This document is an amendment to a Request for Information regarding the potential break up of the North American Aerospace Defense Command Cheyenne Mountain Complex Integrated Tactical Warning/Attack Assessment and Space Support contract into multiple discrete contracts.
The amendment extends the deadline for submitting secondary questions from September 15, 2023 to September 18, 2023 and provides answers to initial questions received. The contract currently managed by the Department of the Air Force Materiel Command Lifecycle Management Center at Peterson Air Force Base could potentially be divided into separate contracts for operations and maintenance, software development and sustainment, and software modernization. The outline of contract line item numbers provided describes labor, travel, materials, other direct costs, and data delivery contract types that could apply to future discrete contracts under consideration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Initial Award PWS NISSC II OM and S PWS 2 JUL 20.docx | DOCX document | |
| SZQN Support Contract PWS Break Up RFI.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION – AMENDMENT 1
Subject: North American Aerospace Defense Command (NORAD) Cheyenne Mountain Complex (NCMC) Integrated Tactical Warning/Attack Assessment (NCMC-ITW/AA) and Space Support Contract
FA8723-23-R-0012 – Support Contract PWS Break-Up RFI Amendment 1 RFI Initial Question & Answers and Question Deadline Extension POCs: Lt Col Jessica Morgan (PM) | Capt Jexenia Bennett (Contracting)
This is an amendment to the above reference RFI. This is not a solicitation or a new RFI. This amendment and its parent RFI do not commit the Government to contract for any supply or service. Furthermore, the Government is not seeking proposals at this time and will not accept any unsolicited proposals. Please acknowledge that you have seen this amendment in any final submission provided in response to this RFI.
This amendment is being published for two purposes. The first, the extend the secondary question deadline listed in the original RFI from 15 September 2023, 1400, MST to 18 September 2023, 1700, MST. The second is to provide the answers to all questions received in the first round of questions. If you have additional questions that are not answered in the original RFI or below, please submit them in accordance with the RFI instructions, in writing via e-mail to Capt Jexenia Bennett at jexenia.bennett.1@spaceforce.mil.
1. Are all the Mission Assurance Centers under a common architecture and managed at the enterprise level, or is each center managed and administered locally?
Both; all MACs are locally administered, however, only one MAC has enterprise-wide capability.
2. How much, if any, of the MAC systems are being considered for migration to a secure cloud environment?
At this time the Government does not have a requirement to migrate to a cloud architecture
3. Are there other roadmap activities that we should consider when making recommendations for this PWS disaggregation?
Yes, generally the following are assumed to impact life cycle sustainment: periodic cybersecurity requirements, modularization projects, and technical refreshes.
4. To provide offerors with the necessary information to propose innovative and cost-efficient contract structures, will the Government please provide the CLIN structure and funding for each CLIN (by year) under the current NISSC II contract?
The Government will provide the outline of the CLIN structure (Name/description, etc.); however, the Government will not release the funding and financial information as those are contract sensitive. Contract CLIN Outline will be included at the bottom of this amendment.
5. After reviewing the RFI instructions, it was not clear where the management concepts are listed that was mentioned in Section 3.0 Requested Information: It states, “The Government is seeking to identify vendors who have experience with any or all of the contract management concepts listed above.” Could the Government please clarify which contract management concepts being referred to within the RFI? Please advise. Thank you.
The phrase “contract management strategy” is intended to mean the ability of a company to do the following:
a) Manage more than one contract, subcontract, and/or task order that are in support of a single Government program.
b) Establish and execute business practices through the letting of contracts and agreements that enable productive cooperation between multiple industry partners, such as the ability to team with other companies who will be required to integrate, sustain, and support technology of both companies as part of the Government’s program management strategy.
Example: A single large contract divided into three separate, but complementary contracts:
a) One contract for operations and maintenance for on-site communication and mission system infrastructure elements
b) One contract for the development, security, operation, and integration of software tools and training capabilities; to include management of cybersecurity standards, engineering, and sustainment tools, etc.
c) One contract for software modernization, deployment, and sustainment of core mission systems
6. To help us provide a better recommendation and meet the Government’s goals, are you able to share why you are considering breaking up the NISSC scope into separate contracts?
The consideration of breaking-up the NISSC scope into more narrow and discrete contracts is one of multiple options being examined as part of strategic planning on behalf of the program management office. Disaggregating the larger contract may offer efficiencies in management, as well as execution and delivery, for both the Government and Industry. This RFI seeks to determine the feasibility of that concept in general and gather insight about how that concept could be defined and scoped.
Contract CLIN Outline
| Item Number | Service | Contract Type | Description |
| CLIN 001 | Labor | FFP | The contractor shall perform all tasks detailed in the NISSC II Sustainment Performance Work Statement (PWS). This CLIN includes all allowable costs to complete the work identified in the applicable PWS, exclusive of all materials (to include software licenses, warranties, equipment, and contractor acquired property (see FAR 45.101 - Definitions) purchased on the Cost Reimbursement Material CLIN and travel costs on the Cost Reimbursement Travel CLIN. This FFP Labor CLIN is reserved for future tasks not identified at this time. |
| CLIN 002 | Labor | FPIF | The contractor shall perform all tasks detailed in the NISSC II Sustainment Performance Work Statement (PWS). This CLIN includes all allowable costs to complete the work identified in the applicable PWS, exclusive of all materials (to include software licenses, warranties, equipment, and contractor acquired property (see FAR 45.101 - Definitions) purchased on the Cost Reimbursement Material CLIN and travel costs on the Cost Reimbursement Travel CLIN. |
| CLIN 003 | Labor | CPFF | The contractor shall perform all tasks detailed in the NISSC II Sustainment Performance Work Statement (PWS) for this CPFF (completion) CLIN. This CLIN includes all allowable costs to complete the work identified in the applicable PWS, exclusive of all materials (to include software licenses, warranties, equipment, and contractor acquired property (see FAR 45.101 - Definitions)) purchased on the Cost Reimbursement Material CLIN and travel costs on the Cost Reimbursement Travel CLIN. This CPFF Labor CLIN is reserved for future tasks not identified at this time. |
| CLIN 004 | Labor | CPIF | The contractor shall perform all tasks detailed in the NISSC II Sustainment Performance Work Statement (PWS). This CLIN includes all allowable costs to complete the work identified in the applicable PWS, exclusive of all materials (to include software licenses, warranties, equipment, and contractor acquired property (see FAR 45.101 - Definitions)) purchased on the Cost Reimbursement Material CLIN and travel costs on the Cost Reimbursement Travel CLIN. |
| CLIN 005 | Travel | Cost | Travel will be reimbursed in accordance with Federal Acquisition Regulation (See FAR 31.205- 46 - Travel Costs), with maximums that do not exceed the per diem rates in effect at the time of travel as set forth in the Joint Travel Regulation (JTR). The contractor shall not incur travel expenses unless funding is available. Local travel, defined as travel within 50 miles of the work location defined in the applicable PWS/SOW, is not authorized as a reimbursable cost. Travel costs are not subject to profit but may include allowable indirect costs. |
| CLIN 006 | Materials | Cost | Materials (to include software licenses, warranties, equipment, and contractor acquired property (see FAR 45.101 - Definitions)) required for this order are negotiated against this CLIN on a cost reimbursement basis. Materials are not subject to profit but may include allowable indirect costs. Any additional materials with an acquisition cost of $25,000.00 or greater requires prior approval of the Contracting Officer. Equipment, licenses, support agreements, and material (site, log line, & CMAFS Materials) including indirect handling rate is 11.14% (not fee bearing). |
| CLIN 007 | ODCs | Cost | Other direct costs (ODCs) (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.) |
| CLIN 008 | Contract Access Fee | Cost | Operating costs associated with the management and administration of this contract are recovered through a CAF. In accordance with the OASIS base contract, the CAF shall be 0.1 percent of the total TO value. This TO shall have a separate cost-reimbursable Contract Line-Item Number (CLIN) to cover this access fee, and this CAF shall be obligated at TO award. |
| CLIN 009 | FFP Data | *NSP | The contractor shall deliver data in accordance with DD Form 1423 as identified in Section J, Exhibit A of this order. This CLIN is Not Separately Priced (NSP). The price of all data furnished under this CLIN is included in the price of CLIN 0001. |
| CLIN 010 | FPIF Data | *NSP | The contractor shall deliver data in accordance with DD Form 1423 as identified in Section J, Exhibit A of this order. This CLIN is Not Separately Priced (NSP). The price of all data furnished under this CLIN is included in the price of CLIN 0002. |
| CLIN 011 | CPFF Data | *NSP | The contractor shall deliver data in accordance with DD Form 1423 as identified in Section J, Exhibit A of this order. This CLIN is Not Separately Priced (NSP). The price of all data furnished under this CLIN is included in the price of CLIN 0003. |
| CLIN 012 | CPIF Data | *NSP | The contractor shall deliver data in accordance with DD Form 1423 as identified in Section J, Exhibit A of this order. This CLIN is Not Separately Priced (NSP). The price of all data furnished under this CLIN is included in the price of CLIN 0004. |
| CLIN 013 | FFP - Performance Incentive | FFP | The contractor shall perform all tasks detailed in the NISSC II Sustainment Performance Work Statement (PWS). This CLIN reflects the Performance Incentive to be paid for work performed under the CPIF CLIN. |