This document is a Questions and Answers (Q&A) clarification for the Plant 42 Commercial Internet Services federal contract opportunity. The solicitation involves providing managed internet and network services to twelve buildings at Air Force Plant 42 in Palmdale, California, with work governed by Los Angeles County Wage Determination 2015-5613, Revision 34.
The contract pricing structure includes CLIN 0002 for one-time installation during the base year, with recurring monthly internet and managed services reflected in option year CLINs. A 1 Gigabit symmetrical circuit with up to five static public IP addresses will flow from the Main Point of Entry (Building 510) to all buildings via government-provided fiber paths; the contractor is responsible for obtaining Authority to Operate (ATO) if not providing an approved service. All installed hardware is contractor-owned under the managed service and must be removed at contract completion or if an option year is not exercised. Individual building sub-CLINs may be independently tested, accepted, and invoiced through WAWF. The Government provides single-mode fiber (SMF) for building interconnection and LC/SC connectors; contractors must supply fiber patch cables and may need to supply a fourth aggregation switch or implement an optimal design. Configuration must follow the AFMC CISP Admin Management Guide, with the AFP 42 IT team requiring full administrative access to the firewall and wireless controller. Contractors must maintain logs for at least six months. The system must be designed for scalability and configured to be WiFi isolation-ready, MFA-ready, and capable of supporting two to twelve independent broadcast domains per building, though these features are not currently planned for immediate implementation.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Plant 42 Commercial Internet Services Questions & Answers
1. The model contract prices each building as a line item with a quantity of one (1) Each under CLINs 0001 through 4001. Please confirm whether each building line item is intended to include both the installation or equipment for that building and the recurring internet and managed service for the full period. Please also clarify where the 1 Gigabit circuit and any one-time ATO and DODIN package pricing.
• The model contract has been updated to include CLIN 0002 for the one-time installation during the base year. The option year CLINs remain accurate and reflect the recurring fully managed services necessary. The 1 Gigabit circuit has been outlined within CLINs X001AA as the circuit will flow from the MPOE Bldg. 510 to all buildings. It is the contractor’s responsibility to obtain the ATO if not providing an approved service, there will be no separate line item for this.
2. SOW paragraphs 3.1.0 and 6.1.4 describe a 1 Gigabit circuit at the main point of entry (MPOE) building and government-issued fiber paths for distribution. Please identify the MPOE building, confirm that Building 510 is the intended location if so, and confirm that government fiber paths currently reach all twelve buildings. Please also advise of the fiber type and connector type at each building (LC and/or SC connectors), if available.
• Building 510 is the Main Point of Entry. The Government provides fibers for distribution, and as part of installation, the contractor needs to provide fiber patch cables. It is confirmed the fibers reach all 12 buildings. LC and/or SC connectors are present.
3. SOW paragraph 2.9.1.0 states that floor plans and layouts are available after award.
May offerors receive building dimensions or floor plans before the quote due date so that cabling can be priced accurately?
• Floor plan may be provided upon request.
4. Please confirm that all work will be performed at Air Force Plant 42 and that Wage Determination 2015-5613, Revision 34 (Los Angeles County) governs all covered labor under this contract.
• Confirming the Place of Performance is Air Force Plant 42, Palmdale, CA. and the Wage Determination for Los Angeles County is accurate.
5. May each completed building sub-CLIN, such as 0001AA for Building 510, be independently tested, accepted, and invoiced through WAWF Invoice 2in1 before completion of all 12 buildings?
• Each individually priced sub-CLIN may be invoiced against. An amendment has been made to the Model Contract to reflect the recurring Internet services on a monthly basis. CLIN 0002 remains the all-encompassing one-time installation
CLIN.
6. Equipment ownership (SOW 2.5.0, 19.2.2.0, 23.0, 24.2.0). Is installed hardware to be contractor-owned under the managed service, or delivered as Government property? If contractor-owned, should it be removed at the end of performance?
• Equipment is contractor-owned under the managed service and is to be removed at the end of performance or option year is not exercised
7. For building 531, is the end user looking for (2) 8 Port Switches?
• Yes, because the distance for ethernet cable exceed 300 feet, thus another switch is needed on the opposite side of the hangar
8. For building 601, does this connect to B560, 553D or B510?
• B601 would be connected to B552
9. Does an existing carrier entrance (conduit or fiber) from the property line to Building
510 exist for use by a new provider, or is the offeror responsible for constructing one? Are there restrictions on aerial or underground construction at AFP 42?
• The existing carrier enters from the city property line to B510 via their own fibers and it is believed to be aerial. Offeror is responsible for leasing the service from existing carrier, if offeror is seeking to construct or install their new fibers, it is offeror responsibility to work with city, county or property owner for easement and installation.
10. Does the Government require the 1 Gigabit circuit to be dedicated and symmetrical? Are static public IP addresses required, and if so, how many?
• Symmetrical, up to 5 static public IP addresses.
11. Does the Government require separate networks for Emergency Response, Mission
Partners, distinguished visitors, and training users? Is a captive portal with acceptable-use acknowledgment, or content filtering, required for any of these groups?
• No separate network is required. All configuration is to be follow on the “AFMC CISP Admin Management Guide”
12. Will AFP 42 IT require read-only or full administrative access to the firewall and wireless controller? Is there a required log retention period, or a Government log collector to which events must be forwarded?
• AFP 42 IT team requires full administrative access as this is co-managed request.
Government has not defined any log retention at this period but all logs should keep and track for at least 6 months or follow the “AFMC CISP Admin Management Guide” if any request is stated.
13. Please provide the wireless design and acceptance criteria, including required minimum signal strength, signal-to-noise ratio, coverage percentage, minimum data rate, concurrent-user capacity, and any areas that may be excluded from coverage, such as open bays, hangars, or unoccupied areas.
• Government provide approximate AP location(s) as wireless design for reference only. Contractor may use its own wireless design tool for optimal location(s) and coverage. Acceptance criteria per Industry Standard is sufficient.
14. How many independent broadcast domains are forecasted?
• Minimum 2 and up to 12 for each building, system should be ready for easy configuration.
15. Do any buildings need independent WiFi isolation?
• No plan for now, but the system should be WIFI isolation ready.
16. How much WiFi traffic is estimated to use IPVPN connectivity?
• No plan for now, but the system should be easily configured for traffic optimization
17. Is multi-factor authorization expected for all users?
• MFA is not planned at this time, but the system should be MFA ready.
18. What is the distance between the buildings?
• All buildings are separated by over 300 feet; government will provide the fibers for interconnection.
19. Does the Government expect to increase the 1Gbps Internet circuit in the future?
• Government has no plan for circuit that exceed 1Gbps at this time, contractor should design the system for scalability.
20. With three of the buildings having Aggregation switches, which of the other buildings will they support? What is the fiber type (MMF or SMF)?
• Government will provide SMF for all building interconnection, see attached “25-010 Comm
WIFI Floor Plan layout 11-6-26”, contractor may need to supply 4th aggregation switch. or a optimal design can eliminate the switch.
21. Is it accurate that Bldg. 510 will not need a PoE switch?
• B510 needs 1 AP, any design capable of powering up that AP is acceptable