11_Attachment_9a_Payment_Plan_NROL-87,_SILENTBARKER_and_AFSPC-44.pdf
PDF 166 KB Posted
- Attached to
- EELV Phase 1A Request for Proposal (RFP) 1A-6 Federal contract opportunity
- Solicitation number
- FA8811-18-R-0001
About this file
Attachment 9a Payment Plan NROL-87, SILENTBARKER and AFSPC-44
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 01_FA8811-18-R-0001.pdf | ||
| 02a_CDRLs_Exhibit_AX_Signed.pdf | ||
| 05_Attachment_3A_Small_Business_Subcontracting_Plan.pdf | ||
| 11_Attachment_9b_Payment_Plan_NROL-85_and_SBIRS_GEO-5.pdf | ||
| 04_Attachment_2_RFP_1A-6_DD_254s.pdf | ||
| 08_Attachment_6_Evaluation_Criteria.pdf | ||
| 05_Attachment_3B_Small_business_participation_commitment_document.pdf | ||
| 02c_CDRLs_Exhibit_CX_Signed.pdf | ||
| 10_Attachment_8_Government_Property_Form.pdf | ||
| 12_Attachment_10_FCIL_Cover.pdf | ||
| 02b_CDRLs_Exhibit_BX_Signed.pdf | ||
| 09_Attachment_7_MRA_Cover.pdf | ||
| 13_Attachment_11_OCI_Plan_Cover.pdf | ||
| 03_Attachment_1_PWS.pdf | ||
| 07_Attachment_5_Instructions_to_Offerors_Combined.pdf | ||
| 06_Attachment_4_Acceptance_Criteria.pdf | ||
| 14_Attachment_12_Security_Plan_Cover.pdf | ||
| 00_RFP_Front_Cover_and_Table_of_Contents.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 9a: Payment Plan for NROL-87, SILENTBARKER and AFSPC-44
FA8811-18-R-0001
31 January 2018
I. Basis of Payment The basis of payment for this effort shall be the successful accomplishment of event milestones scheduled for a Launch Service mission throughout the period of performance of the contract. The milestones represent meaningful efforts or actions that are an integral and necessary part of performance. The basis for an event should be either specifically described events or a measurable criterion of performance.
Included within this Payment Plan is a description of what constitutes successful performance of each event. For purposes of establishing and calculating payment amounts, a percentage of the total contract price for all applicable firm fixed price (FFP) Contract Line Item Numbers (CLINs) pertaining to the mission (1000-5000 CLINs) will be assigned to each milestone. The dollar amount associated with each milestone will be calculated based on the percentages assigned to each milestone. NRO-only references appear in grey text.
A. Milestone Success Criteria and Completion Evidence Each event milestone has associated measurable success criteria that serve to validate milestone accomplishment. All milestone success criteria must be met before the milestone payment will be authorized. When the Launch Vehicle Contractor (LVC) has successfully completed all applicable milestone success criteria, the LVC shall submit a written Notice of Completion (NOC) for the milestone to the Procurement Contracting Officer (PCO). The NOC shall include supporting documentation to substantiate meeting the milestone success criteria as provided in the completion evidence defined herein.
B. Event Milestone Payments and Event Timing Completion of milestones and subsequent NOCs may be submitted non-successively (e.g., if milestone two is completed before milestone one, then the LVC may submit a NOC for milestone two before a NOC for milestone one). Therefore, the NOC may be for multiple milestones. In the event the LVC completes a milestone ahead of the milestone completion date, the LVC may include that milestone in the monthly NOC and the Government will consider, on a case-by-case basis, the early payment of the milestone.
The PCO will determine whether or not the LVC has successfully met each of the milestone success criteria based on inputs provided by the United States Government (USG) Team (for Air Force missions) and the Mission Team (for NRO missions).
For Air Force missions, the USG Team consists of the Air Force Space and Missile Systems Center, Launch Systems Enterprise Directorate (SMC/LE), and Air Force Program Executive Officer for Space office personnel, but also includes The Aerospace Corporation, LE’s Systems Engineering and Integration (SE&I) Contractor, LE’s Systems Engineering and Technical Assistance (SETA) support Contractors, the NRO/Office of Space Launch (OSL) (as applicable), the SMC Independent Readiness Review Team, Defense Contract Management Agency, Defense Contract Audit Agency, 30th Space Wing (30 SW), 45th Space Wing (45 SW), and other organizations as designated by the SMC/LE PCO.
For NRO missions, in addition to the USG Team listed above for Air Force missions, the Mission Team consists of the OSL Mission Manager, the OSL Contracting Officer Technical Representative (COTR), and their support personnel (to include Government, Aerospace Corporation, and SETA personnel). At their discretion, the OMM and COTR may solicit inputs from SMC/LE to assist in their determination of the LVC’s satisfactory completion of the milestone success criteria. Written concurrence from both the OMM and COTR that the LVC has successfully met the milestone success criteria is required before the PCO will authorize payment of the milestone.
To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC, the PCO will provide written notification to the LVC specifying which milestones contained in the NOC are determined to be “met” (complete) and, if necessary, which are considered “not met” (incomplete). For milestones identified as incomplete, the PCO will: (1) specify in the notification the issue(s) that led to the determination based upon the milestone success criteria and completion evidence provided herein, and
(2) the corrective action(s) required to complete the milestone. The Government and LVC will ensure agreement and understanding of the corrective actions, and the LVC will make a good faith effort to quickly reconcile any incomplete milestones. When the LVC accomplishes the corrective actions, the LVC will submit a NOC addendum to the PCO for Government review. To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC addendum, the PCO will provide a written notification to the LVC specifying whether the Government concurs that all corrective actions have been accomplished and the milestone has been “met” (completed).
For each milestone, the Estimated Completion Date is the estimated date that the LVC will complete the payment event and submit the associated NOC for payment of each milestone under this Plan. For each milestone, the value in the percentage “%” column of Table 1 indicates the percentage of the contract value of all applicable FFP CLINs (CLINs 1001-1003; 2001-2003; 3001-3003; 4001-4002, 5001-5003) that will be used to calculate the dollar amount to be paid to the LVC upon successful completion of the milestone. The Government reserves the right to withhold up to fifty percent (50%) of the total payment value for any unpaid milestone(s) in the event of a Government-approved Class 1 change required for the launch service that is not implemented or completed to meet the Government’s approval by the implementation deadlines specified in and in accordance with (IAW) Attachment 1 Performance Work Statement (PWS) section 3.2.4, Table 1.
C. Event Milestone Schedule Criteria for payment of each event milestones appear in Table 1. In no event shall the LVC receive payments in excess of 80% of the total contract price until after acceptance of the launch service IAW Milestone 12 (Government Acceptance of Launch Service IAW contract clause Federal Acquisition Regulation [FAR] 52.212-04, Addendum to Contract Terms and Conditions—Commercial Items [September 2013]). Given that defects in service for the last Milestone 12, Acceptance of Launch Service, are not suitable for correction by re-performance, the Contracting Officer has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event of Milestone 12 defect (e.g., mission failure) is to reduce the contract price by the amount of the full Milestone 10, Upper Stage Disposal, Final Initial As-Built Configuration List (ABCL), and Final Fleet Insight ABCL;
Milestone 11, Mission Orbital Insertion Accuracy Verification; and Milestone 12 payment, which appropriately reflects the reduced value of the services performed.
Table 1: Payment Event Schedule
Milestone
Payment Event Accomplishment Criteria
Est.
Comp.
Date
Total Payment (Dollar Value)*
% of FFP CLINs
1001-5003
Initial Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary; Initial Draft Integrated Master Schedule (IMS); Initial Hazardous Materials Management Program (HMMP) Plan;
Initial Payload Integration & Ops Plan; Initial Flight Critical Items List (FCIL);
Launch Service Provider Space Flight Worthiness of Non-Recurring Engineering (NRE) work closure schedule; Procurement initiated of Long lead hardware; and completed Mission Kickoff Meeting
(KOM)
- First submission and Government acknowledgement of receipt of the following: Initial CWBS and CWBS Dictionary in accordance with (IAW) Contract Data Requirements List (CDRL) AX05; Initial Draft IMS IAW CDRL AX06; HMMP Plan IAW CDRL BX04; Initial Payload Integration & Ops Plan IAW CDRL BX16; and Initial FCIL IAW CDRL
BX18.
- Submission and Government approval of the baseline schedule for NRE work closure IAW CDRL
BX20.
- Long lead hardware procurement or build initiated as required.
- KOM completed IAW Attachment 1 Performance Work Statement (PWS) Appendix H.
Authority to
Proceed
(ATP) +
1 Month
To Be Filled In
By Offeror
10%
Initial As-Designed Configuration List (ADCL);
IMS; and Launch Vehicle Familiarization Course (FAM Course) training materials
- Submission and Government acknowledgement of receipt of the initial ADCL for the launch vehicle
IAW CDRL AX09.
- Submission and Government approval of the IMS IAW CDRL AX06; and the FAM Course training materials IAW CDRL AX07.
ATP + 2
Months
To Be Filled In
By Offeror
5%
Preliminary mission Interface Control Document (ICD); Initial Launch Vehicle Test & Verification Plan (LVT&VP); Initial Systems Safety Program Plan (SSPP); Initial compliance document tailoring submission; and Final Mission Integration Management Plan (MIMP)
- Submission and Government acknowledgement of receipt of the following: preliminary mission ICD IAW CDRL BX09; initial LVT&VP IAW CDRL AX10; initial SSPP IAW CDRL BX02; and initial compliance documents tailoring IAW CDRL
BX05.
- Submission and Government approval of the final MIMP IAW
CDRL BX08.
ATP + 3
Months
To Be Filled In
By Offeror
5%
Initial Verification Planning Matrix (VPM); Initial Flight Hardware Interface Checks;
Updated FCIL; Updated ADCL; Updated Payload
- Submission and Government acknowledgement of receipt of initial VPM IAW CDRL BX11 and initial Flight Hardware Interface Checks
IAW CDRL AX11.
ATP + 6
Months
To Be Filled In
By Offeror
10%
Integration & Ops Plan; and Final LVT&VP
- Submission and Government approval of the following: updated FCIL IAW CDRL BX18; updated ADCL IAW CDRL AX09; updated Payload Integration & Operations Plan IAW CDRL BX16;
and final LVT&VP IAW CDRL
AX10.
Preliminary Coupled Loads Analysis (CLA); Updated
ADCL
- Submission and Government acknowledgement of receipt of preliminary CLA complete and delivery of results IAW CDRL BX10.
- Submission and Government approval of the updated ADCL IAW
CDRL AX09.
ATP + 8
Months
To Be Filled In
By Offeror 5%
Final ADCL; Baseline Mission ICD; Updated VPM; Final Payload Integration & Ops Plan;
Final FCIL; ABCL; Initial Fleet Insight ABCL;
Completion of all NRE Work Closure Plan tasks;
Final Technical Rationale for all Class 1A changes Mission Design Review (MDR) Completed; and Completed Flight Hardware Interface Checks
- Submission and Government approval of the following: Final ADCL IAW CDRL AX09, final Test Facility requirements document IAW CX01 (except for AFSPC-44);
updated baseline mission ICD IAW BX09; updated VPM IAW CDRL BX11; final Payload Integration & Ops Plan IAW CDRL BX16; final
FCIL IAW CDRL BX18;
Government approval of CDRL
BX26.
- Submission and Government acknowledgment of receipt of the initial ABCL IAW CDRL AX12.
- Submission and Government acknowledgement of receipt of the initial Fleet Insight ABCL IAW
CDRL AX13.
- Evidence demonstrating the completion of all NRE Work Closure Plan tasks IAW CDRL BX20; and
- Final technical rationale for all Class 1A changes IAW Attachment 1 PWS Section 3.2.4.
- MDR completed IAW Appendix H.
- Flight Hardware Interface Checks completed IAW Attachment 1 PWS Section 3.4.12.
Launch
(L) – 12 Months
To Be Filled In
By Offeror
20%
Launch countdown parameters and operational redline limits; Mission Assurance Data; Updated ABCL; Updated Fleet Insight ABCL; and
- Submission and Government acknowledgement of receipt of the Launch countdown parameters and operational redline limits baseline IAW Attachment 1 PWS Section 3.2.7; and, Mission Assurance
L – 6 Months
To Be Filled In
By completion of the Mission Verification Review (MVR)
Independent Assessment Data IAW CDRL BX10 to include: intermediate unguided Three Degrees of Freedom;
Collision and Contamination Avoidance Maneuver memo;
acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.
- Submission and Government approval of the updated ABCL IAW
CDRL AX12.
- Submission and Government approval of the updated ABCL IAW
CDRL AX13.
- MVR completed IAW Appendix H.
Verification Evidence Record; Updated ABCL;
Updated Fleet Insight ABCL; Completion of Ground Operations Readiness Review (GORR)
- Submission and Government acknowledgement of receipt of at least 30% of Verification Evidence Record IAW CDRL BX12.
- Submission and Government approval of updated ABCL IAW
CDRL AX12.
- Submission and Government approval of updated Fleet Insight
ABCL IAW CDRL AX13.
- GORR completed IAW Attachment 1 PWS Appendix H.
L – 3
Months
To Be Filled In
By Offeror
5%
Verification Evidence Record; Updated ABCL;
Updated Fleet Insight ABCL; Mission Assurance Data; Completion of Hardware Pre-Ship Review(s) and Independent Hardware Review(s); and Completion of Component and Subsystem Readiness Review (CSRR)
- Submission and Government acknowledgement of receipt of at least 60% of Verification Evidence Record IAW CDRL BX12; Mission Assurance Independent Assessment Data IAW CDRL BX10: controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environments.
- Submission and Government approval of the updated ABCL IAW
CDRL AX12.
- Submission and Government approval of the updated Fleet Insight
ABCL IAW CDRL AX13.
- Completion of major launch vehicle hardware pre-ship reviews and Government independent hardware review(s) complete IAW Attachment 1 PWS 3.6.6 and 3.6.5; respectively.
L – 2 Months
To Be Filled In
By
- Completion of CSRR IAW Attachment 1 PWS Appendix H.
Upper Stage Disposal; Final ABCL; and Final Fleet Insight ABCL
- Submission and Government approval of compliance with upper stage disposal requirements.
- Submission and Government approval of final ABCL IAW CDRL
AX12.
- Submission and Government approval of final ABCL IAW CDRL
AX13.
L + 2 Months
To Be Filled In
By Offeror
2.5%
11 Mission Orbital Insertion Accuracy Verification
- Submission and Government approval of final post-flight assessment report IAW CDRL BX06;
and IAW the Success Criteria outlined in Milestone 12 in Attachment 9, Payment Plan
L + 2 Months
To Be Filled In
By Offeror
7.5%
Government Acceptance of Launch Service
- Submission and Government approval of final post-flight assessment report IAW CDRL BX06;
and Government approval of the launch (launch has not been deemed “mission failure”) IAW Attachment 1 PWS Appendix A and the Launch Service Acceptance Criteria outlined in contract Attachment 4.
L + 2 Months
To Be Filled In
By
*The dollar amount for each milestone is to be filled in by the Offeror and is equal to the percentage listed in the last column multiplied by the value of the contract (1000-4000 series CLINs) prior to award of each milestone. No adjustment to the payment will occur after milestone award.
MILESTONE 1: Initial Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary, Initial Draft Integrated Master Schedule (IMS), Initial Hazardous Materials Management Program (HMMP) Plan, Initial Payload (PL) Integration & Ops Plan, Initial Flight Critical Items List (FCIL), Approval of Non-Recurring Engineering (NRE) work closure schedule, Procurement Initiated of Long Lead Hardware, and Completed Mission Kickoff Meeting
Description:
1. Initial CWBS and CWBS Dictionary. LVC’s initial CWBS and CWBS Dictionary delivered, and
Government has acknowledged receipt IAW CDRL AX05.
2. Initial Draft IMS. LVC’s initial draft IMS delivered, and Government has acknowledged receipt
IAW CDRL AX06.
3. HMMP Plan. LVC’s initial HMMP plan delivered, and the Government has acknowledged receipt IAW Attachment 1 PWS paragraph 3.1.15 and Contract Data Requirements List (CDRL)
BX04.
4. Initial Payload Integration and Ops Plan. LVC’s Initial PL Integration and Operations plan delivered, and the Government has acknowledged receipt IAW Attachment 1 PWS paragraph
3.5.1.9.1 and CDRL BX16.
5. Initial FCIL. LVC’s initial FCIL delivered, and the Government has acknowledged receipt IAW Attachment 1 PWS paragraph 3.6.5 and CDRL BX18.
6. NRE Work Closure Schedule. LVC’s baseline launch service provider NRE work closure schedule and plan delivered and approved by the Government IAW CDRL BX20.
7. Long Lead Hardware Procurement or Production Initiated. LVC has initiated procurement orders for or production of long lead hardware required for the mission.
8. Mission Kickoff Meeting. LVC has conducted the Kickoff Meeting (KOM) IAW Attachment 1 PWS Appendix H with actions and action closure plans, and accepted by the Government.
Success Criteria:
1. The LVC has delivered and Government has acknowledged receipt of initial CWBS and CWBS Dictionary IAW CDRL AX05.
2. The LVC has delivered and Government has acknowledged receipt of initial draft IMS IAW
CDRL AX06.
3. The LVC has delivered and Government has acknowledged receipt of initial HMMP IAW CDRL
BX04.
4. The LVC has delivered and Government has acknowledged receipt of initial PL Integration and Ops Plan IAW Attachment 1 PWS paragraph 3.5.1.9.1 and CDRL BX16.
5. The LVC has delivered and Government has acknowledged receipt of initial FCIL IAW Attachment 1 PWS paragraph 3.6.5 and CDRL BX18.
6. The LVC has delivered and Government has approved the baseline launch service provider Space Flight Worthiness (SFW) NRE work closure schedule and plan IAW CDRL BX20.
7. The LVC has initiated procurement orders for or production of long lead hardware required for the mission.
8. The LVC has conducted the KOM IAW Attachment 1 PWS Appendix H with actions and action closure plans and the Government has accepted.
Completion Evidence:
1. CDRL AX05 initial draft CWBS and CWBS Dictionary accepted by the PCO, appropriate Contracting Officer Representative (COR), or appropriate Contracting Officer Technical Representative (COTR).
2. CDRL AX06 initial draft IMS accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL BX04 initial draft HMMP plan accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL BX16 initial draft PL Integration and Operations plan accepted by the PCO, appropriate
COR, or appropriate COTR.
5. CDRL BX18 initial FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL BX20 baseline launch service provider SFW NRE work closure plan and schedule accepted by the PCO, appropriate COR, or appropriate COTR.
7. Long lead hardware procurement or build initiated as required. Copies of signed, written procurement or build orders for all long lead hardware required for the mission received and accepted by the PCO, appropriate COR, or appropriate COTR.
8. KOM meeting minutes documenting meeting completion, action items, and action item closure plans.
MILESTONE 2: First Submission ADCL, Approved IMS, and Launch Vehicle Familiarization (FAM) Course Materials Approval
Description:
1. ADCL. LVC’s initial ADCL delivered and Government has acknowledged receipt IAW CDRL
AX09.
2. IMS. The LVC has delivered and the Government has approved the IMS IAW Attachment 1
PWS paragraph 3.1.4 and CDRL AX06.
3. Launch Vehicle FAM Course Materials. LVC’s LV familiarization training materials required by
CDRL AX07 delivered and approved by the Government IAW Attachment 1 PWS paragraph
3.1.10 and CDRL AX07.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the initial ADCL IAW
CDRL AX09.
2. The LVC has delivered and the Government has approved the IMS IAW Attachment 1 PWS paragraph 3.1.4 and CDRL AX06.
3. The LVC has delivered and the Government has approved the submission of all LV familiarization training materials required by and IAW CDRL AX07.
Completion Evidence:
1. CDRL AX09 initial ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL AX06 IMS accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL AX07 submission of LV FAM Course training materials accepted by the PCO, appropriate
COR, or appropriate COTR.
MILESTONE 3: Preliminary Interface Control Document (ICD), Initial Launch Vehicle Test & Verification Plan (LVT&VP), Initial Systems Safety Program Plan (SSPP), Initial Compliance Document Tailoring, and Final Mission Integration Management Plan (MIMP) Contractor
Description:
1. ICD. LVC’s initial baseline mission ICD delivered, and the Government has acknowledged receipt IAW Attachment 1 PWS paragraph 3.4.4 and CDRL BX09.
2. LVT&VP. LVC’s initial LVT&VP delivered, and the Government has acknowledged receipt
IAW CDRL AX10.
3. SSPP. LVC’s first draft SSPP delivered, and the Government has acknowledged receipt IAW
Attachment 1 PWS 3.1.7 and CDRL BX02.
4. Compliance Document Tailoring. LVC’s initial compliance documents tailoring delivered, and the Government has acknowledged receipt CDRL BX05.
5. MIMP. The LVC has delivered, and the Government has approved the final MIMP IAW CDRL
BX08.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the initial, first draft baseline mission ICD IAW CDRL BX09.
2. The LVC has delivered and the Government has acknowledged receipt of the initial LVT&VP
IAW CDRL AX10.
3. The LVC has delivered and the Government has acknowledged receipt of the initial, first draft
SSPP IAW CDRL BX02.
4. The LVC has delivered and the Government has acknowledged receipt of initial Compliance Documents Tailoring IAW CDRL BX05.
5. The LVC has delivered and the Government has approved the final MIMP IAW CDRL BX08.
1. CDRL BX09 initial, first draft baseline mission ICD accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL AX10 initial LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL BX02 first draft SSPP accepted by the PCO, appropriate COR or appropriate COTR.
4. CDRL BX05 initial Compliance Documents Tailoring accepted by the PCO, appropriate COR or appropriate COTR.
5. CDRL BX08 final MIMP accepted by the PCO, appropriate COR or appropriate COTR.
MILESTONE 4: Initial Verification Planning Matrix (VPM), Initial Flight Hardware Interface Checks, updated FCIL, updated ADCL, updated PL Integration & Ops Plan, and Final LVT&VP
Description:
1. VPM. LVC’s first draft VPM delivered, and the Government has acknowledged receipt IAW
CDRL BX11.
2. Flight Hardware Interface Checks. LVC’s initial Flight Hardware Interface Checks delivered, and the Government has acknowledged receipt IAW CDRL AX11.
3. FCIL. The LVC has delivered and the Government has approved the updated FCIL IAW
Attachment 1 PWS paragraph 3.6.5 and CDRL BX18.
4. ADCL. The LVC has delivered and the Government has approved the updated ADCL IAW
CDRL AX09.
5. PL Integration & Ops Plan. The LVC has delivered and the Government has approved the updated integration and operations plan IAW Attachment 1 PWS paragraph 3.5.1.9.1 and CDRL
BX16.
6. LVT&VP. The LVC has delivered and the Government has approved the final LVT&VP IAW
CDRL AX10.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the first draft VPM
IAW CDRL BX11.
2. The LVC has delivered and the Government has acknowledged receipt of the initial Flight
Hardware Interface Checks IAW CDRL AX11.
3. The LVC has delivered and the Government has approved the updated FCIL IAW Attachment 1
PWS paragraph 3.6.5 and CDRL BX18.
4. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL
AX09.
5. The LVC has delivered and the Government has approved the updated integration and operations plan IAW Attachment 1 PWS paragraph 3.5.1.9.1 and CDRL BX16.
6. The LVC has delivered and the Government has approved the final LVT&VP IAW CDRL AX10.
1. CDRL BX11 first draft VPM accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL AX11 initial Flight Hardware Interface Checks accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL BX18 updated FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL AX09 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL BX16 updated Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL AX10 final LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
MILESTONE 5: Preliminary Coupled Loads Analysis (CLA) and Updated ADCL submission
Description:
1. Preliminary CLA. LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL BX10.
2. Updated ADCL. The LVC has delivered and Government has approved the updated ADCL IAW
CDRL AX09.
Success Criteria:
1. LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL BX10.
2. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL
AX09.
1. CDRL BX10 Mission Assurance Independent Data preliminary CLA data accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL AX09 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
MILESTONE 6: Final ADCL, Updated Baseline Mission ICD, Updated VPM, Final PL Integrations & Ops Plan, Final FCIL, ABCL, Initial Fleet Insight ABCL, Launch Service Provider SFW NRE Work Closure Plan Complete, Approved Secondary Objectives Do No Harm Analysis;
Initial, Submission for Rationale for All Class 1A Changes MDR completed, and Flight Hardware Interface Checks Complete; Test Facility Requirements Document
Description:
1. Final ADCL. LVC’s final ADCL delivered and Government has approved IAW CDRL
AX09.
2. Updated Baseline Mission ICD. LVC’s updated baseline mission ICD IAW CDRL BX09 has been approved by the Government.
3. Updated Verification Planning Matrix (VPM). LVC has submitted and the Government has approved the updated VPM IAW CDRL BX11.
4. Final PL Integration & Ops Plan. The LVC has delivered and the Government has approved the final Integration and Ops Plan IAW Attachment 1 PWS paragraph 3.5.1.9.1 and CDRL BX16.
CDRL AX12 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
5. Final FCIL. The LVC has delivered and the Government has approved the final FCIL IAW
CDRL BX18.
6. Approved Secondary Objectives Do No Harm Analysis. The LVC has delivered and the
Government has approved the Final Secondary Objectives Do No Harm Analysis IAW CDRL
BX26.
7. Initial ABCL. LVC’s initial ABCL delivered and Government has acknowledged receipt IAW
CDRL AX12.
8. Initial Fleet Insight ABCL. LVC’s initial ABCL delivered and Government has acknowledge receipt IAW CDRL AX13.
9. Launch Service Provider SFW NRE Work Closure Plan Complete. LVC’s launch service provider SFW NRE work is complete with Government-approved exceptions allowed and all action items have been closed with Government-approved exceptions allowed IAW the LVC’s Government-approved baseline SFW NRE work closure plan and schedule, CDRL BX20.
10. Rationale for All Class 1A Changes. LVC’s has submitted technical rationale for all Class 1A changes and approved by the Government IAW Attachment 1 PWS Section 3.2.4.
11. Flight Hardware Interface Tests. The LVC shall perform tests to verify the compatibility of the physical and electrical interfaces and clearances between the LV and PL IAW Attachment 1 PWS section 3.4.12 and CDRL AX11. The LVC shall perform mechanical fit-checks of the adapter harness to the standard electrical interface panel for each SV. The testing shall verify that all physical interfaces meet mission ICD requirements. These tests shall be performed, with Space Vehicle Contractor (SVC)/Launch System Integration Contractor (LSIC) support, to satisfy all applicable requirements in the ICD, contract Attachment 1 PWS, and CDRL AX11.
12. Test Facility Requirements Document. The LVC has delivered and the Government has approved the final Test Facility requirements document submission IAW CDRL CX01.
1. CDRL AX09 final ADCL submission received and approved by the Government.
2. CDRL BX09 updated ICD submission received and approved by the Government.
3. CDRL BX11 updated VPM submission received and approved by the Government.
4. CDRL BX16 final PL Integration & Ops Plan submission received and approved by the
Government.
5. CDRL BX18 final FCIL submission received and approved by the Government.
6. CDRL BX26 final Secondary Objectives Do No Harm Analysis submission received and approved by the Government
7. LVC has delivered and the Government has acknowledged receipt of the initial ABCL IAW
CDRL AX12.
8. LVC has delivered and the Government has acknowledged receipt of the initial Fleet Insight
ABCL IAW CDRL AX13.
9. CDRL BX20 baseline launch service provider SFW NRE Work Closure Plans submission received and approved by the Government.
10. Technical rationale for all Class 1A changes IAW Attachment 1 PWS Section 3.2.4 submission received and approved by the Government.
11. Flight hardware interface checks have been performed IAW Attachment 1 PWS section 3.4.12 and CDRL AX11.
a. CDRL AX11 second submission of as-run interface check procedures received and accepted by the Government.
12. LVC has delivered and the Government has acknowledged receipt of the final Test Facility requirements document submission IAW CDRL CX01.
1. CDRL AX09 final ADCL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
2. CDRL BX09 updated ICD submission accepted by the PCO, appropriate COR, or appropriate
COTR.
3. CDRL BX11 updated VPM submission accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL BX16 final PL Integration & Ops Plan submission accepted by the PCO, appropriate
COR, or appropriate COTR.
5. CDRL BX18 final FCIL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
6. CDRL BX26 final Secondary Objectives Do No Harm Analysis submission accepted by the PCO, appropriate COR, or appropriate COTR.
7. CDRL AX12 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
8. CDRL AX13 initial Fleet Insight ABCL submission accepted by the PCO, appropriate COR, or appropriate COTR.
9. CDRL BX20 submission accepted by the PCO, appropriate COR, or appropriate COTR.
10. Rationale submission accepted by the PCO, appropriate COR, or appropriate COTR.
11. CDRL AX11 Flight hardware interface checks submission accepted by the PCO, appropriate
COR, or appropriate COTR.
12. CDRL CX01 final Test Facility requirements document submission accepted by the PCO, MILESTONE 7: Launch Countdown Parameters and Operational Redline Limits, Mission Assurance Data, Updated ABCL, Updated ABCL, Updated Fleet Insight ABCL, and completion Mission Verification Review (MVR)
Description:
1. Launch countdown parameters and operational redline limits. LVC’s Launch countdown parameters and operational redline limits delivered, and Government has acknowledged receipt IAW Attachment 1 PWS Section 3.2.7.
2. Mission Assurance Data. LVC’s Mission Assurance Independent Assessment Data delivered, and Government has acknowledged receipt IAW CDRL BX10.
3. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL AX12.
4. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL AX13.
5. Completion MVR. LVC shall conduct MVR IAW Attachment 1 PWS Appendix H.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the Launch countdown parameters and operational redline limits baseline IAW Attachment 1 PWS Section 3.2.7.
2. The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance
Independent Assessment Data IAW CDRL BX10 to include: intermediate unguided Three Degrees of Freedom; Collision and Contamination Avoidance Maneuver memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.
3. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL AX12.
4. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL AX13.
5. The LVC has conducted the MVR IAW Attachment 1 PWS Appendix H, with actions and action closure plans identified and accepted by the Government.
Completion Evidence:
1. Written acknowledgement of receipt by the PCO, appropriate COR, or appropriate COTR of the launch countdown parameters and operational redline limits baseline.
2. CDRL BX10 Mission Assurance Independent Assessment Data accepted by the PCO, appropriate
COR, or appropriate COTR.
3. CDRL AX12 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL AX13 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
5. MVR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 8: Verification Evidence Record, Updated ABCL, Updated ABCL, Updated Fleet Insight, and Completion of Ground Operations Readiness Review (GORR)
Description:
1. Verification Evidence Record. LVC’s receipt of at least 30% of Verification Evidence Record delivered, and Government has acknowledged receipt IAW BX12.
2. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL AX12.
3. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL AX12.
4. Completion GORR. LVC shall conduct GORR IAW Attachment 1 PWS Appendix H.
1. The LVC has submitted and the Government has acknowledged receipt of at least 30% of the
Verification Evidence Record IAW CDRL BX12.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL AX12.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW
CDRL AX13.
4. The LVC has conducted the GORR IAW Attachment 1 PWS Appendix H, with actions and action closure plans identified and accepted by the Government.
1. At least 30% of the CDRL BX12 Verification Evidence Record accepted by the PCO, appropriate
COR, or appropriate COTR.
2. CDRL AX12 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL AX13 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
4. GORR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 9: Verification Evidence Record, Updated ABCL, Updated ABCL, Update Fleet Insight ABCL, Mission Assurance Data, Completion of Hardware Pre-Ship Review(s) and Independent Hardware Review(s), and completion of Component and Subsystem Readiness Review (CSRR)
Description:
1. Verification Evidence Record. LVC’s receipt of at least 60% of Verification Evidence Record delivered and Government has acknowledged receipt IAW BX12.
2. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL AX12.
3. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL AX13.
4. Mission Assurance Data. LVC’s Mission Assurance Data delivered and Government has acknowledged receipt IAW CDRL BX10 to include:
a. Controls tools input data
b. Controls analysis outputs (except pad/launch drift analysis)
c. Acoustics, shock, and vibration testing
d. Interface environments
5. The LVC shall conduct and complete pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW Attachment 1 PWS paragraph 3.6.6. These major launch vehicle elements shall include:
a. Core booster(s)
b. Upper stage
c. Payload fairing
d. Payload adapter, and
e. Solid rocket motors (as applicable)
6. CSRR. LVC’s shall conduct CSRR IAW Attachment 1 PWS Appendix H.
Success Criteria:
1. The LVC has submitted and the Government has acknowledged receipt of at least 60% the Verification Evidence Record IAW CDRL BX12.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL AX12.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW
CDRL AX13.
4. The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance
Data to IAW CDRL BX10 to include:
(1a) The LVC has submitted and the Government has acknowledged receipt of the controls tools input data (CDRL BX10).
(1b) The LVC has submitted and the Government has acknowledged receipt of the controls analysis outputs (except pad/launch drift analysis) (CDRL BX10).
(1c) The LVC has submitted and the Government has acknowledged receipt of the acoustics, shock, and vibration testing results (CDRL BX10).
(1d) The LVC has submitted and the Government has acknowledged receipt of the interface environments (CDRL BX10).
5. The LVC has delivered and the Government has acknowledged receipt of the pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW Attachment 1 PWS paragraph 3.6.6 to include:
(2a) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the core booster(s) IAW Attachment 1 PWS paragraph 3.6.6.1.
(2b) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the upper stage IAW Attachment 1 PWS paragraph 3.6.6.1.
(2c) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload fairing IAW Attachment 1 PWS paragraph 3.6.6.1.
(2d) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload adapter IAW Attachment 1 PWS paragraph 3.6.6.1.
(2e) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the solid rocket boosters (as applicable) IAW Attachment 1 PWS paragraph 3.6.6.1.
6. The LVC has conducted the CSRR IAW Attachment 1 PWS Appendix H with actions and action closure plans identified and accepted by the Government.
Completion Evidence:
1. At least 60% of CDRL BX12 Verification Evidence Record accepted by the PCO, appropriate
COR, or appropriate COTR.
2. CDRL AX12 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL AX13 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL BX10 Mission Assurance Data accepted by the PCO, appropriate COR, or appropriate
COTR.
5. Delivery of the Hardware Pre-Ship Review(s) and Independent Hardware Review(s) IAW
Attachment 1 PWS 3.6.5 and 3.6.6 accepted by the PCO, appropriate COR, or appropriate COTR.
(2a-e) Written acknowledgment by the Government that pre-ship reviews have been completed for the core booster(s), upper stage, payload fairing, payload adapter, and (as applicable) solid rocket booster(s) IAW Attachment 1 PWS paragraph 3.6.6.1.
6. CSRR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 10: Upper Stage Disposal, Final ABCL, Final ABCL, and Final Fleet Insight ABCL
Description:
1. The LVC shall identify which upper stage disposal method was planned and flown (random atmospheric reentry, controlled atmospheric reentry, maneuvering to a storage orbit, direct retrieval) IAW CDRL BX06.
2. The LVC shall provide telemetry data confirming the depletion of propellant by blowdown or depletion burn and the release compressed gases IAW CDRL BX06.
3. Upper Stage Disposal Approach: The LVC shall provide the following information appropriate to the selected method of disposal for the as-flown upper stage IAW CDRL BX06.
a. Random atmospheric reentry. Value for risk of human casualty, state vector for end of mission upper stage disposal orbit, disposal orbit lifetime for upper stage based on as-flown end of mission, description of analysis that produced the upper stage disposal orbit lifetime value.
b. Controlled atmospheric reentry. Latitude and longitude of upper stage reentry impact location and comparison to Notice to Airmen and Mariners (NOTAM) box.
c. Maneuvering to storage orbit. Orbital elements at end of mission for as flown upper stage.
d. Direct retrieval. Description of retrieval operation. Time after end of mission when upper stage will be removed.
4. Final ABCL. The LVC has delivered and Government has approved the final ABCL IAW CDRL
AX12.
5. Final Fleet Insight ABCL. The LVC has delivered and Government has approved the final ABCL
IAW CDRL AX13.
6. The Launch Service Order has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, Launch Service Acceptance Criteria (LSAC).
Success Criteria:
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL BX06.
The mission has not been deemed a “Mission Failure” IAW Attachment 1 PWS Appendix A and Attachment 4, LSAC.
2. Upper stage disposal method identified IAW CDRL BX06.
3. Telemetry data confirming the depletion of propellant by blowdown or depletion burn and the propellant and compressed gas depletion was performed on the upper stage prior to end of mission IAW CDRL BX06.
4. Upper Stage Disposal Approach:
a. Random atmospheric reentry.
i. Risk of human casualty is less than 1 in 10,000.
ii. Disposal orbit lifetime is no longer than 25 years.
b. Controlled atmospheric reentry. Impact location is within the NOTAM box.
c. Maneuvering to storage orbit. End of mission disposal orbit is within one of the storage orbit regimes described in the USG Orbital Debris Mitigation Standard Practices (4-1b).
d. Direct retrieval. Upper stage is removed within the time defined in Space Debris
Assessment Report for this mission.
5. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL
AX12.
6. The LVC has delivered and the Government has approved the updated Fleet ABCL IAW
CDRL AX13.
7. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-
04 and contract Attachment 4, LSAC.
1. Orbital Debris Compliance - CDRL BX06, Final Post Flight Assessment Report (to include post-mission disposal of the upper stage). This CDRL shall include the required items appearing in the description portion of this milestone.
2. CDRL BX06 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL BX06 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO,
4. CDRL AX12 final ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL AX13 final Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
6. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission Failure” IAW Attachment 1 PWS Appendix A and Attachment 4, LSAC.
PCO’s written notification to the LVC that the mission launched has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
MILESTONE 11: Mission Orbital Insertion Accuracy Verification Description:
1. The orbital insertion accuracy requirement is met IAW the appropriate ICD, CDRL BX09.
2. The LVC has delivered the Final Post Flight Assessment Report IAW CDRL BX06.
3. The Launch Service Order has been accepted by the Government IAW contract clause FAR
52.212-04 and contract Attachment 4, LSAC.
1. The orbital insertion accuracy requirement is met IAW the appropriate mission ICD, CDRL
BX09.
2. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL BX06.
The mission has not been deemed a “Mission Failure” Attachment 1 PWS Appendix A and Attachment 4, LSAC.
3. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
1. CDRL BX06 final submission accepted by the PCO, appropriate COR, or appropriate COTR.
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW Attachment 1 PWS Appendix A and Attachment 4, LSAC.
MILESTONE 12: Government Acceptance of Launch Service Description:
1. The LVC has delivered and Government has approved the Final Post Flight Assessment Report
IAW CDRL BX06.
2. The Launch Service Order has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Success Criteria:
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL BX06.
The mission has not been deemed a “Mission Failure” IAW Attachment 1 PWS Appendix A and Attachment 4, LSAC.
2. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
1. CDRL BX06 final submission accepted by the PCO, appropriate COR, or appropriate COTR.
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW Attachment 1 PWS Appendix A and Attachment 4, LSAC.
| MILESTONE 1: Initial Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary, Initial Draft Integrated Master Schedule (IMS), Initial Hazardous Materials Management Program (HMMP) Plan, Initial Payload (PL) Integration & Ops Plan, Initial Flig... |
| MILESTONE 2: First Submission ADCL, Approved IMS, and Launch Vehicle Familiarization (FAM) Course Materials Approval |
| MILESTONE 3: Preliminary Interface Control Document (ICD), Initial Launch Vehicle Test & Verification Plan (LVT&VP), Initial Systems Safety Program Plan (SSPP), Initial Compliance Document Tailoring, and Final Mission Integration Management Plan (MIM... |
| MILESTONE 4: Initial Verification Planning Matrix (VPM), Initial Flight Hardware Interface Checks, updated FCIL, updated ADCL, updated PL Integration & Ops Plan, and Final LVT&VP |
| MILESTONE 5: Preliminary Coupled Loads Analysis (CLA) and Updated ADCL submission |
| MILESTONE 6: Final ADCL, Updated Baseline Mission ICD, Updated VPM, Final PL Integrations & Ops Plan, Final FCIL, ABCL, Initial Fleet Insight ABCL, Launch Service Provider SFW NRE Work Closure Plan Complete, Approved Secondary Objectives Do No Harm A... |
| MILESTONE 7: Launch Countdown Parameters and Operational Redline Limits, Mission Assurance Data, Updated ABCL, Updated ABCL, Updated Fleet Insight ABCL, and completion Mission Verification Review (MVR) |
| MILESTONE 8: Verification Evidence Record, Updated ABCL, Updated ABCL, Updated Fleet Insight, and Completion of Ground Operations Readiness Review (GORR) |
| MILESTONE 9: Verification Evidence Record, Updated ABCL, Updated ABCL, Update Fleet Insight ABCL, Mission Assurance Data, Completion of Hardware Pre-Ship Review(s) and Independent Hardware Review(s), and completion of Component and Subsystem Readiness... |
| MILESTONE 10: Upper Stage Disposal, Final ABCL, Final ABCL, and Final Fleet Insight ABCL |
| MILESTONE 11: Mission Orbital Insertion Accuracy Verification |
| MILESTONE 12: Government Acceptance of Launch Service |
File details come from the government source that posted it.