FA930225Q0051 Soliciation Questions and Responses.pdf

PDF 318 KB Posted

Attached to
Office Reconfiguration and Cubicle Installation Federal contract opportunity
Solicitation number
FA930225Q0051
Issued by
Department of the Air Force Materiel Command Test Center

About this file

The document contains Solicitation Questions and Responses for an Office Reconfiguration and Cubicle Installation project (Solicitation Number FA930225Q0051) issued by the Department of the Air Force Materiel Command Test Center. The solicitation is a small business set-aside for modular furniture systems with a 90-day performance period, seeking a contractor to demolish, reconfigure, and install office cubicles at Edwards Air Force Base.

Key details include a firm fixed-price requirement, evaluation criteria prioritizing past performance over price, and a requirement for offerors to demonstrate technical capability in dismantling and assembling cubicles and demountable walls. Quotes are due by July 30, 2025, and must be submitted via email with specific contractor information, including SAM UEI, TIN number, CAGE code, and other standard business identifiers. The solicitation emphasizes technical acceptability and past performance, with offerors required to provide at least two recent work history examples from the past three years.

View the file

Other files for this federal contract opportunity

Other files attached to Office Reconfiguration and Cubicle Installation, newest first.
File Type Posted
Solicitation - FA930225Q0051.pdf PDF
Office Reconfiguration and Cubicle Installation SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Office Reconfiguration & Cubicle Installation Soliciation Questions FA9302-18-A0002

1. What is the brand of the Panel Wall system?

• The brand of the panel wall system is unknown.

2. Will all panel walls be removed, except for the one marked in red?

• Yes, and they will be utilized to form the wall in red. The wall in red is not there yet.

3. Are employees moving their personal items? Will the contractor be providing boxes?

• The employees are responsible for moving their personal items.

4. Approximate allotment(bunch) for accordion walls when they are opened?

• The industry standard allotment for the accordion wall.

5. One of the measurements is covered. Can you please share these measurements?

• The length of the long red line is 34’. The total length is 43’.

Office Reconfiguration & Cubicle Installation Soliciation Questions FA9302-18-A0002