This document is a Notice of Contract Action from the Department of the Air Force Air Force Nuclear Weapons Center regarding the Family of Advanced Beyond Line of Sight Terminals (FAB-T) Production Contract (FA8705-13-C-0005). The government is providing notice that it intends to extend the period of performance for a subset of 15 Cost Plus Fixed-Fee Contract Line Item Numbers on this contract from September 2024 to December 2025. The FAB-T program is a highly complex AEHF satellite communications system that provides secure, survivable communications to strategic and tactical forces. The original contract was competitively awarded in 2013 to Boeing and Raytheon utilizing a limited competition approach. The extensions are due to delays in terminal and hardware deliveries, site infrastructure, and operational constraints. As this is a no-cost extension with no additional work, it is deemed within the scope of the original contract and associated Justification and Approval for Other Than Full and Open Competition.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE NUCLEAR WEAPONS CENTER

HANSCOM AIR FORCE BASE, MASSACHUSETTS

09 September 2024

FROM: AFNWC/PZHS

MTRE D

202 Burlington Road Bedford, MA 01730

SUBJECT: FAMILY OF ADVANCED BEYOND LINE OF SIGHT TERMINALS (FAB-T)

PRODUCTION CONTRACT FA8705-13-C-0005, NOTIFICATION OF PERIOD

OF PERFORMANCE (PoP) EXTENSION.

References: (a) Class Justification for Other Than Full and Open Competition, Final Signed

Dual Approach J&A 20130509.

1. Purpose: The Government is providing notice to industry that it intends on extending the PoP for the FAB-T Production Contract from 24 September 2024 to 31 December 2025 for a subset of Cost Plus Fixed-Fee (CPFF) Contract Line-Item Numbers (CLINs).

2. Background: The Family of Beyond Line-of-Sight Terminal (FAB-T) is a highly complex AEHF (Advanced Extremely High Frequency) program that is the follow-on to the MILSTAR system and will provide near-worldwide, secure, survivable satellite communications to support strategic and tactical forces of the United States and its international partners during all levels of conflict. AEHF satellites will provide over ten (10) times the capacity and six (6) times higher data rate transfer than that of the current MILSTAR II satellites. The contract, FA8705-13-C- 0005, was competitively awarded on 25 September 2013 utilizing the approved Class Justification and Approval (J&A) for Other than Full and Open Competition for a limited competition between The Boeing Company and Raytheon and is currently a sole source acquisition.

3. Requirement Details: A subset of fifteen (15) CPFF CLINs will be extended. The extensions are due to contractor delays in terminal and hardware deliveries, site infrastructure delays, and operational site constraints due to real-world missions. As no additional work or materials are being introduced and this is a no cost extension, this extension is deemed within scope of the FAB-T Production Contract and associated J&A. Primary location will continue to be Marlboro, MA.

4. This notice is for information purposes only.

5. Please direct all questions to both William Fry at william.frye.9@us.af.mil and to the undersigned at stephanie.papia@us.af.mil.

STEPHANIE P. PAPIA, NH-03, DAF

Contracting Officer

AFNWC/PZHS

1 Attachment(s):

1. Class Justification for Other Than Full and Open Competition, Final Signed Dual Approach J&A 20130509.

mailto:william.frye.9@us.af.mil mailto:stephanie.papia@us.af.mil

2024_09_September Notice of Contract Action FabTProduction
Final Signed Dual Approach JandA_Redacted
2024-09-09T13:05:24-0400
PAPIA.STEPHANIE.PALS.1568152057