This is a Questions and Answers document for Air Force solicitation FA930127Q0011 addressing clarifications on proposal submission requirements and contract terms.
The document clarifies five key points for offerors: (1) Past performance examples from proposed first-tier subcontractors may be submitted if directly relevant to their assigned scope of work and responsibility, with subcontractor performance integrated into the prime's overall past performance assessment, though the prime contractor bears responsibility for demonstrating relevant capabilities and must verify compliance with RFO 52.219-14 on subcontracting limitations; (2) no Covered Defense Information, non-public Government data, or Controlled Unclassified Information will be processed on contractor systems for this effort, despite DFARS 252.204-7012 being listed in the model contract; (3) the Total Quoted Amount should be entered in Box 26 of the SF 1449, despite that box being labeled "For Government Use Only"; (4) FAR clauses 52.212-3 and 52.212-5 referenced in SF 1449 Block 27a do not apply to this effort as they were removed under the Revolutionary FAR Overhaul, with all applicable clauses contained in the Model Contract; and (5) foundation design costs for the pedestal and sighting wall should be priced under SLIN 0001AB Granite Elements. The solicitation involves granite elements and architectural/structural components requiring design work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation FA930127Q0011 Q&A Page 1 of 1
Solicitation FA930127Q0011 Questions and Answers
1. Paragraph 9 of the addendum asks for up to 3 examples of past performance. May an offeror submit the past performance of a first-tier subcontractor that will perform the work, identified in the quote as the subcontractor's?
• Past performance of proposed first-tier subcontractors will be evaluated to the extent that past experience directly relates to the specific scope of work and responsibility they will undertake under this effort. Subcontractor past performance will be integrated into the overall Past Performance confidence assessment of the prime offeror based on the subcontractor's assigned role, but as the award will be between the Government and prime it is the responsibility of the prime contractor to display relevant capabilities as described in the addendum. Additionally, the prime must verify compliance with RFO 52.219-14, Limitation on Subcontracting.
2. The model contract lists DFARS 252.204-7012. Will any Covered Defense Information be furnished for the aircraft markings, plaques or replica data?
• There will be no covered defense information, non-public Government data, or CUI processed on contractor information systems for this effort.
3. The addendum says to place the Total Quoted Amount in Block #26 of the SF 1449, and that block is printed "For Government Use Only." Should offerors enter the total there?
• Totals are to be entered into box 26 of the model contract.
4. The addendum footer lists an alternate solicitation reference and the SF-1449 block 27a says FAR 52.212-3 and 52.212-5 are attached, but neither are in the posted package. Please verify whether these are applicable.
• The footer has been updated to reflect FA930127Q0011. Block 27a is auto populated in our contract writing system, clauses 52.212-3 and 52.212-5 were removed with the Revolutionary FAR Overhaul (RFO) and do not apply to this effort. All applicable clauses and provisions can be found within the Model Contract.
5. The contractor is to design the foundation beneath the pedestal and sighting wall. Which CLIN should carry that price
• SLIN 0001AB Granite Elements includes the pedestal and sighting wall requirements.