This document is a question and answer file related to a federal contract solicitation for office furniture. The Air Force Life Cycle Management Center issued Solicitation Number FA860123Q0132 to procure steelcase brand name office furniture for Room E137. The Q&A file clarifies requirements around knockouts in panel tops, interior vertical cable routing, the inventory list to be used from the floorplan drawing, power pole requirements based on circuits available to meet a maximum of 6 duplex outlets per house circuit and 4 per tech circuit, and the need for 1 communication pole per 4 stations. Vendors are to include these clarifications in their proposals and estimates in response to the solicitation by the response date not provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE LIFE CYCLE MANAGEMENT CENTER (AFLCMC)
WRIGHT-PATTERSON AIR FORCE BASE OHIO
15 August 2023
FROM: AFLCMC/PZIBA
1940 Allbrook Drive, Room 109 Wright-Patterson AFB, OH 45433
SUBJECT: Response to Inquiries regarding FA8601-22-Q0132
QUESTIONS
1. QUESTION: Existing panels have knockouts in the top caps, but there is no mention of knockouts in the Statement of Work (SOW). Do you want this to be included in the proposal?
ANSWER: Yes, knockouts in the top caps are needed; this has been updated in the SOW, dated 15 August 2023. Please include this in your proposal and estimate.
2. QUESTION: Existing panels have interior vertical cable routing and are specified for each side of the panel, but there is no mention of these cables in the SOW. Do you want interior vertical cable routing included in the proposal?
ANSWER: Yes, interior vertical cable routing is needed; this has been updated in the SOW, dated 15 August 2023. Please include this in your proposal and estimate.
3. QUESTION: The Statement of Work states the Government will supply an inventory list of existing products available for use. Where is the inventory list?
ANSWER: Please utilize to the floorplan drawing included in the solicitation as the inventory list.
4. QUESTION: As the SOW reads under Salient Characteristics, it states each station to have a minimum of 2 technical duplexes and 2 house duplexes. Does that mean you want a base power infeed or power pole for every two workstations?
ANSWER: Power poles are required. The vendor should determine how many power poles are required to meet the following configuration based on the circuits available in the furniture they propose. There is a maximum of 6 duplex outlets on 1 house circuit and a maximum of 4 duplex outlets on 1 tech circuit.
5. QUESTION: Are cable poles needed, and if so, how many?
ANSWER: Comm Poles are listed as a salient characteristic in each CLIN. Please provide 1 per 4 stations; this information is included in the SOW, dated 15 August 2023.
CANDICE L. SNOW
Contracting Officer
AFLCMC/PZIBA
Attachments:
Attachment 1 – Statement of Work (Revised 15 August 2023)
| 2023-08-15T11:30:22-0400 | |