463L GRC Purchase Description.docx

DOCX document 82 KB Posted

Attached to
463L Pallet Gravity Roller Conveyor System for Arkansas ANGB AR
Solicitation number
FA8604-11-R-7909
Issued by

About this file

Cover Purchase Description (CPD)

View the file

Other files

File Type Posted
FA8604-11-R-7909 0001.pdf PDF
NLR 844-01.dwg DWG drawing
NLR 844-01 Drawing.pdf PDF
Contract Data Rqmts Pricing Sht FA8604-11-R-7909.doc DOC document
SHOPDWGS.DOC DOC document
DI TMSS 80527.pdf PDF
DI MGMT 80909 T.pdf PDF
PROGPLAN.DOC DOC document
DI TMSS 80528 T.pdf PDF
DI DRPR 81003.pdf PDF
Technical Proposa Questionnaire.pdf PDF
Contractor Information.docx DOCX document
DI MGMT 80227 T.pdf PDF
STATUS.DOC DOC document
Notification of Compliance with Contract Insurance Requirements —
CHECKOUT.DOC DOC document
Manuals.doc DOC document
DI ILSS 81092 T.pdf PDF
FA8604-11-R-7909.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offeror: ____________________________ Solicitation Number: FA8604-__-R-____

PURCHASE DESCRIPTION

FOR

463L PALLET GRAVITY ROLLER CONVEYOR SYSTEM

AERIAL PORT TRAINING FACILITY

ARKANSAS AIR NATIONAL GUARD BASE (ARANGB)

LITTLE ROCK AFB, AR

BUILDING 133

CSN: NLR 844

DATE: 4 January 2011

PREPARED BY:

Robert O. Burns

PROJECT ENGINEER

403 SCMC/GUEC

Shane Legge

REVIEWER

403 SCMC/GUEC

THIS AREA LEFT BLANK INTENTIONALLY

ARANG, Purchase Description, TPQ - Page 1 of 4 Table of Contents

1. SCOPE1
1.1. General Scope1
1.2. Definitions1
2. APPLICABLE DOCUMENTS2
2.1. Government documents2
2.2. Non-Government documents2
3. REQUIREMENTS5
3.1. System description5
3.2. REMOVAL OF EXISTING EQUIPMENT5
3.3. Physical and performance characteristics5
3.3.1. Deformation under impact5
3.3.2. Load capacity5
3.3.3. Dimensions6
3.3.4. Rollers6
3.3.4.1. Axles6
3.3.4.2. Bearings6
3.3.5. Frames7
3.3.5.1. Conveyor levelness7
3.3.5.2. Pallet tracking7
3.3.6. Crossties7
3.3.7. Pallet stops8
3.3.7.1. rEMOVABLE stops8
3.3.7.2. fIXED stops8
3.3.8. interfaces8
3.3.9. Conveyor guiderails9
3.3.10. Shims9
3.3.11. Hardwood9
3.3.12. FORK TINE Deflectors10
3.3.13. Interface rollers10
3.3.14. Forklift guard posts10
3.3.15. Scale system11
3.3.15.1. Load cells11
3.3.15.2. Display11
3.3.15.3. Power supply11
3.3.16. OPERATOR PLATFORM12
3.3.17. Noise levels12
3.3.18. Electrical characteristics12
3.3.18.1. Power source12
3.3.18.2. Installation code12
3.3.18.3. Conduit13
3.3.18.4. Grounding13
3.3.18.5. Wiring13
3.3.18.6. Overcurrent protection13
3.3.18.7. Environmental protection14
3.3.18.8. Protection fROM mechanical damage14
3.4. Design and fabrication14
3.4.1. Design criteria14
3.4.1.1. Reliability/availability14
3.4.1.2. Maintainability15
3.4.1.3. Environmental conditions15
3.4.1.4. Standard, commercial components15
3.4.1.5. Standardization15
3.4.1.6. Special tools15
3.4.1.7. Accessibility16
3.4.1.8. Structural requirements16
3.4.1.9. Verification of dimensions16
3.4.1.10. OZONE DEPLETING SUBSTANCES (ods)16
3.4.1.11. Safety16
3.4.1.11.1. Occupational Safety and Health Administration17
3.4.1.11.2. Protection against moving parts17
3.4.1.11.3. Placards17
3.4.1.11.4. Fail-safe controls17
3.4.1.11.5. CLEAN-UP17
3.4.1.12. Human engineering18
3.4.2. MaterialS18
3.4.2.1. Steel18
3.4.2.2. Mechanical fastening devices18
3.4.2.3. Anchors18
3.4.3. Protective coatings19
3.4.3.1. Painting19
3.4.3.2. Plating19
3.4.3.3. Galvanizing19
3.4.3.4. Dissimilar metals19
3.4.4. Welding20
3.4.4.1. Welding procedure qualification20
3.4.4.2. Welder performance qualification20
3.4.4.3. fire protection20
3.4.5. Cutting21
3.4.6. Coordination21
3.4.7. Nameplates21
3.4.8. Precedence22
3.5. Documentation22
3.6. Orientation22
3.6.1. System operator orientation22
3.6.1.1. System operator classroom instructions23
3.6.1.2. System operator hands-on instructions23
3.6.2. Maintenance orientation23
3.6.2.1. Maintenance classroom instruction23
3.6.2.2. Maintenance hands-on instruction23
4. QUALITY ASSURANCE PROVISIONS24
4.1. General24
4.2. Acceptance Tests24
4.2.1. System checkout test24
4.2.2. Quality conformance test24
4.2.3. Reliability demonstration test25
4.3. Inspections, tests, and certifications25
4.3.1. Inspections26
4.3.2. Tests26
4.3.3. Certifications28

ARANG Little Rock AFB AR, Purchase Description - Page iii

SCOPE

General Scope This appendix establishes the minimum performance, design, fabrication, installation, orientation, and test requirements for the replacement of four existing 463L pallet gravity roller conveyor lanes and the addition of a load build-up lane for the Aerial Port Training Facility in Building 133 at the Arkansas Air National Guard Base (ANGB), AR. All work shall be completed in accordance with this appendix, the Cover Purchase Description (PD), and Air Force (AF) Drawing NLR 844-01. This Purchase Description covers all equipment, materials, and labor necessary to complete installation of the system. It also includes performing tests and making adjustments to the system as well as providing classroom and on-the-job instructions to Government personnel.

Definitions

PD - Purchase Description
AF - Air Force
AFB – Air Force Base
ANGB – Air National Guard Base
COTR - Contracting Officer's Technical Representative

Conveyor lane - A set of four roller conveyor sections laid out across the width of the pallet to convey it in a particular direction.

Roller Conveyor Section - A set of gravity rollers within frames along the direction of travel of the pallet. Four roller conveyor sections make one conveyor lane.

463L Pallet - The 463L pallet is used to transport air cargo throughout AF bases worldwide. The 463L pallet consists of an end-grain balsa-wood or redwood core sandwiched between two sheets of aluminum with frames on all sides consisting of extruded aluminum edge rails. Steel tie-down rings are distributed around the perimeter of the pallet to secure nets and to facilitate handling. The entire pallet measure 108 inches wide by 88 inches long by 2.25 inches thick. Cargo on 463L pallets may be stacked up to 108 inches high on a single pallet. The pallet's rated capacity is 10,000 pounds and empty weighs approximately 355 pounds.

Forklift interface - Where forklifts pick-up pallets from and set-down pallets onto the GRC. Forklift interfaces are at the north end of the GRC.

APPLICABLE DOCUMENTS

The following documents form a part of this PD to the extent specified herein. The issue in effect on the date the solicitation is issued shall apply.

Government documents

AIR FORCE OCCUPATIONAL SAFETY AND HEALTH (AFOSH)

AFOSH 48-19

AFOSH 91-5

Hazardous Noise Program

Welding, Cutting, and Brazing

AFOSH 91-56
Fire Protection and Prevention

OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS

29 CFR 1910
Occupational Safety and Health Standards, (General Industry)
29 CFR 1926
Safety and Health Regulations for Construction

AIR FORCE DRAWINGS

NLR 844-01
Aerial Port Facility

Bldg. 133 Arkansas Air National Guard Little Rock AFB AR 4 January 2011

Non-Government documents

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 325
Manual of Steel Construction - Allowable Stress Design, Ninth Edition

(Applications for copies shall be addressed to the American Institute of Steel Construction, Inc, 1 East Wacker Drive, Chicago IL 60601)

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI B15.1
Safety Standard for Mechanical Power Transmission Apparatus
ANSI Z49.1
Safety in Welding and Cutting

(Applications for copies shall be addressed to the American National Standards Institute, 1430 Broadway, New York, NY 10018)

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM A123/

A123M Standard Specification for Zinc (Hot Dip Galvanized) Coatings on Iron and Steel Products

ASTM A153/

A153M

Standard Specification for Zinc Coating(Hot-Dip) on Iron and Steel Hardware

ASTM A307
Standard Specification for Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength
ASTM A325
Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
ASTM B633
Standard Specification for Electrodeposited Coatings of Zinc on Iron and Steel

(Applications for copies shall be addressed to the American Society for Testing and Materials, 1916 Race Street, Philadelphia PA 19103)

AMERICAN WELDING SOCIETY (AWS)

AWS B2.1
Welding Procedure and Performance Qualification
AWS D1.1
Structural Welding Code – Steel
AWS D14.1
Welding of Industrial and Mill Cranes and Other Material Handling Equipment, Spec for

(Applications for copies shall be addressed to the American Welding Society, Inc, 550 NW Lejeune Road, P.O.Box 35140, Miami FL 33135)

NATIONAL ELECTRICAL MANUFACTURER'S ASSOCIATION (NEMA)

NEMA ICS 6
Enclosures for Industrial Controls and Systems

(Applications for copies shall be addressed to the National Electrical Manufacturers Association, 2101 L Street, NW, Washington DC 20037)

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13
Installation of Sprinkler Systems
NFPA 51B
Standard for Fire Prevention During Welding, Cutting and Other Hotwork
NFPA 70
National Electrical Code

(Applications for copies shall be addressed to the National Fire Protection Association, One Batterymarch Park, P.O. Box 9101, Quincy MA 02269-9101)

SOCIETY OF AUTOMOTIVE ENGINEERS, INC (SAE)

SAE J429
Mechanical and Material Requirements for Externally Threaded Fasteners, Standard

(Applications for copies shall be addressed to the Society of Automotive Engineers, Inc, 400 Commonwealth Drive, Warrendale PA 15906)

REQUIREMENTS

System description The pallet gravity roller conveyor system, as shown on AF Drawing NLR 844-01, shall consist of one roller conveyor lane with four roller sections spaced as shown. The roller conveyor system shall aid in the movement, build-up, securing, weighing, and staging of as many as three 463L pallet loads of Mission Readiness Spares Packages (MRSP). The conveyor lane shall have an integral scale. Outbound pallets will be placed on the northeast end of the conveyor by an existing walk-behind electric 463L pallet or a 10K fork truck. The pallets are then manually pushed to the southwest end of the conveyor lane to where they will be picked up by a 10K fork truck. Inbound pallets are handled in the reverse order.

REMOVAL OF EXISTING EQUIPMENT

The contractor shall remove the existing conveyor lanes and prepare the Aerial Port for subsequent use. It will be the responsibility of the Air Force personnel to relocate the items currently stored on the existing conveyor lanes. The existing conveyors shall be dismantled as required, and delivered to a location specified by the Base Project Officer. This location can be a distance of up to five miles from the installation site.

Physical and performance characteristics Deformation under impact All roller frames, rollers, bearings and, roller shafts, shall be capable of withstanding repeated impacts from on-loading of pallets (fully loaded) without suffering any permanent deformations.

Load capacity The roller conveyor system shall be designed to easily convey 463L pallets weighing from ranges of fully loaded to empty. Each roller shall have a minimum load capacity of 550 pounds. The installed conveyor system shall be capable of sustaining distributed impact loadings from the lowering of pallets weighing up to 10,500 pounds by a forklift.

Dimensions All dimensions shown on Air Force (AF) Drawing NLR 844-01 are nominal. The contractor shall field verify all building dimensions. The conveyor lane shall have the following approximate length:

Conveyor
Length
Load Build-up
32’
Storage / Issue
41’

Rollers One of the following commercially produced rollers shall be used for this project: Litton model number RG2507, Interlake model number 4107, Bushman model number 256, or Mathews series B1070 roller or equivalent as approved by the Contracting Officer or technical representative (COTR). If an equivalent roller is proposed, the proposed roller and bearing shall be submitted for approval to the COTR with the shop drawing submittal. The rollers shall be a minimum 2 1/2-inch diameter steel tubing with 7-gauge wall thickness. The rollers shall extend a minimum of 1/4 inch above the frame. Each roller shall have a pin/ring shaft retainer to permit easy removal. The rollers shall be located on a maximum of 6-inch centers and shall provide a level carrying surface. The rollers shall be easily removable for inspection and maintenance. All roller tubes shall have electrodeposited zinc coatings. Roller tube plating shall comply with ASTM B633-85, Service Condition 2, Type I. Rollers shall be designed to have a minimum service life of ten years at a usage rate of 5,000 hours per year based on CEMA 401-78, using an equivalent radial load which is greater than or equal to 10,000 pounds divided by half of the minimum number of rollers under a pallet and a roller surface speed of 40 feet per minute.

Axles Axles shall be a minimum 11/16-inch hex cold rolled steel. All axles shall be of the through type and shall be pin/ring retained to facilitate easy removal of rollers for cleaning and maintenance.

Bearings The conveyor roller bearings shall be the nonprecision, dust-tight, oil lubricated, zinc-plated, antifriction ball type. Greased bearings shall not be acceptable. Each bearing shall have a minimum static load rating of 275 pounds. The bearings shall be securely mounted by swaging the roller ends or an equally suitable method approved by the COTR. The bearings shall be shielded or steel labyrinth sealed on both sides. The conveyor roller bearings shall have separate steel inner and outer rings. The Frantz 4113-GS shall not be an acceptable bearing due to interference caused by the inner hex-shaped shield.

Frames All frames shall be standard 10-foot sections, where possible, of minimum 4-inch high formed or structural steel channel. Frame sections, except at the scale interface, shall be bolted together flush end-to-end with lock washers or self-locking nuts to provide a continuous level conveying surface. All conveyor sections shall be installed such that the top frame rail is flush with the surrounding operator platform. Axle holes shall be punched in the high position on the channel so that rollers will have a minimum 1/4 inch of roller surface above the frame rail. There shall not be an interference fit between the axle holes and the axle. There shall be a 1/2 inch gap between the frames on the operator platform and the frames on the scale to properly isolate the scale. Frame sections shall be securely anchored to the Aerial Port Training Facility floor on 5-foot maximum centers. Each frame section shall be anchored to the scale in a minimum of three places.

Conveyor levelness The gravity roller conveyor shall provide a smooth surface for transporting palletized loads. All roller conveyor sections, including those on the scale, within the conveyor lane shall be at the same elevation along both its entire length and width within plus or minus 1/8 of an inch.

Pallet tracking All conveyor lanes shall be level and true. Palletized loads shall be able to be pushed the entire length of the lane, in either direction, (when previously centered) without the edge of the pallet drifting more than two inches to the left or right.

Crossties A minimum of 4 steel crossties shall be positioned in every 10-foot section to provide structural support. Crossties shall be welded to side frames. Crossties shall not interfere with the operation of the conveyor rollers. Crossties shall be equally spaced along the 10-foot length of the frames in accordance with Air Force (AF) Drawing NLR 844-01. Crossties shall not be used to anchor conveyor sections to Aerial Port Training Facility floor.

Pallet stops The contractor shall provide pallet stops in complete sets. A set of pallet stops, regardless of type, shall be defined as 2ea. minimum 6-inch by 6-inch by 1/2-inch stops and 2ea. minimum 12-inch by 6-inch by 1/2-inch stops. Stops shall be constructed of 1/2-inch structural angle steel. The pallet stop plates shall be constructed as shown on Air Force (AF) Drawing NLR 844-01. All pallet stops shall be painted safety yellow. Pallet stops shall be designed to withstand the impact of a load up to 10,500 pounds, moving a 40 feet/minute without suffering any permanent damage.

rEMOVABLE stops A total of twenty sets of removable pallet stops shall be required for the system. Receptacles for the removable stops shall be placed in the center roller conveyor sections a minimum of every eight feet between rollers. The removable pallet stop plates shall have a handle punched in the stop to facilitate ease of installation and removal.

fIXED stops A total of four sets of fixed pallet stops shall be required for the system. The stops shall be welded to the frame and bolted to the floor using anchor bolts.

interfaces Pallets shall not snag or bind at interfaces between GRC frames and guide rails or across gaps in frames and guide. The GRC shall not interfere with operation of the overhead door. With the overhead door open, pallets (with no overhang) shall not contact the doors, the walls, or any building component. Pallets shall transfer between the forklift interface and 463L electric pallet truck without snagging or binding pallets or damage or permanent deformation to the GRC. Pallets shall transfer between the forklift interfaces and pallet truck without causing damage or permanent deformation to the GRC.

Conveyor guiderails The gravity roller lane shall have pallet guiderails positioned in accordance with Air Force (AF) Drawing NLR 844-01. Rails shall extend a minimum of two inches above the conveyor frames and shall be fabricated from 1/2-inch structural angle steel. Guiderails shall flair out at both ends of the conveyor lane as shown on Air Force (AF) Drawing NLR 844-01 The final 20 inches of a flared guiderail shall flare out 3 inches or 8.5 degrees in accordance with Air Force (AF) Drawing NLR 844-01. Each rail section shall be standard 10-foot sections where possible. Rail sections shall be mounted to the floor on maximum five-foot centers. Additionally, the rails shall be anchored within six inches of the end of each section. Each rail section shall be mounted to the floor in a minimum of two places. Rail sections shall be mounted flush end to end to prevent snag points. Guiderail sections shall be welded or spliced to provide a continuous, smooth surface. All guiderails shall be painted safety yellow.

Shims As a minimum, the conveyor frames shall be shimmed at each anchor point. Slotted shims shall not be acceptable. Beveled or half-shims shall be provided where required to ensure that each conveyor frame is level with the operator platform. The shims shall be held in place by the anchor bolt. Shim holes shall be punched or drilled. Slotted shims shall not be acceptable. Beveled or half-shims shall be provided where required to ensure that each conveyor frame is level with the floor. The guiderails need only be shimmed to the point where they extend a minimum of two inches above the conveyor frames along its entire length. Each shim shall be a minimum of 4 inches in length by 4 inches in width and shall be installed so that they are not visible. Shims shall be of sufficient varying thickness so that no more than five shims are installed at any anchor point.

Hardwood The first 8 to 10 feet of frame at both ends of the lane shall have treated hardwood placed in the inside edge of the outer two roller frames and both edges of the middle roller frames as shown in Air Force (AF) Drawing NLR 844-01. The hardwood shall be bolted to the frame in at least three places. The hardwood shall be easily removable for repair/replacement. The bolt heads shall be recessed into the wood. The hardwood shall protect the frame from forklift tines. The lumber shall be painted the same color as the roller conveyor frame. A 10 gauge bolted galvanized guard, providing the same level of protection as the hardwood, will also be acceptable.

FORK TINE Deflectors Fork tine deflectors shall be installed at both ends of the roller section of all conveyor lanes. The design of the deflector shall be approved by the COTR prior to installation. The deflector shall allow forklift tines to be deflected upwards so the impact is not felt by the frames. The deflectors shall be painted red. Deflectors shall not extend above the frames. A concept design for the deflector is provided on Air Force (AF) Drawing NLR 844-01.

3.2.11. Interface rollers

Interface rollers shall be installed on the building sill, in front of the roll-up doors at the end of each storage/issue conveyor lane as shown on AF Drawing NLR 844-01. The interface rollers shall conform to the requirements of paragraph 3.3.4. Interface rollers shall have a separate frame from the rest of the conveyor. Interface rollers shall not transmit 10K fork trucks impacts or the impacts of pallets being transferred to the frame of the rest of the conveyor lane. The interface rollers shall not interfere with the operation of the roll-up doors. Interface rollers shall be rigidly braced to withstand repeated impacts of 10K fork trucks and fully loaded pallets. Rubber bumpers shall be installed to lessen the impact of 10K fork trucks hitting the interface roller frame. The position of the bumpers shall interface with all types of 10K fork trucks and shall not interfere with pallet transfer or forklift interfaces. Comment by burnsro: Comment by burnsro:

Forklift guard posts Steel pipe forklift guard posts shall be provided at the ends of the 463L build-up conveyor as shown on AF Drawing NLR 844-01. The guard posts shall extend a minimum 3 feet above the floor and shall be installed in such a manner that they do not interfere with the normal usage of the conveyor. A cap shall be installed on the top of the guard post. The guard posts shall not interfere with the normal movement of the trucks and shall protect the conveyor frame and guard rail from an accidental impact with a 4,000 pound capacity forklift. Each forklift guard post shall be anchored to the floor with a minimum of four anchor bolts in accordance with The guard post shall be painted safety yellow.

Scale system The conveyor lane shall have a contractor provided integrated scale with digital readout. The scale system shall stabilize in less than 3 seconds. The scale system shall be accurate to within 0.5 percent at maximum rated load. The Contractor shall provide independent verification and certification of this accuracy. The scale shall have a zero button to reset the weight to zero. The scale shall also have a tare button and a tare indicator to show the tare mode has been selected. The scale shall be designed so that an operator cannot inadvertently change the scale calibration. The scale shall provide the weight in pounds and kilograms. The scale shall have an RS-232 port that is accessible inside the console. An operator can reset the scale by powering off and then on. The scale display shall be located in console as shown on Air Force (AF) Drawing NLR 844-01. All scale controls shall be clearly labeled.

Load cells The scale shall have a minimum of four electronic shear beam load cells, each having a minimum capacity of 10,000 pounds. All shear beam load cells shall be dust and watertight. Mechanical stops shall be used to prevent over extension of the load cells. In addition, a means shall be provided to prevent side travel of load cells. Provisions shall be provided for load cell replacement.

Display The scale displays and associated controls shall be clearly labeled. The digital readout display shall have numbers at least 0.44 inch high. The units for weight measurement and display will be switchable between pounds and kilograms. The display shall be located as shown on Air Force (AF) Drawing NLR 844-01.

Power supply Power for the scales and displays is located on the wall adjacent to the 463L build-up conveyor lane. Power provided is 110 volt, single phase, 60 Hz. The contractor shall provide power, as required from the wall outlet to the scales and display.

OPERATOR PLATFORM

The contractor shall provide an operator platform as shown on AF Drawing NLR 844-01. The operator platform shall be constructed of bar grating, which is able to support a minimum load of 75 pounds per square foot. The bearing bars shall be minimum 1 inch X 1/8 inch bearing plate spaced on nominal 1 inch centers. The cross bars shall be resistance welded at right angles to the bearing bars and spaced on maximum 4.5-inch centers. Bar grating shall conform to the standards established by the National Association of Architectural Metal Manufacturers. Bar grating shall be securely fastened to the framing with steel clips and plated, self-tapping steel screws. The decking shall be sized to fit between the conveyor sections and conveyor lanes. Decking shall be level with the top of the roller conveyor frames, in order to provide a safe walking surface for personnel. Adjacent sections of the operator platform shall be shimmed along the full length of the common side.

Noise levels The Contractor shall consider noise levels in the design of the equipment. Hazardous noise shall not exceed 85 decibels A-weighted sound pressure level (dB(A)) for 8 hours in any 24-hour period or equivalent in accordance with AFOSH 48-19. Noise level measurements will be taken at a three-foot distance from the equipment producing the noise and at a level of five feet above the ground/floor in all locations in which personnel may be present during normal operations. If noise levels of installed equipment exceed this requirement, then noise shall be reduced through engineering controls; i.e., insulation, dampening, and isolation.

Electrical characteristics Power source The Contractor shall furnish and install all necessary wiring and equipment for power distribution to the system and for control of the system.

Installation code The installation shall, at a minimum, conform to applicable rules of NFPA 70 (National Electrical Code).

Conduit All wiring shall be encased in rigid metal conduit conforming to Article 346 of NFPA 70; electrical metallic tubing conforming to Article 348 of NFPA 70; or flexible metallic tubing conforming to Article 349 of NFPA 70. If conduit/cables are dropped from overhead, they shall be enclosed in a power pole. No conduit/cable shall run on top of the floor/ground. Exposed conduit shall be installed parallel or perpendicular to walls, structural members, or intersections of vertical planes and ceilings. Exposed conduit and fasteners shall match the color of the walls and/or existing conduit color. Changes in direction of conduit shall be made with symmetrical bends or cast metal fittings. Field made bends shall be made with the proper hickey or conduit-bending machine. Crushed or deformed conduit shall not be accepted. Conduit shall be rigidly fastened in place at intervals of not more than 10 feet.

Grounding Each component of the system shall be properly grounded to ensure safe working conditions. This shall include adequate ground against static charges that may be generated. Grounding shall conform to Article 250 of NFPA 70.

Wiring Conductors shall be copper. Wire connectors of insulating material or solderless pressure connectors properly taped shall be utilized for all splices where possible. Soldered mechanical joints shall not be accepted. All wiring shall be color-coded, uniquely tagged, or uniquely numbered for identification. Marking shall be applied in such a manner so as to facilitate tracing of wires (circuits) during repairs and/or maintenance. Wiring and wiring installation shall conform to Article 300 of NFPA 70.

Overcurrent protection The power distribution panel shall be equipped with circuit breakers and fuses in compliance with Article 240 of NFPA 70. Motors shall be equipped with disconnect switches and thermal overload devices.

Environmental protection All indoor enclosures and controls shall be in accordance with NEMA ICS 6, Type 12. All outdoor enclosures and controls shall be in accordance with NEMA ICS 6, Type 3S.

Protection fROM mechanical damage No pushbuttons, control panel, conduit, shielded cable, wire, or electrical device shall be installed so as to expose it to mechanical damage during normal use. If an electrical device, which includes photoeyes, is exposed to damage by material or personnel, then it shall be guarded.

Design and fabrication Design criteria Reliability/availability Each component of the system shall demonstrate a mean time between failure (MTBF) and availability greater than or equal to that listed in the following table. A failure is defined as any interruption that causes corrective maintenance to be made to the system. The operating time will be based on the hours listed on the following table or the actual hours read from the hour meter. The following formulas will be used to calculate MTBF and availability.

Reliability/Availability Table

Equipment
Operating Time

(Hours)

MTBF

(Hours) Availability

Conveyors
720
360
99

Maintainability The system shall be designed, fabricated, and installed to facilitate maintainability and ensure a minimum service life of 15 years. The design shall provide for modular assembly of components and subassemblies where feasible to permit repair or replacement of parts in a minimum of time. This shall include plug-in electrical connections for major electrical subassemblies.

Environmental conditions The system shall operate in a temperature range of 20 to 100 degrees Fahrenheit with up to 99 percent relative humidity. The system shall be constructed to operate in an open warehouse environment. For components located outdoors, the component shall be constructed for year-round outdoor use, operating in sun, rain, snow, and wind.

Standard, commercial components Standard, commercial components which have been for sale and available for purchase to the general public or government agencies for at least one year shall be used to the maximum extent possible. If requested by the COTR (Contracting Officer's Technical Representative), the Contractor shall furnish evidence that equipment of approximately the same design as that proposed to be installed has been tested and successfully operated. Where two or more units of the same type of equipment are required, these units shall be products of the same manufacturer. All equipment and materials shall be new.

Standardization Mechanical and electrical interchangeability shall exist between like assemblies, subassemblies, and replaceable parts regardless of the manufacturer's supplier. Interchangeability does not necessarily mean complete identity, but requires that a substitution of such like-assemblies and replacement parts be easily effected without physical or electrical modifications, including cabling, wiring, and mounting.

Special tools Use of special tools shall be minimized and, where required for operational adjustments, shall be securely mounted within the equipment in a readily accessible location. Standard tools, fittings, lubricants, and fluids shall be used to the maximum practicable extent.

Accessibility Structural members shall not prevent access to or removal of components for repair or replacement. Equipment shall be designed for rapid and easy removal as well as replacement or repair of malfunctioning units, by one individual where feasible. Mechanical components shall be designed to permit lubrication of components without disassembly.

Structural requirements The system shall be designed and constructed in accordance with state and local codes. The system shall also be designed to withstand seismic zone 2 conditions.

Verification of dimensions The contractor shall become familiar with all details of the work, verify all dimensions in the field, and shall advise the Contracting Officer of any discrepancy before performing the work.

OZONE DEPLETING SUBSTANCES (ods) The Contractor shall not use or prescribe to the greatest extent possible any ODS in the installation and maintenance of the system. ODS includes, but is not limited to aerosol cans, certain cleaning solvents, and certain lubricants. If there is a question pertaining to the applicability of a substance, submit the name of the substance to the Contracting Officer for verification.

Safety The Contractor shall consider the safety of personnel and equipment when designing and installing the system. Safety provisions shall be incorporated to the maximum extent possible. When possible, hazards shall be eliminated through design. When this is not possible, safety devices such as guards, interlocks, and barriers shall be installed. If this does not eliminate the hazard, warning devices such as warning signs, indicator lights, and audio devices shall be installed. Safety requirements shall include, but are not limited to, the following.

Occupational Safety and Health Administration The system installation practices and completed system shall meet all applicable requirements of OSHA 29 CFR 1910 and OSHA 29 CFR 1926.

Protection against moving parts Moving parts shall be provided with guards to protect personnel from possible injury. Guards shall be in accordance with ANSI B15.1.

Placards Conspicuous placards shall be mounted adjacent to areas where hazards may exist (i.e., high voltage, pinch points, and tripping hazards). Placards shall also be used to identify operating limits (i.e., capacity, speed, and incline) in a conspicuous location for operators' use.

Fail-safe controls No controls shall cause false operation or endanger personnel if a part should fail. No damage or destruction of any component shall result from reduced voltage or complete loss of power.

CLEAN-UP

The Contractor shall, at all times, keep the work area, including storage areas, free from the accumulation of waste materials and dust which would cause a hazard or nuisance to others. The approved methods of stabilization for dust control are sprinkling, chemical treatment (non-ODS) or a similar method approved by the COTR. If there is a cutting process, the solution shall be vacuumed up during the process to prevent dust pollution and water damage. Before leaving the site, the Contractor shall remove all rubbish, tools, equipment, and materials that are not the property of the Government. At the completion of the installation/test, the Contractor shall leave the site in a clean, neat and orderly condition satisfactory to the COTR. Waste will be removed daily from the site and shall not be allowed to accumulate to the extent that it becomes a safety or fire hazard. It shall be the Contractor's responsibility to dispose of waste in accordance with all applicable Federal, State, County and Municipal codes.

Human engineering The system design and layout shall incorporate ergonomic design criteria so the optimal interface between operator and equipment is attained.

MaterialS Steel The structural steel components shall meet all design property requirements of AISC M016.

Mechanical fastening devices Unless otherwise specified, all threaded connectors of diameter greater than 7/16 inch shall be either A325 bolts conforming to ASTM A325 or SAE Grade 5 bolts conforming to SAE J429. All structural joints shall be in accordance with AISC M016. Bolt hole diameters shall not exceed nominal bolt diameters by more than 1/16 inch. All bolt holes shall be free of burrs, pins, or slivers. Bolts shall extend a minimum of two threads beyond the nuts. All nuts, bolts, and other threaded fasteners shall be plated or galvanized to prevent corrosion. All threaded fasteners shall utilize plated flat and lock washers as required.

Anchors Anchors shall, at a minimum, meet the requirements of ASTM A307. Anchors shall be either the drop-in expansion type or wedge type. All anchors shall be sufficient in size to withstand the calculated pullout and shear forces experienced by the equipment. Minimum anchor sizes shall be 3/8 inch in diameter or, if applicable, as specified in the appendices. Anchor lengths shall be long enough to assure that the manufacturer's minimum embedment in concrete is maintained and shall be installed properly to maintain the required minimum concrete embedment. Anchors shall be spaced so that the manufacturer's recommended minimum allowable spacing between anchors is maintained and the recommended minimum allowable edge distance is maintained. All anchors shall be torqued to the manufacturer's recommended installation torque. When required, adhesive anchors may be used; subject to approval by the COTR.

Protective coatings All system component surfaces shall be protected from corrosion by painting, plating, or galvanizing.

Painting Metal surfaces, which are not galvanized or plated, shall be cleaned, treated, and painted to protect against rust, corrosion, and deterioration. The first coat of paint or primer shall be applied to a dry clean surface as soon as practicable after cleaning and treating the metal. The primer shall not interfere with the application and adhesion of subsequent coats. Paint shall last the service life of the equipment. Paint shall be lead and chromate free and meet air pollution requirements for solvent emissions. When several standard colors are available, a color selection chart shall be submitted to the COTR with the shop drawings for selection. The finish coat shall be a smooth, even surface, free from runs, sags, and defects when dry. Welded surfaces shall be cleaned and painted after the welding process is complete. Prepainted accessories, as well as surfaces not requiring paint, shall be protected from overspray.

Plating All surfaces to be plated shall be thoroughly cleaned to provide a surface free of mill scale, oil, grease, dirt, rust, and any other foreign material prior to being plated. Plating at a minimum shall comply with ASTM B633, Service Condition 1, Type I unless otherwise specified.

Galvanizing All metal surfaces to be galvanized shall be thoroughly cleaned to provide smooth surfaces and shall comply with ASTM A153 and ASTM A123.

Dissimilar metals Materials used and their locations shall not promote galvanic corrosion. No combination of materials shall be used that form an electrolytic couple of such nature that corrosion is accelerated.

Welding Dimensional tolerances for welded construction, details of welds, and quality of welds shall be in accordance with the applicable requirements of AWS B2.1, AWS D1.1, and AWS D14.1. The Government reserves the right to perform supplemental nondestructive and destructive tests to determine compliance. Safety precautions during welding shall conform to ANSI Z49.1.

Welding procedure qualification Qualification of welding procedures shall conform to the applicable requirements of AWS B2.1, AWS D1.1, and AWS D14.1. The Government reserves the right to request copies of Welding Procedure Specifications for any welding procedure followed in the fabrication of this system.

Welder performance qualification Each welder, welding operator, and tack welder assigned to work on this system shall be qualified in accordance with the applicable requirements of AWS B2.1, AWS D1.1, and AWS D14.1. The Government reserves the right to request certification (Performance Qualification Test Record) that each welder, welding operator, or tack welder is qualified as specified.

fire protection All welding, cutting, brazing, and burning operations shall be accomplished in strict compliance with the requirements outlined in AFOSH 91-5 and NFPA Standard 51B. Prior to starting any welding, cutting, brazing, or burning operations, the Contractor shall obtain a permit (USAF Welding, Cutting, and Brazing AF Form 592). This permit can be obtained by contacting the Little Rock Fire Department at least 24 hours in advance. A copy of each permit will be retained at the work site until the work has been completed. Operations that produce flying, dropping slag, metal or embers shall have sufficient non-combustible materials and fire blankets on site to protect against fire damage or personal injury. In addition, the contractor shall provide a minimum of 2 portable fire extinguishers at the work site until the work has been completed. Extinguishers shall meet a rating of 4A-40BC and the requirements outlined in AFOSH 91-56. At the close of their operation, the contractor shall make a thorough inspection of each building in which he/she has performed work. This inspection shall ensure that all necessary safeguards relative to potential fire hazards are in effect and operational. The contractor shall familiarize themselves and their personnel on the location of all telephones needed for fire reporting. The contractor shall maintain good housekeeping practices to reduce the risk of fire, damage, and/or personal injury. All scrap materials, rubbish, and refuse shall be removed daily from in and around the building and shall not be permitted to be strewn on adjacent property. Flammable and combustible materials used inside the building shall be kept to a minimum and removed from the building during unused periods. Storage of flammable/combustible materials shall not be permitted inside the building.

Cutting All edges produced by oxygen-flame cutting or any cutting operation shall be finished by grinding (or other method approved by the COTR) to a surface finish equivalent to that of adjacent surfaces. Sharp edges shall not be acceptable.

Coordination The Contractor shall obtain approval from the local base civil engineering, fire, safety, and bioenvironmental offices before making any modifications to the existing structure to accommodate the new system. The modifications shall match existing work and shall be of comparable quality. The COTR shall also approve all modifications before they are made.

Nameplates The Contractor shall provide and install one corrosion resistant metal nameplate for each component. A nameplate for each row of shelving/rack shall be provided such that if one row is dismantled, the nameplates will exist elsewhere. For conveyors, a nameplate shall be provided for each kind of conveyor in the system (i.e. takeaway, gravity, curves, incline/decline, etc). Nameplates shall be located in a visible and safe location. Nameplates shall last the life of the equipment and shall be capable of withstanding local environmental conditions. Nameplates shall be stamped, engraved, or etched in a print type not less than 1/8-inch tall. No nameplate or product marking shall be installed until all touch-up painting has been completed. The nameplate or product marking shall clearly display the following headings and corresponding information.

Type of equipment Name of manufacturer Model Number Contract Number Serial Number Capacity Weight Manufacture Date, Month/Year "Property of US Government"

Precedence Where local codes and standards conflict with the contents of this PD, the more stringent requirement shall prevail.

Documentation The Contractor shall provide documentation (data) in accordance with the Contract Data Requirements Lists (CDRL). Where possible, the Contractor shall print on recycled paper. Also, where possible, the Contractor shall not require the use of any ozone depleting substance in any submittal. The Contractor shall incorporate maintenance, testing, inspection, and operator qualification requirements of AFOSH 91-46 into the maintenance and operator manuals.

Orientation The Contractor shall provide technical services and materials to orient Government personnel. Fully qualified Contractor personnel who are knowledgeable of the system shall accomplish all orientation. Courses shall be combined in accordance with the Contractor's standard commercial training courses, where applicable, provided all aspects of training are included. Orientation shall be provided at Little Rock AFB AR. The Contractor shall provide each attendee with a certificate indicating successful completion of the orientation. All orientation shall be completed prior to the start of the quality conformance test.

System operator orientation This orientation shall provide instructions in the overall operational functions that are performed by the system operators. Instructions shall include the operation of all the system components. Upon completion of this course, the operators shall be able to operate all components of the system. Operators shall be able to perform these functions using only the reference manuals provided with the system relative to operations. An estimated six students with possibly no experience will attend.

System operator classroom instructions The classroom phase shall include instructions in the operational requirements of the installed system. Classroom instructions shall include a briefing and orientation on the use of the operation manuals supplied by the Contractor. Classroom instructions shall be developed so that it can be placed on videotape. Classroom instructions shall be a minimum of one hour.

System operator hands-on instructions The hands on phase shall include actual operation of the system under the supervision and instruction of the Contractor. Hands-on instruction shall be a minimum of one hour.

Maintenance orientation This orientation shall provide instructions in corrective and preventive maintenance of the system delivered. Instruction shall include installation and adjustment of all system components. Upon completion of this orientation, students shall be able to install, adjust, and maintain equipment stated using only the maintenance reference manual delivered. An estimated six students with possibly no experience will attend.

Maintenance classroom instruction The classroom phase shall include instruction in the maintenance requirements of the installed system. Classroom instruction shall include a briefing and orientation on the use of the maintenance manuals supplied by the Contractor. Classroom instruction shall be developed so that it can be placed on videotape. Classroom instruction shall be a minimum of one hour.

Maintenance hands-on instruction The hands-on phase shall include actual field instruction in the maintenance requirements of the installed system. Hands-on instructions shall be a minimum of one hour.

QUALITY ASSURANCE PROVISIONS

General The COTR shall monitor the installation of the system. The system delivery dates shall not be extended because of work stoppages caused by unacceptable practices and/or test failures. For all inspections and tests, the Contractor shall provide all test apparatus (i.e., tape measures, levels, calipers, micrometers, stop watches). All test apparatus will be returned to Contractor upon completion of all tests. The Government will provide all test loads. The Contractor shall be responsible for loading and unloading all test loads and performing all inspections and tests. The Contractor shall provide a knowledgeable and authoritative representative on site during the entire acceptance tests.

Acceptance Tests Three tests must be successfully completed prior to the Government accepting the system. These tests are the system checkout test, the quality conformance test, and the reliability demonstration test.

System checkout test Upon completion of installation, the Contractor using loads of the type specified herein and in the appendices shall check out the system. The Contractor shall inspect the system to assure that the system meets all the requirements of 4.3.1. The Contractor shall also test the system in accordance with the test defined in 4.3.2. All inspections and tests shall be repeated until all modifications and/or adjustments are complete and the system passes all inspections and tests. The Contractor shall submit to the Contracting Officer written certification that the system has passed the requirements of this paragraph. The COTR will schedule the quality conformance test to start within 10 days following the receipt of the written certification from the Contractor.

Quality conformance test As part of the quality conformance test, the Contractor shall provide written certification that the requirements listed in 4.3.3. have been met. This certification is required on or before the start of the quality conformance test. The Contractor, in the presence of the COTR, shall inspect the system to confirm that the system meets all the requirements of 4.3.1. The Contractor, in the presence of the COTR, shall also test the system in accordance with the test defined in 4.3.2. Upon successful completion of all tests and inspections and the receipt of all certifications, the reliability demonstration shall start.

Reliability demonstration test After successful completion of the quality conformance test, each component of the system shall demonstrate a reliability and availability greater than that listed in the reliability/availability table in 3.4.1.1. In addition, all static components shall demonstrate compliance with the requirements of the purchase description (PD). The test period shall be the 30 calendar days immediately following the successful completion of the quality conformance test. If the system does not demonstrate the required reliability and availability or compliance with the PD, the test will be restarted from the beginning after the Contractor has taken corrective action. The Contractor shall be allowed to restart the reliability demonstration test a maximum of 2 times. If the system fails to pass the reliability demonstration within 3 attempts, then the system shall be rejected.

Inspections, tests, and certifications This section defines all inspections and tests that must be completed as part of the system checkout test and repeated at the quality conformance test. This section also includes a list of all certifications that must be received from the Contractor on or before the start of the quality conformance test. The Contractor may add to this list, or question any requirement, by sending a letter to the Contracting Officer prior to the acceptance tests. The COTR will classify all deficiencies encountered into one of the defect classification listed below. Any critical or major defect found shall be cause for rejection of the system. Any combination of two or more minor defects shall leave the rejection of the system at the discretion of the COTR.

Critical Defect - A defect that judgment and experience indicate is likely to result in hazardous or unsafe conditions for individuals using, maintaining, working near, or depending upon the equipment.

Major Defect - A defect other than critical that is likely to result in failure, or reduce materially the system for its intended purpose.

Minor Defect - A defect that is not likely to reduce materially the usability of the system for its intended purpose, or is a departure from established standards having little bearing on the effective use or operation of the system.

Inspections The system shall be inspected to verify that it meets all the requirements of sections 1, 2, and 3 of the cover purchase description (and associate appendices, if applicable).