Attachment 9: Payment Plan for AFSPC-12
FA8811-17-R-0004
03 May 2017
I. Basis of Payment The basis of payment for this effort shall be the successful accomplishment of event milestones scheduled for a Launch Service mission throughout the period of performance of any order issued under the contract. The milestones represent meaningful efforts or actions that are an integral and necessary part of order performance. The basis for an event should be either specifically described events or a measurable criterion of performance. Included within this Payment Plan is a description of what constitutes successful performance of each event. For purposes of establishing and calculating payment amounts, a percentage of the total contract price for all applicable firm fixed price (FFP) Contract Line Item Numbers
(CLINs) pertaining to the mission (5000 series CLINs) will be assigned to each milestone. The dollar amount associated with each milestone will be calculated based on the percentages assigned to each milestone. This contract is for the procurement of the AFSPC-12 mission only; therefore, requirements with specific National Reconnaissance Office (NRO)-only references are not applicable. NRO-only references appear in grey text.
A. Milestone Success Criteria and Completion Evidence
Each event milestone has associated measurable success criteria that serve to validate milestone accomplishment. All milestone success criteria must be met before the milestone payment will be authorized. When the Launch Vehicle Contractor (LVC) has successfully completed all applicable milestone success criteria, the LVC shall submit a written Notice of Completion (NOC) for the milestone to the Procurement Contracting Officer (PCO). The NOC shall include supporting documentation to substantiate meeting the milestone success criteria as provided in the completion evidence defined herein.
B. Event Milestone Payments and Event Timing
Completion of milestones and subsequent NOCs may be submitted non-successively (e.g., if milestone two is completed before milestone one, then the LVC may submit a NOC for milestone two before a
NOC for milestone one). Therefore, the NOC may be for multiple milestones. In the event the LVC completes a milestone ahead of the milestone completion date, the LVC may include that milestone in the monthly NOC and the Government will consider, on a case-by-case basis, the early payment of the milestone.
The PCO will determine whether or not the LVC has successfully met each of the milestone success criteria based on inputs provided by the United States Government (USG) Team (for Air Force missions) and the Mission Team (for NRO missions).
For Air Force missions, the USG Team consists of the Air Force Space and Missile Systems Center, Launch Systems Enterprise Directorate (SMC/LE), and Air Force Program Executive Officer for Space office personnel, but also includes The Aerospace Corporation, LE’s Systems Engineering and Integration
(SE&I) Contractor, LE’s Systems Engineering and Technical Assistance (SETA) support Contractors, the
NRO/Office of Space Launch (OSL) (as applicable), the SMC Independent Readiness Review Team, Defense Contract Management Agency, Defense Contract Audit Agency, 30th Space Wing (30 SW), 45th
Space Wing (45 SW), and other organizations as designated by the SMC/LE PCO.
For NRO missions, in addition to the USG Team listed above for Air Force missions, the Mission Team consists of the OSL Mission Manager, the OSL Contracting Officer Technical Representative (COTR), and their support personnel (to include Government, Aerospace Corporation, and SETA personnel). At their discretion, the OMM and COTR may solicit inputs from SMC/LE to assist in their determination of the LVC’s satisfactory completion of the milestone success criteria. Written concurrence from both the
OMM and COTR that the LVC has successfully met the milestone success criteria is required before the
PCO will authorize payment of the milestone.
To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC, the
PCO will provide written notification to the LVC specifying which milestones contained in the NOC are determined to be “met” (complete) and, if necessary, which are considered “not met” (incomplete). For milestones identified as incomplete, the PCO will: (1) specify in the notification the issue(s) that led to the determination based upon the milestone success criteria and completion evidence provided herein, and
(2) the corrective action(s) required to complete the milestone. The Government and LVC will ensure agreement and understanding of the corrective actions, and the LVC will make a good faith effort to quickly reconcile any incomplete milestones. When the LVC accomplishes the corrective actions, the
LVC will submit a NOC addendum to the PCO for Government review. To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC addendum, the PCO will provide a written notification to the LVC specifying whether the Government concurs that all corrective actions have been accomplished and the milestone has been “met” (completed).
For each milestone, the Estimated Completion Date is the estimated date that the LVC will complete the payment event and submit the associated NOC for payment of each milestone under this Plan. For each milestone, the value in the percentage “%” column of Table 1 indicates the percentage of the contract value of all applicable FFP CLINs (5000 series CLINs) that will be used to calculate the dollar amount to be paid to the LVC upon successful completion of the milestone. The Government reserves the right to withhold up to fifty percent (50%) of the total payment value for any unpaid milestone(s) in the event of a
Government-approved Class 1 change required for the launch service that is not implemented or completed to meet the Government’s approval by the implementation deadlines specified in and in accordance with (IAW) Performance Work Statement (PWS) section 3.2.4, Table 1.
C. Event Milestone Schedule
Criteria for payment of each event milestones appear in Table 1. In no event shall the LVC receive payments in excess of 80% of the total contract price until after acceptance of the launch service IAW
Milestone 14 (Government Acceptance of Launch Service IAW contract clause Federal Acquisition
Regulation [FAR] 52.212-04, Addendum to Contract Terms and Conditions—Commercial Items
[September 2013]). Given that defects in service for the last Milestone 14, Acceptance of Launch
Service, are not suitable for correction by re-performance, the Contracting Officer has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event of Milestone 14 defect (e.g., mission failure) is to reduce the contract price by the amount of the full Milestone 10, Upper
Stage Disposal, Final Initial As-Built Configuration List (ABCL), and Final Fleet Insight ABCL;
Milestone 11, Secondary Mission(s) On-orbit Delivery; Milestone 12, Primary Mission Orbital Insertion
Accuracy Verification; Milestone 13, Mass-to-Orbit Verification; and Milestone 14 payment, which appropriately reflects the reduced value of the services performed.
Table 1: Payment Event Schedule
Milestone
Payment Event Accomplishment Criteria
Est.
Comp.
Date
Total
Payment
(Dollar
Value)*
% of FFP
CLINs
Series
Initial Contractor Work
Breakdown Structure
(CWBS) and CWBS
Dictionary; Initial Draft
Integrated Master Schedule
(IMS); Initial Hazardous
Materials Management
Program (HMMP) Plan;
Initial Payload Integration &
Ops Plan; Initial Flight
Critical Items List (FCIL);
Launch Service Provider
Space Flight Worthiness of
Non-Recurring Engineering
(NRE) work closure schedule; Procurement initiated of Long lead hardware; and completed
Mission Kickoff Meeting
(KOM)
- First submission and Government acknowledgement of receipt of the following: Initial CWBS and CWBS
Dictionary in accordance with (IAW)
Contract Data Requirements List
(CDRL) A005; Initial Draft IMS IAW
CDRL A006; HMMP Plan IAW
CDRL B004; Initial Payload
Integration & Ops Plan IAW CDRL
B016; and Initial FCIL IAW CDRL
B018.
- Submission and Government approval of the baseline schedule for
NRE work closure IAW CDRL B020.
- Long lead hardware procurement or build initiated as required.
- KOM completed IAW Performance
Work Statement (PWS) Appendix H.
Authority to
Proceed
(ATP) +
1 Month
To Be
Filled In
By
Offeror
10%
Initial As-Designed
Configuration List (ADCL);
IMS; and Launch Vehicle
Familiarization Course
(FAM Course) training materials
- Submission and Government acknowledgement of receipt of the initial ADCL for the launch vehicle
IAW CDRL A009.
- Submission and Government approval of the IMS IAW CDRL
A006; and the FAM Course training materials IAW CDRL A007.
ATP + 2
Months
To Be
Filled In
By
Offeror
5%
Preliminary mission
Interface Control Document
(ICD); Initial Launch
Vehicle Test & Verification
Plan (LVT&VP); Initial
Systems Safety Program
Plan (SSPP); Initial compliance document tailoring submission; and
Final Mission Integration
Management Plan (MIMP)
- Submission and Government acknowledgement of receipt of the following: preliminary mission ICD
IAW CDRL B009; initial LVT&VP
IAW CDRL A010; initial SSPP IAW
CDRL B002; and initial compliance documents tailoring IAW CDRL
B005.
- Submission and Government approval of the final MIMP IAW
CDRL B008.
ATP + 3
Months
To Be
Filled In
By
Offeror
5%
Initial Verification Planning
Matrix (VPM); Initial Flight
Hardware Interface Checks;
Updated FCIL; Updated
ADCL; Updated Payload
- Submission and Government acknowledgement of receipt of initial
VPM IAW CDRL B011 and initial
Flight Hardware Interface Checks
IAW CDRL A011.
ATP + 6
Months
To Be
Filled In
By
Offeror
10%
Integration & Ops Plan; and
Final LVT&VP
- Submission and Government approval of the following: updated
FCIL IAW CDRL B018; updated
ADCL IAW CDRL A009; updated
Payload Integration & Operations
Plan IAW CDRL B016;
and final LVT&VP IAW CDRL
A010.
Preliminary Coupled Loads
Analysis (CLA); Updated
ADCL
- Submission and Government acknowledgement of receipt of preliminary CLA complete and delivery of results IAW CDRL B010.
- Submission and Government approval of the updated ADCL IAW
CDRL A009.
ATP + 8
Months
To Be
Filled In
By
Offeror 5%
Final ADCL; Baseline
Mission ICD; Updated
VPM; Final Payload
Integration & Ops Plan;
Final FCIL; ABCL; Initial
Fleet Insight ABCL;
Completion of all NRE
Work Closure Plan tasks;
Final Technical Rationale for all Class 1A changes
Mission Design Review
(MDR) Completed; and
Completed Flight Hardware
Interface Checks
- Submission and Government approval of the following: Final
ADCL IAW CDRL A009; updated baseline mission ICD IAW B009;
updated VPM IAW CDRL B011;
final Payload Integration & Ops Plan
IAW CDRL B016; final FCIL IAW
CDRL B018
- Submission and Government acknowledgment of receipt of the initial ABCL IAW CDRL A012.
- Submission and Government acknowledgement of receipt of the initial Fleet Insight ABCL IAW
CDRL A013.
- Evidence demonstrating the completion of all NRE Work Closure
Plan tasks IAW CDRL B020; and
- Final technical rationale for all
Class 1A changes IAW PWS Section
3.2.4.
- MDR completed IAW Appendix H.
- Flight Hardware Interface Checks completed IAW PWS Section 3.4.12.
Launch
(L) – 12
Months
To Be
Filled In
By
Offeror
20%
Launch countdown parameters and operational redline limits; Mission
Assurance Data; Updated
ABCL; Updated Fleet
Insight ABCL; and completion of the Mission
Verification Review (MVR)
- Submission and Government acknowledgement of receipt of the
Launch countdown parameters and operational redline limits baseline
IAW PWS Section 3.2.7; and, Mission Assurance Independent
Assessment Data IAW CDRL B010 to include: intermediate unguided
Three Degrees of Freedom; Collision and Contamination Avoidance
Maneuver memo; acoustics, shock, L – 6
Months
To Be
Filled In
By and vibration environments;
vibroacoustic modeling and analysis;
engineering drawings; and transportation environments.
- Submission and Government approval of the updated ABCL IAW
CDRL A012.
- Submission and Government approval of the updated ABCL IAW
CDRL A013.
- MVR completed IAW Appendix H.
Verification Evidence
Record; Updated ABCL;
Updated Fleet Insight
ABCL; Completion of
Ground Operations
Readiness Review (GORR)
- Submission and Government acknowledgement of receipt of at least 30% of Verification Evidence
Record IAW CDRL B012.
- Submission and Government approval of updated ABCL IAW
CDRL A012.
- Submission and Government approval of updated Fleet Insight
ABCL IAW CDRL A013.
- GORR completed IAW PWS
Appendix H.
L – 3
Months
To Be
Filled In
By
Offeror
5%
Verification Evidence
Record; Updated ABCL;
Updated Fleet Insight
ABCL; Mission Assurance
Data; Completion of
Hardware Pre-Ship
Review(s) and Independent
Hardware Review(s); and
Completion of Component and Subsystem Readiness
Review (CSRR)
- Submission and Government acknowledgement of receipt of at least 60% of Verification Evidence
Record IAW CDRL B012; Mission
Assurance Independent Assessment
Data IAW CDRL B010: controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environments.
- Submission and Government approval of the updated ABCL IAW
CDRL A012.
- Submission and Government approval of the updated Fleet Insight
ABCL IAW CDRL A013.
- Completion of major launch vehicle hardware pre-ship reviews and
Government independent hardware review(s) complete IAW PWS 3.6.6 and 3.6.5; respectively.
- Completion of CSRR IAW PWS
Appendix H.
L – 2
Months
To Be
Filled In
By
Offeror
10%
Upper Stage Disposal; Final
ABCL; and Final Fleet
Insight ABCL
- Submission and Government approval of compliance with upper stage disposal requirements.
L + 2
Months
To Be
Filled In
By
2.5%
- Submission and Government approval of final ABCL IAW CDRL
A012.
- Submission and Government approval of final ABCL IAW CDRL
A013.
Secondary Mission(s) On-orbit Delivery
- Government approval of the On-orbit delivery IAW the Secondary
Mission(s) On-Orbit Delivery Success
Criteria outlined in Milestone 11 in
Attachment 9, Payment Plan
L + 2
Months
To Be
Filled In
By
Offeror
2.5%
Primary Mission Orbital
Insertion Accuracy
Verification
- Submission and Government approval of final post-flight assessment report IAW CDRL B006;
and IAW the Success Criteria outlined in Milestone 12 in
Attachment 9, Payment Plan
L + 2
Months
To Be
Filled In
By
Offeror
2.5%
13 Mass-to-Orbit Verification
- Submission and Government approval of final post-flight assessment report IAW CDRL B006;
and IAW the Success Criteria outlined in Milestone 13 in
Attachment 9, Payment Plan
L + 2
Months
To Be
Filled In
By
Offeror
2.5%
Government Acceptance of
Launch Service approval of final post-flight assessment report IAW CDRL B006;
and Government approval of the launch (launch has not been deemed
“mission failure”) IAW Federal
Acquisition Regulation 52.212-04 and the Launch Service Acceptance
Criteria outlined in contract
Attachment 4.
L + 2
Months
To Be
Filled In
By
*The dollar amount for each milestone is to be filled in by the Offeror and is equal to the percentage listed in the last column multiplied by the value of the contract (5000 series CLINs) prior to award of each milestone. No adjustment to the payment will occur after milestone award.
MILESTONE 1: Initial Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary, Initial Draft Integrated Master Schedule (IMS), Initial Hazardous Materials
Management Program (HMMP) Plan, Initial Payload (PL) Integration & Ops
Plan, Initial Flight Critical Items List (FCIL), Approval of Non-Recurring
Engineering (NRE) work closure schedule, Procurement Initiated of Long Lead
Hardware, and Completed Mission Kickoff Meeting Description:
1. Initial CWBS and CWBS Dictionary. LVC’s initial CWBS and CWBS Dictionary delivered, and
Government has acknowledged receipt IAW CDRL A005.
2. Initial Draft IMS. LVC’s initial draft IMS delivered, and Government has acknowledged receipt
IAW CDRL A006.
3. HMMP Plan. LVC’s initial HMMP plan delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.1.15 and Contract Data Requirements List (CDRL) B004.
4. Initial Payload Integration and Ops Plan. LVC’s Initial PL Integration and Operations plan delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.5.1.9.1 and
CDRL B016.
5. Initial FCIL. LVC’s initial FCIL delivered, and the Government has acknowledged receipt IAW
PWS paragraph 3.6.5 and CDRL B018.
6. NRE Work Closure Schedule. LVC’s baseline launch service provider NRE work closure schedule and plan delivered and approved by the Government IAW CDRL B020.
7. Long Lead Hardware Procurement or Production Initiated. LVC has initiated procurement orders for or production of long lead hardware required for the mission.
8. Mission Kickoff Meeting. LVC has conducted the Kickoff Meeting (KOM) IAW PWS Appendix
H with actions and action closure plans and accepted by the Government.
Success Criteria:
1. The LVC has delivered and Government has acknowledged receipt of initial CWBS and CWBS
Dictionary IAW CDRL A005.
2. The LVC has delivered and Government has acknowledged receipt of initial draft IMS IAW
CDRL A006.
3. The LVC has delivered and Government has acknowledged receipt of initial HMMP IAW CDRL
B004.
4. The LVC has delivered and Government has acknowledged receipt of initial PL Integration and
Ops Plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.
5. The LVC has delivered and Government has acknowledged receipt of initial FCIL IAW PWS paragraph 3.6.5 and CDRL B018.
6. The LVC has delivered and Government has approved the baseline launch service provider Space
Flight Worthiness (SFW) NRE work closure schedule and plan IAW CDRL B020.
7. The LVC has initiated procurement orders for or production of long lead hardware required for the mission.
8. The LVC has conducted the KOM IAW PWS Appendix H with actions and action closure plans and the Government has accepted.
Completion Evidence:
1. CDRL A005 initial draft CWBS and CWBS Dictionary accepted by the PCO, appropriate
Contracting Officer Representative (COR), or appropriate Contracting Officer Technical
Representative (COTR).
2. CDRL A006 initial draft IMS accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL B004 initial draft HMMP plan accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL B016 initial draft PL Integration and Operations plan accepted by the PCO, appropriate
COR, or appropriate COTR.
5. CDRL B018 initial FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL B020 baseline launch service provider SFW NRE work closure plan and schedule accepted by the PCO, appropriate COR, or appropriate COTR.
7. Long lead hardware procurement or build initiated as required. Copies of signed, written procurement or build orders for all long lead hardware required for the mission received and accepted by the PCO, appropriate COR, or appropriate COTR.
8. KOM meeting minutes documenting meeting completion, action items, and action item closure plans.
MILESTONE 2: First Submission ADCL, Approved IMS, and Launch Vehicle Familiarization
(FAM) Course Materials Approval
Description:
1. ADCL. LVC’s initial ADCL delivered and Government has acknowledged receipt IAW CDRL
A009.
2. IMS. The LVC has delivered and the Government has approved the IMS IAW PWS paragraph
3.1.4 and CDRL A006.
3. Launch Vehicle FAM Course Materials. LVC’s LV familiarization training materials required by
CDRL A007 delivered and approved by the Government IAW PWS paragraph 3.1.10 and CDRL
A007.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the initial ADCL IAW
CDRL A009.
2. The LVC has delivered and the Government has approved the IMS IAW PWS paragraph 3.1.4 and CDRL A006.
3. The LVC has delivered and the Government has approved the submission of all LV familiarization training materials required by and IAW CDRL A007.
Completion Evidence:
1. CDRL A009 initial ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A006 IMS accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A007 submission of LV FAM Course training materials accepted by the PCO, appropriate
COR, or appropriate COTR.
MILESTONE 3: Preliminary Interface Control Document (ICD), Initial Launch Vehicle Test &
Verification Plan (LVT&VP), Initial Systems Safety Program Plan (SSPP), Initial Compliance Document Tailoring, and Final Mission Integration
Management Plan (MIMP) Contractor
Description:
1. ICD. LVC’s initial baseline mission ICD delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.4.4 and CDRL B009.
2. LVT&VP. LVC’s initial LVT&VP delivered, and the Government has acknowledged receipt
IAW CDRL A010.
3. SSPP. LVC’s first draft SSPP delivered, and the Government has acknowledged receipt IAW
PWS 3.1.7 and CDRL B002.
4. Compliance Document Tailoring. LVC’s initial compliance documents tailoring delivered, and the Government has acknowledged receipt CDRL B005.
5. MIMP. The LVC has delivered, and the Government has approved the final MIMP IAW CDRL
B008.
1. The LVC has delivered and the Government has acknowledged receipt of the initial, first draft baseline mission ICD IAW CDRL B009.
2. The LVC has delivered and the Government has acknowledged receipt of the initial LVT&VP
IAW CDRL A010.
3. The LVC has delivered and the Government has acknowledged receipt of the initial, first draft
SSPP IAW CDRL B002.
4. The LVC has delivered and the Government has acknowledged receipt of initial Compliance
Documents Tailoring IAW CDRL B005.
5. The LVC has delivered and the Government has approved the final MIMP IAW CDRL B008.
1. CDRL B009 initial, first draft baseline mission ICD accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A010 initial LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL B002 first draft SSPP accepted by the PCO, appropriate COR or appropriate COTR.
4. CDRL B005 initial Compliance Documents Tailoring accepted by the PCO, appropriate COR or appropriate COTR.
5. CDRL B008 final MIMP accepted by the PCO, appropriate COR or appropriate COTR.
MILESTONE 4: Initial Verification Planning Matrix (VPM), Initial Flight Hardware Interface
Checks, updated FCIL, updated ADCL, updated PL Integration & Ops Plan, and Final LVT&VP
Description:
1. VPM. LVC’s first draft VPM delivered, and the Government has acknowledged receipt IAW
CDRL B011.
2. Flight Hardware Interface Checks. LVC’s initial Flight Hardware Interface Checks delivered, and the Government has acknowledged receipt IAW CDRL A011.
3. FCIL. The LVC has delivered and the Government has approved the updated FCIL IAW PWS paragraph 3.6.5 and CDRL B018.
4. ADCL. The LVC has delivered and the Government has approved the updated ADCL IAW
CDRL A009.
5. PL Integration & Ops Plan. The LVC has delivered and the Government has approved the updated integration and operations plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.
6. LVT&VP. The LVC has delivered and the Government has approved the final LVT&VP IAW
CDRL A010.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the first draft VPM
IAW CDRL B011.
2. The LVC has delivered and the Government has acknowledged receipt of the initial Flight
Hardware Interface Checks IAW CDRL A011.
3. The LVC has delivered and the Government has approved the updated FCIL IAW PWS paragraph 3.6.5 and CDRL B018.
4. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.
5. The LVC has delivered and the Government has approved the updated integration and operations plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.
6. The LVC has delivered and the Government has approved the final LVT&VP IAW CDRL A010.
1. CDRL B011 first draft VPM accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A011 initial Flight Hardware Interface Checks accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL B018 updated FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL B016 updated Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL A010 final LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
MILESTONE 5: Preliminary Coupled Loads Analysis (CLA) and Updated ADCL submission
Description:
1. Preliminary CLA. LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL B010.
2. Updated ADCL. The LVC has delivered and Government has approved the updated ADCL IAW
CDRL A009.
Success Criteria:
1. LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL B010.
2. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.
1. CDRL B010 Mission Assurance Independent Data preliminary CLA data accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
MILESTONE 6: Updated ADCL, Updated Baseline Mission ICD, Updated VPM, Final PL
Integrations & Ops Plan, Final FCIL, Initial ABCL, Initial Fleet Insight ABCL, Launch Service Provider SFW NRE Work Closure Plan Complete, Submission for Rationale for All Class 1A Changes MDR completed, and Flight Hardware
Interface Checks Complete
Description:
1. Updated ADCL. LVC’s updated ADCL delivered and Government has approved IAW
CDRL A009.
2. Updated Baseline Mission ICD. LVC’s updated baseline mission ICD IAW CDRL B009 has been approved by the Government.
3. Updated Verification Planning Matrix (VPM). LVC has submitted and the Government has approved the updated VPM IAW CDRL B011.
4. Final PL Integration & Ops Plan. The LVC has delivered and the Government has approved the final Integration and Ops Plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016. CDRL A012 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate COTR.
5. Final FCIL. The LVC has delivered and the Government has approved the final FCIL IAW
CDRL B018.
6. Initial ABCL. LVC’s initial ABCL delivered and Government has acknowledged receipt IAW
CDRL A012.
7. Initial Fleet Insight ABCL. LVC’s initial ABCL delivered and Government has acknowledge receipt IAW CDRL A013.
8. Launch Service Provider SFW NRE Work Closure Plan Complete. LVC’s launch service provider SFW NRE work is complete with Government-approved exceptions allowed and all action items have been closed with Government-approved exceptions allowed IAW the LVC’s
Government-approved baseline SFW NRE work closure plan and schedule, CDRL B020.
9. Rationale for All Class 1A Changes. LVC’s has submitted technical rationale for all Class 1A changes and approved by the Government IAW PWS Section 3.2.4.
10. Flight Hardware Interface Tests. The LVC shall perform tests to verify the compatibility of the physical and electrical interfaces and clearances between the LV and PL IAW PWS section
3.4.12 and CDRL A011. The LVC shall perform mechanical fit-checks of the adapter harness to the standard electrical interface panel for each SV. The testing shall verify that all physical interfaces meet mission ICD requirements. These tests shall be performed, with Space Vehicle
Contractor (SVC)/Launch System Integration Contractor (LSIC) support, to satisfy all applicable requirements in the ICD, contract PWS, and CDRL A011.
1. CDRL A009 updated ADCL submission received and approved by the Government.
2. CDRL B009 updated ICD submission received and approved by the Government.
3. CDRL B011 updated VPM submission received and approved by the Government.
4. CDRL B016 final PL Integration & Ops Plan submission received and approved by the
Government.
5. CDRL B018 final FCIL submission received and approved by the Government.
6. LVC has delivered and the Government has acknowledged receipt of the initial ABCL IAW
CDRL A012.
7. LVC has delivered and the Government has acknowledged receipt of the initial Fleet Insight
ABCL IAW CDRL A013.
8. CDRL B020 baseline launch service provider SFW NRE Work Closure Plans submission received and approved by the Government.
9. Technical rationale for all Class 1A changes IAW PWS Section 3.2.4 submission received and approved by the Government.
10. Flight hardware interface checks have been performed IAW PWS section 3.4.12 and CDRL
A011.
a. CDRL A011 second submission of as-run interface check procedures received and accepted by the Government.
1. CDRL A009 updated ADCL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
2. CDRL B009 updated ICD submission accepted by the PCO, appropriate COR, or appropriate
COTR.
3. CDRL B011 updated VPM submission accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL B016 final PL Integration & Ops Plan submission accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL B018 final FCIL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
6. CDRL A012 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate
COTR.
7. CDRL A013 initial Fleet Insight ABCL submission accepted by the PCO, appropriate COR, or appropriate COTR.
8. CDRL B020 submission accepted by the PCO, appropriate COR, or appropriate COTR.
9. Rationale submission accepted by the PCO, appropriate COR, or appropriate COTR.
10. CDRL A011 Flight hardware interface checks submission accepted by the PCO, appropriate
MILESTONE 7: Launch Countdown Parameters and Operational Redline Limits, Mission
Assurance Data, Updated ADCL, Updated ABCL, Updated Fleet Insight ABCL, and completion Mission Verification Review (MVR)
Description:
1. Launch countdown parameters and operational redline limits. LVC’s Launch countdown parameters and operational redline limits delivered, and Government has acknowledged receipt
IAW PWS Section 3.2.7.
2. Mission Assurance Data. LVC’s Mission Assurance Independent Assessment Data delivered, and
Government has acknowledged receipt IAW CDRL B010.
3. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL A012.
4. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL A013.
5. Completion MVR. LVC shall conduct MVR IAW PWS Appendix H.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the Launch countdown parameters and operational redline limits baseline IAW PWS Section 3.2.7.
2. The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance
Independent Assessment Data IAW CDRL B010 to include: intermediate unguided Three
Degrees of Freedom; Collision and Contamination Avoidance Maneuver memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.
3. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.
4. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A013.
5. The LVC has conducted the MVR IAW PWS Appendix H, with actions and action closure plans identified and accepted by the Government.
1. Written acknowledgement of receipt by the PCO, appropriate COR, or appropriate COTR of the launch countdown parameters and operational redline limits baseline.
2. CDRL B010 Mission Assurance Independent Assessment Data accepted by the PCO, appropriate
COR, or appropriate COTR.
3. CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A013 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
5. MVR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 8: Verification Evidence Record, Updated ADCL, Updated ABCL, Updated Fleet
Insight, and Completion of Ground Operations Readiness Review (GORR)
Description:
1. Verification Evidence Record. LVC’s receipt of at least 30% of Verification Evidence Record delivered, and Government has acknowledged receipt IAW B012.
2. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL A012.
3. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL A012.
4. Completion GORR. LVC shall conduct GORR IAW PWS Appendix H.
1. The LVC has submitted and the Government has acknowledged receipt of at least 30% of the
Verification Evidence Record IAW CDRL B012.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW
CDRL A013.
4. The LVC has conducted the GORR IAW PWS Appendix H, with actions and action closure plans
1. At least 30% of the CDRL B012 Verification Evidence Record accepted by the PCO, appropriate
COR, or appropriate COTR.
2. CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A013 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
4. GORR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 9: Verification Evidence Record, Updated ADCL, Updated ABCL, Update Fleet
Insight ABCL, Mission Assurance Data, Completion of Hardware Pre-Ship
Review(s) and Independent Hardware Review(s), and completion of Component and Subsystem Readiness Review (CSRR)
Description:
1. Verification Evidence Record. LVC’s receipt of at least 60% of Verification Evidence Record delivered and Government has acknowledged receipt IAW B012.
2. Updated ABCL. The LVC has delivered and Government has approved the updated ABCL IAW
CDRL A012.
3. Updated Fleet Insight ABCL. The LVC has delivered and Government has approved the updated
ABCL IAW CDRL A013.
4. Mission Assurance Data. LVC’s Mission Assurance Data delivered and Government has acknowledged receipt IAW CDRL B010 to include:
a. Controls tools input data
b. Controls analysis outputs (except pad/launch drift analysis)
c. Acoustics, shock, and vibration testing
d. Interface environments
5. The LVC shall conduct and complete pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.6. These major launch vehicle elements shall include:
a. Core booster(s)
b. Upper stage
c. Payload fairing
d. Payload adapter, and
e. Solid rocket motors (as applicable)
6. CSRR. LVC’s shall conduct CSRR IAW PWS Appendix H.
Success Criteria:
1. The LVC has submitted and the Government has acknowledged receipt of at least 60% the
Verification Evidence Record IAW CDRL B012.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW
CDRL A013.
4. The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance
Data to IAW CDRL B010 to include:
(1a) The LVC has submitted and the Government has acknowledged receipt of the controls tools input data (CDRL B010).
(1b) The LVC has submitted and the Government has acknowledged receipt of the controls analysis outputs (except pad/launch drift analysis) (CDRL B010).
(1c) The LVC has submitted and the Government has acknowledged receipt of the acoustics, shock, and vibration testing results (CDRL B010).
(1d) The LVC has submitted and the Government has acknowledged receipt of the interface environments (CDRL B010).
5. The LVC has delivered and the Government has acknowledged receipt of the pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.6 to include:
(2a) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the core booster(s) IAW PWS paragraph 3.6.6.1.
(2b) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the upper stage IAW PWS paragraph 3.6.6.1.
(2c) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload fairing IAW PWS paragraph 3.6.6.1.
(2d) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload adapter IAW PWS paragraph 3.6.6.1.
(2e) The LVC has conducted and completed, and the Government has acknowledged completion in writing of a pre-ship review for the solid rocket boosters (as applicable) IAW PWS paragraph
3.6.6.1.
6. The LVC has conducted the CSRR IAW PWS Appendix H with actions and action closure plans identified and accepted by the Government.
Completion Evidence:
1. At least 60% of CDRL B012 Verification Evidence Record accepted by the PCO, appropriate
COR, or appropriate COTR.
2. CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A013 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
4. CDRL B010 Mission Assurance Data accepted by the PCO, appropriate COR, or appropriate
COTR.
5. Delivery of the Hardware Pre-Ship Review(s) and Independent Hardware Review(s) IAW PWS
3.6.5 and 3.6.6 accepted by the PCO, appropriate COR, or appropriate COTR. (2a-e) Written acknowledgment by the Government that pre-ship reviews have been completed for the core booster(s), upper stage, payload fairing, payload adapter, and (as applicable) solid rocket booster(s) IAW PWS paragraph 3.6.6.1.
6. CSRR meeting minutes documenting meeting completion, action items, and action item closure
MILESTONE 10: Upper Stage Disposal, Final ADCL, Final ABCL, and Final Fleet Insight ABCL
1. The LVC shall identify which upper stage disposal method was planned and flown (random atmospheric reentry, controlled atmospheric reentry, maneuvering to a storage orbit, direct retrieval) IAW CDRL B006.
2. The LVC shall provide telemetry data confirming the depletion of propellant by blowdown or depletion burn and the release compressed gases IAW CDRL B006.
3. Upper Stage Disposal Approach: The LVC shall provide the following information appropriate to the selected method of disposal for the as-flown upper stage IAW CDRL B006.
a. Random atmospheric reentry. Value for risk of human casualty, state vector for end of mission upper stage disposal orbit, disposal orbit lifetime for upper stage based on as-flown end of mission, description of analysis that produced the upper stage disposal orbit lifetime value.
b. Controlled atmospheric reentry. Latitude and longitude of upper stage reentry impact location and comparison to Notice to Airmen and Mariners (NOTAM) box.
c. Maneuvering to storage orbit. Orbital elements at end of mission for as flown upper stage.
d. Direct retrieval. Description of retrieval operation. Time after end of mission when upper stage will be removed.
4. Final ABCL. The LVC has delivered and Government has approved the final ABCL IAW CDRL
A012.
5. Final Fleet Insight ABCL. The LVC has delivered and Government has approved the final ABCL
IAW CDRL A013.
6. The Launch Service Order has been accepted by the Government IAW contract clause FAR
52.212-04 and contract Attachment 4, Launch Service Acceptance Criteria (LSAC).
Success Criteria:
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL B006.
The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
2. Upper stage disposal method identified IAW CDRL B006.
3. Telemetry data confirming the depletion of propellant by blowdown or depletion burn and the propellant and compressed gas depletion was performed on the upper stage prior to end of mission IAW CDRL B006.
4. Upper Stage Disposal Approach:
a. Random atmospheric reentry.
i. Risk of human casualty is less than 1 in 10,000.
ii. Disposal orbit lifetime is no longer than 25 years.
b. Controlled atmospheric reentry. Impact location is within the NOTAM box.
c. Maneuvering to storage orbit. End of mission disposal orbit is within one of the storage orbit regimes described in the USG Orbital Debris Mitigation Standard Practices (4-1b).
d. Direct retrieval. Upper stage is removed within the time defined in Space Debris
Assessment Report for this mission.
5. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL
A012.
6. The LVC has delivered and the Government has approved the updated Fleet ABCL IAW
CDRL A013.
7. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-
04 and contract Attachment 4, LSAC.
1. Orbital Debris Compliance - CDRL B006, Final Post Flight Assessment Report (to include post-mission disposal of the upper stage). This CDRL shall include the required items appearing in the description portion of this milestone.
2. CDRL B006 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL B006 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A012 final ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL A013 final Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate
COTR.
6. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
PCO’s written notification to the LVC that the mission launched has been accepted by the
Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
MILESTONE 11: Secondary Mission(s) On-orbit Delivery
1. The LVC has delivered the Final Post Flight Assessment Report IAW CDRL B006.
2. The secondary mission(s) on-orbit delivery has been accepted by the Government IAW the
Milestone 11 Success Criteria in Attachment 9, Payment Plan.
3. The Launch Service Order has been accepted by the Government IAW contract clause FAR
52.212-04 and contract Attachment 4, LSAC.
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL B006.
The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
2. The secondary missions(s) on-orbit delivery shall be determined by the SMC/LE Director to be acceptable if any of the conditions below are met.
a. The secondary mission(s) is/are placed into an orbit within the allowable dispersions, as defined in the appropriate ICD, from the target values as defined in the mission definition letter or Target Specification and the payload(s) has/have 100% operational utility.
Verification of insertion will be the responsibility of the Government.
b. The secondary mission(s) is placed into orbit, as defined in paragraph (2)a above; independent of the operational utility of the payload, the launch vehicle induced environments are not in excess of those specified in the ICD. Verification of launch vehicle environments to which the payload is exposed is the responsibility of the Contractor with confirmation by the
Government. For the purposes of ICD compliance, the booster-induced flight environments shall be considered satisfied where they are:
1) not in excess of the magnitude of the ICD level where the ICD level is defined as P99/90
(probability of 99%, with 90% confidence level), or;
2) not in excess of the magnitude of the ICD level +6 decibels where the ICD level is defined as P95/50 (probability of 95%, with 50% confidence). ICD violations unrelated to the payload functional failure shall not be considered herein as a material factor in mission success or failure.
c. The secondary mission(s) is/are placed into the orbit, as defined in paragraph (2)a above, and has zero operational utility, and at no fault of the Contractor the environmental data portion of the launch vehicle telemetry has not been obtained or has been obtained but is unreliable or unusable.
d. A mission failure is due to the improper issuance of destruct command by a Government
Agency. Improper issuance is defined as the Government Flight Termination System activation in error.
e. A mission failure is due to any secondary mission(s), Associate Contractor [Federally Funded
Research & Development Contractor, SETA, or SE&I] or Government agency related error.
f. A mission failure is due to inaccurate Government Furnished Data (inclusive of secondary mission[s] Contractor data) leading to an erroneous decision to launch, or the mission failure is determined to be a result of the inaccurate Government Furnished Data.
g. A mission failure is due to the failure of the secondary mission(s) to successfully issue a separation command (for those missions dependent upon the secondary mission(s) to initiate the separation event).
h. A mission failure where the Government overrode the Contractor’s “No-Go” decision and the mission failure is caused by the Contractor’s cited reason for the Contractor’s “No-Go” decision.
3. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
1. CDRL B006 final submission accepted by the PCO, appropriate COR, or appropriate COTR.
2. No written determination by the SMC/LE Director deeming the secondary mission(s) on-orbit delivery “unacceptable” IAW the Milestone 11 Success Criteria in Attachment 9, Payment Plan.
3. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
MILESTONE 12: Primary Mission Orbital Insertion Accuracy Verification
1. The orbital insertion accuracy requirement is met IAW the appropriate ICD, CDRL B009.
2. The LVC has delivered the Final Post Flight Assessment Report IAW CDRL B006.
1. The orbital insertion accuracy requirement is met IAW the appropriate mission ICD, CDRL
B009.
2. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL B006.
The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
MILESTONE 13: Mass-to-Orbit Verification
1. The Mass-to-Orbit requirement is met IAW the appropriate ICD, CDRL B009.
2. The LVC has delivered and Government has approved the Final Post Flight Assessment Report
IAW CDRL B006.
3. The secondary mission(s) on-orbit delivery has been accepted by the Government IAW the
Milestone 11 Success Criteria in Attachment 9, Payment Plan.
4. The Launch Service Order has been accepted by the Government IAW contract clause FAR
52.212-04 and contract Attachment 4, LSAC.
Success Criteria:
1. The Mass-to-Orbit requirement is met IAW the appropriate ICD, CDRL B009.
2. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL B006.
The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
3. The secondary mission(s) on-orbit delivery has been accepted by the Government IAW the
Milestone 11 Success Criteria in Attachment 9, Payment Plan.
4. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
MILESTONE 14: Government Acceptance of Launch Service
1. The LVC has delivered and Government has approved the Final Post Flight Assessment Report
IAW CDRL B006.
2. The Launch Service Order has been accepted by the Government IAW contract clause FAR
52.212-04 and contract Attachment 4, LSAC.
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment
Report IAW CDRL B006.
The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
2. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission
Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.
Attachment 9: Payment Plan for GPS III, AFSPC-8 and AFSPC-52
FA8811-17-R-0004
03 May 2017
I. Basis of Payment The basis of payment for this effort shall be the successful accomplishment of event milestones scheduled for a Launch Service mission throughout the period of performance of any order issued under the contract. The milestones represent meaningful efforts or actions that are an integral and necessary part of order performance. The basis for an event should be either specifically described events or a measurable criterion of performance. Included within this Payment Plan is a description of what constitutes successful performance of each event. For purposes of establishing and calculating payment amounts, a percentage of the total contract price for all applicable firm fixed price (FFP) Contract Line Item Numbers
(CLINs) pertaining to the mission (1000-4000 and 6000 series CLINs) will be assigned to each milestone.
The dollar amount associated with each milestone will be calculated based on the percentages assigned to each milestone. This contract is for the procurement of the GPS III missions, AFSPC-8 mission, and
AFSPC-52 mission only; therefore, requirements with specific National Reconnaissance Office (NRO)-only references are not applicable. NRO-only references appear in grey text.
A. Milestone Success Criteria and Completion Evidence
Each event milestone has associated measurable success criteria that serve to validate milestone accomplishment. All milestone success criteria must be met before the milestone payment will be authorized. When the Launch Vehicle Contractor (LVC) has successfully completed all applicable milestone success criteria, the LVC shall submit a written Notice of Completion (NOC) for the milestone to the Procurement Contracting Officer (PCO). The NOC shall include supporting documentation to substantiate meeting the milestone success criteria as provided in the completion evidence defined herein.
B. Event Milestone Payments and Event Timing
Completion of…