detailed daily project scope and schedule must be reviewed with the FAA COR daily. Usually, the daily scope and schedule meeting is held early morning. Hot work permits, utility lockouts, and fire alarm disabling are issued daily and shall be requested at this meeting.
C. Weekly Meeting - Coordination between the COR and Contractor shall take place weekly at the site.
Ad Hoc meetings will be scheduled if requested by either the COR or Contractor. The subjects to be discussed at the progress meetings shall include, but are not limited to, the following:
1. Safety concerns/Issues
2. Progress of Work
3. Previous meeting action items/issues
4. Field problems
5. Material and Equipment delivery status
6. Submittal status/schedules
7. Three Week Look-Ahead Schedule
8. Review of changes, and potential effects on the schedule
9. Construction schedule revisions
10. Schedule Revisions
11. Other current business
The following persons will be expected to attend meetings; FAA COR, Prime Contractor Superintendent, Project Manager and Project Manager/Superintendents for other major trades.
D. Facility Coordination Meeting – Ad Hoc coordination meetings shall take place between the facility managers, COR and the Contractor’s Project Superintendent.
E. Work Affecting Operational Systems - The contractor shall coordinate all work which has any or may have any impact on any operational system within the facility through the COR in writing 10 days in advance. The contractor shall immediately cease any work that is adversely impacting the operation of the ARTCC and shall immediately repair or restore any portion of the operational system that has been damaged or suffered diminished performance as a result of the contractor's activities.
F. Local permits and Coordination - The Contractor will be responsible for obtaining and payment of all building fees, inspection fees, utility connection charges and any other fees or charges that may be incurred in the performance of this contract.
G. Applicable documents - The contractor shall comply with all local city, county, and state construction codes.
1.2 TESTING
COORDINATION AND TESTING 01 14 16 - 2
A. Contractor's responsibility - Unless otherwise indicated as the responsibility of another identified entity, Contractor shall provide certified testing and inspection agencies, inspections, tests, and other quality-control services specified elsewhere in the Contract Documents and required by authorities having jurisdiction.
1. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Contractor's responsibility, the Contractor shall employ and pay a qualified independent testing agency to perform quality-control services.
2. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Government's responsibility, the Government will employ and pay a qualified independent testing agency to perform those services.
a. Where the Government has engaged a testing agency for testing and inspecting part of the
Work, and the Contractor is also required to engage an entity for the same or related element, the Contractor shall not employ the entity engaged by the Government, unless agreed to in writing by the Government.
B. Retesting - The Contractor is responsible for retesting where results of inspections, tests, or other quality-control services prove unsatisfactory and indicate noncompliance with Contract Document requirements, regardless of whether the original test was Contractor's responsibility.
1. The cost of retesting construction, revised or replaced by the Contractor, is the Contractor's responsibility where required tests performed on original construction indicated noncompliance with Contract Document requirements.
C. Selection and payment - The contractor shall pay for all testing. The contractor shall select and use a certified and qualified testing laboratory to perform the requirements of this contract. The American Association of Laboratory Accreditation shall certify the testing laboratory.
D. Rejected materials or workmanship - All materials or workmanship or both which have been rejected by the COR by reasons of failure to conform to the requirements of the Contract Documents shall be removed and replaced with new, acceptable materials by the contractor at the contractor's own expense.
Contractor shall also pay for testing of new materials that have been installed in place of rejected materials.
1. The testing laboratory will furnish a digital copy directly to the COR covering all of its determinations and conclusions within 14 calendar days of final testing date. Reports will show all data customarily listed by the laboratory in reporting on quantities, qualities, and types of materials, together with their correlation with the project and applicable Specification Section.
END OF SECTION 01 14 16
SUBMITTALS 01 33 00 - 1
SECTION 01 33 00 SUBMITTALS
PART 1 – GENERAL
Applicable provisions of this Section and other provisions and requirements of the Contract Documents apply to all sections, except as modified in Sections of Divisions 1 through 32.
1.1 SUMMARY
Submit Shop Drawings, product data, samples, warranties, certificates, test reports and third party disposal letters as required by the contract documents.
1.2 RELATED REQUIREMENTS (NOT USED)
1.3 SUBMITTALS
Submittals required include, but are not necessarily limited to, the following:
A. Submittal Log
B. Critical Submittals
1.4 SUBMISSION REQUIREMENTS
A. Number of Copies - Submit in ample time for approval before installation. Unless otherwise noted, submit two (2) hard copies of documents to the Contracting Officer’s Representative (COR). One
(1) hard copy will be retained by the COR. In addition to the hard copies, submit a soft copy (PDF).
The time the government has to review will begin when the hard copies are received in hand. If additional copies are required, provide the quantity and submit additional copies to meet this requirement.
B. Time for Approval - Receive submittal approvals prior to starting the work. Time necessary for government approval or disapproval of samples, certificates, test reports, and shop drawings will not be more than thirty (30) calendar days after receipt of an initial submittal. Subsequent re-submittal iterations will not be more than fifteen (15) calendar days after receipt. All materials installed in the work shall match the approved submittals. After a submittal has been approved, no substitutions will be permitted without written approval by the COR. No extension of Contract Time will be authorized because of failure to transmit to the COR sufficiently in advance of the Work to permit processing.
C. Submittal Approval - The checking, marking or approval of the submittal by the FAA shall not be construed as a complete check, but will indicate only that the product or method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for compliance with the specifications or for any error which may exist. The Contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work.
Possible approval actions taken by the FAA include:
1. Approved as submitted - If "approved as submitted" is marked by the COR, each copy of the submittal will be identified as having received such approval by being stamped and dated. After submittal has been approved, no substitutions will be permitted without written approval by the
COR.
SUBMITTALS 01 33 00 - 2
2. Approved as noted - If "approved as noted" is marked by the COR, the submittal is satisfactory contingent upon Contractor acceptance of corrections, notations, or both, and if accepted, does not require resubmittal.
3. Not approved - If "not approved" is marked by the COR, the submittal data does not meet job requirements and the Contractor must resubmit. If the submittal is disapproved, the Contractor shall resubmit the corrected material in the same quantity as specified for the original submittal.
Correct disapproved submittals and resubmit for approval by the COR. Approvals of resubmittals require an additional fourteen (14) calendar days.
4. Distribution - Following response to the initial submittal, print and distribute copies to the COR, Government, subcontractors, and other parties required to comply with submittal dates indicated. When revisions are made, distribute to the same parties. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.
5. Schedule Updates - Revise the schedule after each meeting or activity where revisions have been recognized or made.
D. Submittals - Submit shop drawings, material lists, and all other data required under various headings of these specifications necessary to permit commencement of work. COR will return the submittals within 30 calendar days after receipt, indicating approval or disapproval.
E. Submittal Preparation - Place a permanent label or title block on each submittal for identification.
Indicate the name of the entity that prepared each submittal on the label or title block.
1. Transmittals - All submittals shall be accompanied by transmittal letters identifying the contents of the submittal. It shall be clearly indicated on the transmittal letter with a statement and signature of the Contractor that the submittal item was verified for compliance with the contract requirements and approved by the Contractor. Transmittal letters shall consist of one original.
2. Contents - Submittals shall be complete and detailed and assembled into sets. Lack of completeness or clarity or inadequate description will be justification for disapproval.
Submittals shall bear the following information:
a) Name of project or facility and contract number;
b) Date of submission;
c) Contract drawing number and latest revision;
d) Specification page and paragraph number;
e) Name of contractor and subcontractor or supplier/manufacturer;
f) Clearly identified contents and location of work;
g) Any proposed variances to specification requirements;
h) Contractor’s approval certifying he checked and coordinated the work of other trades.
1.5 SHOP DRAWINGS
A. Applicable Documents
B. Presentation - Present drawings in a clear and thorough manner. Identify details by reference to sheet and detail, building wing and section shown on contract drawings.
SUBMITTALS 01 33 00 - 3
1. Submit newly prepared information drawn accurately to scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not a Shop Drawing.
2. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings.
C. Contents - Provide the following information on each submittal:
1. Submittal number and clearly identify as "Part A" or "Part B" item
2. Date of submission
3. Name of project and facility (full name)
4. Name of Contractor or Subcontractor
5. Reference to drawing number (with revision, if applicable) and/or specification section.
6. Clearly identify contents and location of work.
7. Contractor's approval certifying he checked and coordinated the work of other trades.
8. Dimensions.
9. Identification of products and materials included by sheet and detail number.
10. Compliance with specified standards.
11. Notation of coordination requirements.
12. Notation of dimensions established by field measurement.
13. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop
Drawings on sheets at least 8-1/2 by 11 inches but no larger than 36 by 48 inches.
D. Submittal - Submit blue- or black-line prints for the COR's review. Submit two hard copies and a digital copy, one hard copy will be retained by the COR.
1. One of the prints returned shall be marked up and maintained as a "Record Document."
2. Do not use Shop Drawings without an appropriate final stamp indicating action taken.
1.6 PRODUCT DATA
A. If the submittal is not clearly marked, regarding the following pertinent data, the submittal will be returned marked "DISAPPROVED".
B. Collect Product Data into a single submittal for each element of construction or system. Product
Data includes printed information, such as manufacturer's installation instructions, catalog cuts, SUBMITTALS 01 33 00 - 4
Material Safety Data Sheets (MSDS), standard color charts, roughing-in diagrams and templates, standard wiring diagrams, and performance curves, for all materials brought on site.
C. Preparation
1. Clearly mark or highlight each copy to identify pertinent site specific products or models the
Contractor intends to use
2. Highlight/clearly indicate all performance characteristics and capacities
3. Highlight/clearly indicate all dimensions and clearances required
1.7 WARRANTIES/GUARANTIES
A. Assemble two (2) copies with original signatures of warranties executed by each of the respective manufacturers, suppliers, and subcontractors into a warranty book and prepare a Table of Contents.
B. Additional Data - Provide complete information for each item, include the following:
1. Product or work team
2. Firm, with name of principal, address, and telephone
3. Scope
4. Effective dates of warranty based on Final Acceptance of the item.
5. Information for owner's personnel on proper procedures to evoke the warranty in case of failure and instances which might affect the validity of warranty
C. Warranties - Effective after project completion and acceptance by the FAA.
1.8 CERTIFICATES
Assemble certificates executed by each of the respective manufacturers, suppliers, and subcontractors.
A. Additional Data - Provide complete information for each item to certify compliance with contract documents.
1. Product or work item
2. Firm, with name of principal
3. Scope of compliance
4. Signature by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.
PART 2 – MATERIAL (Not Used)
SUBMITTALS 01 33 00 - 5
PART 3 – EXECUTION
3.1 GENERAL
Submittals are required for, but not limited to, the items listed in the specifications or on the drawings. The following is a partial list of submittals required: Schedules, Manufacturer's Literature, Shop Drawings, Samples, Test Reports, Warranties, Certificates, Design Calculations, MSDS, and Installation Instructions. This list should not be construed as a complete list of all submittals required. Submittal dates shall comply with this specification unless a more stringent date is specified. Substitutions and all requested changes will require a submittal.
3.2 SCHEDULE FOR CRITICAL SUBMITTALS
A. Process after the construction contract has been awarded and prior to NTP: All Submittals are due 30 calendar days after the contract has been awarded. The construction Notice to Proceed (NTP) will not be issued until all submittals are approved.
B. No later than two weeks after the contract has been awarded, the Contractor shall be available to participate in a meeting/telecom with the Contracting Officer, Contracting Officer Representative and Office Project Engineer to discuss and coordinate the following:
1. Contractor’s FAA point of contact for submitting the Critical Submittals.
2. Discuss the submittal process and forms.
3. Discuss process and forms for request of FAA security badges.
4. Discuss the proposed date for Notice to Proceed (NTP).
C. Critical Submittals Required:
1. Section 01 11 00 – Construction Schedule
2. Section 01 35 29 – OSHA Safety Requirements
3. Section 23 81 23 – Computer Room Units
4. Section 23 09 00 – Instrumentation and Controls for HVAC
PART 4 – QUALITY ASSURANCE (Not Used)
END OF SECTION 01 33 00
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 01 35 29 - 1
SECTION 01 35 29 – HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Objectives and Responsibilities: The objectives of the safety and health requirements are to eliminate contractor generated facility shutdowns, interruptions, injuries, illnesses, and incidents. When the Contractor is notified by the Contracting Officer Representative (COR) of non-compliance with the safety or health provisions of the Contract, the Contractor shall immediately, unless otherwise instructed, correct the unsafe act or unsafe condition.
It is the contractor’s responsibility to understand the work to be performed, perform the work in a professional manner and to protect his workforce and FAA from incidents.
B. References: In addition to publications referenced in the Construction Contract Clauses, the following Code of Federal Regulations (CFR) publications designate and define hazardous materials and conditions, and establish procedures for handling these materials and conditions.
1. 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.
2. 29 CFR, Part 1926: OSHA Construction Industry Standards.
3. 40 CFR, Part 61: National Emission Standards for Hazardous Air Pollutants.
4. 40 CFR, Part 261: Environmental Protection Agency (EPA) Characteristics of
Hazardous Waste.
5. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use Prohibitions.
6. 40 CFR, Part 763: EPA Asbestos.
C. Hazardous Materials: Some hazardous and toxic materials and substances are included in 29 CFR Part 1910, subparts H and Z, and in 29 CFR Part 1926. Commonly encountered hazardous materials include but are not limited to asbestos, PCBs, explosives and radioactive material.
1. Asbestos may be found in spray-on fireproofing, insulation, pipe coverings, lath and plaster, and other materials.
2. PCBs may be contained in transformers, capacitors, voltage regulators, oil switches, mechanical insulation and other materials.
3. Lead-based paint or coatings.
D. Acquisition of Publications: Referenced CFR publications may be purchased from the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402.
1.2 COMMUNICATION
A. All contractor tasks must be communicated to FAA prior to the tasks being performed.
B. Preconstruction Safety Meeting: Prior to commencing construction, the FAA will schedule a preconstruction meeting after the Notice to Proceed. The agenda will include:
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 01 35 29 - 2
1. The FAA will identify the Contracting Officer Representative (COR) and Resident Engineer (RE). The contractor will identify his site management.
2. The FAA will review the chain of authority.
3. The FAA will review the procedure to process field decisions and change orders.
4. The FAA will review the facility safety procedures, and safety and health requirements.
5. The FAA will discuss schedules, shop drawings, product data and samples, manufacturer's certifications of products, manpower reports, equipment deliveries and priorities schedules, procedures for maintaining record documents, use of FAA facilities by contractor (access, parking, office area, and storage area), safety and first aid procedures, security procedures and housekeeping procedures.
C. Monthly Project Schedule: A detailed schedule must be submitted to FAA monthly. The date the schedule is due will be identified during the preconstruction safety meeting.
D. Two Week Look-Ahead Schedule: A detailed two week look-ahead schedule must be submitted to FAA weekly. The date the schedule is due will be identified during the preconstruction safety meeting.
E. Daily Project Scope and Schedule: A detailed daily project scope and schedule must be submitted to the FAA daily. Usually the daily scope and schedule meeting is held early morning with the FAA Resident Engineer. Hot work permits, and electrical/pneumatic/water and steam lockouts are issued daily.
F. All safety related schedules should be coordinated with the over all work scheduled required in the specifications.
1.3 COMPLIANCE WITH REGULATIONS
A. The Work, including contact with or handling of hazardous materials, disturbance or dismantling of structures containing hazardous materials, and disposal of hazardous materials, shall comply with the applicable requirements of 29 CFR Parts 1910 and 1926, and 40 CFR Parts 61, 261, 761 and 763.
1. Work involving disturbance or dismantling of asbestos or asbestos containing materials, demolition of structures containing asbestos and removal of asbestos, shall comply with 40 CFR Part 61, Subparts A and M, and 40 CFR Part 763, as applicable
2. Work shall additionally comply with applicable state and local safety and health regulations.
3. In case of a conflict between applicable regulations, the more stringent requirements shall apply.
4. The Contractor is not relieved from adhering to other OSHA requirements not listed herein. The Contractor shall consult the latest referenced OSHA documents for safety regulations.
B. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with all applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work, and shall hold the FAA harmless for any action on the Contractor's part, or that of the Contractor's employees or subcontractors, that results in illness, injury or death.
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 01 35 29 - 3
1. The Contractor shall have written safety and health programs in compliance with 29 CFR Parts 1910 and 1926.
2. The Contractor shall bear full responsibility to provide safe working conditions for its employees and Contractors. The Contractor shall not permit any employee or Subcontractor to work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to the health and safety of the employee.
3. The Contractor shall bear the responsibility of maintaining an accident prevention program such that frequent and regular inspections of the job site, materials and equipment are made by a competent person designated by the employer.
4. The Contractor shall not permit the use of any machinery, tool, material, or equipment that is not in compliance with OSHA regulations. The employer shall permit only those employees qualified by training and/or experience to operate equipment and machinery.
5. The FAA shall not be held responsible for safety inspections to assure Contractor conformance with the OSHA safety regulations. The FAA, however, reserves the right to notify the Contractor of any deficiencies regarding worker safety.
6. The FAA will evaluate the Contractor on its safety performance, including that of its Subcontractors. The number and severity of safety and security violations will be considered in this evaluation. Contractor safety violations are cause for termination for default, may result in notification of the Contractor’s bonding company, and will affect the Contractor’s opportunity to propose on future work. Failure to correct such deficiencies may impact the Contractor’s ability to work on future FAA contracts.
1.4 OCCUPATIONAL SAFETY AND HEALTH – ARTICLE 53
A. Information in this Article is required by the FAA to maintain the health and safety of their Employees at facilities during construction operations.
B. The information in this Article is taken from the Agreement between the National Air Traffic Controllers Association (NATCA), AFL/CIO and the Federal Aviation Administration Department of Transportation Agreement (known as “Agreement”) for the protection of union workers covered under the “Agreement”. “Employer” in Article 53 refers to the FAA; however, construction activities at FAA facilities, and the safety of FAA employees during the construction activities, shall be monitored by the COR. The information in this Article is required to become part of the Contractor’s written Safety and Health plan for this Project. Only those “sections” of Article 53 applicable to Contractor’s Safety Plan are included in the following paragraphs.
C. Section 1: The Employer shall abide by P.L. 91-596 and Executive Order 12196, concerning occupational safety and health, and regulations of the Assistant Secretary of Labor for occupational Safety and health and such other regulations as may be promulgated by appropriate authority.
D. Section 2: The Employer shall make every reasonable effort to provide and maintain safe and healthful working conditions. Factors to be considered include, but are not limited to, proper heating, air conditioning, ventilation, air quality, lighting and water quality.
E. Section 3 (in part): The Employer agrees to continue a national Occupational Safety and Health Committee. The committee will meet as frequently as required by the Charter of the Occupational Safety, Health and Environmental Compliance Committee (OSHE-COMM). The Union shall be entitled to designate a minimum of one representative.
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 01 35 29 - 4
F. Sections 4 through 6: (Not included – Not applicable.)
G. Section 7: Each facility shall periodically review fire evacuation procedures with all personnel and provide training in the operation of fire extinguishers and other related equipment at each facility. Fire plans shall be conspicuously displayed and reviewed with every employee.
Assistance from local fire departments may be utilized in developing evacuation plans and conducting the training required under this Section.
H. Section 8: (Not included – Not applicable.)
I. Section 9: In the event of construction or remodeling within a facility, the Employer shall insure that proper safeguards are maintained to prevent injury to bargaining unit employees.
J. Section 10: If the Employer initiates or permits the use or storage of chemicals, pesticides, or herbicides at any facility, Material Safety Data Sheets (MSDS) for each chemical, pesticide or herbicide shall be provided to the Union prior to use/storage. Any pregnant/nursing employees or personnel with medical conditions which could be aggravated by the use of the chemicals, pesticides or herbicides shall be reasonably accommodated n a manner so as to prevent exposure. All chemicals, pesticides and herbicides shall be used in accordance with applicable law and the manufacturer’s guidelines and precautions.
K. Sections 11 and 12: (Not included – Not applicable.)
L. Section 13: Indoor air quality concerns identified by the local Occupational Safety and Health Committee, including those involving “sick building syndrome” shall be investigated using the advisory standards of the America Society for Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) and EPA and OSHA guidelines. All test results shall be provided to the local Union as soon as they are available.
1.5 OCCUPATIONAL SAFETY AND HEALTH – ARTICLE 77
A. Information in this Article is required by the FAA to maintain the health and safety of their Employees at facilities during construction operations at locations where asbestos abatement is anticipated.
B. The information in this Article is taken from the Agreement between the National Air Traffic Controllers Association (NATCA), AFL/CIO and the Federal Aviation Administration Department of Transportation Agreement (known as “Agreement”) for the protection of union workers covered under the “Agreement”. “Agency” in Article 77 refers to the FAA; however, construction activities at FAA facilities, and the safety of FAA employees during the construction activities, shall be monitored by the COR. The information in this Article is required to become part of the Contractor’s written Safety and Health Plan for this Project, by reference.
C. Section 1. At intervals not greater than every nine (9) months, the Agency shall conduct an inspection of asbestos containing building materials (ACBM) and air monitoring for airborne asbestos fibers, in accordance with OSHA/EPA protocol, in all facilities known to contain friable asbestos containing materials (ACM) or non-friable ACM which is likely to become friable, whether exposed or contained internally in the construction of the facility. Upon request, the Principal Facility Representative or his/her designee shall be allowed to observe the test process and shall receive a written copy of the results. All testing shall be conducted by a
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 01 35 29 - 5
certified contractor specializing in asbestos/air quality monitoring. The Union, at its own expense, may designate an Industrial Hygienist to observe all air monitoring activities conducted by the Agency's certified contractor.
D. Section 2. In the event that a facility is planning a construction project which may cause the release of airborne asbestos fibers in areas frequented by bargaining unit…
This is the start of the file's text. The full file is on GovTribe.