Attachment_L-6_CLIN_Milestone_Schedule_Guidance_22Jan2014.pdf
PDF 158 KB Posted
- Attached to
- AFICA Performance-Based Remediation at the Joint Base Cape Cod, MA Federal contract opportunity
- Solicitation number
- FA8903-14-R-0001
About this file
Attachment L-6 CLIN Milestone Schedule Guidance
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8903-14-R-0001
Attachment L-6
22 January 2014
Supplemental Instructions to Offerors for the Development of Contract Line Item Number (CLIN) Structures/
Milestone Payment Schedules (MPS)/Integrated Master Schedules (IMS)
This guidance is being provided to communicate Air Force expectations for the development of CLIN/Sub-CLIN Structures and the correlation with the subsequent development of the MPS and the IMS. This guidance is not intended to remove Contractor flexibility. The examples provided are for illustration purposes only and are not intended to be inclusive of all acceptable approaches.
When annual Congressional appropriations provide the basis for sourcing these contracts, special consideration must be given to ensure compliance with funding rules concerning period of availability, bona fide need and purpose as they relate to each year of funding applied. This will ensure milestones are developed that support fiscally responsible use of funds. To ensure compliance when establishing milestones, any contingent events that affect the beginning date of any milestone must be considered.
Key to proper use of funds in this context is non-severability. A non-severable deliverable is defined as a deliverable item that represents a single end product or undertaking, entire in its nature, which cannot be feasibly subdivided into discrete elements or phases without losing its identity. Milestones must have a clear delineation of final deliverables, as distinct non-severable options to be fully funded in the fiscal year in which the award of the Sub-CLIN is made, even though the performance may extend into future fiscal years. There is no administrative reservation of funds whatsoever until a determination is made to exercise a separate and non-severable Sub-CLIN. Each non-severable Sub-CLIN will be funded in its entirety with funds current at the time the Sub-CLIN is exercised, and any need for prior year funds in the future will be clearly tied back to the specific non-severable Sub-CLIN and associated well defined requirement(s) and associated deliverable(s).
CLIN AND SUB-CLIN STRUCTURE:
CLINs are identified in the contract. A CLIN should be done for each site and one for the Project Management Plan. Sub-CLINs provide a means for funding economically or programmatically viable stages by identifying the items or activities to be acquired as non-severable contract deliverables (performance objectives). The performance period for the Sub-CLIN may be for more than one, but not more than five fiscal years. Sub-CLINs shall provide a firm fixed price for separately identifiable contract deliverables (performance objectives). Each Sub-CLIN shall have its own performance objective expressly stated. Sub-CLINs should identify remediation objectives or activities that relate directly to, and are an integral part of, the CLIN. For example:
• Achieve [performance objective] for [site number]
Sub-CLIN prices and completion dates must not exceed the value or completion date of the CLIN. Sub- CLINs cannot be partially exercised and must be fully funded when exercised in order to avoid violations of the Anti-Deficiency Act. The use of Sub-CLINs provides the Air Force with the flexibility to match options to be exercised with available funding as the amount of available program funding is sometimes unpredictable. The Air Force may restructure the Sub-CLINs with the Apparent Successful Offeror based upon the submitted MPS.
Sub-CLINs shall consist of numeric digits and alpha characters. Once a Sub-CLIN number has been assigned, it shall not be assigned to another Sub-CLIN in the same contract. Under the contract the numeric digits for the CLIN on Performance-Based Remediation (PBR) contracts shall begin with 0001and so forth. Only 24 alpha characters shall be used in the second position before selecting a
22 January 2014 different alpha character for the first position. Alpha characters I and O should be avoided due to the potential for confusion with numeric digits 1 or 0. The Sub-CLINs must use AA, AB, AC, through AZ before beginning BA, BB, and BC. For example, if the CLIN number is 0001, the first three Sub-CLIN items would be 0001AA, 0001AB, and 0001AC. Each Site should have its own CLIN. For example:
• 0001AA Performance Management Plan
• 0002AA Achieve [performance objective] for [site A]
• 0002AB Achieve [performance objective] for [site A]
• 0003AA Achieve [performance objective] for [site B]
• 0003AB Achieve [performance objective] for [site B]
MILESTONE PAYMENT SCHEDULE:
The Contractor shall propose payment milestones as part of the MPS in its proposal. The Air Force intends to use the Contractor’s proposed MPS to restructure Sub-CLINs, if necessary, to align with projected available funding prior to award. The MPS is not included in the contract and is not considered final with award of the contract. Changes made to the MPS prior to award are used to finalize the Sub- CLINs, (i.e., end state objective of the Sub-CLIN and dollar value), however, award of the contract does not equate to final acceptance of the interim milestones in the MPS. The MPS shall be included as part of the Project Management Plan (PMP). The MPS will be negotiated during development of the PMP and may require additional changes.
Payment milestones shall be based on the completion of a definable and measurable step considered integral and necessary to the achievement of the performance objective/Sub-CLIN. Payment milestones shall include the approval requirements in accordance with the performance standards in Table 1 and Table 2 of the Performance Work Statement (PWS) and the requirements of the regulatory structure.
The AF will not pay for drafts on every deliverable, but on a case by case basis such as for significant reports (e.g., RI, FS, ROD/DD, etc.) and/or more complex site work plans. Draft payment milestones, when determined acceptable, will be made when the AF approves the draft deliverable. An approved draft document suitable for payment approval is defined as that deliverable version for which the contractor has resolved AF comments sufficient to obtain AF or lead agency concurrence for submittal to the regulators. A final document is defined as a deliverable that has Regulatory and AF approval as determined by the appropriate signatures certifying acceptance or approval.
A consolidation of completed payment milestones is to be submitted monthly, however payments shall not represent a “progress” payment or a “monthly” payment for level of effort expended. In addition, milestone payments shall not include management or overhead type costs (program/project management, monthly reporting, mobilization/demobilization, annual inspection reports, routine monitoring/maintenance reports, etc.) that do not provide measurable project advancement. For any performance objective, a payment shall be approved for completion of a definable and measurable step considered integral and necessary to completion of the performance objective. For example, if the performance objective is to achieve Remedy-in-Place (RIP) and the work required to achieve RIP includes Feasibility Study (FS), Proposed Plan (PP), Record of Decision (ROD), Remedial Design (RD), and Remedial Action (RA), then potential interim milestone payments could be:
• Air Force approval of Draft FS;
• Regulator and AF approval of Final FS;
22 January 2014
• Regulator and AF approval of Final PP;
• Air Force approval of Draft ROD;
• Regulator and AF approval of Final ROD;
• Regulator and AF approval of Final RAWP/RD;
• Air Force approval of Remedial Action Completion Report (RACR);
• Regulator and AF approval of Final RACR signifying achievement of RIP.
Contractor proposed payment milestones require sufficient funds to remain associated with the final document to ensure completion of the performance objective. Milestone payments shall not exceed 80% of the total payment for that Sub-CLIN prior to approval of the final deliverable that signifies the achievement of the performance objective. The final Sub-CLIN milestone for each site must be a minimum of 20% of the total Sub-CLIN cost. The proposed amount (percentage) of interim payment milestones for approved deliverables as compared to the total payment for that Sub-CLIN, is discretionary and negotiated on a case-by-case basis between the Air Force and selected Offeror. These negotiations may occur prior to award and/or during development of the PMP.
The Air Force will use performance indicators and performance models in addition to the PMP to establish and execute a Surveillance Plan. The Surveillance Plan will highlight key quality control activities or events. The Contracting Officer’s Representative (COR) will use the Surveillance Plan to determine when Air Force (COR and/or Contracting Officer (CO)) surveillance activities can be conducted to assess progress toward the performance objective.
INTEGRATED MASTER SCHEDULE:
The Contractor shall prepare and submit an activity-based IMS that is consistent with the MPS. The Contractor must include and identify all performance milestones at the appropriate level of detail and logically sequenced to support and manage achievement of the proposed performance objectives. The IMS shall identify completion of the performance objectives in the time designated and shall include identification of any critical path items. The IMS shall include incorporation of Air Force and Regulatory review periods for deliverables while meeting or exceeding any applicable agreements or regulatory schedule requirements.
Sites associated with each milestone/task must be noted in the schedules using the Site IDs and referencing all site aliases noted in Table 1 and Table 2 of the PWS. The schedule shall be provided in hardcopy and electronic format consistent/compatible with Air Force software, currently Microsoft Project, Microsoft Excel, and in Adobe Acrobat portable document file (.pdf). Updated and revised schedules shall be submitted with monthly status reports with changes clearly identified by the Contractor.
An example illustrating the progression of CLIN/Sub-CLIN Structure to MPS and IMS follows:
22 January 2014
EXAMPLE CLIN/SUB-CLIN STRUCTURE
(Air Force approval required prior to Contract Award)
CLIN SUB-CLIN CLIN/SUB-CLIN DESCRIPTION PROJECTED DATE OF
EXERCISE
0001 Project Management Plan
0001AA
Final Opening Phase Project Management Plan in accordance with Table 1, PWS Attachment 1A.
At Award
0001AB
Final Closing Phase Project Management Plan in accordance with Table 1, PWS Attachment 1A.
Approximately 4.5 years from 0001AA or upon CO determination of bona fide need
SS082 – FS-29 Groundwater Plume
0002AA
SS082 – FS-29 Groundwater Plume:
Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS082.
At Award
0002AB
SS082 – FS-29 Groundwater Plume:
Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS082.
Approximately 2 years from 0002AA or upon CO determination of bona fide need
0002AC
SS082 – FS-29 Groundwater Plume:
Continue to implement OES Strategy and deliver achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS082.
Approximately 2 years from 0002AB or upon CO determination of bona fide need
0002AD
SS082 – FS-29 Groundwater Plume:
Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS082.
Approximately 2 years from 0002AC or upon CO
22 January 2014
0002AE
SS082 –FS-29 Groundwater Plume:
Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS082
Approximately 2 years from 0002AD or CO determination of bona fide need
SS016 - CS-4 West Truck Road
Motorpool
0003AA
SS016 - CS-4 West Truck Road Motorpool: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at SS016.
At Award
0003AB
SS016 - CS-4 West Truck Road Motorpool: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS016.
Approximately 2 years from 0003AA or upon CO determination of bona fide need
0003AC
SS016 - CS-4 West Truck Road Motorpool: Continue to implement OES Strategy and deliver achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS016.
Approximately 2 years from 0003AB or upon CO determination of bona fide need
0003AD
SS016 - CS-4 West Truck Road Motorpool: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at
SS016.
Approximately 2 years from 0003AC or upon CO determination of bona fide need
0003AE
SS016 - CS-4 West Truck Road Motorpool: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at SS016.
Approximately 2 years from 0003AD or upon CO
ML701 – Otis Target Butt
0004AA
ML701 – Otis Target Butt: Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
22 January 2014
0005 MMR-003-R-01 – Old Grenade Courts
0005AA
MMR-003-R-01 – Old Grenade Courts:
Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0006 MMR-001-R-01 – Mock Village
0006AA
MMR-001-R-01 – Mock Village:
Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0007 MMR-004-R-01 –Old K Range
0007AA
MMR-004-R-01 –Old K Range: Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0008 MMR-009-R-01 Otis Gun Club
0008AA
Otis Gun Club: Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0009 TS701 – Skeet Range
0009AA
TS701 – Skeet Range: Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0010 MB702 – Ordnance Area 1
0010AA
MB702 – Ordnance Area 1 : Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0011 MB701 – Former Otis Bomb Storage Magazines
0011AA
MB701 – Former Otis Bomb Storage Magazines: Achieve Phase II CSE in accordance with Table 1, PWS Attachment 1A.
At Award
0012 CD500 – Dump Area
0012AA
CD500 – Dump Area: Achieve PA/SI in accordance with Table 1, PWS Attachment 1A.
At Award
0013 OW524 – OWS 6165
0013AA
OW524 – OWS 6165: Achieve PA/SI in accordance with Table 1, PWS At Award
22 January 2014
Attachment 1A.
0014 LF006 - LF-1 Main Base Landfill
0014AA
LF006 - LF-1 Main Base Landfill:
Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
LF006.
At Award
0014AB
LF006 - LF-1 Main Base Landfill:
Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at LF006.
Approximately 2 years from 0014AA or upon CO determination of bona fide need
0014AC
LF006 - LF-1 Main Base Landfill:
Continue to implement OES Strategy and deliver achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
LF006.
Approximately 2 years from 0014AB or upon CO determination of bona fide need
0014AD
LF006 - LF-1 Main Base Landfill:
Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at LF006.
Approximately 2 years from 0014AC or upon CO determination of bona fide need
0014AE
LF006 - LF-1 Main Base Landfill:
Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
LF006.
Approximately 2 years from 0014AD or upon CO determination of bona fide need
0015 SS022 - CS-10 UTES/BOMARC Site
0015AA
SS022 - CS-10 UTES/BOMARC Site:
Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS022.
At Award
0015AB
SS022 - CS-10 UTES/BOMARC Site:
Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS022.
Approximately 2 years from 0015AA or upon CO
22 January 2014
0015AC
SS022 - CS-10 UTES/BOMARC Site:
Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS022.
Approximately 2 years from 0015AB or upon CO determination of bona fide need
0015AD
SS022 - CS-10 UTES/BOMARC Site:
Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS022.
Approximately 2 years from 0015AC or upon CO determination of bona fide need
0015AE
SS022 - CS-10 UTES/BOMARC Site:
Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS022.
Approximately 2 years from 0015AD or upon CO determination of bona fide need
SS031 - FS-1 AVGAS Fuel Test
Dump Site
0016AA
SS031 - FS-1 AVGAS Fuel Test Dump Site: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at SS031.
At Award
0016AB
SS031 - FS-1 AVGAS Fuel Test Dump Site: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS031.
Approximately 2 years from 0016AA or upon CO determination of bona fide need
0016AC
SS031 - FS-1 AVGAS Fuel Test Dump Site: Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS031.
Approximately 2 years from 0016AB or upon CO determination of bona fide need
0016AD
SS031 - FS-1 AVGAS Fuel Test Dump Site: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS031.
Approximately 2 years from 0016AC or upon CO
22 January 2014
0016AE
SS031 - FS-1 AVGAS Fuel Test Dump Site: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS031.
Approximately 2 years from 0016AD or upon CO determination of bona fide need
0017 SS042 - FS-12 Fuel Pipeline Spill
0017AA
SS042 - FS-12 Fuel Pipeline Spill:
Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS042.
At Award
0017AB
SS042 - FS-12 Fuel Pipeline Spill:
Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS042.
Approximately 2 years from 0017AA or upon CO determination of bona fide need
0017AC
SS042 - FS-12 Fuel Pipeline Spill:
Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS042.
Approximately 2 years from 0017AB or upon CO determination of bona fide need
0017AD
SS042 - FS-12 Fuel Pipeline Spill:
Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS042.
Approximately 2 years from 0017AC or upon CO determination of bona fide need
0017AE
SS042 - FS-12 Fuel Pipeline Spill:
Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS042.
Approximately 2 years from 0017AD or upon CO
FT055 - FTA-1 (Ashumet Valley)
0018AA
FT055 - FTA-1 (Ashumet Valley):
Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
FT055.
22 January 2014
0018AB
FT055 - FTA-1 (Ashumet Valley):
Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at FT055.
Approximately 2 years from 0018AA or upon CO determination of bona fide need
0018AC
FT055 - FTA-1 (Ashumet Valley):
Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
FT055.
Approximately 2 years from 0018AB or upon CO determination of bona fide need
0018AD
FT055 - FTA-1 (Ashumet Valley):
Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at FT055.
Approximately 2 years from 0018AC or upon CO determination of bona fide need
0018AE
FT055 - FTA-1 (Ashumet Valley):
Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
FT055.
Approximately 2 years from 0018AD or upon CO determination of bona fide need
SS077 - CS-19 Impact Range
Chemical Dumpsite (Groundwater only)
0019AA
SS077 - CS-19 Impact Range Chemical Dumpsite (Groundwater only): Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at SS077.
At Award
0019AB
SS077 - CS-19 Impact Range Chemical Dumpsite (Groundwater only): Implement OES Strategy and Achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS077.
Approximately 4 years from 0019AA or upon CO determination of bona fide need
0019AC
SS077 - CS-19 Impact Range Chemical Dumpsite (Groundwater only): Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS077.
Approximately 3 years from 0019AB or upon CO
22 January 2014
SS079 - FS-28 EDB Plume
0020AA
SS079 - FS-28 EDB Plume: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS079.
At Award
0020AB
SS079 - FS-28 EDB Plume: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS079.
Approximately 2 years from 0020AA or upon CO determination of bona fide need
0020AC
SS079 - FS-28 EDB Plume: Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS079.
Approximately 2 years from 0020AB or upon CO determination of bona fide need
0020AD
SS079 - FS-28 EDB Plume: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS079.
Approximately 2 years from 0020AC or upon CO determination of bona fide need
0020AE
SS079 - FS-28 EDB Plume: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS079.
Approximately 2 years from 0020AD or upon CO
SS080 - CS-20 PCE Plume
0021AA
SS080 - CS-20 PCE Plume: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS080.
At Award
0021AB
SS080 - CS-20 PCE Plume: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS080.
Approximately 2 years from 0021AA or upon CO
22 January 2014
0021AC
SS080 - CS-20 PCE Plume: Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS080.
Approximately 2 years from 0021AB or upon CO determination of bona fide need
0021AD
SS080 - CS-20 PCE Plume: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS080.
Approximately 2 years from 0021AC or upon CO determination of bona fide need
0021AE
SS080 - CS-20 PCE Plume: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
SS080.
Approximately 2 years from 0021AD or upon CO
SS081 - CS-21 TCE Plume
0022AA
SS081 - CS-21 TCE Plume: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at
SS081.
At Award
0022AB
SS081 - CS-21 TCE Plume: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS081.
Approximately 2 years from 0022AA or upon CO determination of bona fide need
0022AC
SS081 - CS-21 TCE Plume: Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS081.
Approximately 2 years from 0022AB or upon CO determination of bona fide need
0022AD
SS081 - CS-21 TCE Plume: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS081.
Approximately 2 years from 0022AC or upon CO determination of bona fide need
0022AE
SS081 - CS-21 TCE Plume: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at
Approximately 2 years from 0022AD or upon CO
22 January 2014
SS081.
SS087 - CS-23 Plume
0023AA
SS087 - CS-23 Plume: Mobilize and develop an optimized exit strategy/plan to achieve SC while maintaining compliance with current regulatory and binding agreements at SS087.
At Award
0023AB
SS087 - CS-23 Plume: Implement OES strategy and achieve an Interim OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at
SS087.
Approximately 2 years from 0023AA or upon CO determination of bona fide need
0023AC
SS087 - CS-23 Plume: Continue to implement OES Strategy and achieve a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements at SS087.
Approximately 2 years from 0023AB or upon CO determination of bona fide need
0023AD
SS087 - CS-23 Plume: Continue to implement OES Strategy and achieve an Interim OES Effectiveness Report while maintaining compliance with current regulatory and binding agreements at SS087.
Approximately 2 years from 0023AC or upon CO determination of bona fide need
0023AE
SS087 - CS-23 Plume: Achieve Final OES Effectiveness Report to achieve SC documenting the completion of elements of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements at SS087.
Approximately 2 years from 0023AD or upon CO determination of bona fide need
SD005 - SD-5 Storm Drain Disp Site
No. 5 - Groundwater
0024AA
SD005 - SD-5 Storm Drain Disp Site No. 5 - Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
At award for the Land Use Controls program. The next biennial sampling event will be conducted in Sep 2014 under a current task order. Refer to Table 2 (PWS atch 1B) for additional information.
0024AB
SD005 - SD-5 Storm Drain Disp Site No. 5 - Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting
Approximately two years from 0024AA or upon CO
22 January 2014 and application of Land Use Controls.
0024AC
SD005 - SD-5 Storm Drain Disp Site No. 5 - Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately two years from 0024AB or upon CO determination of bona fide need
0024AD
SD005 - SD-5 Storm Drain Disp Site No. 5 - Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately two years from 0024AC or upon CO determination of bona fide need
0024AE
SD005 - SD-5 Storm Drain Disp Site No. 5 - Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately two years from 0024AD or upon CO
SS040 - FS-10 (PFSA)
0025AA
SS040 - FS-10 (PFSA): Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Within one year from award.
Refer to Table 2 (PWS atch 1B) for additional information.
0025AB
SS040 - FS-10 (PFSA): Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AA or upon CO
0025AC
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AB or upon CO
0025AD
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AC or upon CO
0025AE
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AD or upon CO
22 January 2014
0025AF
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AE or upon CO
0025AG
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AF or upon CO
0025AH
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AG or upon CO
0025AJ
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AH or upon CO
0025AK
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0025AJ or upon CO
SS041 - FS-11 (PFSA)
0026AA
SS041 - FS-11 (PFSA): Achieve Long while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Within one year from award.
Refer to Table 2 (PWS atch 1B) for additional information.
0026AB
SS041 - FS-11 (PFSA): Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AA or upon CO
0026AC
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AB or upon CO
0026AD
while conducting RA-Operations to
Approximately one year from 0026AC or upon CO
22 January 2014 include required monitoring/reporting and application of Land Use Controls.
0026AE
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AD or upon CO
0026AF
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AE or upon CO
0026AG
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AF or upon CO
0026AH
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AG or upon CO
0026AJ
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AH or upon CO
0026AK
while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0026AJ or upon CO
SS043 - FS-13 Fuel Pipeline Spill
0027AA
SS043 - FS-13 Fuel Pipeline Spill:
Achieve Long Term Monitoring Summary Report while conducting RA- Operations to include required monitoring/reporting and application of Land Use Controls.
Within two years after award.
Refer to Table 2 (PWS atch 1B) for additional information.
22 January 2014
0027AB
SS043 - FS-13 Fuel Pipeline Spill:
Achieve Final LTM Report (2024) at SS043. Achieve Long Term Monitoring Summary Report while conducting RA- Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately 5 years from 0027AA or upon CO determination of bona fide need
FT056: FTA-2 Former FPTA (1948-
56) - Groundwater
0028AA
FT056: FTA-2 Former FPTA (1948-56)
– : Achieve Long Term Monitoring Summary Report while conducting RA- Operations to include required monitoring/reporting and application of Land Use Controls.
Within one year from award.
Refer to Table 2 (PWS atch 1B) for additional information.
0028AB
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AA or upon CO determination of bona fide need
0028AC
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AB or upon CO determination of bona fide need
0028AD
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AC or upon CO determination of bona fide need
0028AE
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AD or upon CO determination of bona fide need
0028AF
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AE or upon CO determination of bona fide need
0028AG
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AF or upon CO
22 January 2014
0028AH
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AG or upon CO determination of bona fide need
0028AJ
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AH or upon CO determination of bona fide need
0028AK
FT056: FTA-2 Former FPTA (1948-56)
– Groundwater: Achieve Long Term Monitoring Summary Report while conducting RA-Operations to include required monitoring/reporting and application of Land Use Controls.
Approximately one year from 0028AJ or upon CO
PAVE PAWS Wind Turbines
0029AA Conduct operations and maintenance of PAVE PAWS wind turbines. At award
0029AB Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AA or upon CO determination of bona fide need
0029AC Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AB or upon CO determination of bona fide need
0029AD Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AC or upon CO determination of bona fide need
0029AE Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AD or upon CO determination of bona fide need
0029AF Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AE or upon CO determination of bona fide need
0029AG Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AF or upon CO
22 January 2014
0029AH Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AG or upon CO determination of bona fide need
0029AJ Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AH or upon CO determination of bona fide need
0029AK Conduct operations and maintenance of PAVE PAWS wind turbines
Approximately 1 year from 0029AJ or upon CO
EXAMPLE MILESTONE PAYMENT SCHEDULE
(Negotiated between the Air Force and the selected Offeror and approved by the Air Force)
CLIN/SU
B-CLIN CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION
CLIN/SUB
-CLIN
AMOUNT
MILESTONE
PAYMENT
AMOUNT
MILESTONE
PERCENT
0001 Project Management Plan $0
0001AA Opening Project Management Plan (PMP) $25,000 $25,000
0001AB Closing Project Management Plan (PMP) $25,000 $25,000
0002 CG025 Management Unit
0002AA CG025 Management Unit: Achieve RC $200,000
Air Force Approval of Draft FS $30,000 15%
Regulator and AF Approval of Final FS $20,000 25%
Air Force Approval of Draft ROD $6,000 28%
Regulator and AF Approval of Final ROD $4,000 30%
Regulator and AF Approval of Final RAWP/Remedial Design $100,000 80%
Air Force Approval of Draft RACR $10,000 85%
Regulator and AF Approval of Final RACR signifying achievement of RIP $30,000 100%
Total $250,000 $250,000
Note: Payment milestone shall not exceed 80% of the total payment for the CLIN/Sub-CLIN prior to achievement of the final deliverable. In the example above, 80% of $200,000 = $160,000; therefore, RACR (draft + final) = $40,000 or 20% of the Sub-CLIN 0002AA. Approved Draft is defined as that document for which the contractor has resolved AF comments sufficient to obtain AF or lead agency concurrence for submittal to the regulators.
EXAMPLE INTEGRATED MASTER SCHEDULE
(Air Force approval required as part of the PMP)
Activity ID# ACTIVITY DESCRIPTION DURATION START FINISH
0001 Contract Award 1 day 1 OCT 10 1 OCT 10
22 January 2014
0001AA0001 Kick Off Meeting 1 day 15 OCT 10 15 OCT 10
0001AA0002 Prepare Opening PMP 30 days 1 OCT 10 31 OCT 10
0001AA0003QA Air Force Review of Opening PMP 30 days 1 NOV 10 1 DEC 10 0001AA0004PM Air Force Approval of Opening PMP 1 day 1 DEC 10 1 DEC 10
Note: Air Force surveillance activities precede all milestone payments.