About this file
This document is a Single Source Justification (Simplified Acquisition) for a federal contract opportunity.
The key details are:
The Department of the Air Force Materiel Command Research Laboratory (Air Force Research Laboratory) awarded contract FA875124P0060 to Quantum Coax LLC for $48,244.64 on 2024-09-26 for Flexible Superconducting Coaxial Cables. The justification states that the Government determined only a single source, Quantum Coax LLC, was reasonably available to provide the required capabilities. The Government attempted market research but the only other potential vendor, who was contacted, indicated they would be unable to submit a capability statement for at least a few more days and no longer wished to pursue the opportunity. The document outlines steps the Government will take in the future to identify opportunities to maximize competition for similar future requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Single Source Justification (Simplified Acquisition)
April 2021 Page 2 of 2 potential consideration by the technical team. The POC ultimately responded back that they would be unable to submit a capability statement for at least a few more days and would take this particular opportunity as a learning experience for which they no longer wished to pursue. Accordingly, the originally intended sole-source approach to Quantum Coax, LLC remained intact.
Section E: Steps to Preclude Future Single Source or Brand Name Awards
In the future, the Government will continue to monitor the market in order to identify opportunities to maximize competition in potential future requirements. In the event that the research and development need changes, other products will once again be evaluated to determine their capability to support those future projects.
Section F: Contracting Officer's Determination
I have determined, in accordance with FAR 13.106-1(b)(1), that the circumstances of this contract action deem only a single source is reasonably available.