FA9101-23-Q-0001 Questions and Answers.pdf

PDF 166 KB Posted

Attached to
Concrete Target Demolition and Disposal Services Federal contract opportunity
Solicitation number
FA9101-23-Q-0001
Issued by
Department of the Air Force Materiel Command Test Center

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

28 Nov 2022

MEMORANDUM TO WHOM IT MAY CONCERN

SUBJECT: Concrete Target Demolition and Disposal Services (FA9101-23-Q-0001), Questions and Answers

1. Section 1.6.2 Scheduling states the complete demolition and disposal requirements within a specific timeframe, seen as the following:

• Urgent Volume, 0 – 4,000 cubic feet: Complete destruction and removal of targets no later than (NLT) seven (7) calendar days after receipt of the task order. Performance shall begin NLT three (3) calendar days after receipt of the task order.

• Urgent Volume, 4,001 – 8,000 cubic feet: Complete destruction and removal of targets NLT 14 calendar days after receipt of the task order. Performance shall begin NLT three

(3) calendar days after receipt of the task order.

• Urgent Volume, 8,001 – 12,000 cubic feet: Complete destruction and removal of targets NLT 21 calendar days after receipt of the task order. Performance shall begin NLT three (3) calendar days after receipt of the task order.

• Routine Volume, 0 – 12,000 cubic feet: Complete destruction and removal of targets NLT 30 calendar days after receipt of the task order. Performance shall begin NLT seven (7) calendar days after receipt of the task order.

• Routine Volume, 12,001 – 24,000 cubic feet: Complete destruction and removal of targets NLT 45 calendar days after receipt of the task order. Performance shall begin NLT seven (7) calendar days after receipt of the task order.

• Routine Volume, 24,001 – 48,000 cubic feet: Complete destruction and removal of targets NLT 60 calendar days after receipt of the task order. Performance shall begin NLT seven (7) calendar days after receipt of the task order.

• Evacuate equipment to a disclosed location within seven (7) calendar days of notification in cases of HHSTT operations requiring removal for testing purposes.

Will there be a form that can be filled out for a time extension? What are the penalties if the contractor doesn't complete the demolition and disposal requirements within the specified timeframe?

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS AIR FORCE TEST CENTER

(AFMC)

a. There are no time extension forms nor listed penalties for exceeding the timeframes, however, repeated instances of the contractor failing to adhere to the timeframes in the contract will negatively impact CPARS ratings and performance indicators for future contracts.

2. Does the work area need to be fenced off?

a. No.

3. Can equipment be left on site during target demolition?

a. Yes, for the duration of the specific delivery order. The vendor assumes all liability for the equipment.

4. What material needs to be removed after demolition?

a. See the Performance Work Statement (PWS) section 1.6.

5. Is there an incumbent? If so, are they eligible to re-compete for this solicitation? Do you know if they plan to re-compete?

a. The previous contract expired in October 2021 and the incumbent is eligible to compete in this solicitation, but we do not know if they intend to do so.

6. Is the site visit mandatory?

a. No.