GRISSOM ARB Q A.docx

DOCX document 21 KB Posted

Attached to
Operations and Maintenance of the Base Telecommunications System (BTS) at GRISSOM ARB IN
Solicitation number
FA8773-10-R-0050
Issued by

About this file

Grissom ARB Question and Answers (Q A)

View the file

Other files

File Type Posted
Attch 5 SCA WD Rev 11.pdf PDF
Attch 2 PWS .pdf PDF
Attch 6 CDRL A0001 -.pdf PDF
CO Signature Page FA8773-11-D-0002.pdf PDF
Attachment 1 - Pricing Table.pdf PDF
KTR Signature Page.pdf PDF
FA8773-11-D-0002.pdf PDF
Attch 3 EIPS Final 30 JUL 2010.pdf PDF
Attch 5 DBA .pdf PDF
Attch 5 DBA .pdf PDF
Attch 3 EIPS Final 30 JUL 2010.docx DOCX document
Attachment 1 - Pricing Table.pdf PDF
Attch 2 PWS .docx DOCX document
Attch 6 CDRL A0001 -.pdf PDF
Contract.pdf PDF
Attch 4 SCA .pdf PDF
FBO Amendment 0005.pdf PDF
Solicitation Amendment FA8773-10-R-0050.pdf PDF
J A 1 month extension.pdf PDF
Amendment 0003 Comformed Copy.pdf PDF
Attachment 1 - Pricing Table Amendment 0003 dated 102210.xls XLS spreadsheet
Amendment 0003.pdf PDF
pre-proposal sign sheet.pdf PDF
Attch 1- Pricing Table Amendment 0002 dated 10062010.xls XLS spreadsheet
pre-proposal talking points 10 07 10.pdf PDF
Amendment 0002.pdf PDF
Preproposal Conf Slides.pdf PDF
Conform Copy Solicitation .pdf PDF
Attch 3 EIPS Final 30 JUL 2010-Amendment 01.pdf PDF
Solicitation Amendment 0001.pdf PDF
Attch 1- Pricing Table Amendment 01.xls XLS spreadsheet
FA8773-05-D-0001 GRISSOM ARB IN.pdf PDF
Current Pricing Table.pdf PDF
Attch 4 SCA .pdf PDF
Attch 5 DBA .pdf PDF
FA8773-10-R-0050 GRISSOM ARB IN.pdf PDF
Attch 2 PWS .pdf PDF
Attch 1- Pricing Table.xls XLS spreadsheet
Attch 7 - Performance Plan.pdf PDF
Attch 3 EIPS .pdf PDF
Attch 6 CDRL A0001 -.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Grissom ARB, IN FA8773-10-R-0050 Solicitation Q&A

PWS (QUESTIONS)
ANSWERS
GENERAL QUESTIONS
ANSWERS

1. What portion of the contract employees will be required to have a final DOD Security Clearance?

In order to obtain a CAC card, the contractor must have a favorable NACI. This is accomplished as stated in the solicitation, before they are allowed access to controlled areas, network and base access.
1. What records management system will be used?

Microsoft Excel Database.

2. Section 1.3.16.2 – Does the base use the Telecommunications Management System (Netplus) or, as 1.3.16.12 states, “MS Office is the TMS system used at the base.”
No, the TMS system is not used at this location, a locally developed database is used (Access).
2. Will access to automated government work order generation and reporting system be available to the contractor?

Yes, after contract award.

3. Section 1.3.16.3 – Does the base use Remedy?

Yes.
3. Where is the contractor lay down/storage area located?

At the north end of the DCO, Building 427.

4. Section 1.3.16.6.1 – When does the Air Force expect to launch the Cyberspace Infrastructure Planning System, Visualization Component (CVC)?

CVC is already operational. It can be accessed through any .mil network.
4. Please identify all LMR locations (base stations, remotes).

LMR does not apply to this procurement.

5. Section 1.3.16.6.2 – It is unclear how much Outside Plant Legacy information would need to be transferred to CVC, could you please clarify?

All data has been transferred. There is still more recent work to be added which should be complete by calendar EOY.
5. Where is the BTS manager’s office located?

In the DCO.

6. Section 1.3.16.6.3 – Even though CVC is not currently designed to store Inside Plant information shall we assume it may have that capability during the term of this contract?

It is currently expected that the Inside Plant portion of CVC will be available around Jan 2010.
6. Where do the contractor personnel operate from?

The DCO.

7. Section 1.3.16.6.3 – How much Inside Plant Legacy information would need to be transferred to CVC?

None.
7. Is VOIP active on the base?

No, not at this time.

8. Section 1.3.16.6.3 - This section references maintaining Inside Plant Drawing records in the “locally approved format.” What is that format?

No, Inside Plant drawings are maintained at this time.
8. Product ID 3301 – Non Metallic Raceway Is there a particular size that should be priced?

Generic Non-Metallic Single Channel surface Raceway.

9. Product ID 3344 thru 3355 – Fiber Cables for Inside Structure Installation

a) Should these cables be priced as PVC or plenum Rated?

b) Should the MM fiber be 62.5 or 50 micron?

a) Plenum rated.

b) For new installs I would recommend 50 microns. For runs that interface with existing 62.5 use 62.5 microns.

10. How does a company do 4 years worth of ISP/OSP work for $1.7M? This solicitation has the appearance of favoritism for an incumbent and seems the contracting office is trying to scare away competitors with a lowball price. We do ISP/OSP for the military and I know for a fact that 4 years will far exceed the $1.7M threshold. Please put out an amendment immediately and push the due date out 30 days so you can get competition. We will protest unless the solicitation is amended to be reasonable.

The current Contract and Schedule B Pricing Table was made public for REFERENCE only, after receiving numerous requests under the Freedom of Information Act (FOIA). Pursuant to FAR Subpart 5.303 and the contract terms and conditions, the information was determined releasable. It is an Offeror’s Business Decision as to how they utilize the information requested; it is not a condition or threshold established by contracting for the requirement defined in the Solicitation.

The allegation that the contracting office is trying to “scare away” competition is unwarranted; it is noted, that extensive Market Research was accomplished to ensure competition existed during Acquisition Planning phase. Moreover, in accordance with the Competition In Contracting Act (CICA) and the Source Selection Method utilized, competition is highly encouraged for the subject procurement.

Likewise, the allegation that the solicitation has “the appearance of “favoritism” is unwarranted. Specifically, the Source Selection Method for this procurement in conjunction with the release of information regarding the current contractors pricing and contract promotes transparency and fairness.

If an offeror utilizes the current contract and pricing for purposes for which is was not intended, that is a Corporate Business Decision that lacks prudent business judgment and could very well render an offerors proposal unreasonable, incomplete and unbalanced.

It is noted the questions addressed in this form nor the administrative changes made to the Solicitation and attachment(s), did not cause a substantive change in said documents. As such, the proposal due date remains unchanged.

File details come from the government source that posted it. Updated .