04. RFI Questions and Answers.pdf
PDF 225 KB Posted
- Solicitation number
- FA8730-FALCONER-NG
About this file
This is a Questions and Answers document for a Request for Information (RFI) regarding the Next-Generation Air Operations Center (AOC) Weapon System, issued on 11 March 2026.
The RFI is open to both small and large businesses and does not constitute a small business set-aside. The document clarifies that the Program Announcement schedule is subject to change with no specific industry engagement event currently scheduled. Respondents must address the Requested Information posted on SAM.gov and provide responses to seven technical questions contained in Attachment 3, as well as Program/Contract Management Requirements cited in SAM.gov. The word "following" in Question 7 should be replaced with "preceding" when referencing technical questions. Companies without Joint Certification Program (JCP) certification are not precluded from responding to the publicly available portions of the RFI on SAM.gov. Regarding AI platform usage, if a company's purpose-built large language model platform is CMMC Level 2 compliant, authorized to host Controlled Unclassified Information, operates in a dedicated tenant environment, does not retain prompts for model training, and does not use uploaded data to improve foundation models, use of such a platform for internal analysis and proposal development is permissible under the Documentation Request and Disclaimer Form Paragraph 3.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
internal analysis and proposal development be considered permissible under Paragraph 3?
Instructions for response seem to have Please respond to the Requested conflicting guidance. Please confirm Information posted on SAM.gov and to the vendors should provide a response to: Technical Questions (Attachment 3).
1. Technical Requirements in SAM.gov;
2. Program/Contract Management
Requirements cited in SAM.gov;
3. and a response to the seven Technical
Questions found in Attachment 3.
If we aren't able to get the JCP Not having JCP certification does not processed/issued before [the RFI response due date], would it still be possible or worthwhile for us to submit a response to preclude a company from responding to the portions of the RFI that are publicly available at SAM.gov.