Questions and Answers (23Q0050) Question: Will there be a loading dock or will a truck with a liftgate be required, is there a service elevator or regular for access to the battery install location?

Answer: There is a loading dock for Building 3. Would suggest liftgate for ease of unloading. No elevator. Everything is on one level.

Question: Can the batteries be transported on a pallet using a jack, or will they need to be removed and transported using a hand truck?

Answer: Pallet jack and or hand truck will work. Pallet jacks are located in Building 3.

Question: Are there any other issues that we need to be aware of related to transportation of the batteries to the service location?

Answer: No.