Attachment_2-_SOW_for_Lab_Furniture.doc
DOC document 39 KB Posted
- Attached to
- Wright Line Furniture Federal contract opportunity
- Solicitation number
- FA8751-18-Q-0417
About this file
Attachment 2 - Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1-_List_of_Materials-Updated_8-1-18.xlsx | XLSX spreadsheet | |
| Attachment_5-_Rep_&_Certs.pdf | ||
| Attachment_3-_C2-D1_Drawing.pdf | ||
| Attachment_6-_Wage_Determination.pdf | ||
| Attachment_4-_Brand_Name_J&A.pdf | ||
| Attachment_1-_List_of_Materials.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
MODIFY LAB FURNITURE, IN SUITES C2-D1
BUILDING 3
AT
AIR FORCE RESEARCH LABORATORY- ROME, NY
03 MAY 2018
1.01 SCOPE
A. The scope of this effort consists of furnishing all design services, delivery and labor, equipment, devices, and materials, and to perform all work required to Reconfigure existing Eaton-Wrightline Technical Lab furniture, and provide new components as required for SUITE C2, SUITE D1, located in Building 3 at the Air Force Research Laboratory.
1.02 PRINCIPAL FEATURES:
A. The work to be performed involves the following principal features:
1. Reconfiguring/install (26) workstations in the Suite C2-D1 Lab area (See project Drawings)
2. Perform site visits and document accurate field measurements prior to ordering all lab furniture.
3. After AFRL/RIOC approval, order all new parts (see attached Parts List) and deliver new parts and materials to work area site.
4. Install complete furniture system, utilizing new and existing parts and all accessories as shown on plans. NOTE: Remove all packing materials and boxes from the job site.
5. Inventory, palletize & properly store any remaining product in Bldg. 2, warehouse.
6. Building 3 is a one story building so the furniture will all be delivered and installed on the same level. There is a loading dock with dock leveler.
7. Building 2 is also a one story building, loading zone available, loading dock available upon request.
END OF SOW
Attachment 2- Statement of Work (SOW)