DRAFT Technical Requirement.pdf
PDF 845 KB Posted
- Attached to
- Limitorques Valve Actuators Sources Sought
- Solicitation number
- FA910126Limitorques
About this file
This Statement of Work (SOW) details the replacement of two torque limiting valve actuators for 60" gate valves at Tunnel 9 within the Arnold Engineering Development Complex. The specific requirement is for two Limitorque SMB-2-60/4P-INT-3/60/460VAC drives to replace existing actuators with serial numbers 123581 and 123582. The new actuators must include an integral reversing starter, 440V heater, double pole torque switch, and a special ratio stem nut threaded to fit the valve stem.
The vendor must supply inspection and test reports, manufacturer drawings, and O&M manuals for each actuator. The parts are to be factory lubricated with NLGI Grade 0 calcium sulfonate base grease, with an additional 5-gallon pail of matching grease to be provided. Delivery is required within 50 weeks after receipt of order (ARO), with all parts to be shipped to the Arnold Engineering Development Complex - White Oak Site in Silver Spring, MD. The actuators must match the specifications of the existing V34 and V35 Limitorque drives, including specific motor characteristics and valve specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOURCES SOUGHT NOTICE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
Distribution A.
Approved for Public Release. Distribution is unlimited.
IRA-25-1176
Thursday, December 18, 2025
STATEMENT OF WORK
FOR
V34/V35 Torque Limiting Valve Actuator Replacements
ARNOLD ENGINEERING DEVELOPMENT COMPLEX
ARNOLD AIR FORCE BASE, TN 37389-9998
ARNOLD ENGINEERING DEVELOPMENT COMPLEX – WHITE OAK SITE
FEDERAL RESEARCH CENTER AT WHITE OAK
10905 NEW HAMPSHIRE AVE
SILVER SPRING, MD 20903-1050
Approved for Public Release. Distribution is unlimited.
IRA-25-1176
Table of Contents-1
Table of Contents
1. SCOPE
2. Applicable Documents
3. DELIVERABLES
4. REQUIREMENTS
5. PERIOD OF PERFORMANCE
Appendix A – Submittal Procedure
IRA-25-1176
1. SCOPE
1.1. The scope of this effort is to provide new torque limiting valve actuators for 60” gate valves in use at Tunnel 9. Newly supplied drives shall be drop-in replacements for the existing limitorque drives on site S/N 123581, ad S/N 123582. The fabricator shall supply an inspection and test report for each actuator. The fabricator shall supply a set of manufacturer drawings and O&M manual for each actuator.
Table 1. Required Parts
Item # Part Number Description Quantity
1 SMB-2-60/4P-INT-3/60/460VAC
Supply Replacements parts for O/N 349153A and S/N’s 123581, 123582
Supplied equipment shall have: Integral Reversing Starter, 440V heater, Double
Pole Torque Switch, Special Ratio Stem Nut Threaded to Fit Valve Stem.
2. APPLICABLE FILES
2.1. V34/V35 DRAWINGS.PDF
2.2. EXISTING ACTUATORS PICTURES.PDF
3. DELIVERABLES
3.1. All parts as required per this SOW.
3.2. Inspection and test reports for all parts.
3.3. Drawings and O&M Manual for all parts
4. REQUIREMENTS
4.1. Submittals: The Contractor shall submit all documentation in accordance with Appendix A – Submittal Procedure.
4.2. Vendor shall supply QTY 2 Limitorque drives per SMB-2-60/4P-INT- 3/60/460VAC as described in Table 1. Required Parts.
IRA-25-1176
4.3. Limitorque actuators shall be a drop-in replacement for actuators originally supplied per O/N 349153A, as S/N’s 123581, 123582. The name plates for Motor and actuators of the existing equipment are shown below.
Table 2. V35 Limitorqe Nameplates
V35 Limitorque
Type SMB
Size 2
Order 349153A
Serial 123582
Valve 60” 034059
V35 Motor
SN B9096067-010002
Start Torque 60 ft-lb
Run Torque 12 ft-lb
RPM 1720
V34 Motor 230/460
Phase 3
HZ 60
Table 3. V34 Limitorque Nameplates
V34 Limitorque
Type SMB
Size 2
Order 349153A
Serial 123581
Valve 60" 034059
V34 Motor
SN 940-03644
Start Torque 60 ft-lb
Run Torque 12 ft-lb
RPM 1720
V34 Motor 230/460
HZ 60
4.4. Limitorques shall include:
IRA-25-1176
4.4.1. Integral reversing starter
4.4.2. 440V Heater
4.4.3. Double pole Torque Switch
4.4.4. Special ratio stem nut threaded to fit valve stem.
4.5. The existing valve stem dimensions shall be verified at the Tunnel 9 site by the vendor prior to threading the stem nuts.
4.6. Valve actuator shall be supplied with OEM motor for the drive unit.
4.7. Vendor shall supply the actuators factory lubricated with appropriate NLGI Grade 0 calcium sulfonate base grease.
4.7.1. Vendor shall supply an additional 5-gal pail of grease matching what was installed in the factory.
4.8. Upon completion, all parts will be shipped to ATTN: Jake Johnson Arnold
Engineering Development Complex, Federal Research Center at White Oak, 10905 New Hampshire Ave, Silver Spring, MD 20903-1050.
4.9. Parts shall be packed prepared for long term storage.
4.10. Parts shall be packed to avoid damage during shipping.
5. PERIOD OF PERFORMANCE
5.1. The fabricator shall deliver the finished parts no later than 50 weeks ARO.
IRA-25-1176
APPENDIX A
SUBMITTAL PROCEDURE
PART 1 GENERAL
1.1 DESCRIPTION OF REQUIREMENTS. This section specifies procedural requirements for non-administrative submittals, including but not limited to shop drawings, product data, manufacturer’s certificate, design data, calculations, and verifications, manufacturer’s instructions, manufacturer’s field service reports, samples, operation and maintenance manuals, and other miscellaneous work-related submittals. These submittals are required to amplify, expand, and coordinate other information contained in the contract.
Non-work-related submittals are addressed elsewhere in the contract rather than in the specification and may include items such as: contract progress schedule, permits, payment applications, performance and payment bonds, insurance certificates, and progress reports.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections of the specification or statement of work.
1.2 SUBMITTAL PROCEDURE
A. Definition: For the purposes of this section, the term “Contractor” denotes the prime contractor.
B. Listing: The statement of work contains a summarized listing of item submittals requiring approval for the work. The listing is included for the convenience of users of the contract documents. The listing may not be all inclusive and additional item submittals may be required.
C. Risk: Do not proceed with the part of the work covered by an item submittal including purchasing, fabricating, and delivering until approval is received.
Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. Any fabrication or other work performed in advance of the receipt of accepted item submittals and approvals shall be entirely at the Contractor’s risk and expense.
D. Transmittal Timing: Coordinate the preparation and processing of item submittals with the performance of the work. Prepare and transmit each item submittal to the Contracting Officer sufficiently in advance of the performance of related work and other applicable activities. Transmit related item submittals for the same unit of work so that processing will not
IRA-25-1176
be delayed by the Government's need to review submittals concurrently for coordination. No delay damages or time extensions will be allowed for time lost in late submittals.
E. Content: Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Complete AF Form 3000 and attach as cover sheet for each submittal. Contractor may include multiple item numbers on an AF Form 3000.
F. Language: All item submittals shall be written in English, including documents, notes on drawings, sketches, and/or samples, calculations, manuals, and all other instances of written text and communication.
G. Units: All item submittals shall be marked or show dimensions and values in the same units as specified in the contract documents.
H. Review Time: Allow sufficient time so that contract performance will not be delayed as a result of the time required to properly process submittals, including time for re-submittals, if necessary. Allow 10 working days for initial Government processing of each submittal. No extension of time will be authorized because of the Contractor's failure to transmit submittals to the Government sufficiently in advance of the work.
I. Contractor Certification: All submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Government. Each submittal shall be dated, signed, and certified by the Contractor as being correct and in strict conformance with the contract documents. No consideration for review by the Government of any Contractor’s submittal will be made for any items which have not been so certified by the Contractor. All noncertified submittals will be returned to the Contractor without action taken by the Government, and any delays caused thereby shall be the total responsibility of the Contractor.
J. Deviations: Should any item submittals required by the contract documents show deviations from the contract requirement, the Contractor shall make specific mention of such deviations in the letter of transmittal, including stating cost effects, and product and system limitations which may adversely affect the work, in order that if acceptable, suitable action may be taken for proper adjustment of the contract; otherwise the Contractor will not be relieved of the responsibility for executing the work in accordance with the contract documents and the approved submittals. Contractor shall clearly mark the proposed variation in all documentation and specifically point out deviations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. Deviations
IRA-25-1176
from contract requirements require Government approval and will only be considered when advantageous to the Government. When proposing deviations, deliver written request to the Contracting Officer, with documentation of the nature and features of the deviation and why the deviation is desirable and beneficial to the Government. If lower cost is a benefit, include an estimate of the cost savings. In addition to documentation required for deviation, include the submittal information required for the item. Allow an additional 10 working days beyond normal submittal review period for consideration by the Government of submittals with deviations.
K. Approved Submittals: The part of the work covered by the approved item submittal may proceed provided it complies with the requirements of the contract documents. Final acceptance will depend upon that compliance.
The term “Approved” shall only indicate that there is no exception taken to the submittal. Approval of the item submittal shall not be construed as a complete check, and indicates only that the general method or other information appears to meet the contract requirements. Approval does not relieve the Contractor of the responsibility for any error which may exist.
After item submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment, or changes to any other information will be considered unless accompanied by an explanation of why a substitution or change is necessary.
L. Disapproved Submittals: Contractor shall correct disapproved item submittals and resubmit for approval within timeframe noted. If no date is given, Contractor shall submit corrected submittal within 10 working days.
If the Contractor considers any correction or notation on the returned submittal to constitute a change to the contract drawings, specification, or statement of work the Contractor shall notify the Contracting Officer.
M. Responsibility: The Government’s review of Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions and conformance to the specifications. The Contractor shall assume all responsibility and risk for any mistakes and/or costs due to any errors in submittals.
N. Inconsistencies: If a conflict or inconsistency arises between an approved item submittal and the contract documents, the contract documents shall govern.
1.3 SPECIFIC SUBMITTAL DESCRIPTIONS AND REQUIREMENTS: Submittal requirements for individual units of work are specified in the Statement of Work (SOW). Except as otherwise indicated in the SOW, comply with the following requirements for each type of submittal.
IRA-25-1176
A. Shop Drawings: These are technical drawings and data specially prepared for this contract including fabrication and installation drawings, setting and seaming diagrams, and coordination drawings (for use on-site). Shop drawings include drawings, diagrams and schedules specifically prepared to illustrate some portion of the work, diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project, or drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated. Information required on shop drawings includes dimensions, identification of specific products and materials which are included in the work, compliance with specified standards, and notations of coordination requirements with other work.
Provide special notations of dimensions that have been established by field measurements. Highlight, encircle, or otherwise indicate deviations from the contract documents on the shop drawings. Furnish one hard copy and one electronic copy.
B. Product Data: This data includes standard printed information on manufactured products that has not been specially prepared for this contract, including manufacturers' product specifications illustrating size, physical appearance and other characteristics of materials, installation instructions, standard color charts, catalog cuts, illustrations, schedules, standard wiring diagrams, standard product operating and maintenance manuals, and samples of warranty language when the contract requires extended product warranties. General information required specifically as product data includes manufacturers' standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, the application of their labels and seals (if any), special notation of dimensions which have been verified by way of field measurement, and special coordination requirements for interfacing the material, product, or system with other work. Furnish three hard copies and one electronic copy.
C. Design Data: Design data includes design calculations, mix designs, analyses or other data pertaining to a part of work. Refer to statement of work for required quantities, formats, and signatures or certifications required. Furnish three hard copies and one electronic copy.
D. Test Reports: These include reports signed by an authorized official of a testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with the specified requirements. Testing shall have been within three years of date of contract award for the project. Reports also include findings of tests required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to the job site, findings
IRA-25-1176
of tests made at the job site or on a sample taken from the job site, investigation reports, daily logs and checklists, and final acceptance test and operational test procedures. Furnish three hard copies and one electronic copy of each such report required.
E. Certificates: These include statements printed on the manufacturer’s letterhead and signed by the responsible officials of the manufacturer of a product, system or material attesting that the product, system or material meets specification requirements. Certificates include documentation required of the Contractor, or of a manufacturer, supplier, installer or subcontractor through the Contractor, to further demonstrate the quality of orderly progressions of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications. Certificates shall be dated after award of the project contract and clearly name the project.
Furnish three hard copies and one electronic copy of each certificate required.
F. Manufacturer’s Instructions: Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
Furnish three hard copies and one electronic copy.
G. Operation and Maintenance Data: Data furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer’s help and product line documentation necessary to maintain and install the equipment, and needed by operating and maintenance personnel for the safe and efficient operation, maintenance, and repair of the item. The data is intended to be incorporated in an operations and maintenance manual or control system. Furnish two hard copies and one electronic copy.
H. Miscellaneous Submittals: These are work-related, non-administrative submittals that do not fit in the previous categories, including the following:
1. Maintenance agreements. Furnish one hard copy and one electronic copy.
2. Maintenance tools, spare parts, and overrun or maintenance stock.
Refer to SOW for required quantities of spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted.
3. Qualification certificates. Furnish one hard copy and one electronic copy.
4. Warranties.
END OF SOW
File details come from the government source that posted it. Updated .