Attachment 1 SOO - Service Air System Revitalization.pdf

PDF 239 KB Posted

Attached to
Service Air System Revitalization
Solicitation number
FA9101_Service_Air_System_Revitalization
Issued by

About this file

This is a Statement of Objectives (SOO) for the Service Air System Revitalization project at Arnold Engineering Development Complex (AEDC), Arnold Air Force Base, Tennessee, issued October 27, 2026, under SOO No. 17416-26-001.

The project requires engineering, design, procurement, installation, integration, refurbishment, and commissioning of compressed air and dry air infrastructure across three facility locations: Buildings 541, 913, and 878. The scope includes replacing eleven obsolete Ingersoll-Rand (IR) HPE300-2S rotary-screw air compressors with modern IR RS220IE units (seven water-cooled and four air-cooled), replacing one centrifugal compressor (1CV14M2) with a water-cooled RS220IE, relocating and reinstalling one existing RS220ie compressor, replacing one desiccant dryer (EHD1000-FGH) with an 1800 SCFM capacity unit, refurbishing six existing IR HB4000 desiccant dryers, and upgrading electrical, piping, and condensate management infrastructure. Five primary objectives guide performance: deliver modernized and reliable air generation capacity meeting baseline specifications and Form, Fit, and Function compatibility with existing spatial footprints; optimize air quality and dryness capabilities through dryer replacement and revitalization; ensure seamless integration with base utility infrastructure without system degradation; minimize operational downtime through coordinated scheduling; and execute high-quality, compliant, and safe performance under zero-accident protocols. Critical constraints require coordination with AEDC Point of Contact, submission of utility outage requests four weeks in advance, OEM factory-trained and certified personnel for Ingersoll-Rand systems, maintenance of continuous air supply during installation using contractor-provided temporary systems, adherence to AEDC Safety, Health, and Environmental standards, and compliance with NFPA, API, OSHA, UFC, and SSPC codes. Key deliverables include comprehensive system design drawings, Operation and Maintenance manuals, Rigging and Heavy-Lift plans, technician OEM certifications, and commissioning test reports with dew point verification, all due prior to mobilization and system acceptance. All decommissioned equipment must be removed from base property within ten working days following commissioning.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

17416-26-001 SOO No: 17416-26-001 27 October 2026

NOT SENSITIVE

IRA-26-2125

STATEMENT OF OBJECTIVES (SOO)

FOR

SERVICE AIR SYSTEM REVITALIZATION

1.0 PURPOSE

The purpose of this project is to revitalize a Service Air System at the Arnold Engineering Development Complex (AEDC), located at Arnold Air Force Base, Tennessee. The current service air infrastructure has experienced reduced reliability and capacity due to aging equipment. The goal of this revitalization is to deliver a fully operational, safe, energy-efficient, and modernized compressed air and dry air network. This will be achieved through the engineering, design, procurement, installation, and commissioning of new Ingersoll-Rand (IR) compressed air equipment, alongside the refurbishment and integration of existing system components.

2.0 SCOPE

The scope of this initiative encompasses the engineering, system design, procurement, delivery, installation, integration, refurbishment, and commissioning of new and existing service air assets across three primary facility locations:

• Building 541

• Building 913

• Building 878 This program entails replacing eleven (11) obsolete IR air compressors, replacing one (1) IR desiccant dryer, relocating and reinstalling an existing compressor, refurbishing six (6) existing IR desiccant dryers, and upgrading associated electrical, piping, and condensate management infrastructure.

3.0 BACKGROUND

The Service Air System provides essential compressed air capacity to support facility operations.

To maintain this system, several key replacements and system refurbishments are required:

• Building 913: Six (6) rotary-screw air compressors require replacement.

• Building 878: Four (4) rotary-screw air compressors require replacement. One (1) rotary-screw compressor was replaced in 2020; it is in good working order but must be relocated and integrated into the new facility layout.

• Building 541: One (1) obsolete centrifugal air compressor (CENTAC) and one (1) associated desiccant dryer require replacement.

• Dryer Revitalization: Six (6) existing Ingersoll-Rand (IR) HB4000 desiccant dryers located in Buildings 913 and 878 require complete refurbishment to restore them to full moisture-removal capacity.

The critical assets involved in this program are outlined below:

Current Model Number

Current Serial Number

Location Project Action Required

HPE300-2S EE2816U08074 Bldg. 913 Replace with Water-cooled

RS220IE

HPE300-2S EE2817U08084 Bldg. 913 Replace with Water-cooled

RS220IE

HPE300-2S EE3262U11101 Bldg. 913 Replace with Water-cooled

RS220IE

HPE300-2S EE3261U11101 Bldg. 913 Replace with Water-cooled

RS220IE

HPE300-2S EE3260U11098 Bldg. 913 Replace with Air-cooled RS220IE HPE300-2S EE3263U11102 Bldg. 913 Replace with Air-cooled RS220IE HPE300-2S EE3033U09107 Bldg. 878 Replace with Air-cooled RS220IE HPE300-2S EE3032U09106 Bldg. 878 Replace with Air-cooled RS220IE

RS220ie MOX1002634 Bldg. 878 Relocate and Reinstall (Keep Unit) HPE300-2S EE3030U09104 Bldg. 878 Replace with Water-cooled

RS220IE

HPE300-2S EE3031U09106 Bldg. 878 Replace with Water-cooled

RS220IE

HB4000 301050 Bldg. 913 Refurbish to Full Capacity HB4000 504074 Bldg. 913 Refurbish to Full Capacity HB4000 504075 Bldg. 913 Refurbish to Full Capacity HB4000 319459 Bldg. 878 Refurbish to Full Capacity HB4000 319461 Bldg. 878 Refurbish to Full Capacity HB4000 301050 Bldg. 878 Refurbish to Full Capacity

1CV14M2

(Centrifugal)

M97-9566 Bldg. 541 Replace with Water-cooled

RS220IE

EHD1000-FGH 97DEHD2095 Bldg. 541 Replace with 1800SCFM Desiccant Dryer

Various (PS-

1125 / PSG-60)

Various Bldg.

913/878/541

Integrate and Revitalize Condensate Systems

4.0 PROGRAM GOALS AND PERFORMANCE OBJECTIVES

The government's primary goals are to achieve a highly reliable service air footprint, minimize operational downtime during installation, and optimize the total cost of ownership. The contractor shall propose a technical approach to meet the following objectives:

Objective 1: Deliver Modernized and Reliable Air Generation Capacity

• Establish Baseline Capacity: Replace compressors with modern, highly efficient IR equivalents that restore nominal base compressed air capabilities. The proposed configuration should meet or exceed the following footprint specifications:

• Water-cooled Compressors (7 Units): Replacing Compressors 1-4 in Bldg. 913;

Compressors 10-11 in Bldg. 878; and the Centrifugal Compressor in Bldg. 541.

• Air-cooled Compressors (4 Units): Replacing Compressors 5-6 in Bldg. 913 and Compressors 7-8 in Bldg. 878.

• Asset Reuse Optimization: Successfully relocate, reinstall, and integrate the newly inherited compressor (S/N: MOX1002634) within the updated layout of Bldg. 878, ensuring its performance is optimized alongside the new installations.

• Form, Fit, and Function (FFF) Compatibility: The proposed replacement IR compressors, desiccant dryers, and auxiliary skid components shall match or fit within the existing spatial, structural, mechanical, and electrical footprints of Buildings 541, 878, and 913. The contractor's solution shall minimize structural or architectural facility modifications, utilizing existing equipment pads, access ways, and utility penetration points wherever technically viable.

Objective 2: Optimize Air Quality and Dryness Capabilities

• Dryer Replacement: Implement a highly reliable desiccant air drying system in Bldg. 541 capable of handling at least an 1800 SCFM flow rate to ensure downstream air meets dewpoint standards.

• Desiccant Dryer Revitalization: Fully refurbish all six (6) existing HB4000 desiccant dryers (3 in Bldg. 913 and 3 in Bldg. 878) to restore them to original equipment manufacturer (OEM) operational efficiency and capacity.

Objective 3: Seamless Integration with Base Infrastructure

• Utility Interconnections: Connect new and refurbished equipment to existing facilities' utility loops (including air discharge lines, cooling water systems, and electrical feeds) without causing structural or system degradation.

• Condensate Management Upgrade: Overhaul and integrate the condensate collection systems (including traps, pumps, and filter elements) to handle the condensate generated by the new operational capacity safely and in compliance with base drainage guidelines.

Objective 4: Minimize Operational Downtime and Disruptions

• Outage Minimization: Plan, schedule, and execute all work in a manner that prevents unscheduled outages. Any required utilities shutdowns must be tightly coordinated and approved.

• Continuity of Operations: Coordinate all activities with the AEDC Point of Contact (POC) to ensure zero impact on AEDC’s mission.

Objective 5: Execute High-Quality, Compliant, and Safe Performance

• Safety Adherence: Ensure all on-site work is executed under zero-accident protocols, strictly following Lockout/Tagout (LOTO), electrical safety, hoisting/rigging, and base environmental parameters.

• Quality Assurance & Material Integrity: Provide only brand-new, commercial-grade parts and systems that guarantee high reliability. Secure robust warranties for labor and materials to protect the government's long-term investment.

• Demolition and Disposal: Safely remove, demilitarize (if applicable), and dispose of all replaced, obsolete equipment from AEDC property swiftly upon commissioning.

5.0 OPERATING AND TECHNICAL CONSTRAINTS

The contractor's proposed solution must adhere to the following critical constraints and guidelines:

5.1 Coordination & Operational Constraints

• AEDC Test Schedules: All work must be scheduled in coordination with the AEDC POC to prevent interference with critical operations.

• Utility Outage Authorizations: Unilateral utility interruptions are strictly prohibited. The contractor must submit formal written requests for any proposed utility outage at least four (4) weeks prior to the desired outage date. Outages are subject to facility availability and may be restricted to weekends or holidays.

• Base Support (LOTO): AEDC will provide support for Lockout/Tagout (LOTO) and related disconnects. The contractor must coordinate and request this support with a minimum of two

(2) weeks' advance notice.

• Continuity of Air Supply: The contractor is responsible for proposing work sequences that maintain required service air to the facility. Temporary compressed air systems needed to sustain operations during installation are the responsibility of the contractor.

• Personnel Qualifications & OEM Standards: Field technicians, mechanics, electricians, and commissioning engineers performing work on compressor and dryer equipment shall be certified, factory-trained, and experienced in servicing Ingersoll-Rand compressed air systems.

The contractor shall ensure all lead commissioning personnel hold active certifications from the respective equipment Original Equipment Manufacturer (OEM), Ingersoll-Rand.

• Hoisting, Rigging, and Equipment Transport: The contractor shall furnish all certified crane equipment, rigging apparatus, heavy transport vehicles, and licensed operators necessary to remove legacy equipment and set new machinery in mechanical bays. All heavy rigging operations shall strictly adhere to AEDC Safety Standard D5 (Hoisting Devices) and applicable OSHA regulations.

5.2 Regulatory and Safety Compliance

The contractor must comply with all federal, state, local, and military base regulations. Applicable guidelines include:

Government Policies and Standards:

Environmental Policy: https://media.defense.gov/2026/Aug/17/2003982724/-1/-

1/1/ENVIRONMENTAL%20COMMITMENT%20MEMO.PDF

AEDC Safety, Health, and Environmental (SHE) Standards: Available at the BNH Joint Venture

Supplier Portal, specifically:

• A6: User and Contractor Safety

• B1: Master Work Permit

• B2: Lockout/Tagout (LOTO)

• B3: Control of Hazardous Areas Using Safety Signs, Tags, and Barricades https://media.defense.gov/2026/Aug/17/2003982724/-1/-1/1/ENVIRONMENTAL%20COMMITMENT%20MEMO.PDF https://media.defense.gov/2026/Aug/17/2003982724/-1/-1/1/ENVIRONMENTAL%20COMMITMENT%20MEMO.PDF https://bnh-jv.com/supplier-portal/ https://bnh-jv.com/supplier-portal/

• B6: Low Voltage Electrical Safety Related Work

• D5: Hoisting Devices

• F2: Personal Protective Equipment (PPE)

Unified Facilities Criteria (UFC):

• UFC 3-420-02: Compressed Air

Non-Government Codes and Standards:

National Fire Protection Association (NFPA):

• NFPA 70: National Electrical Code (NEC)

• NFPA 70E: Electrical Safety in the Workforce

American Petroleum Institute (API):

• API 672: Packaged, Integrally Geared Centrifugal Air Compressors for Petroleum, Chemical, and Gas Industry Services

• API 614: Lubrication, Shaft-sealing and Oil-control systems and Auxiliaries

Occupational Safety and Health Administration (OSHA):

• OSHA 1926.803: Compressed Air

Society for Protective Coatings (SSPC): Industry standards for painting and anti-corrosive coating of newly installed black iron piping systems.

6.0 PLACE OF PERFORMANCE

• Place of Performance: Arnold Engineering Development Complex (AEDC), Arnold Air

Force Base, TN 37389. Specifically within Buildings 541, 913, and 878.

• Equipment Demobilization Constraint: All decommissioned, obsolete equipment must be fully processed and transported off-base within ten (10) working days following the formal commissioning and acceptance of the corresponding new system.

7.0 KEY DELIVERABLES & SUBMITTALS

To ensure proper oversight, safety, and training, the contractor's proposal shall account for the following programmatic submittals:

1. System Design & Drawings: Comprehensive engineering layouts and electrical schematic drawings for all three locations, submitted for approval prior to the start of physical installation.

2. Operation and Maintenance (O&M) Manuals: Complete, bound technical documentation for all newly installed systems (including assembly drawings, wiring diagrams, step-by-step operating manuals, maintenance parameters, and spare parts lists) delivered concurrently with equipment arrival.

3. Rigging, Heavy-Lift, and Demolition Plan: Prior to equipment extraction or mobilization of cranes and hoisting gear, the contractor shall submit a comprehensive Rigging and Lift Plan to AEDC for formal engineering and safety review. The plan shall detail crane load charts, rigging apparatus inspection certifications, equipment transit routes through AEDC facilities, structural floor-loading verifications, overhead interference mitigations, and safety exclusion zones.

4. Technician & Lead Commissioning Personnel OEM Certifications: Prior to mobilization or the commencement of any physical work on site, the contractor shall submit formal documentation verifying that all lead mechanical, electrical, and commissioning field technicians are factory-trained and actively certified by the relevant equipment OEM for the specified systems. Site mobilization and installation activities shall not commence until technician qualifications have been reviewed and accepted by the AEDC Point of Contact

(POC).

5. Commissioning & Baseline Performance Test Reports: Formal functional test reports and dew point verification data demonstrating that the installed systems meet all flow, pressure, air quality, and operational parameters prior to final Government acceptance.

END OF DOCUMENT

STATEMENT OF OBJECTIVES (SOO)
FOR
SERVICE AIR SYSTEM REVITALIZATION
1.0 PURPOSE
2.0 SCOPE
3.0 BACKGROUND
4.0 PROGRAM GOALS AND PERFORMANCE OBJECTIVES
Objective 1: Deliver Modernized and Reliable Air Generation Capacity
Objective 2: Optimize Air Quality and Dryness Capabilities
Objective 3: Seamless Integration with Base Infrastructure
Objective 4: Minimize Operational Downtime and Disruptions
Objective 5: Execute High-Quality, Compliant, and Safe Performance
5.0 OPERATING AND TECHNICAL CONSTRAINTS
5.1 Coordination & Operational Constraints
5.2 Regulatory and Safety Compliance
Government Policies and Standards:
Non-Government Codes and Standards:
6.0 PLACE OF PERFORMANCE
7.0 KEY DELIVERABLES & SUBMITTALS

File details come from the government source that posted it. Updated .