This is a Statement of Work (SOW) for the procurement of a Scanning Transmission Electron Microscope Electron Beam-Induced Current (EBIC) System to be installed at the Air Force Institute of Technology (AFIT) Cleanroom Laboratory at Wright Patterson Air Force Base, Ohio (2950 Hobson Way, Building 644). The EBIC system must integrate with the existing Zeiss Crossbeam 350 SEM and support advanced materials characterization research for AFIT microelectronics and physics education, enabling internal structural, chemical, and energetic analysis at the atomistic scale to support graduate-level thesis and dissertation work within 10-week courses and 18/36-month MS/PhD programs.
The contractor must deliver, install, and complete on-site calibration within eight months of contract award. System requirements include full compatibility with the Zeiss Crossbeam 350 SEM and future aSTEM detector upgrades, with capability for TEM use at AFRL Materials Characterization Laboratory. Performance specifications mandate current measurement sensitivity of 10 picoamperes with additional amplification to less than 5 picoamperes or better, adjustable gain range from 10³ to 10⁹ V/A, spatial resolution of 50 nanometers or better, and dual-tilt sample alignment capability. The software must operate on Windows 10 without network connectivity, synchronize with the SEM scan generator at resolutions up to 2048x1536 pixels, and include perpetual software licenses. The contractor shall provide comprehensive training to AFIT microelectronics faculty and cleanroom staff during installation and offer a minimum one-year warranty with on-site or virtual calibration support throughout the warranty period. Payment is 100% upon completion of all requirements through WAWF. This RFQ (Solicitation Number FA8601-EBIC_SYSTEM) is set-aside for small business concerns under NAICS code 334516 with a size standard of 1,000 employees, with award on a lowest-priced technically acceptable (LPTA) basis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REQUIRED INFORMATION SHEET.docx | DOCX document | |
| SOW_EBIC 17 SEP 2026.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for Scanning Transmission Electron Microscope Electron Beam-Induced Current System
Title: STEM Electron Beam Induced current (EBIC) System, double tilt holder Document Date: 23 September 2026
1. Scope: A EBIC detector requires installation in the AFIT Cleanroom lab. The EBIC system must be able to provide data sufficient for a Master’s level thesis or doctorate level dissertation on time scales that can accommodate 10-week AFIT courses and 18/36 month MS/PhD programs. The expendable material requirements in the form of chemicals, gases, power, etc. must be compatible with AFIT's current Clean Room facility (standard 120 V AC Wall power, no concrete floor pad). Use of the tool must be possible with Windows operating systems without network access.
1.1 Background: Materials characterization and analysis is the driving force for advancing technological capabilities and occurs from the macroscopic to the atomistic scale. While AFIT microelectronics and physics education has benefited greatly from the use of Scanning Electron Microscopy (SEM) characterization, SEM is limited to surface level analysis. Internal structural, chemical, and energetic analysis requires advanced microscopy and spectroscopy techniques, which requires a different suite of detectors. Fortunately, our existing Zeiss Crossbeam SEM can accommodate such a detector suite produced by manufacturers such as Nanoelectronic Imaging (NEI). The EBIC system will thus enable the study of ultra-high temperature materials, microelectronics, microelectromechanical systems (MEMS), and materials for aerospace applications. The new EBIC capability at AFIT will enable materials research from many different research groups both internal and external to AFIT/WPAFB/DoD, providing a unique ability to link cross-correlative, multi-imaging and analysis modalities from the macroscopic to the atomic levels. The ability to ‘link’ cross-correlative, imaging/analysis modalities across length scales on the same instrument system allows students and research groups for a more detailed and comprehensive materials analysis and increases experimental throughput. This instrument supports EENG 675, EENG 717, and EENG 777.
2. Period of Performance: Delivery, installation, and on-site calibration no more than 8 months after contract is awarded.
3. Training Requirements: The contractor shall train all AFIT microelectronics faculty and cleanroom staff at the time of installation such that current AFIT measurement campaigns can be completed and future students/staff can be trained by the AFIT personnel. Additional training may be requested by the AFIT member(s) while the contractor is on-site for calibration/adjustments/repairs through the life of the warranty.
3. Delivery Location: 2950 Hobson Way, WPAFB, OH 45433-7765, Area B, Bldg. 644
4. Requirements/Salient Characteristics: The contractor shall train all AFIT microelectronics faculty and cleanroom staff at the time of installation such that current AFIT measurement campaigns can be completed and future students/staff can be trained by the AFIT personnel. The instrument shall be compatible with instruments already installed on the Zeiss Crossbeam SEM, such as the Oxford Instruments ESD/EBSD.
A) System Compatibility:
· Item 1.1: The EBIC system must be fully compatible with the existing Zeiss Crossbeam 350 SEM, including integration with the chamber, use of an available accessory port, and compatibility with the SEM's scan generator.
· Item 1.2: The EBIC system must be fully compatible with a Zeiss aSTEM detector upgrade in the Zeiss Crossbeam 350 SEM.
· Item 1.3: The EBIC system must be equipped for TEM use at the AFRL Materials Characterization Laboratory facility (a partner/collaborator with AFIT) to enable STEM EBIC/SEEBIC measurements. Adaptors/additional parts such as sample holders and stages to facilitate transfer between SEM (with or without aSTEM detector installed) and TEM uses are permissible and may require additional manufacturer assistance if needed.
· Item 1.4: All necessary hardware for installation, including a vacuum feedthrough flange, in-chamber cabling, and external connectors, must be included.
B) Performance Specifications:
· Item 2.1 (Current Measurement): The system must include a preamplifier capable of measuring currents with a sensitivity of 10 picoamperes (pA) and additional amplifier capable of less than 5 picoamperes (pA) or better.
· Item 2.2 (Gain & Bandwidth): The EBIC amplifier must have an adjustable gain range from at least 10^3 to 10^9 V/A or better and an adjustable bandwidth of at least 1 kHz to balance signal-to-noise and acquisition speed and suitable for large semiconductor EBIC signals.
· Item 2.3 (Resolution): When integrated with the Zeiss Crossbeam 350, the system must be capable of producing EBIC maps with a spatial resolution of 50 nanometers (nm) or better on a known test sample.
· Item 2.4 (Probing): The system must include a means of making electrical contact with samples inside the SEM chamber such that the signal can pass to the SEM data stream. Solutions may consist of a micro-manipulator or nanoprobing solution that allows for in-situ adjustment, or may require ex-situ preparation (e.g., wire-bonding and packaging).
· Item 2.5 (Alignment): The system should enable double tilt sample alignment.
C) Software & IT:
· Item 3.1: The control software must be compatible with Windows 10 (or specify the required OS). All necessary software licenses for operation must be perpetual.
· Item 3.2: The system must be capable of synchronizing with the SEM's scan generator to simultaneously acquire a secondary electron (SE) image and an EBIC current map at resolutions up to 2048x1536 pixels.
· Item 3.3: The system must be able to operate without an external network connection.
5. Warrant Requirements: Minimum 1 year warranty on system, materials, and labor. Throughout the life of the warranty, the contractor will conduct on-site calibration of the system if needed or virtually assist in the calibration of the system completed by a trained AFIT member. If on-site calibration is required, the contractor will be available to provide hands-on training to the AFIT member while calibrating/adjusting the EBIC System.
6. Payments: 100% payment upon completion of all requirements specified in this document through Wide Area Workflow (WAWF) (https://wawf.eb.mil)