FA8773-10-R-0051 March ARB CA - Solicitation
751 KB Posted
- Solicitation number
- FA8773-10-R-0051
About this file
FA8773-10-R-0051 March ARB CA - Solicitation (Amendment)
Text of this file
CODE
(Hour)
PAGE(S)
until 03:00 PM local t ime 14 Oct 2010
X
A X B
C D
EX
X G F 106 - 112
113 - 128 X H 129 - 134
Jacqueline.West@tinker.af.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 134
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
FA8773 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 7 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
See Block 7 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
JACQUELINE K WEST 734-9731
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
1 - 2 3 - 54
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
55 - 59
60 - 66 X K REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 67 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 68 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
69 - 104
PART II - CO NTRACT CLAUSES
38 CEG/PK - FA8773
JACQUELINE K WEST
4079 HILLTOP RD
TINKER AFB OK 73145-2713 405-734-9731
405-734-9220FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
30 Aug 2010
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
FA8773-10-R-0051
Section A - Solicitation/Contract Form
CLAUSES INCORPORATED BY FULL TEXT
Section A Statements - Solicitation/Contract Form
A-1 The minimum guarantee for this contract is two months of the base year for Operation and Maintenance of the Base Telephone System (BTS).
A-2 The maximum value for this contract is the total value of the basic period and all exercised options, as modified.
A-3 The acceptance period in Block 12 on page one of the SF 33 must be 120 days or more. An amount less may cause your offer not to be accepted.
A-4 Page numbering. Depending on the printer and settings used, the “total number of pages” indicated on the SF33 may differ from that posted on FBO.gov.
A-5 Foreign participation is permitted only at the sub-contractor level for this contract.
A-6 If awarded a contract for this effort, the successful contractor agrees to the release of prices in response to Freedom of Information Act (FOIA) requests and for publication electronically to include, but not limited to, the Federal Business Opportunities Web site.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Months Operation & Maintenance (O&M), March ARB
FFP
Services non-personal: The contractor shall furnish all labor, tools, parts and incidentals necessary to provide operation and maintenance (O&M)for the Base Telecommunication System (BTS) in accordance with (IAW) contract terms and conditions.
FOB: Destination
NSN: D316-38-PKL-NMMI
SIGNAL CODE: A
NET AMT
0001AA 6 Months O&M,March ARB, BTS
FFP
O&M for the Base Telecommunication System (BTS) IAW contract terms and conditions.
FOB: Destination
NSN: D316-38-PKL-NMMP
0001AB 999 Months Additional Funding, O&M
FFP
Additional Funding for O&M of the systems identified in the PWS (BTS)IAW contract terms and conditions.
FOB: Destination
NSN: D316-38-PKL-NMMA
0002 Each
CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
NSN: D316-38-PKL-NRES
0003 Each Other Services, Additional
FFP
This SLIN provides additional funding for CLIN x003 SLINs specified within individual task or work order(s).
FOB: Destination
NSN: D316-38-PKL-NOSA
0003AA 75,000 Foot Cable Marking and Locating
FFP
The Contractor shall conduct cable marking and locating services IAW the terms and conditions of the contract. See also PWS Section 1.3.
FOB: Destination
NSN: D316-38-PKL-NOSM
0003AB 10 Each Maintenance Inspections, Manhole & Handhole
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
NSN: D316-38-PKL-NMHI
0003AC 10 Each Maintenance Inspections, Distribution Pedestals
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4 FOB: Destination
NSN: D316-38-PKL-NDPI
0003AD 10 Each Maintenance Inspections, Bldg. Entrance Terminal
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
NSN: D316-38-PKL-NBTI
0004 1 Lump Sum Purchase
FFP
Contractor shall purchase pre-priced material items (and applicable mounting hardware) identified by Product Identification (PID) number and "A" on Attachment 1, Pricing Table for work orders in accordance with the terms of this contract. See also the attached EIPS. Purchase prices include expenses associated with maintenance requirements described in the PWS for the remainder of the contract (including any exercised options). Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
NSN: D316-38-PKL-NPRC
0005 1 Lump Sum Installation
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide installation or services identified by PID number and "B" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract.
Installation prices shall include operation & maintenance expenses associated with requirements in Section 1 of the PWS for the remainder of the contract (including any exercised options). See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
NSN: D316-38-PKL-NINS
0006 1 Lump Sum Removal
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide removal of items identified by PID number and "C" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort.Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
NSN: D316-38-PKL-NREM
0007 1 Lump Sum Relocate
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide relocation of items identified by PID number and "D" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
NSN: D316-38-PKL-NREL
0008 1 Each
CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
0009 Lump Sum Special Projects, MARCH ARB, CA
FFP
Special Projects. Special projects are Firm Fixed Price (FFP) negotiated requirements when an effort is needed that is not covered by current line items on the contract. These are one-time efforts that are within the scope of the contract and will be accomplished IAW the terms and conditions of the contract including, but not limited to, PWS Section 1.5.
FOB: Destination
NSN: D316-38-PKL-NSPC
0009AA 999 Lump Sum Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
FOB: Destination
NSN: D316-38-PKL-NSPF
0010 1 Lump Sum Extension of Services Option, MARCH ARB
FFP
Extension of Service. Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Operation and Maintenance of the Base Telephone System services at MARCH ARB, CA IAW FAR Clause 52.217-8, Option to Extend Services.
FOB: Destination
NSN: D316-38-PKL-NEXT
0011 Lump Sum CDRL A001, Annual Contract Manpower Reporting
FFP
Provide data IAW DD Form 1423-1.
FOB: Destination
NSN: D316-38-PKL-NCDRL
0012 Lump Sum Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s). The contractor shall use this CLIN and/or it's associated SLINs (as applicable) to invoice monthly for completed work orders IAW the terms of the contract.
NSN: D316-38-PKL-NWOI
0012AA 999 Lump Sum Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s).
NSN: D316-38-PKL-NWOF
1001 Months OPTION Operation & Maintenance (O&M), March ARB
FFP
Services non-personal: The contractor shall furnish all labor, tools, parts and incidentals necessary to provide operation and maintenance (O&M)for the Base Telecommunication System (BTS) in accordance with (IAW) contract terms and conditions.
FOB: Destination
1001AA 12 Months OPTION O&M,March ARB, BTS
FFP
O&M for the Base Telecommunication System (BTS) IAW contract terms and conditions.
FOB: Destination
1001AB 999 Months OPTION Additional Funding, O&M
FFP
Additional Funding for O&M of the systems identified in the PWS (BTS)IAW contract terms and conditions.
FOB: Destination
1002 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
1003 Each OPTION Other Services, Additional
FFP
This SLIN provides additional funding for CLIN x003 SLINs specified within individual task or work order(s).
FOB: Destination
1003AA 75,000 Foot OPTION Cable Marking and Locating
FFP
The Contractor shall conduct cable marking and locating services IAW the terms and conditions of the contract. See also PWS Section 1.3.
FOB: Destination
1003AB 10 Each OPTION Maintenance Inspections, Manhole & Handhole
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
1003AC 10 Each OPTION Maintenance Inspections, Distribution Pedestals
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4 FOB: Destination
1003AD 10 Each OPTION Maintenance Inspections, Bldg. Entrance Terminal
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
1004 1 Lump Sum OPTION Purchase
FFP
Contractor shall purchase pre-priced material items (and applicable mounting hardware) identified by Product Identification (PID) number and "A" on Attachment 1, Pricing Table for work orders in accordance with the terms of this contract. See also the attached EIPS. Purchase prices include expenses associated with maintenance requirements described in the PWS for the remainder of the contract (including any exercised options). Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
1005 1 Lump Sum OPTION Installation
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide installation or services identified by PID number and "B" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract.
Installation prices shall include operation & maintenance expenses associated with requirements in Section 1 of the PWS for the remainder of the contract (including any exercised options). See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
1006 1 Lump Sum OPTION Removal
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide removal of items identified by PID number and "C" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort.Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
1007 1 Lump Sum OPTION Relocate
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide relocation of items identified by PID number and "D" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
1008 1 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
1009 Lump Sum OPTION Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
FOB: Destination
1009AA 999 Lump Sum Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
1010 1 Lump Sum OPTION Extension of Services Option, MARCH
FFP
Extension of Service. Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Operation and Maintenance of the Base Telephone System services at MARCH ARB, CA IAW FAR Clause 52.217-8, Option to Extend Services.
FOB: Destination
1011 Lump Sum OPTION CDRL A001, Annual Contract Manpower Reporting
FFP
Provide data IAW DD Form 1423-1.
FOB: Destination
1012 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s). The contractor shall use this CLIN and/or it's associated SLINs (as applicable) to invoice monthly for completed work orders IAW the terms of the contract.
1012AA 999 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s).
2001 Months OPTION Operation & Maintenance (O&M), March ARB
FFP
Services non-personal: The contractor shall furnish all labor, tools, parts and incidentals necessary to provide operation and maintenance (O&M)for the Base Telecommunication System (BTS) in accordance with (IAW) contract terms and conditions.
FOB: Destination
2001AA 12 Months OPTION O&M,March ARB, BTS
FFP
O&M for the Base Telecommunication System (BTS) IAW contract terms and conditions.
FOB: Destination
2001AB 999 Months OPTION Additional Funding, O&M
FFP
Additional Funding for O&M of the systems identified in the PWS (BTS)IAW contract terms and conditions.
FOB: Destination
2002 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
2003 Each OPTION Other Services, Additional
FFP
This SLIN provides additional funding for CLIN x003 SLINs specified within individual task or work order(s).
FOB: Destination
2003AA 75,000 Foot OPTION Cable Marking and Locating
FFP
The Contractor shall conduct cable marking and locating services IAW the terms and conditions of the contract. See also PWS Section 1.3.
FOB: Destination
2003AB 10 Each OPTION Maintenance Inspections, Manhole & Handhole
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
2003AC 10 Each OPTION Maintenance Inspections, Distribution Pedestals
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4 FOB: Destination
2003AD 10 Each OPTION Maintenance Inspections, Bldg. Entrance Terminal
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
2004 1 Lump Sum OPTION Purchase
FFP
Contractor shall purchase pre-priced material items (and applicable mounting hardware) identified by Product Identification (PID) number and "A" on Attachment 1, Pricing Table for work orders in accordance with the terms of this contract. See also the attached EIPS. Purchase prices include expenses associated with maintenance requirements described in the PWS for the remainder of the contract (including any exercised options). Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
2005 1 Lump Sum OPTION Installation
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide installation or services identified by PID number and "B" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract.
Installation prices shall include operation & maintenance expenses associated with requirements in Section 1 of the PWS for the remainder of the contract (including any exercised options). See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
2006 1 Lump Sum OPTION Removal
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide removal of items identified by PID number and "C" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort.Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
2007 1 Lump Sum OPTION Relocate
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide relocation of items identified by PID number and "D" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
2008 1 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
2009 Lump Sum OPTION Special Projects, MARCH ARB, CA
FFP
Special Projects. Special projects are Firm Fixed Price (FFP) negotiated requirements when an effort is needed that is not covered by current line items on the contract. These are one-time efforts that are within the scope of the contract and will be accomplished IAW the terms and conditions of the contract including, but not limited to, PWS Section 1.5.
FOB: Destination
2009AA 1 Lump Sum Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
2010 1 Lump Sum OPTION Extension of Services Option, MARCH ARB
FFP
Extension of Service. Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Operation and Maintenance of the Base Telephone System services at MARCH ARB, CA IAW FAR Clause 52.217-8, Option to Extend Services.
FOB: Destination
2011 Lump Sum OPTION CDRL A001, Annual Contract Manpower Reporting
FFP
Provide data IAW DD Form 1423-1.
FOB: Destination
2012 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s). The contractor shall use this CLIN and/or it's associated SLINs (as applicable) to invoice monthly for completed work orders IAW the terms of the contract.
2012AA 999 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s).
3001 Months OPTION Operation & Maintenance (O&M), March ARB
FFP
Services non-personal: The contractor shall furnish all labor, tools, parts and incidentals necessary to provide operation and maintenance (O&M)for the Base Telecommunication System (BTS) in accordance with (IAW) contract terms and conditions.
FOB: Destination
3001AA 12 Months OPTION O&M,March ARB, BTS
FFP
O&M for the Base Telecommunication System (BTS) IAW contract terms and conditions.
FOB: Destination
3001AB 999 Months OPTION Additional Funding, O&M
FFP
Additional Funding for O&M of the systems identified in the PWS (BTS)IAW contract terms and conditions.
FOB: Destination
3002 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
3003 Each OPTION Other Services, Additional
FFP
This SLIN provides additional funding for CLIN x003 SLINs specified within individual task or work order(s).
FOB: Destination
3003AA 75,000 Foot OPTION Cable Marking and Locating
FFP
The Contractor shall conduct cable marking and locating services IAW the terms and conditions of the contract. See also PWS Section 1.3.
FOB: Destination
3003AB 10 Each OPTION Maintenance Inspections, Manhole & Handhole
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
3003AC 10 Each OPTION Maintenance Inspections, Distribution Pedestals
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4 FOB: Destination
3003AD 10 Each OPTION Maintenance Inspections, Bldg. Entrance Terminal
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
3004 1 Lump Sum OPTION Purchase
FFP
Contractor shall purchase pre-priced material items (and applicable mounting hardware) identified by Product Identification (PID) number and "A" on Attachment 1, Pricing Table for work orders in accordance with the terms of this contract. See also the attached EIPS. Purchase prices include expenses associated with maintenance requirements described in the PWS for the remainder of the contract (including any exercised options). Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
3005 1 Lump Sum OPTION Installation
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide installation or services identified by PID number and "B" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract.
Installation prices shall include operation & maintenance expenses associated with requirements in Section 1 of the PWS for the remainder of the contract (including any exercised options). See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
3006 1 Lump Sum OPTION Removal
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide removal of items identified by PID number and "C" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort.Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
3007 1 Lump Sum OPTION Relocate
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide relocation of items identified by PID number and "D" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
3008 1 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
3009 Lump Sum OPTION Special Projects, MARCH ARB, CA
FFP
Special Projects. Special projects are Firm Fixed Price (FFP) negotiated requirements when an effort is needed that is not covered by current line items on the contract. These are one-time efforts that are within the scope of the contract and will be accomplished IAW the terms and conditions of the contract including, but not limited to, PWS Section 1.5.
FOB: Destination
3009AA 1 Lump Sum Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
3010 1 Lump Sum OPTION Extension of Services Option, MARCH ARB
FFP
Extension of Service. Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Operation and Maintenance of the Base Telephone System services at MARCH ARB, CA IAW FAR Clause 52.217-8, Option to Extend Services.
FOB: Destination
3011 Lump Sum OPTION CDRL A001, Annual Contract Manpower Reporting
FFP
Provide data IAW DD Form 1423-1.
FOB: Destination
3012 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s). The contractor shall use this CLIN and/or it's associated SLINs (as applicable) to invoice monthly for completed work orders IAW the terms of the contract.
3012AA 999 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s).
4001 Months OPTION Operation & Maintenance (O&M), March ARB
FFP
Services non-personal: The contractor shall furnish all labor, tools, parts and incidentals necessary to provide operation and maintenance (O&M)for the Base Telecommunication System (BTS) in accordance with (IAW) contract terms and conditions.
FOB: Destination
4001AA 12 Months OPTION O&M,March ARB, BTS
FFP
O&M for the Base Telecommunication System (BTS) IAW contract terms and conditions.
FOB: Destination
4001AB 999 Months OPTION Additional Funding, O&M
FFP
Additional Funding for O&M of the systems identified in the PWS (BTS)IAW contract terms and conditions.
FOB: Destination
4002 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
4003 Each OPTION Other Services, Additional
FFP
This SLIN provides additional funding for CLIN x003 SLINs specified within individual task or work order(s).
FOB: Destination
4003AA 75,000 Foot OPTION Cable Marking and Locating
FFP
The Contractor shall conduct cable marking and locating services IAW the terms and conditions of the contract. See also PWS Section 1.3.
FOB: Destination
4003AB 10 Each OPTION Maintenance Inspections, Manhole & Handhole
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
4003AC 10 Each OPTION Maintenance Inspections, Distribution Pedestals
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4 FOB: Destination
4003AD 10 Each OPTION Maintenance Inspections, Bldg. Entrance Terminal
FFP
The Contractor shall conduct Inspections IAW the terms and conditions of the contract. See PWS Section 1.4.
FOB: Destination
4004 1 Lump Sum OPTION Purchase
FFP
Contractor shall purchase pre-priced material items (and applicable mounting hardware) identified by Product Identification (PID) number and "A" on Attachment 1, Pricing Table for work orders in accordance with the terms of this contract. See also the attached EIPS. Purchase prices include expenses associated with maintenance requirements described in the PWS for the remainder of the contract (including any exercised options). Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
4005 1 Lump Sum OPTION Installation
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide installation or services identified by PID number and "B" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract.
Installation prices shall include operation & maintenance expenses associated with requirements in Section 1 of the PWS for the remainder of the contract (including any exercised options). See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
4006 1 Lump Sum OPTION Removal
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide removal of items identified by PID number and "C" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS.
Certain aspects of this work may be subject to the Davis Bacon Act (DBA).
Individual work orders subject to the DBA shall be annotated by the contractor IAW the PWS. PID item pricing reflects the appropriate labor law applicable to the specified effort.Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
4007 1 Lump Sum OPTION Relocate
FFP
Contractor shall provide all labor, tools, parts and incidentals necessary to provide relocation of items identified by PID number and "D" on Attachment 1, Pricing Table to accomplish work orders in accordance with the terms of this contract. See also the attached EIPS. Contractor shall use pre-priced (PID) items to the maximum extent.
FOB: Destination
4008 1 Each
OPTION CLIN RESERVED
FFP
This CLIN is not used for this requirement.
FOB: Destination
4009 Lump Sum OPTION Special Projects, MARCH ARB, CA
FFP
Special Projects. Special projects are Firm Fixed Price (FFP) negotiated requirements when an effort is needed that is not covered by current line items on the contract. These are one-time efforts that are within the scope of the contract and will be accomplished IAW the terms and conditions of the contract including, but not limited to, PWS Section 1.5.
FOB: Destination
4009AA 1 Lump Sum Funding for Special Projects
FFP
This CLIN provides funding for special projects accomplished using CLIN X009 on individual task or work order(s).
4010 1 Lump Sum OPTION Extension of Services Option, MARCH ARB
FFP
Extension of Service. Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Operation and Maintenance of the Base Telephone System services at MARCH ARB, CA IAW FAR Clause 52.217-8, Option to Extend Services.
FOB: Destination
4011 Lump Sum OPTION CDRL A001, Annual Contract Manpower Reporting
FFP
Provide data IAW DD Form 1423-1.
FOB: Destination
4012 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s). The contractor shall use this CLIN and/or it's associated SLINs (as applicable) to invoice monthly for completed work orders IAW the terms of the contract.
4012AA 999 Lump Sum OPTION Funding for Work Orders
FFP
This CLIN provides funding for work orders accomplished using CLINs/SLINs X003 through X008 on individual task or work order(s).
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0001AA Destination Government Destination Government 0001AB Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0003AA Destination Government Destination Government 0003AB Destination Government Destination Government 0003AC Destination Government Destination Government 0003AD Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0009AA Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government 0012 Destination Government Destination Government 0012AA Destination Government Destination Government 1001 Destination Government Destination Government 1001AA Destination Government Destination Government 1001AB Destination Government Destination Government 1002 Destination Government Destination Government 1003 Destination Government Destination Government 1003AA Destination Government Destination Government 1003AB Destination Government Destination Government 1003AC Destination Government Destination Government 1003AD Destination Government Destination Government 1004 Destination Government Destination Government 1005 Destination Government Destination Government 1006 Destination Government Destination Government 1007 Destination Government Destination Government 1008 Destination Government Destination Government 1009 Destination Government Destination Government 1009AA Destination Government Destination Government 1010 Destination Government Destination Government 1011 Destination Government Destination Government 1012 Destination Government Destination Government 1012AA Destination Government Destination Government 2001 Destination Government Destination Government 2001AA Destination Government Destination Government
2001AB Destination Government Destination Government 2002 Destination Government Destination Government 2003 Destination Government Destination Government 2003AA Destination Government Destination Government 2003AB Destination Government Destination Government 2003AC Destination Government Destination Government 2003AD Destination Government Destination Government 2004 Destination Government Destination Government 2005 Destination Government Destination Government 2006 Destination Government Destination Government 2007 Destination Government Destination Government 2008 Destination Government Destination Government 2009 Destination Government Destination Government 2009AA Destination Government Destination Government 2010 Destination Government Destination Government 2011 Destination Government Destination Government 2012 Destination Government Destination Government 2012AA Destination Government Destination Government 3001 Destination Government Destination Government 3001AA Destination Government Destination Government 3001AB Destination Government Destination Government 3002 Destination Government Destination Government 3003 Destination Government Destination Government 3003AA Destination Government Destination Government 3003AB Destination Government Destination Government 3003AC Destination Government Destination Government 3003AD Destination Government Destination Government 3004 Destination Government Destination Government 3005 Destination Government Destination Government 3006 Destination Government Destination Government 3007 Destination Government Destination Government 3008 Destination Government Destination Government 3009 Destination Government Destination Government 3009AA Destination Government Destination Government 3010 Destination Government Destination Government 3011 Destination Government Destination Government 3012 Destination Government Destination Government 3012AA Destination Government Destination Government 4001 Destination Government Destination Government 4001AA Destination Government Destination Government 4001AB Destination Government Destination Government 4002 Destination Government Destination Government 4003 Destination Government Destination Government 4003AA Destination Government Destination Government 4003AB Destination Government Destination Government 4003AC Destination Government Destination Government 4003AD Destination Government Destination Government 4004 Destination Government Destination Government 4005 Destination Government Destination Government 4006 Destination Government Destination Government 4007 Destination Government Destination Government 4008 Destination Government Destination Government 4009 Destination Government Destination Government 4009AA Destination Government Destination Government
4010 Destination Government Destination Government 4011 Destination Government Destination Government 4012 Destination Government Destination Government 4012AA Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-16 Responsibility For Supplies APR 1984
52.246-4 INSPECTION OF SERVICES--FIXED-PRICE (AUG 1996)
(a) Definitions. "Services," as used in this clause, includes services performed, workmanship, and material furnished or utilized in the performance of services.
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering the services under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the Government during contract performance and for as long afterwards as the contract requires.
(c) The Government has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections and tests in a manner that will not unduly delay the work.
(d) If the Government performs inspections or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.
(e) If any of the services do not conform with contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by reperformance, the Government may (1) require the Contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.
(f) If the Contractor fails to promptly perform the services again or to take the necessary action to ensure future performance in conformity with contract requirements, the Government may (1) by contract or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that is directly related to the performance of such service or (2) terminate the contract for default.
(End of clause)
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 POP 01-APR-2011 TO
30-SEP-2011
N/A N/A
0001AA POP 01-APR-2011 TO
30-SEP-2011
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
F5F3CS
0001AB POP 01-APR-2011 TO
N/A (SAME AS PREVIOUS LOCATION)
0002 POP 01-APR-2011 TO
0003 POP 01-APR-2011 TO
0003AA POP 01-APR-2011 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
0003AB POP 01-APR-2011 TO
N/A (SAME AS PREVIOUS LOCATION)
0003AC POP 01-APR-2011 TO
N/A (SAME AS PREVIOUS LOCATION)
0003AD POP 01-APR-2011 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 01-APR-2011 TO
0005 POP 01-APR-2011 TO
0006 POP 01-APR-2011 TO
0007 POP 01-APR-2011 TO
0008 POP 01-APR-2011 TO
0009 POP 01-APR-2011 TO
0009AA POP 01-APR-2011 TO
0010 POP 01-APR-2011 TO
0011 POP 01-APR-2011 TO
0012 POP 01-APR-2011 TO
0012AA POP 01-APR-2011 TO
1001 POP 01-OCT-2011 TO
30-SEP-2012
1001AA POP 01-OCT-2011 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
1001AB POP 01-OCT-2011 TO
N/A (SAME AS PREVIOUS LOCATION)
1002 POP 01-OCT-2011 TO
1003 POP 01-OCT-2011 TO
1003AA POP 01-OCT-2011 TO
1003AB POP 01-OCT-2011 TO
1003AC POP 01-OCT-2011 TO
1003AD POP 01-OCT-2011 TO
1004 POP 01-OCT-2011 TO
1005 POP 01-OCT-2011 TO
1006 POP 01-OCT-2011 TO
1007 POP 01-OCT-2011 TO
1008 POP 01-OCT-2011 TO
1009 POP 01-OCT-2011 TO
1009AA POP 01-OCT-2011 TO
1010 POP 01-OCT-2011 TO
1011 POP 01-OCT-2011 TO
1012 POP 01-OCT-2011 TO
1012AA POP 01-OCT-2011 TO
2001 POP 01-OCT-2012 TO
30-SEP-2013
2001AA POP 01-OCT-2012 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
2001AB POP 01-OCT-2012 TO
N/A (SAME AS PREVIOUS LOCATION)
2002 POP 01-OCT-2012 TO
2003 POP 01-OCT-2012 TO
2003AA POP 01-OCT-2012 TO
2003AB POP 01-OCT-2012 TO
2003AC POP 01-OCT-2012 TO
2003AD POP 01-OCT-2012 TO
2004 POP 01-OCT-2012 TO
2005 POP 01-OCT-2012 TO
2006 POP 01-OCT-2012 TO
2007 POP 01-OCT-2012 TO
2008 POP 01-OCT-2012 TO
2009 POP 01-OCT-2012 TO
2009AA POP 01-OCT-2012 TO
2010 POP 01-OCT-2012 TO
2011 POP 01-OCT-2012 TO
2012 POP 01-OCT-2012 TO
2012AA POP 01-OCT-2012 TO
3001 POP 01-OCT-2013 TO
30-SEP-2014
3001AA POP 01-OCT-2013 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
3001AB POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3002 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3003 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3003AA POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3003AB POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3003AC POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3003AD POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3004 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3005 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3006 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3007 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3008 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3009 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3009AA POP 01-OCT-2013 TO
3010 POP 01-OCT-2013 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
3011 POP 01-OCT-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
3012 POP 01-OCT-2013 TO
3012AA POP 01-OCT-2013 TO
4001 POP 01-OCT-2014 TO
30-SEP-2015
4001AA POP 01-OCT-2014 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
4001AB POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4002 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4003 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4003AA POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4003AB POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4003AC POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4003AD POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4004 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4005 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4006 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4007 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4008 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4009 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4009AA POP 01-OCT-2014 TO
4010 POP 01-OCT-2014 TO
N/A 452 CS/SC - F5F3CS
670 MEYER DR BLDG 2404
MARCH ARB CA 92518-2166
4011 POP 01-OCT-2014 TO
N/A (SAME AS PREVIOUS LOCATION)
4012 POP 01-OCT-2014 TO
4012AA POP 01-OCT-2014 TO
52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984
Section G - Contract Administration Data
G-1 Remittance Address. If the remittance address is different from the mailing address, enter the remittance address below. Failure to provide this information may impact payment.
G-2 Invoice Address. Submit invoices for certification to the following address: Contact QAP for invoice address.
G-3 Accounting and Appropriation data will be set forth on individual Task Orders issued hereunder.
G-4 Payment by Government Purchase Card (GPC). For payments made by GPC, reference clause 52.232-46, paragraph (f). After certification of invoice(s), the QAP will provide the Contractor with the GPC information for billing.
This is the start of the file's text. The full file is on GovTribe.
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .